Presupuesto
Presupu
esto
Cliente
Lugar

Item Descripción Und. Metrado Precio S/. Parcial S/.

01 OBRAS PRELIMINARES 22,115.36


01.01 CARTEL DE IDENTIFICACION DE OBRA DE und 1.00 1,315.36 1,315.36
8.50X3.60M. SEGÚN DISEÑO

01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 20,000.00 20,000.00


Y MAQUINARIAS

01.03 CAMPAMENTO Y ALMACENES glb 1.00 800.00 800.00

02 PAVIMENTACION 2,578,312.18

02.01 CONSTRUCCION DE CALZADA DE PAVIMENTO 1,928,026.63

02.01.01 TRABAJOS PRELIMINARES 26,756.13

02.01.01. TRAZO Y REPLANTEO m2 10,617.51 2.52 26,756.13

02.01.02 EXPLANACIONES 73,952.80

02.01.02. CORTE DE MATERIAL SEMIROCOSO CON EQUIPO m3 6,204.45 4.56 28,292.29

02.01.02. RELLENO COMPACTADO CON MATERIAL PROPIO m3 2,365.14 6.61 15,633.58

02.01.02. ELIMINACION DE DESMONTE PROVENIENTE DEL m3 6,871.15 4.37 30,026.93


MOVIMIENTO EN TERRENO SEMIROSO

02.01.03 ESTRUCTURA DE PAVIMENTO 1,333,581.78

02.01.03. MEJORAMIENTO DE BASE 490,847.48

02.01.03. PERFILADO Y COMPACTADO DE SUB-RASANTE m2 10,617.51 4.46 47,354.09

02.01.03. BASE DE AFIRMADO H=0.30 m m2 10,617.51 41.77 443,493.39

02.01.03. PAVIMENTO RIGIDO 842,734.30

02.01.03. CONCRETO LOSAS f'c= 210 kg/cm2 m3 1,898.50 396.03 751,862.96

02.01.03. ENCOFRADO Y DESENCOFRADO NORMAL EN m2 972.33 33.78 32,845.31


LOSAS

02.01.03. ACERO LISO DE 3/4" EN LOSA kg 4,551.64 7.58 34,501.43

02.01.03. ACERO LISO DE 1/2" EN LOSA kg 3,800.42 6.19 23,524.60

02.01.04 SARDINELES 315,837.61

02.01.04. MOVIMIENTO DE TIERRAS 11,088.89


02.01.04. EXCAVACION PARA SARDINELES m 3,652.00 1.36 4,966.72

02.01.04. EXCAVACION A MANO EN TERRENO NORMAL m3 156.00 15.58 2,430.48

02.01.04. RELLENO COMPACTADO m3 61.60 59.93 3,691.69

02.01.04. CONCRETO SIMPLE 219,948.62

02.01.04. CONCRETO F'c=100 kg/cm2, e=0.10 SOLADO m2 120.00 27.84 3,340.80

02.01.04. ENCOFRADO Y DESENCOFRADO NORMAL EN m2 3,317.70 23.33 77,401.94


SARDINELES

02.01.04. CONCRETO PARA SARDINELES f'c=175 kg/cm2 m3 366.64 379.68 139,205.88

02.01.04. CONCRETO ARMADO 56,668.48

02.01.04. CONCRETO EN CIMENTACION f'c=175 kg/cm2 m3 24.00 346.96 8,327.04

02.01.04. ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,468.80 5.30 7,784.64

02.01.04. ENCOFRADO Y DESENCOFRADO EN MURO m2 352.00 44.82 15,776.64

02.01.04. CONCRETO EN MURO FC=175 kg/cm2 m3 34.20 395.78 13,535.68

02.01.04. ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,121.60 5.30 11,244.48

02.01.04. REVOQUES 28,131.62

02.01.04. TARRAJEO EN SARDINELES m2 1,773.10 14.20 25,178.02

02.01.04. TARRAJEO EN MURO DE CONTENCION m2 208.00 14.20 2,953.60

02.01.05 CUNETAS 97,482.30

02.01.05. CONCRETO f'c=210 kg/cm2 PARA CUNETAS m3 195.61 397.23 77,702.16

02.01.05. TARRAJEO Y PULIDO EN CUNETAS m2 1,388.08 14.25 19,780.14

02.01.06 JUNTAS 13,452.25

02.01.06. JUNTAS ASFALTICAS m 3,832.55 3.51 13,452.25

02.01.07 SEÑALIZACION 7,577.49

02.01.07. MARCAS EN EL PAVIMENTO 7,577.49

02.01.07. PINTURA EN SARDINELES m 1,891.87 1.56 2,951.32

02.01.07. SEÑALIZACION VERTICAL und 1.00 318.11 318.11

02.01.07. SEÑALIZACION HORIZONTAL und 1.00 4,308.06 4,308.06


02.01.08 VARIOS 59,386.27

02.01.08. REHABILITACION DE SISTEMAS DE AGUA Y 59,386.27


DESAGUE

02.01.08. ENCIMADO DE CAJAS DOMICILIARIAS DE AGUA Y und 241.00 123.83 29,843.03


DESAGUE PARA CONSTRUCCION DE VEREDAS

02.01.08. ENCIMADO DE BUZON DE CONCRETO EXISTENTE und 38.00 528.38 20,078.44

02.01.08. INSTALACION DE BUZON DE CONCRETO und 5.00 1,892.96 9,464.80

02.02 CONSTRUCCION DE VEREDAS 650,285.55

02.02.01 TRABAJOS PRELIMINARES 7,719.16

02.02.01. TRAZO Y REPLANTEO m2 3,840.38 2.01 7,719.16

02.02.02 MOVIMIENTO DE TIERRAS 137,252.95

02.02.02. CORTE SUPERFICIAL MANUAL m3 1,763.90 18.19 32,085.34

02.02.02. RELLENO CON MATERIAL DE PRESTAMO m3 1,141.56 87.08 99,407.04


SELECCIONADO

02.02.02. NIVELACION INTERIOR Y APISONADO CON m2 3,840.38 1.50 5,760.57


EQUIPO

02.02.03 CONCRETO SIMPLE 228,153.22

02.02.03. ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 2,698.24 18.55 50,052.35

02.02.03. CONCRETO f'c=140 kg/cm2 EN PISO DE VEREDAS m3 534.34 333.31 178,100.87

02.02.04 OBRAS DE ARTE EN PISOS 277,160.22

02.02.04. PISO DE VEREDA CON ADOQUINES DE CONCRETO m2 3,840.38 72.17 277,160.22

03 LIMPIEZA FINAL DE OBRA 6,755.90

03.01 LIMPIEZA FINAL DE OBRA m2 25,021.86 0.27 6,755.90

04 FLETE TERRESTRE 76,962.84

04.01 FLETE TERRESTRE glb 1.00 76,962.84 76,962.84

COSTO DIRECTO
GASTOS GENERALES (8%)

TOTAL PRESUPUESTO
K CALCULADA EN EL EXPEDIENTE

FORMULA POLINOMICA DE ENERO A FEBRERO


SIMB IU COEF INC % Ir (Ene 14) Io (Feb 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 388.14 390.36 0.994312942
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 779.19 784.79 0.992864333
M05 49 0.124 100 249.28 249.92 0.997439181
M06 39 0.084 100 393.46 395.83 0.994012581
0.992 TOTAL

FORMULA POLINOMICA DE FEBRERO A MARZO


SIMB IU COEF INC % Ir (Feb 14) Io (Mar 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 390.36 389.12 1.003186678
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 784.79 786.55 0.99776238
M05 49 0.124 100 249.92 249.75 1.000680681
M06 39 0.084 100 395.83 397.88 0.994847693
TOTAL

FORMULA POLINOMICA DE MARZO A ABRIL


SIMB IU COEF INC % Io (Mar 14) Io (Abr 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 389.12 388.89 1.000591427
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 786.55 784.9 1.002102179
M05 49 0.124 100 249.75 248.5 1.005030181
M06 39 0.084 100 397.88 399.44 0.996094532
TOTAL

FORMULA POLINOMICA DE ABRIL A MAYO


SIMB IU COEF INC % Io (Abr 14) Io (May 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 388.89 389.66 0.998023918
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 784.9 791.43 0.991749112
M05 49 0.124 100 248.5 248.06 1.001773764
M06 39 0.084 100 399.44 400.34 0.997751911
TOTAL

FORMULA POLINOMICA DE MAYO A JUNIO


SIMB IU COEF INC % Io (May 14) Io (Jun 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 389.66 393.67 0.989813803
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 791.43 797.19 0.992774621
M05 49 0.124 100 248.06 248.68 0.997506836
M06 39 0.084 100 400.34 400.98 0.99840391
TOTAL

FORMULA POLINOMICA DE ENERO A FEBRERO


SIMB IU COEF INC % Ir (Ene 14) Io (Feb 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 388.14 390.36 0.994312942
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 779.19 784.79 0.992864333
M05 49 0.124 100 249.28 249.92 0.997439181
M06 39 0.084 100 393.46 395.83 0.994012581
TOTAL

FORMULA POLINOMICA DE ENERO A MARZO


SIMB IU COEF INC % Ir (Ene 14) Io (Mar 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 388.14 389.12 0.997481497
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 779.19 786.55 0.99064268
M05 49 0.124 100 249.28 249.75 0.998118118
M06 39 0.084 100 393.46 397.88 0.988891123
TOTAL

FORMULA POLINOMICA DE ENERO A ABRIL


SIMB IU COEF INC % Ir (Ene 14) Io (Abr 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 388.14 388.89 0.998071434
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 779.19 784.9 0.992725188
M05 49 0.124 100 249.28 248.5 1.003138833
M06 39 0.084 100 393.46 399.44 0.985029041
TOTAL
FORMULA POLINOMICA DE ENERO A MAYO
SIMB IU COEF INC % Ir (Ene 14) Io (May 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 388.14 389.66 0.996099163
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 779.19 791.43 0.984534324
M05 49 0.124 100 249.28 248.06 1.004918165
M06 39 0.084 100 393.46 400.34 0.982814608
TOTAL

FORMULA POLINOMICA DE ENERO A JUNIO


SIMB IU COEF INC % Ir (Ene 14) Io (Jun 14) Ir/Io
M01 47 0.151 100 498.1 498.1 1
M02 05 0.254 100 388.14 393.67 0.985952702
M03 21 0.308 100 354.74 354.74 1
M04 43 0.071 100 779.19 797.19 0.97742069
M05 49 0.124 100 249.28 248.68 1.002412739
M06 39 0.084 100 393.46 400.98 0.981245947
TOTAL
K CALCULADA POR EL GRUPO

RERO FORMULA POLINOMICA DE ENERO A FEBRERO


K SIMB IU COEF INC % Ir (Ene 14)
0.151 M01 47 0.145782743 100 498.1
0.253 M02 05 0.24608389 100 388.14
0.308 M03 21 0.263745653 100 354.74
0.130 M04 02 0.063536112 100 479.33
0.124 M05 49 0.150416819 100 249.28
0.083 M06 39 0.130434783 100 393.46
1.049

ARZO FORMULA POLINOMICA DE FEBRERO A MARZO


K SIMB IU COEF INC % Ir (Feb 14)
0.151 M01 47 0.145782743 100 498.1
0.255 M02 05 0.24608389 100 390.36
0.308 M03 21 0.263745653 100 354.74
0.131 M04 02 0.063536112 100 477.98
0.124 M05 49 0.150416819 100 249.92
0.084 M06 39 0.130434783 100 395.83
1.052

RIL FORMULA POLINOMICA DE MARZO A ABRIL


K SIMB IU COEF INC % Io (Mar 14)
0.151 M01 47 0.145782743 100 498.1
0.254 M02 05 0.24608389 100 389.12
0.308 M03 21 0.263745653 100 354.74
0.131 M04 02 0.063536112 100 478.28
0.125 M05 49 0.150416819 100 249.75
0.084 M06 39 0.130434783 100 397.88
1.053

YO FORMULA POLINOMICA DE ABRIL A MAYO


K SIMB IU COEF INC % Io (Abr 14)
0.151 M01 47 0.145782743 100 498.1
0.253 M02 05 0.24608389 100 388.89
0.308 M03 21 0.263745653 100 354.74
0.130 M04 02 0.063536112 100 471.74
0.124 M05 49 0.150416819 100 248.5
0.084 M06 39 0.130434783 100 399.44
1.051

IO FORMULA POLINOMICA DE MAYO A JUNIO


K SIMB IU COEF INC % Io (May 14)
0.151 M01 47 0.145782743 100 498.1
0.251 M02 05 0.24608389 100 389.66
0.308 M03 21 0.263745653 100 354.74
0.130 M04 02 0.063536112 100 478.45
0.124 M05 49 0.150416819 100 248.06
0.084 M06 39 0.130434783 100 400.34
1.048

RERO FORMULA POLINOMICA DE ENERO A FEBRERO


K SIMB IU COEF INC % Ir (Ene 14)
0.151 M01 47 0.145782743 100 498.1
0.253 M02 05 0.24608389 100 388.14
0.308 M03 21 0.263745653 100 354.74
0.130 M04 02 0.063536112 100 479.33
0.124 M05 49 0.150416819 100 249.28
0.083 M06 39 0.130434783 100 393.46
1.049

RZO FORMULA POLINOMICA DE ENERO A MARZO


K SIMB IU COEF INC % Ir (Ene 14)
0.151 M01 47 0.145782743 100 498.1
0.253 M02 05 0.24608389 100 388.14
0.308 M03 21 0.263745653 100 354.74
0.130 M04 02 0.063536112 100 479.33
0.124 M05 49 0.150416819 100 249.28
0.083 M06 39 0.130434783 100 393.46
1.050

RIL FORMULA POLINOMICA DE ENERO A ABRIL


K SIMB IU COEF INC % Ir (Ene 14)
0.151 M01 47 0.145782743 100 498.1
0.254 M02 05 0.24608389 100 388.14
0.308 M03 21 0.263745653 100 354.74
0.130 M04 02 0.063536112 100 479.33
0.124 M05 49 0.150416819 100 249.28
0.083 M06 39 0.130434783 100 393.46
1.050
YO FORMULA POLINOMICA DE ENERO A MAYO
K SIMB IU COEF INC % Ir (Ene 14)
0.151 M01 47 0.145782743 100 498.1
0.253 M02 05 0.24608389 100 388.14
0.308 M03 21 0.263745653 100 354.74
0.130 M04 02 0.063536112 100 479.33
0.125 M05 49 0.150416819 100 249.28
0.083 M06 39 0.130434783 100 393.46
1.049

NIO FORMULA POLINOMICA DE ENERO A JUNIO


K SIMB IU COEF INC % Ir (Ene 14)
0.151 M01 47 0.145782743 100 498.1
0.250 M02 05 0.24608389 100 388.14
0.308 M03 21 0.263745653 100 354.74
0.129 M04 02 0.063536112 100 479.33
0.124 M05 49 0.150416819 100 249.28
0.082 M06 39 0.130434783 100 393.46
1.046
OR EL GRUPO

DE ENERO A FEBRERO
Io (Feb 14) Ir/Io K
498.1 1 0.146
390.36 0.994312942 0.245
354.74 1 0.264
477.98 1.002824386 0.124
249.92 0.997439181 0.150
395.83 0.994012581 0.130
TOTAL 1.058

DE FEBRERO A MARZO
Io (Mar 14) Ir/Io K
498.1 1 0.146
389.12 1.003186678 0.247
354.74 1 0.264
478.28 0.999372752 0.123
249.75 1.000680681 0.151
397.88 0.994847693 0.130
TOTAL 1.060

A DE MARZO A ABRIL
Io (Abr 14) Ir/Io K
498.1 1 0.146
388.89 1.000591427 0.246
354.74 1 0.264
471.74 1.013863569 0.124
248.5 1.005030181 0.151
399.44 0.996094532 0.130
TOTAL 1.061

A DE ABRIL A MAYO
Io (May 14) Ir/Io K
498.1 1 0.146
389.66 0.998023918 0.246
354.74 1 0.264
478.45 0.985975546 0.123
248.06 1.001773764 0.151
400.34 0.997751911 0.130
TOTAL 1.059

A DE MAYO A JUNIO
Io (Jun 14) Ir/Io K
498.1 1 0.146
393.67 0.989813803 0.244
354.74 1 0.264
492.06 0.972340771 0.122
248.68 0.997506836 0.150
400.98 0.99840391 0.130
TOTAL 1.055

DE ENERO A FEBRERO
Io (Feb 14) Ir/Io K
498.1 1 0.146
390.36 0.994312942 0.245
354.74 1 0.264
477.98 1.002824386 0.124
249.92 0.997439181 0.150
395.83 0.994012581 0.130
TOTAL 1.058

DE ENERO A MARZO
Io (Mar 14) Ir/Io K
498.1 1 0.146
389.12 0.997481497 0.245
354.74 1 0.264
478.28 1.002195367 0.124
249.75 0.998118118 0.150
397.88 0.988891123 0.129
TOTAL 1.058

A DE ENERO A ABRIL
Io (Abr 14) Ir/Io K
498.1 1 0.146
388.89 0.998071434 0.246
354.74 1 0.264
471.74 1.016089371 0.125
248.5 1.003138833 0.151
399.44 0.985029041 0.128
TOTAL 1.059
A DE ENERO A MAYO
Io (May 14) Ir/Io K
498.1 1 0.146
389.66 0.996099163 0.245
354.74 1 0.264
478.45 1.001839273 0.124
248.06 1.004918165 0.151
400.34 0.982814608 0.128
TOTAL 1.058

A DE ENERO A JUNIO
Io (Jun 14) Ir/Io K
498.1 1 0.146
393.67 0.985952702 0.243
354.74 1 0.264
492.06 0.974129171 0.122
248.68 1.002412739 0.151
400.98 0.981245947 0.128
TOTAL 1.053
CRONOGRAMA DE EJECUCION FISICA DE OBRA
PROYECTO : CREACION DE PISTAS Y VEREDAS DE LAS CALLES CENTENARIO, MARISCAL CACERES, 28 DE JULIO, MANCO CAPAC Y BOLOGNESI DE LA LOCALIDAD DE CAJA, DISTRITO DE CAJA - ACOBAMBA - HUANCAVELICA

PERIODO MENSUAL DE EJECUCION


PARTIDA DESCRIPCION MES 1 / SEMANA MES 2 / SEMANA MES 3 / SEMANA MES 4 / SEMANA MES 5 / SEMANA
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
01 OBRAS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 8.50X3.60M. SEGÚN DISEÑO 1,315.36 0.00 0.00 0.00
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS 10,000.00 10,000.00 0.00 0.00 0.00
01.03 CAMPAMENTO Y ALMACENES 40.00 40.00 40.00 40.00 40.00 40.00 40.00 40.00 160.00 40.00 40.00 40.00 40.00 160.00 40.00 40.00 40.00 40.00 160.00 40.00 40.00 40.00 40.00
02 PAVIMENTACION 0.00 0.00 0.00
02.01 CONSTRUCCION DE CALZADA DE PAVIMENTO 0.00 0.00 0.00
02.01.01 TRABAJOS PRELIMINARES 0.00 0.00 0.00
02.01.01.01 TRAZO Y REPLANTEO 6,689.03 6,689.03 6,689.03 6,689.03 0.00 0.00 0.00
02.01.02 EXPLANACIONES 0.00 0.00 0.00
02.01.02.01 CORTE DE MATERIAL SEMIROCOSO CON EQUIPO 7,073.07 7,073.07 7,073.07 7,073.07 14,146.15 0.00 0.00
02.01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO 5,211.19 5,211.19 5,211.19 15,633.58 0.00 0.00
02.01.02.03 ELIMINACION DE DESMONTE PROVENIENTE DEL MOVIMIENTO EN TERREN 10,008.98 10,008.98 10,008.98 30,026.93 0.00 0.00
02.01.03 ESTRUCTURA DE PAVIMENTO 0.00 0.00 0.00
02.01.03.01 MEJORAMIENTO DE BASE 0.00 0.00 0.00
02.01.03.01.01 PERFILADO Y COMPACTADO DE SUB-RASANTE 11,838.52 11,838.52 11,838.52 11,838.52 35,515.57 0.00 0.00
02.01.03.01.02 BASE DE AFIRMADO H=0.30 m 63,356.20 63,356.20 63,356.20 63,356.20 253,424.79 63,356.20 63,356.20 63,356.20 190,068.60 0.00
02.01.03.02 PAVIMENTO RIGIDO 0.00 0.00 0.00
02.01.03.02.01 CONCRETO LOSAS f'c= 210 kg/cm2 0.00 93,982.87 93,982.87 187,965.74 93,982.87 93,982.87 93,982.87 93,982.87 375,931.48 93,982.87 93,982.87
02.01.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS 0.00 4,105.66 4,105.66 8,211.33 4,105.66 4,105.66 4,105.66 4,105.66 16,422.66 4,105.66 4,105.66
02.01.03.02.03 ACERO LISO DE 3/4" EN LOSA 0.00 4,312.68 4,312.68 8,625.36 4,312.68 4,312.68 4,312.68 4,312.68 17,250.72 4,312.68 4,312.68
02.01.03.02.04 ACERO LISO DE 1/2" EN LOSA 0.00 2,940.58 2,940.58 5,881.15 2,940.58 2,940.58 2,940.58 2,940.58 11,762.30 2,940.58 2,940.58
02.01.04 SARDINELES 0.00 0.00 0.00
02.01.04.01 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00
02.01.04.01.01 EXCAVACION PARA SARDINELES 0.00 709.53 709.53 709.53 709.53 2,838.13 709.53 709.53 709.53 2,128.59
02.01.04.01.02 EXCAVACION A MANO EN TERRENO NORMAL 0.00 347.21 347.21 347.21 347.21 1,388.85 347.21 347.21 347.21 1,041.63
02.01.04.01.03 RELLENO COMPACTADO 0.00 527.38 527.38 527.38 527.38 2,109.54 527.38 527.38 527.38 1,582.15
02.01.04.02 CONCRETO SIMPLE 0.00 0.00 0.00
02.01.04.02.01 CONCRETO F'c=100 kg/cm2, e=0.10 SOLADO 0.00 1,670.40 1,670.40 3,340.80 0.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES 0.00 15,480.39 15,480.39 30,960.78 15,480.39 15,480.39 15,480.39 46,441.16
02.01.04.02.03 CONCRETO PARA SARDINELES f'c=175 kg/cm2 0.00 27,841.18 27,841.18 55,682.35 27,841.18 27,841.18 27,841.18 83,523.53
02.01.04.03 CONCRETO ARMADO 0.00 0.00 0.00
02.01.04.03.01 CONCRETO EN CIMENTACION f'c=175 kg/cm2 0.00 0.00 4,163.52 4,163.52 8,327.04
02.01.04.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 0.00 3,892.32 3,892.32 3,892.32 3,892.32
02.01.04.03.03 ENCOFRADO Y DESENCOFRADO EN MURO 0.00 0.00 7,888.32 7,888.32 15,776.64
02.01.04.03.04 CONCRETO EN MURO FC=175 kg/cm2 0.00 0.00 6,767.84 6,767.84 13,535.68
02.01.04.03.05 ACERO DE REFUERZO fy=4,200 kg/cm2 0.00 0.00 5,622.24 5,622.24 11,244.48
02.01.04.04 REVOQUES 0.00 0.00 0.00
02.01.04.04.01 TARRAJEO EN SARDINELES 0.00 0.00 8,392.67 8,392.67 8,392.67 8,392.67
02.01.04.04.02 TARRAJEO EN MURO DE CONTENCION 0.00 0.00 1,476.80 1,476.80 1,476.80
02.01.05 CUNETAS 0.00 0.00 0.00
02.01.05.01 CONCRETO f'c=210 kg/cm2 PARA CUNETAS 0.00 0.00 25,900.72 25,900.72 25,900.72 25,900.72
02.01.05.02 TARRAJEO Y PULIDO EN CUNETAS 0.00 0.00 6,593.38 6,593.38 6,593.38 6,593.38
02.01.06 JUNTAS 0.00 0.00 0.00
02.01.06.01 JUNTAS ASFALTICAS 0.00 0.00 0.00 13,452.25
02.01.07 SEÑALIZACION 0.00 0.00 0.00
02.01.07.01 MARCAS EN EL PAVIMENTO 0.00 0.00 0.00
02.01.07.01.01 PINTURA EN SARDINELES 0.00 0.00 0.00 2,951.32
02.01.07.01.02 SEÑALIZACION VERTICAL 0.00 0.00 0.00 318.00
02.01.07.01.03 SEÑALIZACION HORIZONTAL 0.00 0.00 0.00 4,308.06
02.01.08 VARIOS 0.00 0.00 0.00
02.01.08.01 REHABILITACION DE SISTEMAS DE AGUA Y DESAGUE 0.00 0.00 0.00
02.01.08.01.01 ENCIMADO DE CAJAS DOMICILIARIAS DE AGUA Y DESAGUE PARA CONSTR 4,973.84 4,973.84 4,973.84 4,973.84 4,973.84 4,973.84 19,895.35 0.00 0.00
02.01.08.01.02 ENCIMADO DE BUZON DE CONCRETO EXISTENTE 4,923.86 4,923.86 4,923.86 4,923.86 4,923.86 4,923.86 19,695.43 0.00 0.00
02.01.08.01.03 INSTALACION DE BUZON DE CONCRETO 4,923.86 4,923.86 4,923.86 4,923.86 4,923.86 4,923.86 19,695.43 0.00 0.00
02.02 CONSTRUCCION DE VEREDAS 0.00 0.00 0.00
02.02.01 TRABAJOS PRELIMINARES 0.00 0.00 0.00
02.02.01.01 TRAZO Y REPLANTEO 7,719.16 0.00 0.00 0.00
02.02.02 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00
02.02.02.01 CORTE SUPERFICIAL MANUAL 16,042.67 16,042.67 0.00 0.00 0.00
02.02.02.02 RELLENO CON MATERIAL DE PRESTAMO SELECCIONADO 33,135.68 33,135.68 33,135.68 33,135.68 0.00 0.00
02.02.02.03 NIVELACION INTERIOR Y APISONADO CON EQUIPO 1,920.19 1,920.19 1,920.19 1,920.19 0.00 0.00
02.02.03 CONCRETO SIMPLE 0.00 0.00 0.00
02.02.03.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS 12,513.09 12,513.09 12,513.09 37,539.26 12,513.09 12,513.09 0.00
02.02.03.02 CONCRETO f'c=140 kg/cm2 EN PISO DE VEREDAS 44,525.22 44,525.22 44,525.22 133,575.65 44,525.22 44,525.22 0.00
02.02.04 OBRAS DE ARTE EN PISOS 0.00 0.00 0.00
02.02.04.01 PISO DE VEREDA CON ADOQUINES DE CONCRETO 34,645.03 34,645.03 34,645.03 103,935.08 34,645.03 34,645.03 34,645.03 34,645.03 138,580.11 34,645.03 34,645.03
03 LIMPIEZA FINAL DE OBRA 0.00 0.00 0.00
03.01 LIMPIEZA FINAL DE OBRA 0.00 0.00 0.00 6,755.90
04 FLETE TERRESTRE 0.00 0.00 0.00
04.01 FLETE TERRESTRE 15,392.57 15,392.57 15,392.57 15,392.57 15,392.57 15,392.57 15,392.57 15,392.57

COSTO DIRECTO TOTAL S/. 33,436.96 16,729.03 87,441.36 91,560.72 162,797.96 204,032.85 196,959.78 169,901.09 172,056.23 99,625.35 249,959.10 190,495.23 216,269.23 162,339.32 162,677.56 160,135.44 163,137.93 146,268.56 40.00 27,825.53
GASTOS GENERALES S/. 1,671.85 836.45 4,372.07 4,578.04 8,139.90 10,201.64 9,847.99 8,495.05 8,602.81 4,981.27 12,497.96 9,524.76 10,813.46 8,116.97 8,133.88 8,006.77 8,156.90 7,313.43 2.00 1,391.28
COSTO DE OBRA S/. 35,108.81 17,565.48 91,813.43 96,138.76 170,937.85 214,234.49 206,807.77 178,396.14 180,659.04 104,606.62 262,457.06 200,019.99 227,082.70 170,456.28 170,811.44 168,142.21 171,294.83 153,581.99 42.00 29,216.81
OBRA: CREACION DE PISTAS Y VEREDAS DE LAS CALLES CENTENARIO, MARISCAL CACERES, 28 DE JULIO,

VALORIZACION D

CONTRATO PRINCIP
METRAD
ITEM DESCRIPCION DE PARTIDA UNIDAD O RE-
ESTRUCT
URADO
01 OBRAS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 8.50X3.60M. SEGÚN DISEÑ und 1.00
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00
01.03 CAMPAMENTO Y ALMACENES glb 1.00
02 PAVIMENTACION
02.01 CONSTRUCCION DE CALZADA DE PAVIMENTO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 TRAZO Y REPLANTEO m2 10,617.51
02.01.02 EXPLANACIONES
02.01.02.01 CORTE DE MATERIAL SEMIROCOSO CON EQUIPO m3 6,204.45
02.01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 2,365.14
02.01.02.03 ELIMINACION DE DESMONTE PROVENIENTE DEL MOVIMIENTO EN T m3 6,871.15
02.01.03 ESTRUCTURA DE PAVIMENTO
02.01.03.01 MEJORAMIENTO DE BASE
02.01.03.01.01 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 10,617.51
02.01.03.01.02 BASE DE AFIRMADO H=0.30 m m2 10,617.51
02.01.03.02 PAVIMENTO RIGIDO
02.01.03.02.01 CONCRETO LOSAS f'c= 210 kg/cm2 m3 1,898.50
02.01.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS m2 972.33
02.01.03.02.03 ACERO LISO DE 3/4" EN LOSA kg 4,551.64
02.01.03.02.04 ACERO LISO DE 1/2" EN LOSA kg 3,800.42
02.01.04 SARDINELES
02.01.04.01 MOVIMIENTO DE TIERRAS
02.01.04.01.01 EXCAVACION PARA SARDINELES m 3,652.00
02.01.04.01.02 EXCAVACION A MANO EN TERRENO NORMAL m3 156.00
02.01.04.01.03 RELLENO COMPACTADO m3 61.60
02.01.04.02 CONCRETO SIMPLE
02.01.04.02.01 CONCRETO F'c=100 kg/cm2, e=0.10 SOLADO m2 120.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES m2 3,317.70
02.01.04.02.03 CONCRETO PARA SARDINELES f'c=175 kg/cm2 m3 366.64
02.01.04.03 CONCRETO ARMADO
02.01.04.03.01 CONCRETO EN CIMENTACION f'c=175 kg/cm2 m3 24.00
02.01.04.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,468.80
02.01.04.03.03 ENCOFRADO Y DESENCOFRADO EN MURO m2 352.00
02.01.04.03.04 CONCRETO EN MURO FC=175 kg/cm2 m3 34.20
02.01.04.03.05 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,121.60
02.01.04.04 REVOQUES
02.01.04.04.01 TARRAJEO EN SARDINELES m2 1,773.10
02.01.04.04.02 TARRAJEO EN MURO DE CONTENCION m2 208.00
02.01.05 CUNETAS
02.01.05.01 CONCRETO f'c=210 kg/cm2 PARA CUNETAS m3 195.61
02.01.05.02 TARRAJEO Y PULIDO EN CUNETAS m2 1,388.08
02.01.06 JUNTAS
02.01.06.01 JUNTAS ASFALTICAS m 3,832.55
02.01.07 SEÑALIZACION
02.01.07.01 MARCAS EN EL PAVIMENTO
02.01.07.01.01 PINTURA EN SARDINELES m 1,891.87
02.01.07.01.02 SEÑALIZACION VERTICAL und 1.00
02.01.07.01.03 SEÑALIZACION HORIZONTAL und 1.00
02.01.08 VARIOS
02.01.08.01 REHABILITACION DE SISTEMAS DE AGUA Y DESAGUE
02.01.08.01.01 ENCIMADO DE CAJAS DOMICILIARIAS DE AGUA Y DESAGUE PARA und 241.00
02.01.08.01.02 ENCIMADO DE BUZON DE CONCRETO EXISTENTE und 38.00
02.01.08.01.03 INSTALACION DE BUZON DE CONCRETO und 20.00
02.02 CONSTRUCCION DE VEREDAS
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 TRAZO Y REPLANTEO m2 3,840.38
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 CORTE SUPERFICIAL MANUAL m3 1,763.90
02.02.02.02 RELLENO CON MATERIAL DE PRESTAMO SELECCIONADO m3 1,141.56
02.02.02.03 NIVELACION INTERIOR Y APISONADO CON EQUIPO m2 3,840.38
02.02.03 CONCRETO SIMPLE
02.02.03.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 2,698.24
02.02.03.02 CONCRETO f'c=140 kg/cm2 EN PISO DE VEREDAS m3 534.34
02.02.04 OBRAS DE ARTE EN PISOS
02.02.04.01 PISO DE VEREDA CON ADOQUINES DE CONCRETO m2 3,840.38
03 LIMPIEZA FINAL DE OBRA
03.01 LIMPIEZA FINAL DE OBRA m2 25,021.86
04 FLETE TERRESTRE
04.01 FLETE TERRESTRE glb 1.00

(A) COSTO DIRECTO

(B) GASTOS GENERALES 15.00 %

(C) UTILIDADES 8.00 %


TOTAL VALORIZADO SIN I.G.V. ( A + B + C ) :

PORCENTAJE DE AVANCE VALORIZADO

REAJUSTE DE VALORIZACION N° 1

R=REAJUSTE
V=VALORIZACION
A=ADELANTO
C=MONTO CONTRACTUAL
K=FACTOR DE MES

N° MES
1.00 ENE

CONTROL DE REAJUSTE

PROGRAMADO
N° MES
V1 ENERO

EJECUTADO
N° MES
V1 ENERO

R
ITEM DESCRIPCION
1.00 MONTO CONTRACTU
1.01 VALORIZACION

2.00 REAJUSTE(R)
2.01 REAJUSTE

3.00 DEDUCCIONES(
3.01 RETENCIONES DE REA

4.00 VALORIZACION BRU


4.01 (VB=V+R-D)

5.00 AMORTIZACIONE
5.01 AMORTIZACIONES POR A

6.00 VALORIZACION NET


6.01 (VB-M)
7.00 MULTAS
7.01 MULTA POR ATRASO DE

8.00 MONTO A PAGAR AL CON


8.01 SUB TOTAL(VN-
8.02 EN IGV(VN*0.18
8.03 MONTO A FACTUR
ARISCAL CACERES, 28 DE JULIO, MANCO CAPAC Y BOLOGNESI DE LA LOCALIDAD DE CAJA, DISTRITO DE CAJA - ACOBAMBA

VALORIZACION DE OBRA N°1

CONTRATO PRINCIPAL VALORIZACIONES CAL


PRECIO VALORIZACION
UNITARI PRESUPUESTO ACUMULADO ACTUAL VALORIZACION ACUM
O ANTERIOR
S/. S/. METRADO S/. METRADO S/. METRADO

1,315.36 1,315.36 0.00 0.00 1.00 1,315.36 1.00


20,000.00 20,000.00 0.00 0.00 1.00 20,000.00 1.00
800.00 800.00 0.00 0.00 0.20 160.00 0.20
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
2.52 26,756.13 0.00 0.00 10,617.51 26,756.13 10,617.51
0.00 0.00 0.00 0.00
4.56 28,292.29 0.00 0.00 3,102.22 14,146.15 3,102.22
6.61 15,633.58 0.00 0.00 0.00 0.00 0.00
4.37 30,026.93 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
4.46 47,354.09 0.00 0.00 2,654.38 11,838.52 2,654.38
41.77 443,493.39 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
396.03 751,862.96 0.00 0.00 0.00 0.00 0.00
33.78 32,845.31 0.00 0.00 0.00 0.00 0.00
7.58 34,501.43 0.00 0.00 0.00 0.00 0.00
6.19 23,524.60 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
1.36 4,966.72 0.00 0.00 0.00 0.00 0.00
15.58 2,430.48 0.00 0.00 0.00 0.00 0.00
59.93 3,691.69 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
27.84 3,340.80 0.00 0.00 0.00 0.00 0.00
23.33 77,401.94 0.00 0.00 0.00 0.00 0.00
379.68 139,205.88 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
346.96 8,327.04 0.00 0.00 0.00 0.00 0.00
5.30 7,784.64 0.00 0.00 0.00 0.00 0.00
44.82 15,776.64 0.00 0.00 0.00 0.00 0.00
395.78 13,535.68 0.00 0.00 0.00 0.00 0.00
5.30 11,244.48 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
14.20 25,178.02 0.00 0.00 0.00 0.00 0.00
14.20 2,953.60 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
397.23 77,702.16 0.00 0.00 0.00 0.00 0.00
14.25 19,780.14 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
3.51 13,452.25 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
1.56 2,951.32 0.00 0.00 0.00 0.00 0.00
318.11 318.11 0.00 0.00 0.00 0.00 0.00
4,308.06 4,308.06 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
123.83 29,843.03 0.00 0.00 80.33 9,947.68 80.33
528.38 20,078.44 0.00 0.00 18.64 9,847.72 18.64
1,892.96 37,859.20 0.00 0.00 5.20 9,847.72 5.20
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
2.01 7,719.16 0.00 0.00 3,840.38 7,719.16 3,840.38
0.00 0.00 0.00 0.00
18.19 32,085.34 0.00 0.00 1,763.90 32,085.34 1,763.90
87.08 99,407.04 0.00 0.00 761.04 66,271.36 761.04
1.50 5,760.57 0.00 0.00 2,560.25 3,840.38 2,560.25
0.00 0.00 0.00 0.00
18.55 50,052.35 0.00 0.00 0.00 0.00 0.00
333.31 178,100.87 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
72.17 277,160.22 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.27 6,755.90 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
76,962.84 76,962.84 0.00 0.00 0.20 15,392.57 0.20
0.00 0.00

2,712,540.67 229,168.08

DE ( A ) 406,881.10 34,375.21

DE ( A ) 217,003.25 18,333.45
3,336,425.03 281,876.73

8.45%

VALORIZACION N° 1

0.00
NTRACTUAL

VALORIZACIK REAJUSTE A CUENTA REAJUSTE MES


281,876.73 1.05

MONTO K REAJUSTE
240,626.48 1.05 11,845.65

MONTO K REAJUSTE
281,876.73 1.05 13,876.33

RESUMEN DE VALORIZACION N° 1 CON K DEL EXPEDIENTE


DESCRIPCION ACUMULADO ANTERIOR MONTO ACTUAL
MONTO CONTRACTUAL(V)
VALORIZACION 0 281,876.73

REAJUSTE(R) 0 13,876.33
REAJUSTE

DEDUCCIONES(D) 0
RETENCIONES DE REAJUSTES 0

VALORIZACION BRUTA(VB) 0
(VB=V+R-D) 295,753.06

AMORTIZACIONES(M) 0
AMORTIZACIONES POR ADELANTO 0

VALORIZACION NETA(VN) 0
(VB-M) 295,753.06
MULTAS 0
MULTA POR ATRASO DE OBRA(M) 0

MONTO A PAGAR AL CONTRATISTA 0


SUB TOTAL(VN-M) 295,753.06
EN IGV(VN*0.18) 53,235.55
MONTO A FACTURAR 348,988.62
RITO DE CAJA - ACOBAMBA - HUANCAVELICA

ACIONES CALCULADAS
VALORIZACION ACUMULADO SALDOS POR VALORIZAR

S/. % METRADO S/. %

1,315.36 100.00 0.00 0.00 0.00


20,000.00 100.00 0.00 0.00 0.00
160.00 20.00 0.80 640.00 80.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
26,756.13 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
14,146.15 50.00 3,102.23 14,146.15 50.00
0.00 0.00 2,365.14 15,633.58 100.00
0.00 0.00 6,871.15 30,026.93 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
11,838.52 25.00 7,963.13 35,515.57 75.00
0.00 0.00 10,617.51 443,493.39 100.00
0.00 0.00 0.00 100.00
0.00 0.00 1,898.50 751,862.96 100.00
0.00 0.00 972.33 32,845.31 100.00
0.00 0.00 4,551.64 34,501.43 100.00
0.00 0.00 3,800.42 23,524.60 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 3,652.00 4,966.72 100.00
0.00 0.00 156.00 2,430.48 100.00
0.00 0.00 61.60 3,691.69 100.00
0.00 0.00 0.00 100.00
0.00 0.00 120.00 3,340.80 100.00
0.00 0.00 3,317.70 77,401.94 100.00
0.00 0.00 366.64 139,205.88 100.00
0.00 0.00 0.00 100.00
0.00 0.00 24.00 8,327.04 100.00
0.00 0.00 1,468.80 7,784.64 100.00
0.00 0.00 352.00 15,776.64 100.00
0.00 0.00 34.20 13,535.68 100.00
0.00 0.00 2,121.60 11,244.48 100.00
0.00 0.00 0.00 100.00
0.00 0.00 1,773.10 25,178.02 100.00
0.00 0.00 208.00 2,953.60 100.00
0.00 0.00 0.00 100.00
0.00 0.00 195.61 77,702.16 100.00
0.00 0.00 1,388.08 19,780.14 100.00
0.00 0.00 0.00 100.00
0.00 0.00 3,832.55 13,452.25 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 1,891.87 2,951.32 100.00
0.00 0.00 1.00 318.11 100.00
0.00 0.00 1.00 4,308.06 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
9,947.68 33.33 160.67 19,895.35 66.67
9,847.72 49.05 19.36 10,230.72 50.95
9,847.72 26.01 14.80 28,011.48 73.99
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
7,719.16 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
32,085.34 100.00 0.00 0.00 0.00
66,271.36 66.67 380.52 33,135.68 33.33
3,840.38 66.67 1,280.13 1,920.19 33.33
0.00 0.00 0.00 100.00
0.00 0.00 2,698.24 50,052.35 100.00
0.00 0.00 534.34 178,100.87 100.00
0.00 0.00 0.00 100.00
0.00 0.00 3,840.38 277,160.22 100.00
0.00 0.00 0.00 100.00
0.00 0.00 25,021.86 6,755.90 100.00
0.00 0.00 0.00 100.00
15,392.57 20.00 0.80 61,570.27 80.00
0.00

229,168.08 2,483,372.60

34,375.21 372,505.89

18,333.45 198,669.81
281,876.73 3,054,548.29

8.45% 91.55%

REAJUSTE DE VALORIZACION N° 1

R=REAJUSTE
V=VALORIZACION
A=ADELANTO 0.00
C=MONTO CONTRACTUAL
K=FACTOR DE MES

N° MES VALORIZACIK
1.00 ENE 281,876.73 1.06

CONTROL DE REAJUSTE

PROGRAMADO
N° MES MONTO K
V1 ENERO 240,626.48 1.06

EJECUTADO
N° MES MONTO K
V1 ENERO 281,876.73 1.06

RESUMEN DE VALORIZACI
ACUMULADO ACTUAL ITEM DESCRIPCION
1.00 MONTO CONTRACTUAL(V)
- 1.01 VALORIZACION
-
4,791.90 2.00 REAJUSTE(R)
- 2.01 REAJUSTE
-
- 3.00 DEDUCCIONES(D)
- 3.01 RETENCIONES DE REAJUSTES
-
- 4.00 VALORIZACION BRUTA(VB)
286,668.64 4.01 (VB=V+R-D)

5.00 AMORTIZACIONES(M)
5.01 AMORTIZACIONES POR ADELANTO

6.00 VALORIZACION NETA(VN)


286,668.64 6.01 (VB-M)
7.00 MULTAS
7.01 MULTA POR ATRASO DE OBRA(M)

8.00 MONTO A PAGAR AL CONTRATISTA


286,668.64 8.01 SUB TOTAL(VN-M)
51,600.35 8.02 EN IGV(VN*0.18)
338,268.99 8.03 MONTO A FACTURAR
REAJUSTE A CUENTA REAJUSTE MES
16,239.99

REAJUSTE
13,863.41

REAJUSTE
16,239.99

RESUMEN DE VALORIZACION N° 1 CON K HALLADO


CION ACUMULADO ANTERIOR MONTO ACTUAL ACUMULADO ACTUAL
ACTUAL(V) - -
ACION 281,876.73 -
-
TE(R) 0.00 16,239.99 -
STE -
-
NES(D) 0 -
E REAJUSTES 0 -
-
BRUTA(VB) 0 -
R-D) 298,116.72 -

ONES(M) 0
POR ADELANTO 0

N NETA(VN) 0
M) 298,116.72 -
AS 0
SO DE OBRA(M) 0

L CONTRATISTA 0
(VN-M) 298,116.72 -
N*0.18) 53,661.01 -
CTURAR 351,777.73 -
OBRA: CREACION DE PISTAS Y VEREDAS DE LAS CALLES CENTENARIO, MARISCAL CACERES, 28 DE JULIO,

VALORIZACION

CONTRATO PRINCIP
METRAD
ITEM DESCRIPCION DE PARTIDA UNIDAD O RE-
ESTRUCT
URADO
01 OBRAS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 8.50X3.60M. SEGÚN DISEÑ und 1.00
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00
01.03 CAMPAMENTO Y ALMACENES glb 1.00
02 PAVIMENTACION
02.01 CONSTRUCCION DE CALZADA DE PAVIMENTO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 TRAZO Y REPLANTEO m2 10,617.51
02.01.02 EXPLANACIONES
02.01.02.01 CORTE DE MATERIAL SEMIROCOSO CON EQUIPO m3 6,204.45
02.01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 2,365.14
02.01.02.03 ELIMINACION DE DESMONTE PROVENIENTE DEL MOVIMIENTO EN T m3 6,871.15
02.01.03 ESTRUCTURA DE PAVIMENTO
02.01.03.01 MEJORAMIENTO DE BASE
02.01.03.01.01 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 10,617.51
02.01.03.01.02 BASE DE AFIRMADO H=0.30 m m2 10,617.51
02.01.03.02 PAVIMENTO RIGIDO
02.01.03.02.01 CONCRETO LOSAS f'c= 210 kg/cm2 m3 1,898.50
02.01.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS m2 972.33
02.01.03.02.03 ACERO LISO DE 3/4" EN LOSA kg 4,551.64
02.01.03.02.04 ACERO LISO DE 1/2" EN LOSA kg 3,800.42
02.01.04 SARDINELES
02.01.04.01 MOVIMIENTO DE TIERRAS
02.01.04.01.01 EXCAVACION PARA SARDINELES m 3,652.00
02.01.04.01.02 EXCAVACION A MANO EN TERRENO NORMAL m3 156.00
02.01.04.01.03 RELLENO COMPACTADO m3 61.60
02.01.04.02 CONCRETO SIMPLE
02.01.04.02.01 CONCRETO F'c=100 kg/cm2, e=0.10 SOLADO m2 120.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES m2 3,317.70
02.01.04.02.03 CONCRETO PARA SARDINELES f'c=175 kg/cm2 m3 366.64
02.01.04.03 CONCRETO ARMADO
02.01.04.03.01 CONCRETO EN CIMENTACION f'c=175 kg/cm2 m3 24.00
02.01.04.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,468.80
02.01.04.03.03 ENCOFRADO Y DESENCOFRADO EN MURO m2 352.00
02.01.04.03.04 CONCRETO EN MURO FC=175 kg/cm2 m3 34.20
02.01.04.03.05 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,121.60
02.01.04.04 REVOQUES
02.01.04.04.01 TARRAJEO EN SARDINELES m2 1,773.10
02.01.04.04.02 TARRAJEO EN MURO DE CONTENCION m2 208.00
02.01.05 CUNETAS
02.01.05.01 CONCRETO f'c=210 kg/cm2 PARA CUNETAS m3 195.61
02.01.05.02 TARRAJEO Y PULIDO EN CUNETAS m2 1,388.08
02.01.06 JUNTAS
02.01.06.01 JUNTAS ASFALTICAS m 3,832.55
02.01.07 SEÑALIZACION
02.01.07.01 MARCAS EN EL PAVIMENTO
02.01.07.01.01 PINTURA EN SARDINELES m 1,891.87
02.01.07.01.02 SEÑALIZACION VERTICAL und 1.00
02.01.07.01.03 SEÑALIZACION HORIZONTAL und 1.00
02.01.08 VARIOS
02.01.08.01 REHABILITACION DE SISTEMAS DE AGUA Y DESAGUE
02.01.08.01.01 ENCIMADO DE CAJAS DOMICILIARIAS DE AGUA Y DESAGUE PARA und 241.00
02.01.08.01.02 ENCIMADO DE BUZON DE CONCRETO EXISTENTE und 38.00
02.01.08.01.03 INSTALACION DE BUZON DE CONCRETO und 20.00
02.02 CONSTRUCCION DE VEREDAS
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 TRAZO Y REPLANTEO m2 3,840.38
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 CORTE SUPERFICIAL MANUAL m3 1,763.90
02.02.02.02 RELLENO CON MATERIAL DE PRESTAMO SELECCIONADO m3 1,141.56
02.02.02.03 NIVELACION INTERIOR Y APISONADO CON EQUIPO m2 3,840.38
02.02.03 CONCRETO SIMPLE
02.02.03.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 2,698.24
02.02.03.02 CONCRETO f'c=140 kg/cm2 EN PISO DE VEREDAS m3 534.34
02.02.04 OBRAS DE ARTE EN PISOS
02.02.04.01 PISO DE VEREDA CON ADOQUINES DE CONCRETO m2 3,840.38
03 LIMPIEZA FINAL DE OBRA
03.01 LIMPIEZA FINAL DE OBRA m2 25,021.86
04 FLETE TERRESTRE
04.01 FLETE TERRESTRE glb 1.00

(A) COSTO DIRECTO

(B) GASTOS GENERALES 15.00 %

(C) UTILIDADES 8.00 %


TOTAL VALORIZADO SIN I.G.V. ( A + B + C ) :

PORCENTAJE DE AVANCE VALORIZADO

CONTROL DE REAJUSTE

PROGRAMADO
N° MES
V1 ENERO
V2 FEBRERO

EJECUTADO
N° MES
V1 ENERO
V2 FEBRERO

ITEM DESCRIPCION
1.00 MONTO CONTRACTU
1.01 VALORIZACION

2.00 REAJUSTE(R)
2.01 REAJUSTE

3.00 DEDUCCIONES(
3.01 RETENCIONES DE REA

4.00 VALORIZACION BRU


4.01 (VB=V+R-D)

5.00 AMORTIZACIONE
5.01 AMORTIZACIONES POR A

6.00 VALORIZACION NET


6.01 (VB-M)

7.00 MULTAS
7.01 MULTA POR ATRASO DE

8.00 MONTO A PAGAR AL CON


8.01 SUB TOTAL(VN-
8.02 EN IGV(VN*0.18
8.03 MONTO A FACTUR
ARISCAL CACERES, 28 DE JULIO, MANCO CAPAC Y BOLOGNESI DE LA LOCALIDAD DE CAJA, DISTRITO DE CAJA - ACOBAMBA

VALORIZACION DE OBRA N°2

CONTRATO PRINCIPAL VALORIZACIONES CA


PRECIO VALORIZACION
UNITARI PRESUPUESTO VALORIZADO ACTUAL VALORIZACION AC
O ANTERIOR
S/. S/. METRADO S/. METRADO S/. METRADO

1,315.36 1,315.36 1.00 1,315.36 0.00 0.00 1.00


20,000.00 20,000.00 1.00 20,000.00 0.00 0.00 1.00
800.00 800.00 0.20 160.00 0.20 160.00 0.40
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
2.52 26,756.13 10,617.51 26,756.13 0.00 0.00 10,617.51
0.00 0.00 0.00 0.00
4.56 28,292.29 3,102.22 14,146.15 3,102.22 14,146.15 6,204.45
6.61 15,633.58 0.00 0.00 2,365.14 15,633.58 2,365.14
4.37 30,026.93 0.00 0.00 6,871.15 30,026.93 6,871.15
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
4.46 47,354.09 2,654.38 11,838.52 7,963.13 35,515.57 10,617.51
41.77 443,493.39 0.00 0.00 6,067.15 253,424.79 6,067.15
0.00 0.00 0.00 0.00
396.03 751,862.96 0.00 0.00 0.00 0.00 0.00
33.78 32,845.31 0.00 0.00 0.00 0.00 0.00
7.58 34,501.43 0.00 0.00 0.00 0.00 0.00
6.19 23,524.60 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
1.36 4,966.72 0.00 0.00 0.00 0.00 0.00
15.58 2,430.48 0.00 0.00 0.00 0.00 0.00
59.93 3,691.69 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
27.84 3,340.80 0.00 0.00 0.00 0.00 0.00
23.33 77,401.94 0.00 0.00 0.00 0.00 0.00
379.68 139,205.88 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
346.96 8,327.04 0.00 0.00 0.00 0.00 0.00
5.30 7,784.64 0.00 0.00 0.00 0.00 0.00
44.82 15,776.64 0.00 0.00 0.00 0.00 0.00
395.78 13,535.68 0.00 0.00 0.00 0.00 0.00
5.30 11,244.48 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
14.20 25,178.02 0.00 0.00 0.00 0.00 0.00
14.20 2,953.60 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
397.23 77,702.16 0.00 0.00 0.00 0.00 0.00
14.25 19,780.14 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
3.51 13,452.25 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
1.56 2,951.32 0.00 0.00 0.00 0.00 0.00
318.11 318.11 0.00 0.00 0.00 0.00 0.00
4,308.06 4,308.06 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
123.83 29,843.03 80.33 9,947.68 160.67 19,895.35 241.00
528.38 20,078.44 18.64 9,847.72 37.28 19,695.43 55.91
1,892.96 37,859.20 5.20 9,847.72 10.40 19,695.43 15.61
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
2.01 7,719.16 3,840.38 7,719.16 0.00 0.00 3,840.38
0.00 0.00 0.00 0.00
18.19 32,085.34 1,763.90 32,085.34 0.00 0.00 1,763.90
87.08 99,407.04 761.04 66,271.36 380.52 33,135.68 1,141.56
1.50 5,760.57 2,560.25 3,840.38 1,280.13 1,920.19 3,840.38
0.00 0.00 0.00 0.00
18.55 50,052.35 0.00 0.00 2,023.68 37,539.26 2,023.68
333.31 178,100.87 0.00 0.00 400.76 133,575.65 400.76
0.00 0.00 0.00 0.00
72.17 277,160.22 0.00 0.00 1,440.14 103,935.08 1,440.14
0.00 0.00 0.00 0.00
0.27 6,755.90 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
76,962.84 76,962.84 0.20 15,392.57 0.20 15,392.57 0.40
0.00

2,712,540.67 733,691.67

DE ( A ) 406,881.10 110,053.75

DE ( A ) 217,003.25 58,695.33
3,336,425.03 902,440.76

27.05%

MONTO K REAJUSTE
240,626.48 1.0492 11,845.65
902,440.76 1.0523 47,199.60

MONTO K REAJUSTE
281,876.73 1.0492 13,876.33
902,440.76 1.05 47,199.60

RESUMEN DE VALORIZACION N° 1 CON K DEL EXPEDIENTE


DESCRIPCION ACUMULADO ANTERIOR MONTO ACTUAL
MONTO CONTRACTUAL(V)
VALORIZACION 0 902,440.76

REAJUSTE(R) 0 13,876.33
REAJUSTE

DEDUCCIONES(D) 0
RETENCIONES DE REAJUSTES 0

VALORIZACION BRUTA(VB) 0
(VB=V+R-D) 916,317.09

AMORTIZACIONES(M) 0
AMORTIZACIONES POR ADELANTO 0

VALORIZACION NETA(VN) 0
(VB-M) 916,317.09

MULTAS 0
MULTA POR ATRASO DE OBRA(M) 0

MONTO A PAGAR AL CONTRATISTA 0


SUB TOTAL(VN-M) 916,317.09
EN IGV(VN*0.18) 164,937.08
MONTO A FACTURAR 1,081,254.17
TO DE CAJA - ACOBAMBA - HUANCAVELICA

ACIONES CALCULADAS
VALORIZACION ACUMULADO SALDOS POR VALORIZAR

S/. % METRADO S/. %

1,315.36 100.00 0.00 0.00 0.00


20,000.00 100.00 0.00 0.00 0.00
320.00 40.00 0.60 480.00 60.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
26,756.13 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
28,292.29 100.00 0.00 0.00 0.00
15,633.58 100.00 0.00 0.00 0.00
30,026.93 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
47,354.09 100.00 0.00 0.00 0.00
253,424.79 57.14 4,550.36 190,068.60 42.86
0.00 0.00 0.00 100.00
0.00 0.00 1,898.50 751,862.96 100.00
0.00 0.00 972.33 32,845.31 100.00
0.00 0.00 4,551.64 34,501.43 100.00
0.00 0.00 3,800.42 23,524.60 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 3,652.00 4,966.72 100.00
0.00 0.00 156.00 2,430.48 100.00
0.00 0.00 61.60 3,691.69 100.00
0.00 0.00 0.00 100.00
0.00 0.00 120.00 3,340.80 100.00
0.00 0.00 3,317.70 77,401.94 100.00
0.00 0.00 366.64 139,205.88 100.00
0.00 0.00 0.00 100.00
0.00 0.00 24.00 8,327.04 100.00
0.00 0.00 1,468.80 7,784.64 100.00
0.00 0.00 352.00 15,776.64 100.00
0.00 0.00 34.20 13,535.68 100.00
0.00 0.00 2,121.60 11,244.48 100.00
0.00 0.00 0.00 100.00
0.00 0.00 1,773.10 25,178.02 100.00
0.00 0.00 208.00 2,953.60 100.00
0.00 0.00 0.00 100.00
0.00 0.00 195.61 77,702.16 100.00
0.00 0.00 1,388.08 19,780.14 100.00
0.00 0.00 0.00 100.00
0.00 0.00 3,832.55 13,452.25 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 1,891.87 2,951.32 100.00
0.00 0.00 1.00 318.11 100.00
0.00 0.00 1.00 4,308.06 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
29,843.03 100.00 0.00 0.00 0.00
29,543.15 147.14 -17.91 -9,464.71 -47.14
29,543.15 78.03 4.39 8,316.05 21.97
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
7,719.16 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
32,085.34 100.00 0.00 0.00 0.00
99,407.04 100.00 0.00 0.00 0.00
5,760.57 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
37,539.26 75.00 674.56 12,513.09 25.00
133,575.65 75.00 133.58 44,525.21 25.00
0.00 0.00 0.00 100.00
103,935.08 37.50 2,400.24 173,225.14 62.50
0.00 0.00 0.00 100.00
0.00 0.00 25,021.86 6,755.90 100.00
0.00 0.00 0.00 100.00
30,785.14 40.00 0.60 46,177.70 60.00
0.00

962,859.75 1,749,680.92

144,428.96 262,452.14

77,028.78 139,974.47
1,184,317.49 2,152,107.54

35.50% 64.50%

CONTROL DE REAJUSTE

PROGRAMADO
N° MES MONTO K
V1 ENERO 240,626.48 1.0576
V2 FEBRERO 902,440.76 1.0602

EJECUTADO
N° MES MONTO K
V1 ENERO 240,626.48 1.0576
V2 FEBRERO 902,440.76 1.0602

RESUMEN DE VALORIZA
ACUMULADO ACTUAL ITEM DESCRIPCION
1.00 MONTO CONTRACTUAL(V)
- 1.01 VALORIZACION
-
4,791.90 2.00 REAJUSTE(R)
- 2.01 REAJUSTE
-
- 3.00 DEDUCCIONES(D)
- 3.01 RETENCIONES DE REAJUSTES
-
- 4.00 VALORIZACION BRUTA(VB)
286,668.64 4.01 (VB=V+R-D)

5.00 AMORTIZACIONES(M)
5.01 AMORTIZACIONES POR ADELANTO

6.00 VALORIZACION NETA(VN)


286,668.64 6.01 (VB-M)

7.00 MULTAS
7.01 MULTA POR ATRASO DE OBRA(M)

8.00 MONTO A PAGAR AL CONTRATISTA


286,668.64 8.01 SUB TOTAL(VN-M)
51,600.35 8.02 EN IGV(VN*0.18)
338,268.99 8.03 MONTO A FACTURAR
REAJUSTE
13,863.41
54,304.09

REAJUSTE
13,863.41
54,304.09

RESUMEN DE VALORIZACION N° 1 CON K HALLADO


CION ACUMULADO ANTERIOR MONTO ACTUAL ACUMULADO ACTUAL
ACTUAL(V) - -
ACION #REF! -
-
TE(R) 0.00 13,863.41 -
STE -
-
NES(D) 0 -
E REAJUSTES 0 -
-
BRUTA(VB) 0 -
R-D) #REF! -

ONES(M) 0
POR ADELANTO 0

N NETA(VN) 0
M) #REF! -

AS 0
SO DE OBRA(M) 0

L CONTRATISTA 0
(VN-M) #REF! -
N*0.18) #REF! -
CTURAR #REF! -
OBRA: CREACION DE PISTAS Y VEREDAS DE LAS CALLES CENTENARIO, MARISCAL CACERES, 28 DE JULIO,

VALORIZACION

CONTRATO PRINCIP
METRAD
ITEM DESCRIPCION DE PARTIDA UNIDAD O RE-
ESTRUCT
URADO
01 OBRAS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 8.50X3.60M. SEGÚN DISEÑ und 1.00
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00
01.03 CAMPAMENTO Y ALMACENES glb 1.00
02 PAVIMENTACION
02.01 CONSTRUCCION DE CALZADA DE PAVIMENTO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 TRAZO Y REPLANTEO m2 10,617.51
02.01.02 EXPLANACIONES
02.01.02.01 CORTE DE MATERIAL SEMIROCOSO CON EQUIPO m3 6,204.45
02.01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 2,365.14
02.01.02.03 ELIMINACION DE DESMONTE PROVENIENTE DEL MOVIMIENTO EN T m3 6,871.15
02.01.03 ESTRUCTURA DE PAVIMENTO
02.01.03.01 MEJORAMIENTO DE BASE
02.01.03.01.01 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 10,617.51
02.01.03.01.02 BASE DE AFIRMADO H=0.30 m m2 10,617.51
02.01.03.02 PAVIMENTO RIGIDO
02.01.03.02.01 CONCRETO LOSAS f'c= 210 kg/cm2 m3 1,898.50
02.01.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS m2 972.33
02.01.03.02.03 ACERO LISO DE 3/4" EN LOSA kg 4,551.64
02.01.03.02.04 ACERO LISO DE 1/2" EN LOSA kg 3,800.42
02.01.04 SARDINELES
02.01.04.01 MOVIMIENTO DE TIERRAS
02.01.04.01.01 EXCAVACION PARA SARDINELES m 3,652.00
02.01.04.01.02 EXCAVACION A MANO EN TERRENO NORMAL m3 156.00
02.01.04.01.03 RELLENO COMPACTADO m3 61.60
02.01.04.02 CONCRETO SIMPLE
02.01.04.02.01 CONCRETO F'c=100 kg/cm2, e=0.10 SOLADO m2 120.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES m2 3,317.70
02.01.04.02.03 CONCRETO PARA SARDINELES f'c=175 kg/cm2 m3 366.64
02.01.04.03 CONCRETO ARMADO
02.01.04.03.01 CONCRETO EN CIMENTACION f'c=175 kg/cm2 m3 24.00
02.01.04.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,468.80
02.01.04.03.03 ENCOFRADO Y DESENCOFRADO EN MURO m2 352.00
02.01.04.03.04 CONCRETO EN MURO FC=175 kg/cm2 m3 34.20
02.01.04.03.05 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,121.60
02.01.04.04 REVOQUES
02.01.04.04.01 TARRAJEO EN SARDINELES m2 1,773.10
02.01.04.04.02 TARRAJEO EN MURO DE CONTENCION m2 208.00
02.01.05 CUNETAS
02.01.05.01 CONCRETO f'c=210 kg/cm2 PARA CUNETAS m3 195.61
02.01.05.02 TARRAJEO Y PULIDO EN CUNETAS m2 1,388.08
02.01.06 JUNTAS
02.01.06.01 JUNTAS ASFALTICAS m 3,832.55
02.01.07 SEÑALIZACION
02.01.07.01 MARCAS EN EL PAVIMENTO
02.01.07.01.01 PINTURA EN SARDINELES m 1,891.87
02.01.07.01.02 SEÑALIZACION VERTICAL und 1.00
02.01.07.01.03 SEÑALIZACION HORIZONTAL und 1.00
02.01.08 VARIOS
02.01.08.01 REHABILITACION DE SISTEMAS DE AGUA Y DESAGUE
02.01.08.01.01 ENCIMADO DE CAJAS DOMICILIARIAS DE AGUA Y DESAGUE PARA und 241.00
02.01.08.01.02 ENCIMADO DE BUZON DE CONCRETO EXISTENTE und 38.00
02.01.08.01.03 INSTALACION DE BUZON DE CONCRETO und 20.00
02.02 CONSTRUCCION DE VEREDAS
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 TRAZO Y REPLANTEO m2 3,840.38
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 CORTE SUPERFICIAL MANUAL m3 1,763.90
02.02.02.02 RELLENO CON MATERIAL DE PRESTAMO SELECCIONADO m3 1,141.56
02.02.02.03 NIVELACION INTERIOR Y APISONADO CON EQUIPO m2 3,840.38
02.02.03 CONCRETO SIMPLE
02.02.03.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 2,698.24
02.02.03.02 CONCRETO f'c=140 kg/cm2 EN PISO DE VEREDAS m3 534.34
02.02.04 OBRAS DE ARTE EN PISOS
02.02.04.01 PISO DE VEREDA CON ADOQUINES DE CONCRETO m2 3,840.38
03 LIMPIEZA FINAL DE OBRA
03.01 LIMPIEZA FINAL DE OBRA m2 25,021.86
04 FLETE TERRESTRE
04.01 FLETE TERRESTRE glb 1.00

(A) COSTO DIRECTO

(B) GASTOS GENERALES 15.00 %

(C) UTILIDADES 8.00 %


TOTAL VALORIZADO SIN I.G.V. ( A + B + C ) :

PORCENTAJE DE AVANCE VALORIZADO

REAJUSTE DE VALORIZACION N° 1

R=REAJUSTE
V=VALORIZACION
A=ADELANTO
C=MONTO CONTRACTUAL
K=FACTOR DE MES

N° MES
1.00 ENE

CONTROL DE REAJUSTE

PROGRAMADO
N° MES
V1 ENERO

EJECUTADO
N° MES
V1 ENERO

ITEM DESCRIPCION
1.00 MONTO CONTRACTU
1.01 VALORIZACION

2.00 REAJUSTE(R)
2.01 REAJUSTE

3.00 DEDUCCIONES(
3.01 RETENCIONES DE REA

4.00 VALORIZACION BRU


4.01 (VB=V+R-D)

5.00 AMORTIZACIONE
5.01 AMORTIZACIONES POR A

6.00 VALORIZACION NET


6.01 (VB-M)
7.00 MULTAS
7.01 MULTA POR ATRASO DE

8.00 MONTO A PAGAR AL CON


8.01 SUB TOTAL(VN-
8.02 EN IGV(VN*0.18
8.03 MONTO A FACTUR
ARISCAL CACERES, 28 DE JULIO, MANCO CAPAC Y BOLOGNESI DE LA LOCALIDAD DE CAJA, DISTRITO DE CAJA - ACOBAMBA

VALORIZACION DE OBRA N° 3

CONTRATO PRINCIPAL VALORIZACIONES CA


PRECIO VALORIZACION
UNITARI PRESUPUESTO VALORIZADO ACTUAL VALORIZACION AC
O ANTERIOR
S/. S/. METRADO S/. METRADO S/. METRADO

1,315.36 1,315.36 1.00 1,315.36 0.00 0.00 1.00


20,000.00 20,000.00 1.00 20,000.00 0.00 0.00 1.00
800.00 800.00 0.40 320.00 0.20 160.00 0.60
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
2.52 26,756.13 10,617.51 26,756.13 0.00 0.00 10,617.51
0.00 0.00 0.00 0.00 0.00
4.56 28,292.29 6,204.45 28,292.29 0.00 0.00 6,204.45
6.61 15,633.58 2,365.14 15,633.58 0.00 0.00 2,365.14
4.37 30,026.93 6,871.15 30,026.93 0.00 0.00 6,871.15
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
4.46 47,354.09 10,617.51 47,354.09 0.00 0.00 10,617.51
41.77 443,493.39 6,067.15 253,424.79 4,550.36 190,068.60 10,617.51
0.00 0.00 0.00 0.00 0.00
396.03 751,862.96 0.00 0.00 474.63 187,965.74 474.63
33.78 32,845.31 0.00 0.00 243.08 8,211.33 243.08
7.58 34,501.43 0.00 0.00 1,137.91 8,625.36 1,137.91
6.19 23,524.60 0.00 0.00 950.11 5,881.15 950.11
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
1.36 4,966.72 0.00 0.00 2,086.86 2,838.13 2,086.86
15.58 2,430.48 0.00 0.00 89.14 1,388.85 89.14
59.93 3,691.69 0.00 0.00 35.20 2,109.54 35.20
0.00 0.00 0.00 0.00 0.00
27.84 3,340.80 0.00 0.00 120.00 3,340.80 120.00
23.33 77,401.94 0.00 0.00 1,327.08 30,960.78 1,327.08
379.68 139,205.88 0.00 0.00 146.66 55,682.35 146.66
0.00 0.00 0.00 0.00 0.00
346.96 8,327.04 0.00 0.00 0.00 0.00 0.00
5.30 7,784.64 0.00 0.00 734.40 3,892.32 734.40
44.82 15,776.64 0.00 0.00 0.00 0.00 0.00
395.78 13,535.68 0.00 0.00 0.00 0.00 0.00
5.30 11,244.48 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
14.20 25,178.02 0.00 0.00 0.00 0.00 0.00
14.20 2,953.60 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
397.23 77,702.16 0.00 0.00 0.00 0.00 0.00
14.25 19,780.14 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
3.51 13,452.25 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
1.56 2,951.32 0.00 0.00 0.00 0.00 0.00
318.11 318.11 0.00 0.00 0.00 0.00 0.00
4,308.06 4,308.06 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
123.83 29,843.03 241.00 29,843.03 0.00 0.00 241.00
528.38 20,078.44 55.91 29,543.15 0.00 0.00 55.91
1,892.96 37,859.20 15.61 29,543.15 0.00 0.00 15.61
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
2.01 7,719.16 3,840.38 7,719.16 0.00 0.00 3,840.38
0.00 0.00 0.00 0.00 0.00
18.19 32,085.34 1,763.90 32,085.34 0.00 0.00 1,763.90
87.08 99,407.04 1,141.56 99,407.04 0.00 0.00 1,141.56
1.50 5,760.57 3,840.38 5,760.57 0.00 0.00 3,840.38
0.00 0.00 0.00 0.00 0.00
18.55 50,052.35 2,023.68 37,539.26 674.56 12,513.09 2,698.24
333.31 178,100.87 400.76 133,575.65 133.59 44,525.22 534.34
0.00 0.00 0.00 0.00 0.00
72.17 277,160.22 1,440.14 103,935.08 1,920.19 138,580.11 3,360.33
0.00 0.00 0.00 0.00 0.00
0.27 6,755.90 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
76,962.84 76,962.84 0.40 30,785.14 0.20 15,392.57 0.60
0.00

2,712,540.67 712,135.91

DE ( A ) 406,881.10 106,820.39

DE ( A ) 217,003.25 56,970.87
3,336,425.03 875,927.17

26.25%

VALORIZACION N° 1

0.00
NTRACTUAL

VALORIZACIK REAJUSTE A CUENTA REAJUSTE MES


281,876.73 1.05

MONTO K REAJUSTE
240,626.48 1.05 12,655.79

MONTO K REAJUSTE
281,876.73 1.05 14,825.35

RESUMEN DE VALORIZACION N° 1 CON K DEL EXPEDIENTE


DESCRIPCION ACUMULADO ANTERIOR MONTO ACTUAL
MONTO CONTRACTUAL(V)
VALORIZACION 0 875,927.17

REAJUSTE(R) 0 14,825.35
REAJUSTE

DEDUCCIONES(D) 0
RETENCIONES DE REAJUSTES 0

VALORIZACION BRUTA(VB) 0
(VB=V+R-D) 890,752.52

AMORTIZACIONES(M) 0
AMORTIZACIONES POR ADELANTO 0

VALORIZACION NETA(VN) 0
(VB-M) 890,752.52
MULTAS 0
MULTA POR ATRASO DE OBRA(M) 0

MONTO A PAGAR AL CONTRATISTA 0


SUB TOTAL(VN-M) 890,752.52
EN IGV(VN*0.18) 160,335.45
MONTO A FACTURAR 1,051,087.98
TO DE CAJA - ACOBAMBA - HUANCAVELICA

ACIONES CALCULADAS
VALORIZACION ACUMULADO SALDOS POR VALORIZAR

S/. % METRADO S/. %

1,315.36 100.00 0.00 0.00 0.00


20,000.00 100.00 0.00 0.00 0.00
480.00 60.00 0.40 320.00 40.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
26,756.13 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
28,292.29 100.00 0.00 0.00 0.00
15,633.58 100.00 0.00 0.00 0.00
30,026.93 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
47,354.09 100.00 0.00 0.00 0.00
443,493.39 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
187,965.74 25.00 1,423.87 563,897.22 75.00
8,211.33 25.00 729.25 24,633.98 75.00
8,625.36 25.00 3,413.73 25,876.07 75.00
5,881.15 25.00 2,850.31 17,643.45 75.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
2,838.13 57.14 1,565.14 2,128.59 42.86
1,388.85 57.14 66.86 1,041.63 42.86
2,109.54 57.14 26.40 1,582.15 42.86
0.00 0.00 0.00 100.00
3,340.80 100.00 0.00 0.00 0.00
30,960.78 40.00 1,990.62 46,441.16 60.00
55,682.35 40.00 219.98 83,523.52 60.00
0.00 0.00 0.00 100.00
0.00 0.00 24.00 8,327.04 100.00
3,892.32 50.00 734.40 3,892.32 50.00
0.00 0.00 352.00 15,776.64 100.00
0.00 0.00 34.20 13,535.68 100.00
0.00 0.00 2,121.60 11,244.48 100.00
0.00 0.00 0.00 100.00
0.00 0.00 1,773.10 25,178.02 100.00
0.00 0.00 208.00 2,953.60 100.00
0.00 0.00 0.00 100.00
0.00 0.00 195.61 77,702.16 100.00
0.00 0.00 1,388.08 19,780.14 100.00
0.00 0.00 0.00 100.00
0.00 0.00 3,832.55 13,452.25 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 1,891.87 2,951.32 100.00
0.00 0.00 1.00 318.11 100.00
0.00 0.00 1.00 4,308.06 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
29,843.03 100.00 0.00 0.00 0.00
29,543.15 147.14 -17.91 -9,464.71 -47.14
29,543.15 78.03 4.39 8,316.05 21.97
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
7,719.16 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
32,085.34 100.00 0.00 0.00 0.00
99,407.04 100.00 0.00 0.00 0.00
5,760.57 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
50,052.35 100.00 0.00 0.00 0.00
178,100.87 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
242,515.19 87.50 480.05 34,645.03 12.50
0.00 0.00 0.00 100.00
0.00 0.00 25,021.86 6,755.90 100.00
0.00 0.00 0.00 100.00
46,177.70 60.00 0.40 30,785.14 40.00
0.00

1,674,995.66 1,037,545.01

251,249.35 155,631.75

133,999.65 83,003.60
2,060,244.66 1,276,180.37

61.75% 38.25%

REAJUSTE DE VALORIZACION N° 1

R=REAJUSTE
V=VALORIZACION
A=ADELANTO 0.00
C=MONTO CONTRACTUAL
K=FACTOR DE MES

N° MES VALORIZACIK
1.00 ENE 875,927.17 1.06

CONTROL DE REAJUSTE

PROGRAMADO
N° MES MONTO K
V1 ENERO 240,626.48 1.06

EJECUTADO
N° MES MONTO K
V1 ENERO 875,927.17 1.06

RESUMEN DE VALORIZA
ACUMULADO ACTUAL ITEM DESCRIPCION
1.00 MONTO CONTRACTUAL(V)
- 1.01 VALORIZACION
-
4,791.90 2.00 REAJUSTE(R)
- 2.01 REAJUSTE
-
- 3.00 DEDUCCIONES(D)
- 3.01 RETENCIONES DE REAJUSTES
-
- 4.00 VALORIZACION BRUTA(VB)
286,668.64 4.01 (VB=V+R-D)

5.00 AMORTIZACIONES(M)
5.01 AMORTIZACIONES POR ADELANTO

6.00 VALORIZACION NETA(VN)


286,668.64 6.01 (VB-M)
7.00 MULTAS
7.01 MULTA POR ATRASO DE OBRA(M)

8.00 MONTO A PAGAR AL CONTRATISTA


286,668.64 8.01 SUB TOTAL(VN-M)
51,600.35 8.02 EN IGV(VN*0.18)
338,268.99 8.03 MONTO A FACTURAR
REAJUSTE A CUENTA REAJUSTE MES
53,671.20

REAJUSTE
14,744.05

REAJUSTE
53,671.20

RESUMEN DE VALORIZACION N° 1 CON K HALLADO


CION ACUMULADO ANTERIOR MONTO ACTUAL ACUMULADO ACTUAL
ACTUAL(V) - -
ACION 875,927.17 -
-
TE(R) 0.00 53,671.20 -
STE -
-
NES(D) 0 -
E REAJUSTES 0 -
-
BRUTA(VB) 0 -
R-D) 929,598.37 -

ONES(M) 0
POR ADELANTO 0

N NETA(VN) 0
M) 929,598.37 -
AS 0
SO DE OBRA(M) 0

L CONTRATISTA 0
(VN-M) 929,598.37 -
N*0.18) 167,327.71 -
CTURAR ### -
OBRA: CREACION DE PISTAS Y VEREDAS DE LAS CALLES CENTENARIO, MARISCAL CACERES, 28 DE JULIO,

VALORIZACION

CONTRATO PRINCIP
METRAD
ITEM DESCRIPCION DE PARTIDA UNIDAD O RE-
ESTRUCT
URADO
01 OBRAS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 8.50X3.60M. SEGÚN DISEÑ und 1.00
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00
01.03 CAMPAMENTO Y ALMACENES glb 1.00
02 PAVIMENTACION
02.01 CONSTRUCCION DE CALZADA DE PAVIMENTO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 TRAZO Y REPLANTEO m2 10,617.51
02.01.02 EXPLANACIONES
02.01.02.01 CORTE DE MATERIAL SEMIROCOSO CON EQUIPO m3 6,204.45
02.01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 2,365.14
02.01.02.03 ELIMINACION DE DESMONTE PROVENIENTE DEL MOVIMIENTO EN T m3 6,871.15
02.01.03 ESTRUCTURA DE PAVIMENTO
02.01.03.01 MEJORAMIENTO DE BASE
02.01.03.01.01 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 10,617.51
02.01.03.01.02 BASE DE AFIRMADO H=0.30 m m2 10,617.51
02.01.03.02 PAVIMENTO RIGIDO
02.01.03.02.01 CONCRETO LOSAS f'c= 210 kg/cm2 m3 1,898.50
02.01.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS m2 972.33
02.01.03.02.03 ACERO LISO DE 3/4" EN LOSA kg 4,551.64
02.01.03.02.04 ACERO LISO DE 1/2" EN LOSA kg 3,800.42
02.01.04 SARDINELES
02.01.04.01 MOVIMIENTO DE TIERRAS
02.01.04.01.01 EXCAVACION PARA SARDINELES m 3,652.00
02.01.04.01.02 EXCAVACION A MANO EN TERRENO NORMAL m3 156.00
02.01.04.01.03 RELLENO COMPACTADO m3 61.60
02.01.04.02 CONCRETO SIMPLE
02.01.04.02.01 CONCRETO F'c=100 kg/cm2, e=0.10 SOLADO m2 120.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES m2 3,317.70
02.01.04.02.03 CONCRETO PARA SARDINELES f'c=175 kg/cm2 m3 366.64
02.01.04.03 CONCRETO ARMADO
02.01.04.03.01 CONCRETO EN CIMENTACION f'c=175 kg/cm2 m3 24.00
02.01.04.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,468.80
02.01.04.03.03 ENCOFRADO Y DESENCOFRADO EN MURO m2 352.00
02.01.04.03.04 CONCRETO EN MURO FC=175 kg/cm2 m3 34.20
02.01.04.03.05 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,121.60
02.01.04.04 REVOQUES
02.01.04.04.01 TARRAJEO EN SARDINELES m2 1,773.10
02.01.04.04.02 TARRAJEO EN MURO DE CONTENCION m2 208.00
02.01.05 CUNETAS
02.01.05.01 CONCRETO f'c=210 kg/cm2 PARA CUNETAS m3 195.61
02.01.05.02 TARRAJEO Y PULIDO EN CUNETAS m2 1,388.08
02.01.06 JUNTAS
02.01.06.01 JUNTAS ASFALTICAS m 3,832.55
02.01.07 SEÑALIZACION
02.01.07.01 MARCAS EN EL PAVIMENTO
02.01.07.01.01 PINTURA EN SARDINELES m 1,891.87
02.01.07.01.02 SEÑALIZACION VERTICAL und 1.00
02.01.07.01.03 SEÑALIZACION HORIZONTAL und 1.00
02.01.08 VARIOS
02.01.08.01 REHABILITACION DE SISTEMAS DE AGUA Y DESAGUE
02.01.08.01.01 ENCIMADO DE CAJAS DOMICILIARIAS DE AGUA Y DESAGUE PARA und 241.00
02.01.08.01.02 ENCIMADO DE BUZON DE CONCRETO EXISTENTE und 38.00
02.01.08.01.03 INSTALACION DE BUZON DE CONCRETO und 20.00
02.02 CONSTRUCCION DE VEREDAS
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 TRAZO Y REPLANTEO m2 3,840.38
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 CORTE SUPERFICIAL MANUAL m3 1,763.90
02.02.02.02 RELLENO CON MATERIAL DE PRESTAMO SELECCIONADO m3 1,141.56
02.02.02.03 NIVELACION INTERIOR Y APISONADO CON EQUIPO m2 3,840.38
02.02.03 CONCRETO SIMPLE
02.02.03.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 2,698.24
02.02.03.02 CONCRETO f'c=140 kg/cm2 EN PISO DE VEREDAS m3 534.34
02.02.04 OBRAS DE ARTE EN PISOS
02.02.04.01 PISO DE VEREDA CON ADOQUINES DE CONCRETO m2 3,840.38
03 LIMPIEZA FINAL DE OBRA
03.01 LIMPIEZA FINAL DE OBRA m2 25,021.86
04 FLETE TERRESTRE
04.01 FLETE TERRESTRE glb 1.00

(A) COSTO DIRECTO

(B) GASTOS GENERALES 15.00 %

(C) UTILIDADES 8.00 %


TOTAL VALORIZADO SIN I.G.V. ( A + B + C ) :

PORCENTAJE DE AVANCE VALORIZADO

REAJUSTE DE VALORIZACION N° 1

R=REAJUSTE
V=VALORIZACION
A=ADELANTO
C=MONTO CONTRACTUAL
K=FACTOR DE MES

N° MES
1.00 ENE

CONTROL DE REAJUSTE

PROGRAMADO
N° MES
V1 ENERO

EJECUTADO
N° MES
V1 ENERO

ITEM DESCRIPCION
1.00 MONTO CONTRACTU
1.01 VALORIZACION

2.00 REAJUSTE(R)
2.01 REAJUSTE

3.00 DEDUCCIONES(
3.01 RETENCIONES DE REA

4.00 VALORIZACION BRU


4.01 (VB=V+R-D)

5.00 AMORTIZACIONE
5.01 AMORTIZACIONES POR A

6.00 VALORIZACION NET


6.01 (VB-M)
7.00 MULTAS
7.01 MULTA POR ATRASO DE

8.00 MONTO A PAGAR AL CON


8.01 SUB TOTAL(VN-
8.02 EN IGV(VN*0.18
8.03 MONTO A FACTUR
ARISCAL CACERES, 28 DE JULIO, MANCO CAPAC Y BOLOGNESI DE LA LOCALIDAD DE CAJA, DISTRITO DE CAJA - ACOBAMBA

VALORIZACION DE OBRA N° 4

CONTRATO PRINCIPAL VALORIZACIONES CA


PRECIO VALORIZACION
UNITARI PRESUPUESTO VALORIZADO ACTUAL VALORIZACION AC
O ANTERIOR
S/. S/. METRADO S/. METRADO S/. METRADO

1,315.36 1,315.36 1.00 1,315.36 0.00 0.00 1.00


20,000.00 20,000.00 1.00 20,000.00 0.00 0.00 1.00
800.00 800.00 0.60 480.00 0.20 160.00 0.80
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
2.52 26,756.13 10,617.51 26,756.13 0.00 0.00 10,617.51
0.00 0.00 0.00 0.00 0.00
4.56 28,292.29 6,204.45 28,292.29 0.00 0.00 6,204.45
6.61 15,633.58 2,365.14 15,633.58 0.00 0.00 2,365.14
4.37 30,026.93 6,871.15 30,026.93 0.00 0.00 6,871.15
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
4.46 47,354.09 10,617.51 47,354.09 0.00 0.00 10,617.51
41.77 443,493.39 10,617.51 443,493.39 0.00 0.00 10,617.51
0.00 0.00 0.00 0.00 0.00
396.03 751,862.96 474.63 187,965.74 949.25 375,931.48 1,423.88
33.78 32,845.31 243.08 8,211.33 486.17 16,422.66 729.25
7.58 34,501.43 1,137.91 8,625.36 2,275.82 17,250.72 3,413.73
6.19 23,524.60 950.11 5,881.15 1,900.21 11,762.30 2,850.32
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
1.36 4,966.72 2,086.86 2,838.13 1,565.14 2,128.59 3,652.00
15.58 2,430.48 89.14 1,388.85 66.86 1,041.63 156.00
59.93 3,691.69 35.20 2,109.54 26.40 1,582.15 61.60
0.00 0.00 0.00 0.00 0.00
27.84 3,340.80 120.00 3,340.80 0.00 0.00 120.00
23.33 77,401.94 1,327.08 30,960.78 1,990.62 46,441.16 3,317.70
379.68 139,205.88 146.66 55,682.35 219.98 83,523.53 366.64
0.00 0.00 0.00 0.00 0.00
346.96 8,327.04 0.00 0.00 24.00 8,327.04 24.00
5.30 7,784.64 734.40 3,892.32 734.40 3,892.32 1,468.80
44.82 15,776.64 0.00 0.00 352.00 15,776.64 352.00
395.78 13,535.68 0.00 0.00 34.20 13,535.68 34.20
5.30 11,244.48 0.00 0.00 2,121.60 11,244.48 2,121.60
0.00 0.00 0.00 0.00 0.00
14.20 25,178.02 0.00 0.00 591.03 8,392.67 591.03
14.20 2,953.60 0.00 0.00 104.00 1,476.80 104.00
0.00 0.00 0.00 0.00 0.00
397.23 77,702.16 0.00 0.00 65.20 25,900.72 65.20
14.25 19,780.14 0.00 0.00 462.69 6,593.38 462.69
0.00 0.00 0.00 0.00 0.00
3.51 13,452.25 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
1.56 2,951.32 0.00 0.00 0.00 0.00 0.00
318.11 318.11 0.00 0.00 0.00 0.00 0.00
4,308.06 4,308.06 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
123.83 29,843.03 241.00 29,843.03 0.00 0.00 241.00
528.38 20,078.44 55.91 29,543.15 0.00 0.00 55.91
1,892.96 37,859.20 15.61 29,543.15 0.00 0.00 15.61
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
2.01 7,719.16 3,840.38 7,719.16 0.00 0.00 3,840.38
0.00 0.00 0.00 0.00 0.00
18.19 32,085.34 1,763.90 32,085.34 0.00 0.00 1,763.90
87.08 99,407.04 1,141.56 99,407.04 0.00 0.00 1,141.56
1.50 5,760.57 3,840.38 5,760.57 0.00 0.00 3,840.38
0.00 0.00 0.00 0.00 0.00
18.55 50,052.35 2,698.24 50,052.35 0.00 0.00 2,698.24
333.31 178,100.87 534.34 178,100.87 0.00 0.00 534.34
0.00 0.00 0.00 0.00 0.00
72.17 277,160.22 3,360.33 242,515.19 480.05 34,645.03 3,840.38
0.00 0.00 0.00 0.00 0.00
0.27 6,755.90 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
76,962.84 76,962.84 0.60 46,177.70 0.20 15,392.57 0.80
0.00

2,712,540.67 701,421.55

DE ( A ) 406,881.10 105,213.23

DE ( A ) 217,003.25 56,113.72
3,336,425.03 862,748.51

25.86%

VALORIZACION N° 1

0.00
NTRACTUAL

VALORIZACIK REAJUSTE A CUENTA REAJUSTE MES


281,876.73 1.05

MONTO K REAJUSTE
240,626.48 1.05 12,258.32

MONTO K REAJUSTE
281,876.73 1.05 14,359.75

RESUMEN DE VALORIZACION N° 1 CON K DEL EXPEDIENTE


DESCRIPCION ACUMULADO ANTERIOR MONTO ACTUAL
MONTO CONTRACTUAL(V)
VALORIZACION 0 862,748.51

REAJUSTE(R) 0 14,359.75
REAJUSTE

DEDUCCIONES(D) 0
RETENCIONES DE REAJUSTES 0

VALORIZACION BRUTA(VB) 0
(VB=V+R-D) 877,108.26

AMORTIZACIONES(M) 0
AMORTIZACIONES POR ADELANTO 0

VALORIZACION NETA(VN) 0
(VB-M) 877,108.26
MULTAS 0
MULTA POR ATRASO DE OBRA(M) 0

MONTO A PAGAR AL CONTRATISTA 0


SUB TOTAL(VN-M) 877,108.26
EN IGV(VN*0.18) 157,879.49
MONTO A FACTURAR 1,034,987.75
TO DE CAJA - ACOBAMBA - HUANCAVELICA

ACIONES CALCULADAS
VALORIZACION ACUMULADO SALDOS POR VALORIZAR

S/. % METRADO S/. %

1,315.36 100.00 0.00 0.00 0.00


20,000.00 100.00 0.00 0.00 0.00
640.00 80.00 0.20 160.00 20.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
26,756.13 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
28,292.29 100.00 0.00 0.00 0.00
15,633.58 100.00 0.00 0.00 0.00
30,026.93 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
47,354.09 100.00 0.00 0.00 0.00
443,493.39 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
563,897.22 75.00 474.62 187,965.74 25.00
24,633.98 75.00 243.08 8,211.32 25.00
25,876.07 75.00 1,137.91 8,625.36 25.00
17,643.45 75.00 950.10 5,881.15 25.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
4,966.72 100.00 0.00 0.00 0.00
2,430.48 100.00 0.00 0.00 0.00
3,691.69 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
3,340.80 100.00 0.00 0.00 0.00
77,401.94 100.00 0.00 0.00 0.00
139,205.88 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
8,327.04 100.00 0.00 0.00 0.00
7,784.64 100.00 0.00 0.00 0.00
15,776.64 100.00 0.00 0.00 0.00
13,535.68 100.00 0.00 0.00 0.00
11,244.48 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
8,392.67 33.33 1,182.07 16,785.35 66.67
1,476.80 50.00 104.00 1,476.80 50.00
0.00 0.00 0.00 100.00
25,900.72 33.33 130.41 51,801.44 66.67
6,593.38 33.33 925.39 13,186.76 66.67
0.00 0.00 0.00 100.00
0.00 0.00 3,832.55 13,452.25 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
0.00 0.00 1,891.87 2,951.32 100.00
0.00 0.00 1.00 318.11 100.00
0.00 0.00 1.00 4,308.06 100.00
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
29,843.03 100.00 0.00 0.00 0.00
29,543.15 147.14 -17.91 -9,464.71 -47.14
29,543.15 78.03 4.39 8,316.05 21.97
0.00 0.00 0.00 100.00
0.00 0.00 0.00 100.00
7,719.16 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
32,085.34 100.00 0.00 0.00 0.00
99,407.04 100.00 0.00 0.00 0.00
5,760.57 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
50,052.35 100.00 0.00 0.00 0.00
178,100.87 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
277,160.22 100.00 0.00 0.00 0.00
0.00 0.00 0.00 100.00
0.00 0.00 25,021.86 6,755.90 100.00
0.00 0.00 0.00 100.00
61,570.27 80.00 0.20 15,392.57 20.00
0.00

2,376,417.21 336,123.46

356,462.58 50,418.52

190,113.38 26,889.88
2,922,993.17 413,431.86

87.61% 12.39%

REAJUSTE DE VALORIZACION N° 1

R=REAJUSTE
V=VALORIZACION
A=ADELANTO 0.00
C=MONTO CONTRACTUAL
K=FACTOR DE MES

N° MES VALORIZACIK
1.00 ENE 862,748.51 1.06

CONTROL DE REAJUSTE

PROGRAMADO
N° MES MONTO K
V1 ENERO 240,626.48 1.06

EJECUTADO
N° MES MONTO K
V1 ENERO 862,748.51 1.06

RESUMEN DE VALORIZA
ACUMULADO ACTUAL ITEM DESCRIPCION
1.00 MONTO CONTRACTUAL(V)
- 1.01 VALORIZACION
-
4,791.90 2.00 REAJUSTE(R)
- 2.01 REAJUSTE
-
- 3.00 DEDUCCIONES(D)
- 3.01 RETENCIONES DE REAJUSTES
-
- 4.00 VALORIZACION BRUTA(VB)
286,668.64 4.01 (VB=V+R-D)

5.00 AMORTIZACIONES(M)
5.01 AMORTIZACIONES POR ADELANTO

6.00 VALORIZACION NETA(VN)


286,668.64 6.01 (VB-M)
7.00 MULTAS
7.01 MULTA POR ATRASO DE OBRA(M)

8.00 MONTO A PAGAR AL CONTRATISTA


286,668.64 8.01 SUB TOTAL(VN-M)
51,600.35 8.02 EN IGV(VN*0.18)
338,268.99 8.03 MONTO A FACTURAR
REAJUSTE A CUENTA REAJUSTE MES
50,553.81

REAJUSTE
14,099.81

REAJUSTE
50,553.81

RESUMEN DE VALORIZACION N° 1 CON K HALLADO


CION ACUMULADO ANTERIOR MONTO ACTUAL ACUMULADO ACTUAL
ACTUAL(V) - -
ACION 862,748.51 -
-
TE(R) 0.00 50,553.81 -
STE -
-
NES(D) 0 -
E REAJUSTES 0 -
-
BRUTA(VB) 0 -
R-D) 913,302.32 -

ONES(M) 0
POR ADELANTO 0

N NETA(VN) 0
M) 913,302.32 -
AS 0
SO DE OBRA(M) 0

L CONTRATISTA 0
(VN-M) 913,302.32 -
N*0.18) 164,394.42 -
CTURAR ### -
OBRA: CREACION DE PISTAS Y VEREDAS DE LAS CALLES CENTENARIO, MARISCAL CACERES, 28 DE JULIO,

VALORIZACION

CONTRATO PRINCIP
METRAD
ITEM DESCRIPCION DE PARTIDA UNIDAD O RE-
ESTRUCT
URADO
01 OBRAS PRELIMINARES
01.01 CARTEL DE IDENTIFICACION DE OBRA DE 8.50X3.60M. SEGÚN DISEÑ und 1.00
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00
01.03 CAMPAMENTO Y ALMACENES glb 1.00
02 PAVIMENTACION
02.01 CONSTRUCCION DE CALZADA DE PAVIMENTO
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 TRAZO Y REPLANTEO m2 10,617.51
02.01.02 EXPLANACIONES
02.01.02.01 CORTE DE MATERIAL SEMIROCOSO CON EQUIPO m3 6,204.45
02.01.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 2,365.14
02.01.02.03 ELIMINACION DE DESMONTE PROVENIENTE DEL MOVIMIENTO EN T m3 6,871.15
02.01.03 ESTRUCTURA DE PAVIMENTO
02.01.03.01 MEJORAMIENTO DE BASE
02.01.03.01.01 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 10,617.51
02.01.03.01.02 BASE DE AFIRMADO H=0.30 m m2 10,617.51
02.01.03.02 PAVIMENTO RIGIDO
02.01.03.02.01 CONCRETO LOSAS f'c= 210 kg/cm2 m3 1,898.50
02.01.03.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS m2 972.33
02.01.03.02.03 ACERO LISO DE 3/4" EN LOSA kg 4,551.64
02.01.03.02.04 ACERO LISO DE 1/2" EN LOSA kg 3,800.42
02.01.04 SARDINELES
02.01.04.01 MOVIMIENTO DE TIERRAS
02.01.04.01.01 EXCAVACION PARA SARDINELES m 3,652.00
02.01.04.01.02 EXCAVACION A MANO EN TERRENO NORMAL m3 156.00
02.01.04.01.03 RELLENO COMPACTADO m3 61.60
02.01.04.02 CONCRETO SIMPLE
02.01.04.02.01 CONCRETO F'c=100 kg/cm2, e=0.10 SOLADO m2 120.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN SARDINELES m2 3,317.70
02.01.04.02.03 CONCRETO PARA SARDINELES f'c=175 kg/cm2 m3 366.64
02.01.04.03 CONCRETO ARMADO
02.01.04.03.01 CONCRETO EN CIMENTACION f'c=175 kg/cm2 m3 24.00
02.01.04.03.02 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,468.80
02.01.04.03.03 ENCOFRADO Y DESENCOFRADO EN MURO m2 352.00
02.01.04.03.04 CONCRETO EN MURO FC=175 kg/cm2 m3 34.20
02.01.04.03.05 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 2,121.60
02.01.04.04 REVOQUES
02.01.04.04.01 TARRAJEO EN SARDINELES m2 1,773.10
02.01.04.04.02 TARRAJEO EN MURO DE CONTENCION m2 208.00
02.01.05 CUNETAS
02.01.05.01 CONCRETO f'c=210 kg/cm2 PARA CUNETAS m3 195.61
02.01.05.02 TARRAJEO Y PULIDO EN CUNETAS m2 1,388.08
02.01.06 JUNTAS
02.01.06.01 JUNTAS ASFALTICAS m 3,832.55
02.01.07 SEÑALIZACION
02.01.07.01 MARCAS EN EL PAVIMENTO
02.01.07.01.01 PINTURA EN SARDINELES m 1,891.87
02.01.07.01.02 SEÑALIZACION VERTICAL und 1.00
02.01.07.01.03 SEÑALIZACION HORIZONTAL und 1.00
02.01.08 VARIOS
02.01.08.01 REHABILITACION DE SISTEMAS DE AGUA Y DESAGUE
02.01.08.01.01 ENCIMADO DE CAJAS DOMICILIARIAS DE AGUA Y DESAGUE PARA und 241.00
02.01.08.01.02 ENCIMADO DE BUZON DE CONCRETO EXISTENTE und 38.00
02.01.08.01.03 INSTALACION DE BUZON DE CONCRETO und 20.00
02.02 CONSTRUCCION DE VEREDAS
02.02.01 TRABAJOS PRELIMINARES
02.02.01.01 TRAZO Y REPLANTEO m2 3,840.38
02.02.02 MOVIMIENTO DE TIERRAS
02.02.02.01 CORTE SUPERFICIAL MANUAL m3 1,763.90
02.02.02.02 RELLENO CON MATERIAL DE PRESTAMO SELECCIONADO m3 1,141.56
02.02.02.03 NIVELACION INTERIOR Y APISONADO CON EQUIPO m2 3,840.38
02.02.03 CONCRETO SIMPLE
02.02.03.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 2,698.24
02.02.03.02 CONCRETO f'c=140 kg/cm2 EN PISO DE VEREDAS m3 534.34
02.02.04 OBRAS DE ARTE EN PISOS
02.02.04.01 PISO DE VEREDA CON ADOQUINES DE CONCRETO m2 3,840.38
03 LIMPIEZA FINAL DE OBRA
03.01 LIMPIEZA FINAL DE OBRA m2 25,021.86
04 FLETE TERRESTRE
04.01 FLETE TERRESTRE glb 1.00

(A) COSTO DIRECTO

(B) GASTOS GENERALES 15.00 %

(C) UTILIDADES 8.00 %


TOTAL VALORIZADO SIN I.G.V. ( A + B + C ) :

PORCENTAJE DE AVANCE VALORIZADO

REAJUSTE DE VALORIZACION N° 1

R=REAJUSTE
V=VALORIZACION
A=ADELANTO
C=MONTO CONTRACTUAL
K=FACTOR DE MES

N° MES
1.00 ENE

CONTROL DE REAJUSTE

PROGRAMADO
N° MES
V1 ENERO

EJECUTADO
N° MES
V1 ENERO

ITEM DESCRIPCION
1.00 MONTO CONTRACTU
1.01 VALORIZACION

2.00 REAJUSTE(R)
2.01 REAJUSTE

3.00 DEDUCCIONES(
3.01 RETENCIONES DE REA

4.00 VALORIZACION BRU


4.01 (VB=V+R-D)

5.00 AMORTIZACIONE
5.01 AMORTIZACIONES POR A

6.00 VALORIZACION NET


6.01 (VB-M)
7.00 MULTAS
7.01 MULTA POR ATRASO DE

8.00 MONTO A PAGAR AL CON


8.01 SUB TOTAL(VN-
8.02 EN IGV(VN*0.18
8.03 MONTO A FACTUR
ARISCAL CACERES, 28 DE JULIO, MANCO CAPAC Y BOLOGNESI DE LA LOCALIDAD DE CAJA, DISTRITO DE CAJA - ACOBAMBA

VALORIZACION DE OBRA N° 5

CONTRATO PRINCIPAL VALORIZACIONES CA


PRECIO VALORIZACION
UNITARI PRESUPUESTO VALORIZADO ACTUAL VALORIZACION AC
O ANTERIOR
S/. S/. METRADO S/. METRADO S/. METRADO

1,315.36 1,315.36 1.00 1,315.36 0.00 0.00 1.00


20,000.00 20,000.00 1.00 20,000.00 0.00 0.00 1.00
800.00 800.00 0.80 640.00 0.20 160.00 1.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
2.52 26,756.13 10,617.51 26,756.13 0.00 0.00 10,617.51
0.00 0.00 0.00 0.00 0.00
4.56 28,292.29 6,204.45 28,292.29 0.00 0.00 6,204.45
6.61 15,633.58 2,365.14 15,633.58 0.00 0.00 2,365.14
4.37 30,026.93 6,871.15 30,026.93 0.00 0.00 6,871.15
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
4.46 47,354.09 10,617.51 47,354.09 0.00 0.00 10,617.51
41.77 443,493.39 10,617.51 443,493.39 0.00 0.00 10,617.51
0.00 0.00 0.00 0.00 0.00
396.03 751,862.96 1,423.88 563,897.22 474.63 187,965.74 1,898.50
33.78 32,845.31 729.25 24,633.98 243.08 8,211.33 972.33
7.58 34,501.43 3,413.73 25,876.07 1,137.91 8,625.36 4,551.64
6.19 23,524.60 2,850.32 17,643.45 950.11 5,881.15 3,800.42
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
1.36 4,966.72 3,652.00 4,966.72 0.00 0.00 3,652.00
15.58 2,430.48 156.00 2,430.48 0.00 0.00 156.00
59.93 3,691.69 61.60 3,691.69 0.00 0.00 61.60
0.00 0.00 0.00 0.00 0.00
27.84 3,340.80 120.00 3,340.80 0.00 0.00 120.00
23.33 77,401.94 3,317.70 77,401.94 0.00 0.00 3,317.70
379.68 139,205.88 366.64 139,205.88 0.00 0.00 366.64
0.00 0.00 0.00 0.00 0.00
346.96 8,327.04 24.00 8,327.04 0.00 0.00 24.00
5.30 7,784.64 1,468.80 7,784.64 0.00 0.00 1,468.80
44.82 15,776.64 352.00 15,776.64 0.00 0.00 352.00
395.78 13,535.68 34.20 13,535.68 0.00 0.00 34.20
5.30 11,244.48 2,121.60 11,244.48 0.00 0.00 2,121.60
0.00 0.00 0.00 0.00 0.00
14.20 25,178.02 591.03 8,392.67 1,182.07 16,785.35 1,773.10
14.20 2,953.60 104.00 1,476.80 104.00 1,476.80 208.00
0.00 0.00 0.00 0.00 0.00
397.23 77,702.16 65.20 25,900.72 130.41 51,801.44 195.61
14.25 19,780.14 462.69 6,593.38 925.39 13,186.76 1,388.08
0.00 0.00 0.00 0.00 0.00
3.51 13,452.25 0.00 0.00 3,832.55 13,452.25 3,832.55
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
1.56 2,951.32 0.00 0.00 1,891.87 2,951.32 1,891.87
318.11 318.11 0.00 0.00 3.40 318.00 3.40
4,308.06 4,308.06 0.00 0.00 1.00 4,308.06 1.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
123.83 29,843.03 241.00 29,843.03 0.00 0.00 241.00
528.38 20,078.44 55.91 29,543.15 0.00 0.00 55.91
1,892.96 37,859.20 15.61 29,543.15 0.00 0.00 15.61
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
2.01 7,719.16 3,840.38 7,719.16 0.00 0.00 3,840.38
0.00 0.00 0.00 0.00 0.00
18.19 32,085.34 1,763.90 32,085.34 0.00 0.00 1,763.90
87.08 99,407.04 1,141.56 99,407.04 0.00 0.00 1,141.56
1.50 5,760.57 3,840.38 5,760.57 0.00 0.00 3,840.38
0.00 0.00 0.00 0.00 0.00
18.55 50,052.35 2,698.24 50,052.35 0.00 0.00 2,698.24
333.31 178,100.87 534.34 178,100.87 0.00 0.00 534.34
0.00 0.00 0.00 0.00 0.00
72.17 277,160.22 3,840.38 277,160.22 0.00 0.00 3,840.38
0.00 0.00 0.00 0.00 0.00
0.27 6,755.90 0.00 0.00 25,021.85 6,755.90 25,021.85
0.00 0.00 0.00 0.00 0.00
76,962.84 76,962.84 0.80 61,570.27 0.20 15,392.57 1.00
0.00 0.00

2,712,540.67 337,272.02

DE ( A ) 406,881.10 50,590.80

DE ( A ) 217,003.25 26,981.76
3,336,425.03 414,844.58

12.43%

VALORIZACION N° 1

0.00
NTRACTUAL

VALORIZACIK REAJUSTE A CUENTA REAJUSTE MES


281,876.73 1.05

MONTO K REAJUSTE
240,626.48 1.05 11,659.91

MONTO K REAJUSTE
281,876.73 1.05 13,658.75

RESUMEN DE VALORIZACION N° 1 CON K DEL EXPEDIENTE


DESCRIPCION ACUMULADO ANTERIOR MONTO ACTUAL
MONTO CONTRACTUAL(V)
VALORIZACION 0 414,844.58

REAJUSTE(R) 0 13,658.75
REAJUSTE

DEDUCCIONES(D) 0
RETENCIONES DE REAJUSTES 0

VALORIZACION BRUTA(VB) 0
(VB=V+R-D) 428,503.34

AMORTIZACIONES(M) 0
AMORTIZACIONES POR ADELANTO 0

VALORIZACION NETA(VN) 0
(VB-M) 428,503.34
MULTAS 0
MULTA POR ATRASO DE OBRA(M) 0

MONTO A PAGAR AL CONTRATISTA 0


SUB TOTAL(VN-M) 428,503.34
EN IGV(VN*0.18) 77,130.60
MONTO A FACTURAR 505,633.94
TO DE CAJA - ACOBAMBA - HUANCAVELICA

ACIONES CALCULADAS
VALORIZACION ACUMULADO SALDOS POR VALORIZAR

S/. % METRADO S/. %

1,315.36 100.00 0.00 0.00 0.00 1


20,000.00 100.00 0.00 0.00 0.00 1
800.00 100.00 0.00 0.00 0.00 1
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
26,756.13 100.00 0.00 0.00 0.00 10617.5119
0.00 0.00 0.00
28,292.29 100.00 0.00 0.00 0.00 6204.44956
15,633.58 100.00 0.00 0.00 0.00 2365.1407
30,026.93 100.00 0.00 0.00 0.00 6871.15103
0.00 0.00 0.00
0.00 0.00 0.00
47,354.09 100.00 0.00 0.00 0.00 10617.509
443,493.39 100.00 0.00 0.00 0.00 10617.5099
0.00 0.00 0.00
751,862.96 100.00 0.00 -0.01 0.00 1898.50001
32,845.31 100.00 0.00 0.00 0.00 972.330077
34,501.43 100.00 0.00 0.00 0.00 4551.63984
23,524.60 100.00 0.00 0.00 0.00 3800.42003
0.00 0.00 0.00
0.00 0.00 0.00
4,966.72 100.00 0.00 0.00 0.00 3652
2,430.48 100.00 0.00 0.00 0.00 156
3,691.69 100.00 0.00 0.00 0.00 61.6000334
0.00 0.00 0.00
3,340.80 100.00 0.00 0.00 0.00 120
77,401.94 100.00 0.00 0.00 0.00 3317.69996
139,205.88 100.00 0.00 0.00 0.00 366.640013
0.00 0.00 0.00
8,327.04 100.00 0.00 0.00 0.00 24
7,784.64 100.00 0.00 0.00 0.00 1468.8
15,776.64 100.00 0.00 0.00 0.00 352
13,535.68 100.00 0.00 0.00 0.00 34.2000101
11,244.48 100.00 0.00 0.00 0.00 2121.6
0.00 0.00 0.00
25,178.02 100.00 0.00 0.00 0.00 1773.1
2,953.60 100.00 0.00 0.00 0.00 208
0.00 0.00 0.00
77,702.16 100.00 0.00 0.00 0.00 195.609999
19,780.14 100.00 0.00 0.00 0.00 1388.08
0.00 0.00 0.00
13,452.25 100.00 0.00 0.00 0.00 3832.54986
0.00 0.00 0.00
0.00 0.00 0.00
2,951.32 100.00 0.00 0.00 0.00 1891.87179
318.00 99.97 -2.40 0.11 0.03 3.40077332
4,308.06 100.00 0.00 0.00 0.00 1
0.00 0.00 0.00
0.00 0.00 0.00
29,843.03 100.00 0.00 0.00 0.00 241
29,543.15 147.14 -17.91 -9,464.71 -47.14 55.9126954
29,543.15 78.03 4.39 8,316.05 21.97 15.6068538
0.00 0.00 0.00
0.00 0.00 0.00
7,719.16 100.00 0.00 0.00 0.00 3840.37811
0.00 0.00 0.00
32,085.34 100.00 0.00 0.00 0.00 1763.89995
99,407.04 100.00 0.00 0.00 0.00 1141.55994
5,760.57 100.00 0.00 0.00 0.00 3840.38
0.00 0.00 0.00
50,052.35 100.00 0.00 0.00 0.00 2698.23989
178,100.87 100.00 0.00 0.00 0.00 534.340014
0.00 0.00 0.00
277,160.22 100.00 0.00 0.00 0.00 3840.37994
0.00 0.00 0.00
6,755.90 100.00 0.01 0.00 0.00 25021.8519
0.00 0.00 0.00
76,962.84 100.00 0.00 0.00 0.00 1
0.00

2,713,689.23 (1,148.56)

407,053.38 (172.28)

217,095.14 (91.88)
3,337,837.75 (1,412.73)

100.04% -0.04%

REAJUSTE DE VALORIZACION N° 1

R=REAJUSTE
V=VALORIZACION
A=ADELANTO 0.00
C=MONTO CONTRACTUAL
K=FACTOR DE MES

N° MES VALORIZACIK
1.00 ENE 414,844.58 1.06

CONTROL DE REAJUSTE

PROGRAMADO
N° MES MONTO K
V1 ENERO 240,626.48 1.06

EJECUTADO
N° MES MONTO K
V1 ENERO 414,844.58 1.06

RESUMEN DE VALORIZA
ACUMULADO ACTUAL ITEM DESCRIPCION
1.00 MONTO CONTRACTUAL(V)
- 1.01 VALORIZACION
-
4,791.90 2.00 REAJUSTE(R)
- 2.01 REAJUSTE
-
- 3.00 DEDUCCIONES(D)
- 3.01 RETENCIONES DE REAJUSTES
-
- 4.00 VALORIZACION BRUTA(VB)
286,668.64 4.01 (VB=V+R-D)

5.00 AMORTIZACIONES(M)
5.01 AMORTIZACIONES POR ADELANTO

6.00 VALORIZACION NETA(VN)


286,668.64 6.01 (VB-M)
7.00 MULTAS
7.01 MULTA POR ATRASO DE OBRA(M)

8.00 MONTO A PAGAR AL CONTRATISTA


286,668.64 8.01 SUB TOTAL(VN-M)
51,600.35 8.02 EN IGV(VN*0.18)
338,268.99 8.03 MONTO A FACTURAR
REAJUSTE A CUENTA REAJUSTE MES
22,879.83

REAJUSTE
13,271.22

REAJUSTE
22,879.83

RESUMEN DE VALORIZACION N° 1 CON K HALLADO


CION ACUMULADO ANTERIOR MONTO ACTUAL ACUMULADO ACTUAL
ACTUAL(V) - -
ACION 414,844.58 -
-
TE(R) 0.00 22,879.83 -
STE -
-
NES(D) 0 -
E REAJUSTES 0 -
-
BRUTA(VB) 0 -
R-D) 437,724.42 -

ONES(M) 0
POR ADELANTO 0

N NETA(VN) 0
M) 437,724.42 -
AS 0
SO DE OBRA(M) 0

L CONTRATISTA 0
(VN-M) 437,724.42 -
N*0.18) 78,790.40 -
CTURAR 516,514.81 -