MES 1 MES 2 MES 3 MES4


Rendimiento TiempoUnitario FactorMultiplicidad Duracion
Item Descripción Partida Und. Metrado
(Ru) (Tu=Metrado/Ru) (f) (D=Tu/f) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108

01 CERCO PERIMETRICO Y MURO DE CONTENCION

01.01 OBRAS PROVISIONALES


MOVILIZACION DE MAQUINARIAS HERRAMIENTAS
01.01.01 PARA LA OBRA
glb 1.00 1.00 1.00 1.00 1
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X u 1.00 2.00 0.50 1 1
2.40 m
01.01.03 CAMPAMENTO PROVISIONAL DE LA OBRA m2 36.00 150.00 0.24 1.00 1
01.02 OBRAS PRELIMINARES
01.02.01 DESMONTAJE DE COBERTURA DE TECHO m3 83.06 1
01.02.02 DEMOLICION DE CIMIENTOS Y SOBRECIMIENTOS m3 52.95 1
01.02.03 DEMOLICION DE MURO DE ADOBE m3 179.03 1
01.02.04 ELIMINACION DE DESMONTE CON EQUIPO m2 315.04 100.00 2.46 1.00 1
01.02.05 LIMPIEZA DE TERRENO MANUAL m3 452.00 300.00 1.11 1.00 2
01.02.06 TRAZO Y REPLANTEO m2 452.00 200.00 1.19 1.00 2
01.03 MOVIMIENTO DE TIERRAS
01.03.01 EXCAVACION DE ZANJAS PARA CIMIENTOS H=0.80 m3 217.83 2.50 96.20 1.00 16
01.03.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3 47.51 2.50 11.95 1.00 12
01.03.03 RELLENO CON MATERIAL PROPIO m3 62.78 10.00 3.79 1.00 4
01.03.04 ELIMINACION DE MATERIAL EXCEDENTE D=60 mts m3 243.07 300.00 0.93 1.00 1
DISTANCIA PROMEDIO

01.04 CONCRETO SIMPLE


01.04.01 SOLADOS PARA ZAPATAS DE 4" MEZCLA 1:12 m2 61.27 120.00 0.27 1.00 1
CEMENTO HORMIGON
01.04.02 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS m3 130.32 10.00 7.17 1.00 5
CORRIDOS
01.04.03 ENCOFRADO Y DESENCOFRADO PARA m2 77.80 14.50 2.34 1.00 5
SOBRECIMIENTOS CORRIDOS

01.04.04 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS m3 46.68 10.00 1.02 1.00 5


CORRIDOS
01.04.05 ENCOFRADO Y DESENCOFRADO EN VEREDA m2 1.35 16.00 0.08 1.00 1
01.04.06 CONCRETO f'c=175 kg/cm2 EN VEREDAS m3 1.20 15.00 0.08 1.00 1
01.05 CONCRETO ARMADO
01.05.01 ZAPATAS
01.05.01.01 ACERO fy=4200 kg/cm2 GRADO 60 en ZAPATAS kg 1,008.17 250.00 2.21 1.00 5
01.05.01.02 CONCRETO PARA ZAPATAS f'c=210 kg/cm2 m3 40.28 24.00 0.95 1.00 2
01.05.02 VIGAS DE CIMENTACION
01.05.02.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGA m2 0.71 9.00 0.08 1.00 1
DE CIMENTACION
01.05.02.02 ACERO fy=4200 kg/cm2 GRADO 60 PARA VIGA DE kg 35.67 250.00 0.14 1.00 1
CIMENTACION
01.05.02.03 CONCRETO f'c=210 kg/cm2 PARA VIGA DE m3 0.71 16.00 0.04 1.00 1
CIMENTACION
01.05.03 COLUMNAS
01.05.03.01 ENCOFRADO Y DESENCOFRADO NORMAL EN m2 122.64 8.50 10.45 1.00 14
COLUMNAS
01.05.03.02 ACERO fy=4200 kg/cm2 GRADO 60 EN COLUMNAS kg 6,768.09 250.00 16.32 1.00 18

01.05.03.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 32.78 10.00 1.70 1.00 3


01.05.04 VIGAS SOLERA
01.05.04.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGA m2 61.31 9.00 3.56 1.00 7
SOLERA
01.05.04.02 ACERO fy=4200 kg/cm2 GRADO 60 PARA VIGA kg 3,654.22 250.00 7.91 1.00 15
SOLERA
01.05.04.03 CONCRETO f'c=210 kg/cm2 PARA VIGA SOLERA m3 16.72 16.00 0.55 1.00 1
01.05.05 VIGAS EN VOLADIZO DEL PORTON

01.05.05.01 ENCOFRADO Y DESENCOFRADO NORMAL EN m2 2.60 9.00 0.29 1.00 1


VIGAS VOLADIZO
01.05.05.02 ACERO fy=4200 kg/cm2 GRADO 60 PARA VIGA kg 31.81 250.00 0.13 1.00 1
VOLADIZO

01.05.05.03 CONCRETO f'c=210 kg/cm2 PARA VIGA VOLADIZO m3 1.15 16.00 0.07 1.00 1

01.06 MUROS Y TABIQUES DE ALBAÑILERIA

01.06.01 MURO DE SOGA LADRILLO CARAVISTA KK 18 m2 529.44 6.00 86.39 1.00 20


HUECOS
01.06.02 ALAMBRE DE REFUERZO HORIZONTAL EN MUROS kg 144.14 700.00 0.21 1.00 1

01.07 CARPINTERIA METALICA

01.07.01 CERCO METALICO PROTECTOR CON ALAMBRE m2 446.40 20


GALVANIZADO N.10 X COCADAS DE 2"
01.07.02 PUERTA PRINCIPAL METALICA 3.00x2.60 INCL. GLB 1.00 1
ACCESORIOS+INSTALACION
01.07.03 PUERTA PRINCIPAL 0.90X2.60 INCL. GLB 1.00 1
ACCESORIOS+INSTALACION
01.08 REVOQUES ENLUCIDOS Y MOLDURAS
01.08.01 TARRAJEO DE SUPERFICIE DE COLUMNAS m2 347.15 8.00 27.49 1.00 20
C/MORTERO C:A 1:5
01.08.02 TARRAJEO DE SUPERFICIE DE VIGAS C/MORTERO m2 144.38 6.00 13.40 1.00 14
C:A 1:5
01.08.03 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS m 983.20 18.00 10.22 1.00 20
Y VANOS
01.09 ZOCALOS
01.09.01 ZOCALO DE CEMENTO PULIDO h=30 cm. MEZCLA m2 269.22 14.00 10.09 1.00 15
CEMENTO-ARENA 1:5
1.1 PINTURA
01.10.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS m2 536.26 33.00 15.91 1.00 16
01.10.02 PINTURA VINILICA EN MUROS EXTERIORES 2 MANOS m2 536.29 30.00 17.51 1.00 13
01.10.03 PINTURA LATEX EN SUPERFICIES DE COLUMNAS 2 m2 347.15 33.00 6.66 1.00 8
MANOS
01.10.04 PINTURA LATEX EN SUPERFICIES DE VIGAS 2 m2 144.38 33.00 2.44 1.00 4
MANOS
01.10.05 PINTURA EN ESTRUCTURAS METALICAS m 446.40 10
1.11 JUNTAS
01.11.01 JUNTAS ASFALTICAS EN VEREDAS m 3.30 100.00 0.03 1.00 1
01.11.02 JUNTAS DE DILATACION EN MUROS e=1" m 196.00 100.00 0.84 1.00 2
1.12 LUMINARIAS
01.12.01 LUMINARIA PARA ALUMBRADO EN PUERTA glb 1.00 1.00 1.00 1.00 1
1.13 FLETE
01.13.01 FLETE TERRESTRE CERCO CHAVIN - CHUNA glb 1.00 1.00 1.00 1.00 1
002 LOSA DEPORTIVA, GRADERIAS Y EQUIPAMIENTO
02 LOSA DEPORTIVA, GRADERIAS, ACCESOS Y RAMPAS

02.01 OBRAS PRELIMINARES


02.01.02 TRAZO Y REPLANTEO m2 984.00 200.00 3.24 1.00 2
02.02 MOVIMIENTO DE TIERRAS
02.02.01 CORTE DE MATERIAL SUELTO R=570 m3/día m3 1,468.76 570.00 1.88 1.00 2
02.02.02 EXCAVACION MANUAL DE CIMIENTO PARA RAMPA m3 8.70 2.50 1.86 1.00 2
02.02.03 EXCAVACION MANUAL DE CIMIENTO PARA GRADERIA m3 22.03 2.50 7.78 1.00 4
02.02.04 NIVELACION Y COMPACTACION DE SUBRASANTE m2 969.47 300.00 2.85 1.00 3
02.02.05 AFIRMADO DE 4" PARA LOSAS m2 847.21 180.00 4.28 1.00 4
02.02.06 ELIMINACION DE MATERIAL EXCEDENTE D=60 mts m3 1,762.52 300.00 4.29 1.00 4
DISTANCIA PROMEDIO
02.03 LOSA DEPORTIVA 18 X 36 m.
02.03.01 ENCOFRADO Y DESENCOFRADO PARA LOSA m2 30.45 45.00 0.68 1.00 4
DEPORTIVA
02.03.02 CONCRETO f'c=175 kg/cm2 + PASTA C:A 1:2 PARA m3 71.55 10.00 7.16 1.00 8
LOSA DEPORTIVA
02.03.03 ANCLAJES DE CONCRETO PARA POSTES Y ARCOS m3 0.84 10.00 0.08 1.00 1
f'c=140 kg/cm2
02.03.04 CURADO DE CONCRETO EN LOSA DEPORTIVA m2 720.00 400.00 1.80 1.00 2
02.03.05 JUNTAS DE DILATACION m 486.00 80.00 6.08 1.00 4
02.03.06 SUMINISTRO E INSTALACION DE ANCLAJE PARA u 2.00 12.00 0.17 1.00 1
POSTE DE VOLEY
02.03.07 SUMINISTRO E INSTALACION DE ANCLAJE PARA u 8.00 12.00 0.67 1.00 1
ARCO
02.03.08 SUMINISTRO E INSTALACION DE ARCO CON u 2.00 2.00 1.00 1.00 1
TABLERO DE BASKET
02.03.09 SUMINISTRO E INSTALACION DE POSTES DE VOLEY u 2.00 2.00 1.00 1.00 1
02.03.10 PINTURA DE LINEA DEMARCATORIA (PINTURA DE m 343.50 200.00 1.72 1.00 2
TRAFICO)
02.03.11 PINTURA EN ESTRUCTURAS METALICAS m 79.88 80.00 1.00 1.00 1
02.03.12 PINTADO DE SERIGRAFIA EN TABLERO DE BASQUET u 2.00 100.00 0.02 1.00 1
02.03.13 SUMINISTRO DE PELOTAS Y MALLAS glb 1.00 1.00 1.00 1.00 1
02.04 GRADERIAS
02.04.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS m3 21.22 10.00 1.75 1.00 2
CORRIDOS
02.04.02 ENCOFRADO Y DESENCOFRADO PARA m2 8.84 14.50 0.50 1.00 1
SOBRECIMIENTOS CORRIDOS
02.04.03 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS m3 6.66 10.00 0.56 1.00 1
CORRIDOS
02.04.04 ENCOFRADO Y DESENCOFRADO EN LOSA DE m2 26.30 11.25 0.22 1.00 1
GRADERIAS
COMPAÑIA
CRONOGRAMA DE EJECUCION DE OBRA CONSTRUCTORA
CONSULTORA

MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E. N° 86725 DE LA LOCALIDAD DE CHUNA, DISTRITO DE CHAVIN DE HUANTAR - HUARI - ANCASH

MES 1 MES 2 MES 3 MES4


Rendimiento TiempoUnitario FactorMultiplicidad Duracion
Item Descripción Partida Und. Metrado
(Ru) (Tu=Metrado/Ru) (f) (D=Tu/f) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108

02.04.05 CONCRETO f'c=175 kg/cm2 PARA GRADA Y/O PISO m3 12.00 10.00 0.79 1.00 1
SIMPLE
02.04.06 MUROS DE LADRILLO KK DE ARCILLA DE SOGA PARA m2 57.60 9.45 3.79 1.00 4
GRADERIAS
02.04.07 MUROS DE LADRILLO KK DE ARCILLA DE CABEZA m2 15.60 6.45 2.98 1.00 3
PARA GRADERIAS
02.04.08 JUNTA DE CONSTRUCCION CON TEKNOPORT m2 23.40 100.00 0.13 1.00 1
02.04.09 REVESTIMIENTO DE GRADAS CON MORTERO O m2 209.10 12.00 15.95 1.00 8

MEZCLA 1:4 X 2 cm PULIDO 1:2 X 1 cm


02.04.10 PINTURA EN GRADERIAS m2 209.10 33.00 5.80 1.00 4
02.05 ACCESOS Y RAMPAS
02.05.01 ACERO fy=4200 kg/cm2 GRADO 60 PARA RAMPAS kg 390.59 260.00 0.35 1.00 1
02.05.02 ENCOFRADO Y DESENCOFRADO EN ACCESO Y m2 6.75 11.25 0.33 1.00 1
RAMPAS
02.05.03 CONCRETO f'c=175 kg/cm2 EN ACCESOS Y RAMPAS m3 31.83 10.00 1.35 1.00 2
02.05.04 REVESTIMIENTO DE RAMPAS Y ACCESOS CON m2 219.70 12.00 4.84 1.00 5
MORTERO MEZCLA 1:4 X 2 cm PULIDO 1:2 X 1 cm
02.05.05 JUNTAS DE DILATACION m 105.40 80.00 0.74 1.00 1
02.05.06 BRUÑAS m 170.60 25.00 3.22 1.00 3
PASAMANO DE F°G° D=2" CON PARANTE DE F°G° 1
02.05.07 1/2"
m 54.40 6.00 2.50 1.00 3
2.06 MITIGACION AMBIENTAL
02.06.01 REFORESTACION u 1,000.00 2
2.07 CAPACITACION
02.07.01 CAPACITACION A LA POBLACION BENEFICIARIA glb 1.00 1
02.06 FLETE
FLETE TERRESTRE LOSA DEPORTIVA CHAVIN -
02.06.01 CHUNA
glb 1.00 1.00 1.00 1.00 24
109 110 111 112 113 114 115 116 117 118 119 120
109 110 111 112 113 114 115 116 117 118 119 120
COMPAÑIA
CONSTRUCTORA
CONSULTORA

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E. N° 86725 DE LA LOCALIDAD DE CHUNA, DISTRITO DE


CHAVIN DE HUANTAR - HUARI - ANCASH

AVANCE POR MES (%) VALORIZACION POR MES (S/.)


Item Descripción Partida C.D. (S/.) TOTAL
MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4

01 CERCO PERIMETRICO Y MURO DE CONTENCION

01.01 OBRAS PROVISIONALES

01.01.01 MOVILIZACION DE MAQUINARIAS HERRAMIENTAS PARA LA OBRA S/. 3,360.00 100.00 0.00 0.00 0.00 3360.00 0.00 0.00 0.00 3360.00

01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m S/. 630.31 100.00 0.00 0.00 0.00 630.31 0.00 0.00 0.00 630.31
01.01.03 CAMPAMENTO PROVISIONAL DE LA OBRA S/. 3,876.12 100.00 0.00 0.00 0.00 3876.12 0.00 0.00 0.00 3876.12
01.02 OBRAS PRELIMINARES
01.02.01 DESMONTAJE DE COBERTURA DE TECHO S/. 205.99 100.00 0.00 0.00 0.00 205.99 0.00 0.00 0.00 205.99
01.02.02 DEMOLICION DE CIMIENTOS Y SOBRECIMIENTOS S/. 746.07 100.00 0.00 0.00 0.00 746.07 0.00 0.00 0.00 746.07
01.02.03 DEMOLICION DE MURO DE ADOBE S/. 1,262.16 100.00 0.00 0.00 0.00 1262.16 0.00 0.00 0.00 1262.16
01.02.04 ELIMINACION DE DESMONTE CON EQUIPO S/. 3,024.38 100.00 0.00 0.00 0.00 3024.38 0.00 0.00 0.00 3024.38
01.02.05 LIMPIEZA DE TERRENO MANUAL S/. 343.52 100.00 0.00 0.00 0.00 343.52 0.00 0.00 0.00 343.52
01.02.06 TRAZO Y REPLANTEO S/. 1,188.76 100.00 0.00 0.00 0.00 1188.76 0.00 0.00 0.00 1188.76
01.03 MOVIMIENTO DE TIERRAS
01.03.01 EXCAVACION DE ZANJAS PARA CIMIENTOS H=0.80 S/. 5,402.18 100.00 0.00 0.00 0.00 5402.18 0.00 0.00 0.00 5402.18
01.03.02 EXCAVACION DE ZANJAS PARA ZAPATAS S/. 1,178.25 100.00 0.00 0.00 0.00 1178.25 0.00 0.00 0.00 1178.25
01.03.03 RELLENO CON MATERIAL PROPIO S/. 2,611.02 100.00 0.00 0.00 0.00 2611.02 0.00 0.00 0.00 2611.02
ELIMINACION DE MATERIAL EXCEDENTE D=60 mts DISTANCIA
01.03.04 S/. 2,333.47 100.00 0.00 0.00 0.00 2333.47 0.00 0.00 0.00 2333.47
PROMEDIO
01.04 CONCRETO SIMPLE
01.04.01 SOLADOS PARA ZAPATAS DE 4" MESCLA 1:12 CEMENTO HORMIGON S/. 1,233.98 100.00 0.00 0.00 0.00 1233.98 0.00 0.00 0.00 1233.98

01.04.02 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS S/. 28,676.92 100.00 0.00 0.00 0.00 28676.92 0.00 0.00 0.00 28676.92

01.04.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS CORRIDOS S/. 2,228.19 100.00 0.00 0.00 0.00 2228.19 0.00 0.00 0.00 2228.19

01.04.04 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS CORRIDOS S/. 14,087.09 100.00 0.00 0.00 0.00 14087.09 0.00 0.00 0.00 14087.09
01.04.05 ENCOFRADO Y DESENCOFRADO EN VEREDA S/. 36.49 100.00 0.00 0.00 0.00 36.49 0.00 0.00 0.00 36.49
01.04.06 CONCRETO f'c=175 kg/cm2 EN VEREDAS S/. 451.74 100.00 0.00 0.00 0.00 451.74 0.00 0.00 0.00 451.74
01.05 CONCRETO ARMADO
01.05.01 ZAPATAS
01.05.01.01 ACERO fy=4200 kg/cm2 GRADO 60 en ZAPATAS S/. 4,587.17 100.00 0.00 0.00 0.00 4587.17 0.00 0.00 0.00 4587.17
01.05.01.02 CONCRETO PARA ZAPATAS f'c=210 kg/cm2 S/. 15,517.47 100.00 0.00 0.00 0.00 15517.47 0.00 0.00 0.00 15517.47
01.05.02 VIGAS DE CIMENTACION
01.05.02.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGA DE CIMENTACION S/. 40.84 100.00 0.00 0.00 0.00 40.84 0.00 0.00 0.00 40.84
01.05.02.02 ACERO fy=4200 kg/cm2 GRADO 60 PARA VIGA DE CIMENTACION S/. 162.30 100.00 0.00 0.00 0.00 162.30 0.00 0.00 0.00 162.30
01.05.02.03 CONCRETO f'c=210 kg/cm2 PARA VIGA DE CIMENTACION S/. 295.83 100.00 0.00 0.00 0.00 295.83 0.00 0.00 0.00 295.83
COMPAÑIA
CONSTRUCTORA
CONSULTORA

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E. N° 86725 DE LA LOCALIDAD DE CHUNA, DISTRITO DE


CHAVIN DE HUANTAR - HUARI - ANCASH

AVANCE POR MES (%) VALORIZACION POR MES (S/.)


Item Descripción Partida C.D. (S/.) TOTAL
MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4

01.05.03 COLUMNAS
01.05.03.01 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS S/. 6,026.53 13.00 87.00 0.00 0.00 783.45 5243.08 0.00 0.00 6026.53
01.05.03.02 ACERO fy=4200 kg/cm2 GRADO 60 EN COLUMNAS S/. 30,794.81 0.00 100.00 0.00 0.00 0.00 30794.81 0.00 0.00 30794.81
01.05.03.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 S/. 14,476.96 0.00 100.00 0.00 0.00 0.00 14476.96 0.00 0.00 14476.96
01.05.04 VIGAS SOLERA
01.05.04.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGA SOLERA S/. 3,526.55 0.00 0.00 100.00 0.00 0.00 0.00 3526.55 0.00 3526.55
01.05.04.02 ACERO fy=4200 kg/cm2 GRADO 60 PARA VIGA SOLERA S/. 16,626.70 0.00 20.00 80.00 0.00 0.00 3325.34 13301.36 0.00 16626.70
01.05.04.03 CONCRETO f'c=210 kg/cm2 PARA VIGA SOLERA S/. 6,966.56 0.00 0.00 100.00 0.00 0.00 0.00 6966.56 0.00 6966.56
01.05.05 VIGAS EN VOLADIZO DEL PORTON
01.05.05.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS VOLADIZO S/. 149.55 0.00 0.00 100.00 0.00 0.00 0.00 149.55 0.00 149.55

01.05.05.02 ACERO fy=4200 kg/cm2 GRADO 60 PARA VIGA VOLADIZO S/. 144.74 0.00 0.00 100.00 0.00 0.00 0.00 144.74 0.00 144.74

01.05.05.03 CONCRETO f'c=210 kg/cm2 PARA VIGA VOLADIZO S/. 479.16 0.00 0.00 100.00 0.00 0.00 0.00 479.16 0.00 479.16

01.06 MUROS Y TABIQUES DE ALBAÑILERIA

01.06.01 MURO DE SOGA LADRILLO CARAVISTA KK 18 HUECOS S/. 40,692.76 0.00 15.00 85.00 0.00 0.00 6103.91 34588.85 0.00 40692.76
01.06.02 ALAMBRE DE REFUERZO HORIZONTAL EN MUROS S/. 639.98 0.00 0.00 100.00 0.00 0.00 0.00 639.98 0.00 639.98
01.07 CARPINTERIA METALICA
CERCO METALICO PROTECTOR CON ALAMBRE GALVANIZADO N.10 X
01.07.01 S/. 24,235.06 0.00 0.00 100.00 0.00 0.00 0.00 24235.06 0.00 24235.06
COCADAS DE 2"
01.07.02 PUERTA PRINCIPAL METALICA 3.00x2.60 INCL. ACCESORIOS+INSTALACION S/. 2,000.00 0.00 0.00 0.00 100.00 0.00 0.00 0.00 2000.00 2000.00
01.07.03 PUERTA PRINCIPAL 0.90X2.60 INCL. ACCESORIOS+INSTALACION S/. 1,000.00 0.00 0.00 0.00 100.00 0.00 0.00 0.00 1000.00 1000.00
01.08 REVOQUES ENLUCIDOS Y MOLDURAS
01.08.01 TARRAJEO DE SUPERFICIE DE COLUMNAS C/MORTERO C:A 1:5 S/. 8,932.17 0.00 0.00 65.00 35.00 0.00 0.00 5805.91 3126.26 8932.17
01.08.02 TARRAJEO DE SUPERFICIE DE VIGAS C/MORTERO C:A 1:5 S/. 8,000.10 0.00 0.00 29.00 71.00 0.00 0.00 2320.03 5680.07 8000.10
01.08.03 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS S/. 11,916.38 0.00 0.00 0.00 100.00 0.00 0.00 0.00 11916.38 11916.38
01.09 ZOCALOS
01.09.01 ZOCALO DE CEMENTO PULIDO h=30 cm. MEZCLA CEMENTO-ARENA 1:5 S/. 3,171.41 0.00 0.00 0.00 100.00 0.00 0.00 0.00 3171.41 3171.41
1.10 PINTURA
01.10.01 PINTURA LATEX EN MUROS INTERIORES 2 MANOS S/. 2,557.96 0.00 0.00 0.00 100.00 0.00 0.00 0.00 2557.96 2557.96
01.10.02 PINTURA VINILICA EN MUROS EXTERIORES 2 MANOS S/. 2,729.56 0.00 0.00 0.00 100.00 0.00 0.00 0.00 2729.56 2729.56
01.10.03 PINTURA LATEX EN SUPERFICIES DE COLUMNAS 2 MANOS S/. 3,620.77 0.00 0.00 0.00 100.00 0.00 0.00 0.00 3620.77 3620.77
01.10.04 PINTURA LATEX EN SUPERFICIES DE VIGAS 2 MANOS S/. 1,505.88 0.00 0.00 0.00 100.00 0.00 0.00 0.00 1505.88 1505.88
01.10.05 PINTURA EN ESTRUCTURAS METALICAS S/. 915.12 0.00 0.00 0.00 100.00 0.00 0.00 0.00 915.12 915.12
COMPAÑIA
CONSTRUCTORA
CONSULTORA

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E. N° 86725 DE LA LOCALIDAD DE CHUNA, DISTRITO DE


CHAVIN DE HUANTAR - HUARI - ANCASH

AVANCE POR MES (%) VALORIZACION POR MES (S/.)


Item Descripción Partida C.D. (S/.) TOTAL
MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4

1.11 JUNTAS
01.11.01 JUNTAS ASFALTICAS EN VEREDAS S/. 16.37 0.00 0.00 0.00 100.00 0.00 0.00 0.00 16.37 16.37
01.11.02 JUNTAS DE DILATACION EN MUROS e=1" S/. 2,520.56 100.00 0.00 0.00 0.00 2520.56 0.00 0.00 0.00 2520.56
1.12 LUMINARIAS
01.12.01 LUMINARIA PARA ALUMBRADO EN PUERTA S/. 715.72 0.00 0.00 0.00 100.00 0.00 0.00 0.00 715.72 715.72
1.13 FLETE
01.13.01 FLETE TERRESTRE CERCO CHAVIN - CHUNA S/. 11,595.52 45.00 55.00 0.00 0.00 5217.98 6377.54 0.00 0.00 11595.52
002 LOSA DEPORTIVA, GRADERIAS Y EQUIPAMIENTO

02 LOSA DEPORTIVA, GRADERIAS, ACCESOS Y RAMPAS

02.01 OBRAS PRELIMINARES


02.01.01 TRAZO Y REPLANTEO S/. 2,587.92 100.00 0.00 0.00 0.00 2587.92 0.00 0.00 0.00 2587.92
02.02 MOVIMIENTO DE TIERRAS
02.02.01 CORTE DE MATERIAL SUELTO R=570 m3/día S/. 4,567.84 100.00 0.00 0.00 0.00 4567.84 0.00 0.00 0.00 4567.84
02.02.02 EXCAVACION MANUAL DE CIMIENTO PARA RAMPA S/. 259.00 100.00 0.00 0.00 0.00 259.00 0.00 0.00 0.00 259.00
02.02.03 EXCAVACION MANUAL DE CIMIENTO PARA GRADERIA S/. 655.83 100.00 0.00 0.00 0.00 655.83 0.00 0.00 0.00 655.83
02.02.04 NIVELACION Y COMPACTACION DE SUBRASANTE S/. 3,305.89 100.00 0.00 0.00 0.00 3305.89 0.00 0.00 0.00 3305.89
02.02.05 AFIRMADO DE 4" PARA LOSAS S/. 8,090.86 100.00 0.00 0.00 0.00 8090.86 0.00 0.00 0.00 8090.86
ELIMINACION DE MATERIAL EXCEDENTE D=60 mts DISTANCIA
02.02.06 S/. 5,728.19 100.00 0.00 0.00 0.00 5728.19 0.00 0.00 0.00 5728.19
PROMEDIO
02.03 LOSA DEPORTIVA 18 X 36 m.
02.03.01 ENCOFRADO Y DESENCOFRADO PARA LOSA DEPORTIVA S/. 723.80 100.00 0.00 0.00 0.00 723.80 0.00 0.00 0.00 723.80
02.03.02 CONCRETO f'c=175 kg/cm2 + PASTA C:A 1:2 PARA LOSA DEPORTIVA S/. 27,952.44 88.00 12.00 0.00 0.00 24598.15 3354.29 0.00 0.00 27952.44
02.03.03 ANCLAJES DE CONCRETO PARA POSTES Y ARCOS f'c=140 kg/cm2 S/. 257.01 100.00 0.00 0.00 0.00 257.01 0.00 0.00 0.00 257.01
02.03.04 CURADO DE CONCRETO EN LOSA DEPORTIVA S/. 1,677.60 0.00 100.00 0.00 0.00 0.00 1677.60 0.00 0.00 1677.60
02.03.05 JUNTAS DE DILATACION S/. 4,271.94 75.00 25.00 0.00 0.00 3203.96 1067.99 0.00 0.00 4271.94
02.03.06 SUMINISTRO E INSTALACION DE ANCLAJE PARA POSTE DE VOLEY S/. 177.16 0.00 0.00 100.00 0.00 0.00 0.00 177.16 0.00 177.16
02.03.07 SUMINISTRO E INSTALACION DE ANCLAJE PARA ARCO S/. 464.08 0.00 0.00 100.00 0.00 0.00 0.00 464.08 0.00 464.08
02.03.08 SUMINISTRO E INSTALACION DE ARCO CON TABLERO DE BASKET S/. 3,432.02 0.00 0.00 100.00 0.00 0.00 0.00 3432.02 0.00 3432.02
02.03.09 SUMINISTRO E INSTALACION DE POSTES DE VOLEY S/. 538.74 0.00 0.00 100.00 0.00 0.00 0.00 538.74 0.00 538.74
02.03.10 PINTURA DE LINEA DEMARCATORIA (PINTURA DE TRAFICO) S/. 707.61 0.00 0.00 100.00 0.00 0.00 0.00 707.61 0.00 707.61
02.03.11 PINTURA EN ESTRUCTURAS METALICAS S/. 163.75 0.00 0.00 100.00 0.00 0.00 0.00 163.75 0.00 163.75
02.03.12 PINTADO DE SERIGRAFIA EN TABLERO DE BASQUET S/. 390.90 0.00 0.00 100.00 0.00 0.00 0.00 390.90 0.00 390.90
02.03.13 SUMINISTRO DE PELOTAS Y MALLAS S/. 532.12 0.00 0.00 100.00 0.00 0.00 0.00 532.12 0.00 532.12
COMPAÑIA
CONSTRUCTORA
CONSULTORA

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E. N° 86725 DE LA LOCALIDAD DE CHUNA, DISTRITO DE


CHAVIN DE HUANTAR - HUARI - ANCASH

AVANCE POR MES (%) VALORIZACION POR MES (S/.)


Item Descripción Partida C.D. (S/.) TOTAL
MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4

02.04 GRADERIAS
02.04.01 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS S/. 6,339.69 0.00 100.00 0.00 0.00 0.00 6339.69 0.00 0.00 6339.69
02.04.02 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS CORRIDOS S/. 253.18 0.00 100.00 0.00 0.00 0.00 253.18 0.00 0.00 253.18
02.04.03 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS CORRIDOS S/. 2,009.85 0.00 100.00 0.00 0.00 0.00 2009.85 0.00 0.00 2009.85
02.04.04 ENCOFRADO Y DESENCOFRADO EN LOSA DE GRADERIAS S/. 1,093.82 0.00 100.00 0.00 0.00 0.00 1093.82 0.00 0.00 1093.82
02.04.05 CONCRETO f'c=175 kg/cm2 PARA GRADA Y/O PISO SIMPLE S/. 5,456.64 0.00 100.00 0.00 0.00 0.00 5456.64 0.00 0.00 5456.64
02.04.06 MUROS DE LADRILLO KK DE ARCILLA DE SOGA PARA GRADERIAS S/. 3,512.45 0.00 100.00 0.00 0.00 0.00 3512.45 0.00 0.00 3512.45
02.04.07 MUROS DE LADRILLO KK DE ARCILLA DE CABEZA PARA GRADERIAS S/. 1,536.13 0.00 100.00 0.00 0.00 0.00 1536.13 0.00 0.00 1536.13
02.04.08 JUNTA DE CONSTRUCCION CON TEKNOPORT S/. 300.92 0.00 100.00 0.00 0.00 0.00 300.92 0.00 0.00 300.92
REVESTIMIENTO DE GRADAS CON MORTERO O MEZCLA 1:4 X 2 cm
02.04.09 S/. 5,175.23 0.00 100.00 0.00 0.00 0.00 5175.23 0.00 0.00 5175.23
PULIDO 1:2 X 1 cm
02.04.10 PINTURA EN GRADERIAS S/. 1,929.99 0.00 50.00 50.00 0.00 0.00 965.00 965.00 0.00 1929.99
02.05 ACCESOS Y RAMPAS
02.05.01 ACERO fy=4200 kg/cm2 GRADO 60 PARA RAMPAS S/. 1,773.28 0.00 100.00 0.00 0.00 0.00 1773.28 0.00 0.00 1773.28
02.05.02 ENCOFRADO Y DESENCOFRADO EN ACCESO Y RAMPAS S/. 280.73 0.00 100.00 0.00 0.00 0.00 280.73 0.00 0.00 280.73
02.05.03 CONCRETO f'c=175 kg/cm2 EN ACCESOS Y RAMPAS S/. 14,473.74 0.00 100.00 0.00 0.00 0.00 14473.74 0.00 0.00 14473.74
REVESTIMIENTO DE RAMPAS Y ACCESOS CON MORTERO MEZCLA 1:4
02.05.04 S/. 5,437.58 0.00 100.00 0.00 0.00 0.00 5437.58 0.00 0.00 5437.58
X 2 cm PULIDO 1:2 X 1 cm
02.05.05 JUNTAS DE DILATACION S/. 926.47 0.00 100.00 0.00 0.00 0.00 926.47 0.00 0.00 926.47
02.05.06 BRUÑAS S/. 1,228.32 0.00 100.00 0.00 0.00 0.00 1228.32 0.00 0.00 1228.32
02.05.07 PASAMANO DE F°G° D=2" CON PARANTE DE F°G° 1 1/2" S/. 6,077.02 0.00 100.00 0.00 0.00 0.00 6077.02 0.00 0.00 6077.02
02.06 MITIGACION AMBIENTAL
02.06.01 REFORESTACION S/. 1,950.00 0.00 0.00 0.00 100.00 0.00 0.00 0.00 1950.00 1950.00
2.07 CAPACITACION
02.07.01 CAPACITACION A LA POBLACION BENEFICIARIA S/. 1,500.00 0.00 0.00 0.00 100.00 0.00 0.00 0.00 1500.00 1500.00
2.08 FLETE
02.08.01 FLETE TERRESTRE LOSA DEPORTIVA CHAVIN - CHUNA S/. 5,000.00 67.00 33.00 0.00 0.00 3350.00 1650.00 0.00 0.00 5000.00

TOTAL COSTO DIRECTO 432,176.87 - - - - 159,330.69 130,911.56 99,529.12 42,405.50


GASTOS GENERALES (8%) 34,574.15 - - - - 12,746.46 10,472.92 7,962.33 3,392.44
UTILIDAD (8%) 34,574.15 - - - - 12,746.46 10,472.92 7,962.33 3,392.44
SUB TOTAL 501,325.17 - - - - 184,823.61 151,857.40 115,453.78 49,190.38
I.G.V. (19%) 95,251.78 - - - - 35,116.49 28,852.91 21,936.22 9,346.17
COSTO TOTAL PRESUPUESTO REFERENCIAL 596,576.95 - - - - 219,940.10 180,710.31 137,390.00 58,536.55

PORCENTAJE PARCIAL 36.87% 30.29% 23.03% 9.81%


COMPAÑIA
CONSTRUCTORA
CONSULTORA

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E. N° 86725 DE LA LOCALIDAD DE CHUNA, DISTRITO DE


CHAVIN DE HUANTAR - HUARI - ANCASH

AVANCE POR MES (%) VALORIZACION POR MES (S/.)


Item Descripción Partida C.D. (S/.) TOTAL
MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4

PORCENTAJE ACUMULADO 36.87% 67.16% 90.19% 100.00%