CURVA S - PROYECTO ANTAPACCAY

Nombre de Oct-15 Oct-15 Oct-15 Oct-15


Comienzo Fin Metros Dias Horas Peso HH %
tarea SEM 1 SEM 2 SEM 3 SEM 4
0.99
P-1 12/17/2015 21/12/2015 40.00 4 96 3840 18.18%

0.89

P-2 12/21/2015 25/12/2015 40.00 4 96 3840 18.18%


0.79

0.69
P-3 12/25/2015 29/12/2015 40.00 4 96 3840 18.18%
0.59

P-4 12/29/2015 02/01/2016 40.00 4 96 3840 18.18% 0.49

0.39
P-5 1/2/2016 05/01/2016 40.00 3 72 2880 13.64%
0.29

0.19
P-6 1/5/2016 08/01/2016 40.00 3 72 2880 13.64%

0.09

Real Prog Forecast


-0.01
Total 240.00 22 528 21120 100.00%

Prog 27.27% 59.09% 90.91% 100.00%


Real 27.27% 45.45% 45.45% 45.45%
Forecast
PROGRAMADO
Nombre de tarea FASE 1 P-1 FASE 1 P-2 FASE 1 P-3 FASE 1 P-4 FASE 1 P-5 FASE 1 P-6 % AVANCE
Comienzo 12/17/2015 12/21/2015 12/25/2015 12/29/2015 1/2/2016 1/5/2016
Total
Fin 21/12/2015 25/12/2015 29/12/2015 02/01/2016 05/01/2016 08/01/2016
Metros 40.00 40.00 40.00 40.00 40.00 40.00 240
Dias 4 4 4 4 3 3 22
Horas 96 96 96 96 72 72 528
Peso HH 3840 3840 3840 3840 2880 2880 21120
% 18.18% 18.18% 18.18% 18.18% 13.64% 13.64% 1.00
12/17/2015 Dec-15 SEM 1 100.00% 50.00% 27.27%
12/24/2015 Dec-15 SEM 2 50.00% 100.00% 25.00% 59.09%
12/31/2015 Dec-15 SEM 3 75.00% 100.00% 33.33% 90.91%
1/7/2016 Jan-16 SEM 4 66.67% 100.00%
REAL
Nombre de tarea POZO 1 POZO 2 POZO 3 POZO 4 POZO 5 POZO 6 % AVANCE
Comienzo 12/17/2015 12/20/2015 12/26/2015 12/30/2015 1/3/2016 1/7/2016
Total
Fin 20/12/2015 23/12/2015 30/12/2015 03/01/2016 07/01/2016 11/01/2016
Metros 40.00 40.00 40.00 40.00 40.00 40.00 240
Dias 3 3 4 4 4 4 22
Horas 72 72 96 96 96 96 528
Peso HH 2880 2880 3840 3840 3840 3840 21120
% 13.64% 13.64% 18.18% 18.18% 18.18% 18.18% 1.00
12/17/2015 Dec-15 SEM 1 100.00% 100.00% 27.27%
12/24/2015 Dec-15 SEM 2 100.00% 45.45%
12/31/2015 Dec-15 SEM 3 45.45%
1/7/2016 Jan-16 SEM 4 45.45%