Item Descripción Und. Metrado Precio (S/.) Parcial (S/.

Und. Metrado Precio (S/.) Parcial (S/.) MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9
01 OBRAS PRELIMINARES 4,530.76
01.01 CARTEL DE OBRA IMPRESION DE BANNER DE4.80 m X 3.60 m (Soporte de Maderund 1.00 930.76 930.76 930.76
01.02 OFICINA Y ALMACEN mes 6.00 600.00 3,600.00 3,600.00
02 TRABAJOS PRELIMINARES 123,073.98
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 45,628.67 45,628.67 45,628.67
02.02 LIMPIEZA DE TERRENO MANUAL m2 20,168.05 1.00 20,168.05 12,218.50 7,949.55
02.03 TRAZO NIVELACION Y REPLANTEO DE INICIO DE OBRA m2 20,168.05 2.84 57,277.26 57,277.26
03 MOVIMIENTO DE TIERRAS 529,682.35
03.01 CORTE A NIVEL DE SUBRASANTE m3 7,885.40 27.81 219,292.97 143,011.72 76,281.25
03.02 ELIMINACION DE MATERIAL EXCEDENTE m3 11,315.69 27.43 310,389.38 106,400.69 170,478.20 33,510.49
04 PAVIMENTOS 2,324,952.91
04.01 PAVIMENTO RIGIDO 2,312,344.30
04.01.01 PERFILADO Y COMPACTADO DE SUB RASANTE m2 12,387.81 5.69 70,486.64 70,486.64
04.01.02 CONFORMACION Y COMPACTACION BASE GRANULAR E=0.30 m m2 12,387.81 46.28 573,307.85 545,881.99 27,425.86
04.01.03 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO RIGIDO m2 2,206.51 36.31 80,118.38 59,998.32 20,120.06
04.01.04 CONCRETO F'C=210 KG/CM2 EN PAVIMENTO RIGIDO e=0.20m. m3 2,477.56 589.35 1,460,149.99 1,212,037.19 190,138.05 57,974.75
04.01.05 CURADO DEL CONCRETO EN PAVIMENTO RIGIDO m2 12,387.81 3.66 45,339.38 33,591.57 11,747.81
04.01.06 JUNTAS ASFALTICAS m 4,293.17 5.98 25,673.16 23,066.66 2,606.50
04.01.07 ACERO F´Y=4200 KG/CM2 (PASADORES) kg 5,587.21 10.25 57,268.90 53,885.51 3,383.39
04.02 BERMAS DE CONCRETO SIMPLE 12,608.61
04.02.01 TRAZO NIVELACION Y REPLANTEO m2 85.50 2.46 210.33 210.33
04.02.02 EXCAVACION MANUAL EN TERRENO SUELTO m3 25.65 34.87 894.42 894.42
04.02.03 NIVELACION Y COMPACTADO DE SUB RASANTE m2 85.50 4.84 413.82 413.82
04.02.04 CONFORMACION Y COMPACTACION BASE GRANULAR EN BERMAS E=0.15 m m2 85.50 27.81 2,377.76 2,377.76
04.02.05 CONCRETO FC=175 KG/CM2 EN BERMAS m3 17.10 507.09 8,671.24 8,671.24
04.02.06 CURADO DEL CONCRETO EN BERMAS m2 85.50 0.48 41.04 41.04
05 SEÑALIZACION 13,395.33
05.01 PINTADO DE SARDINELES ML 441.59 12.22 5,396.23 5,396.23
05.02 PINTADO DE SIMBOLOS Y LETRA DE TRANSITO m2 313.69 25.50 7,999.10 4,091.20 3,907.90
06 VEREDAS 655,801.79
06.01 VEREDAS 464,538.49
06.01.01 TRAZO NIVELACION Y REPLANTEO m2 3,893.54 2.46 9,578.11 9,578.11
06.01.02 EXCAVACION MANUAL EN TERRENO SUELTO m3 778.71 34.87 27,153.62 13,233.95 13,919.67
06.01.03 PERFILADO Y COMPACTADO DE SUB RASANTE PARA VEREDA m2 3,893.54 7.32 28,500.71 19,330.57 9,170.14
06.01.04 CONFORMACION Y COMPACTACION BASE GRANULAR EN VEREDAS E=0.10 m2 3,893.54 22.02 85,735.75 85,735.75
06.01.05 CONCRETO FC=175 KG/CM2 m3 584.03 507.09 296,155.77 254,260.40 41,895.37
06.01.06 JUNTAS ASFALTICAS m 1,323.46 5.98 7,914.29 7,148.81 765.48
06.01.07 CURADO DEL CONCRETO EN VEREDAS m2 3,893.54 2.44 9,500.24 9,500.24
06.02 SARDINELES 171,709.25
06.02.01 TRAZO NIVELACION Y REPLANTEO m2 441.15 2.46 1,085.23 1,085.23
06.02.02 EXCAVACION MANUAL EN TERRENO SUELTO m3 88.23 34.87 3,076.58 969.21 2,107.37
06.02.03 CONCRETO FC=175 KG/CM2 m3 176.46 507.09 89,481.10 73,438.87 16,042.23
06.02.04 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 1,764.61 42.50 74,995.93 18,428.94 56,566.99
06.02.05 JUNTAS ASFALTICAS m 441.15 5.98 2,638.08 2,638.08
06.02.06 CURADO DEL CONCRETO EN SARDINELES DE VEREDA m2 441.15 0.98 432.33 432.33
06.03 RAMPA PARA DISCAPACITADOS 19,554.05
06.03.01 TRAZO NIVELACION Y REPLANTEO m2 288.00 2.46 708.48 708.48
06.03.02 EXCAVACION MANUAL EN TERRENO SUELTO m3 28.80 34.87 1,004.26 801.5 202.76
06.03.03 CONCRETO FC=175 KG/CM2 m3 28.80 507.09 14,604.19 14,604.19
06.03.04 BRUÑA DE RAMPA ML 3,840.00 0.66 2,534.40 2,534.40
06.03.05 CURADO DEL CONCRETO EN RAMPAS m2 288.00 2.44 702.72 702.72
07 CUNETAS PARA LA EVACUACION DE AGUAS PLUVIALES 874,620.72
07.01 CUNETAS 859,886.53
07.01.01 TRAZO NIVELACION Y REPLANTEO m2 1,322.97 2.46 3,254.51 3,254.51
07.01.02 EXCAVACION MANUAL EN TERRENO SUELTO m3 264.59 34.87 9,226.25 4,980.84 4,245.41
07.01.03 CONCRETO FC=210 KG/CM2 EN CUNETA m3 440.99 580.87 256,157.86 231,948.35 24,209.51
07.01.04 ENCOFRADO Y DESENCOFRADO DE CUNETAS m2 3,086.94 45.35 139,992.73 139,992.73
07.01.05 JUNTAS ASFALTICAS m 1,469.97 5.98 8,790.42 8,790.42
07.01.06 CONCRETO FC=210 KG/CM2 EN TAPA DE CUNETA m3 198.45 589.35 116,956.51 105,801.08 11,155.43
07.01.07 ENCOFRADO Y DESENCOFRADO EN TAPA DE CUNETAS m2 1,740.75 37.58 65,417.39 30,793.69 34,623.70
07.01.08 ACERO F´Y=4200 KG/CM2 EN TAPAS DE CUNETA kg 19,426.81 13.25 257,405.23 249,000.47 8,404.76
07.01.09 CURADO DEL CONCRETO EN CUNETAS m2 1,322.97 2.03 2,685.63 2,685.63
07.02 ALCANTARILLA DE EVACUACION DE AGUAS PLUVIALES 14,734.19
07.02.01 TRAZO NIVELACION Y REPLANTEO m2 19.93 2.46 49.03 49.03
07.02.02 EXCAVACION MANUAL EN TERRENO SUELTO m3 9.97 34.87 347.65 347.65
07.02.03 ENCOFRADO Y DESENCOFRADO m2 15.94 37.58 599.03 599.03
07.02.04 CONCRETO FC=210 KG/CM2 m3 5.18 568.94 2,947.11 2,676.22 270.89
07.02.05 TARRAJEO CON IMPERMEABILIZANTES m2 47.83 41.47 1,983.51 1,983.51
07.02.06 REJILLA SUMIDERO-PLAT 1 1/4"X1/4"+L 1 1/1/4" m2 39.86 220.97 8,807.86 8,807.86
08 GRADERIAS DE CONCRETO 96,092.88
08.01 GRADERIAS DE CONCRETO 84,460.32
08.01.01 TRAZO NIVELACION Y REPLANTEO m2 538.55 2.46 1,324.83 1,324.83
08.01.02 EXCAVACION MANUAL EN TERRENO SUELTO m3 107.71 34.87 3,755.85 515.24 2,345.26 895.35
08.01.03 PERFILADO Y COMPACTADO DE SUB RASANTE m2 538.55 7.32 3,942.19 3,942.19
08.01.04 CONFORMACION Y COMPACTACION BASE GRANULAR EN GRADERIA E=0.10 m2 538.55 22.02 11,858.87 11,858.87
08.01.05 ENCOFRADO Y DESENCOFRADO DE GRADERIAS m2 519.79 38.26 19,887.17 7,318.53 9,096.05 3,472.59
08.01.06 CONCRETO FC=175 KG/CM2 m3 80.78 507.09 40,962.73 40,962.73
08.01.07 JUNTAS ASFALTICAS EN GRADERIAS m 179.52 7.88 1,414.62 1,414.62
08.01.08 CURADO DEL CONCRETO EN GRADERIA m2 538.55 2.44 1,314.06 1,314.06
08.02 SARDINELES 11,632.56
08.02.01 TRAZO NIVELACION Y REPLANTEO m2 31.25 2.46 76.88 76.88
08.02.02 EXCAVACION MANUAL EN TERRENO SUELTO m3 9.38 34.87 327.08 327.08
08.02.03 CONCRETO FC=175 KG/CM2 m3 12.50 507.09 6,338.63 6,338.63
08.02.04 ENCOFRADO Y DESENCOFRADO DE SARDINE m2 125.00 38.26 4,782.50 2,050.66 2,731.84
08.02.05 JUNTAS ASFALTICAS EN SARDINELES m 12.13 7.88 95.58 95.58
08.02.06 CURADO DEL CONCRETO EN SARDINELES EN GRADERIA m2 12.13 0.98 11.89 11.89
09 OBRAS DE MUROS DE CONTENCIONCONCRETO ARMADO 700,405.16
09.01 MURO CºAº tipo I,II y III 700,405.16
09.01.01 OBRAS PRELIMINARES 1,713.83
09.01.01.0 TRAZO NIVELACION Y REPLANTEO m2 696.68 2.46 1,713.83 1,713.83
09.01.02 MOVIMIENTO DE TIERRAS 124,279.01
09.01.02.0 EXCAVACION MANUAL EN TERRENO SUELTO m3 1,467.90 34.87 51,185.67 51,185.67
09.01.02.0 RELLENO CON MATERIAL PROPIO m3 263.56 4.60 1,212.38 1,212.38
09.01.02.0 RELLENO CON MATERIAL DE PRESTAMO MANUAL m3 263.56 168.66 44,452.03 44,277.01 175.02
09.01.02.0 ELIMINACION DE MATERIAL EXEDENTE m3 1,505.43 18.22 27,428.93 17,828.01 9,600.92
09.01.03 OBRAS DE CONCRETO SIMPLE 6,969.76
09.01.03.0 SOLADO CONCRETO FC=100 KG/CM2 m3 73.84 94.39 6,969.76 6,969.76
09.01.04 OBRAS DE CONCRETO ARMADO 567,442.56
09.01.04.0 CONCRETO F'C=210 KG/CM2 m3 390.88 575.38 224,904.53 199,085.61 25,818.92
09.01.04.0 ENCOFRADO Y DESENCOFRADO DE MUROS DE CONTENCION m2 1,517.42 55.12 83,640.19 23,510.75 14,020.40 13,109.51 13,995.78 13,564.96 5,438.79
09.01.04.0 ACERO F´Y=4200 KG/CM2 kg 23,237.24 11.08 257,468.62 222,185.72 8,431.22 7,883.96 8,418.39 8,157.59 2,391.73
09.01.04.0 JUNTAS DE DILATACION CON ASFALTO m 239.00 5.98 1,429.22 1,429.22
10 MITIGACION DE IMPACTO AMBIENTAL 10,000.00
10.01 MITIGACION DE IMAPCTO AMBIENTAL GLB 1.00 10,000.00 10,000.00 10,000.00
11 OTROS 422,571.80
11.01 FLETE TERRESTRE GLB 1.00 373,551.92 373,551.92 373,551.92
11.02 MANTENIMIENTO Y SEGURIDAD VIAL GLB 1.00 1,036.98 1,036.98 1,036.98
11.03 REPOSICION DE CAJAS DE REGISTRO DE AGUA Y DESAGUE GLB 38.00 164.08 6,235.04 6,235.04
11.04 LIMPIEZA FINAL DE OBRA m2 20,168.05 2.07 41,747.86 41,747.86

202,592.26 877,018.88 268,993.97 737,353.66 607,985.22 1,862,951.38 941,253.11 199,575.62 57,403.57