ANTEPROYECTO: CISTERNA DE ALMACENAMIENTO PARA AGUA

1. TRAZO Y NIVELACION
16.0M. X 4.80M = 76.80M2 X $10.0 = $ 768.00

2. EXCAVACION EN ROCA CON MAQUINARIA CON ROTOMARTILLO


16.0M. X 4.80M X 2.0M = 153.60M3 X $600.00 = $
92,160.00

3. AFINE DE CORTE DE EXCAVACION EN MUROS Y FONDO


83.20M2 + 76.80M2 = 160M2 X $25.00= $ 4,000.00

4. ACARREO DE PIEDRA PRODUCTO DE EXCAVACION A UNA ESTACION DE 40M.


153.60M3 X $60.00 = $ 9,216.00

5. PLANTILLA DE CONCRETO POBRE DE 100KG/CM2


16.00M X 4.80M = 76.80M2 X $170.00= $
13,056.00

6. LOSA DE FONDO DE CONCRETO ARMADO DE 12CM DE ESPESOR, ARMADO CON VARILLA DEL #3 @ 40CM
76.80M2 X $565.00 = $ 43,392.00

7. MUROS DE MAMPOSTERIA DE PIEDRA ACABADO COMUN


62.12M3 X $880.00 = $ 54,665.60

8. COLUMNAS DE CONCRETO ARMADO CON VARILLA DEL #4 ESTRIBOS DEL #3 @ 20CM DE SECCION DE 40 X 40
CM.
24.00ML X $1,400 = $ 33,600.00

9. CADENA DE CERRAMIENTO DE CONCRETO ARMADO CON 4 VARILLAS DE #4, ESTRIBOS DE ALAMBRON @


20CM, DE SECCION 40 X 15CM.
(32.0M + 20.0M) = 52ML X $730= $ 37,960.00

10. APLANADO DE MUROS DE MAMPOSTERIA ACABADO PULIDO CON MORTERO-ARENA DE 5CM DE ESPESOR
CON FESTERBOND
120.0M2 X $320.0 = $ 38,400.00

11. ACARREO DE MATERIAL PRODUCTO DE EXCAVACION


153.60M3 – 62.12M3 = 91.48M3 X $150.0 = $ 13,722.00

12. LOSA DE CONCRETO ARMADO DE 12CM DE ESPESOR, ARMADO CON VARILLA DEL #3 @ 15CM.
(16.0M X 4,8M) = 76.80M2 X $1,125.0 = $ 86,400.00

13. CARCAMO DE BOMBA Y TUBO VENTILADOR DE 4”


1.0 PZA X $ 3,500.00 = $ 3,500.00

14. TAPA REGISTRO DE 60 X 60CM CON MARCO Y LAMINA CALIBRE #18


1.0 PZA X $ 1,800.00 = $ 1,800.00

15. LIMPIEZA DE OBRA GRUESA


1 LOTE X $ 3,500.00 = $ 3,500.00

SUBTOTAL= $ 436,139.60
UTILIDAD= $ 43,613.96
TOTAL= $ 479,753.56