CALCULO DEL FLETE TERRESTRE (CHICLAYO - UTCUBAMBA-VICTORIA)

PROYECTO: INSTALACION DEL CANAL LA BOCANA


LOCALIDADES : VERSALLA,VICTORIA,LA BOCANA; DISTRITO DE BAGUA GRANDE, PROVINCIA : UTCUBAMA, DEPARTAMENTO : AMAZONAS

FECHA : OCTUBRE 2014

POR PESO

DESCRIPCION UNIDAD CANTIDAD PESO UNIT. (KG.) PESO PARCIAL PESO TOTAL (KG)
ALAMBRE Y CLAVOS. KG 3,915.00 1.00 3,915.00
ACERO CORRUGADO Fy= 4200 KG/CM2 x 9 m GRADO 60º KG 25,596.36 1.00 25,596.36
TUBERIA DE PVC PARA AGUA D=250 mm C -5 UF ISO 4422 INC. ANILLO ML 7,318.36 6.65 48,653.68
TUBERIA DE PVC PARA AGUA D=200 mm C 5-7.5 UF ISO 4422 INC. ANILLO ML 11,012.28 4.20 46,302.97
TUBERIA DE PVC PARA AGUA D=63 mm C 5-7.5 UF ISO 4422 INC. ANILLO IN ML 3,000.00 0.88 2,655.00
GEOMENBRANA HPDE e=1.50mm - Inc. Accesorios M2 9,790.83 2.85 27,903.87
CEMENTO PORTLAND TIPO I (42.5KG) BOL 15,999.11 42.50 679,962.18
MADERA P2 16,496.56 1.48 24,414.91
OTROS MATERIALES KG 500.00 1.00 500.00

TOTAL KG 859,903.95

Nota: El precio de agregados incluye flete (material puesto en Obra), por ello no se incluye en este análisis

RESUMEN: FLETE TERRESTRE CHICLAYO - UTCUBAMBA

FLETE POR VIAJE : S/. 500.00


CARGA DEL CAMIÓN S/. 10,000.00 kg
FLETE POR KG. : S/. 0.050

DESCRIPCION CANT. TOTAL FLETE POR KG TOTAL


FLETE POR PESO 859,903.95 0.050 42,995.00
COSTO TOTAL FLETE TERRESTRE : S/. 42,995.00

CALCULO FLETE RURAL (UTCUBAMBA/VICTORIA - OBRA)

DISTANCIA PROMEDIO: 1 KM
COSTO ACEMILA: S/ 20.00
VIAJES ACEMILA (IDA Y VUELTA) 2.00
CAPACIDAD DE ACEMILA: KG 100.00
PRECIO POR KILOGRAMO: 0.100

POR PESO( CONSIDREMAOS UN 20 % USADO DEL TOTAL)

DESCRIPCION UNIDAD CANTIDAD PESO UNIT. (KG.) PESO PARCIAL PESO TOTAL (KG)
ALAMBRE Y CLAVOS. KG 3,915.00 1.00 3,915.00
ACERO CORRUGADO Fy= 4200 KG/CM2 x 9 m GRADO 60º KG 25,596.36 1.00 25,596.36
TUBERIA DE PVC PARA AGUA D=300 mm C -5 UF ISO 4422 INC. ANILLO ML 7,318.36 6.65 48,653.68
TUBERIA DE PVC PARA AGUA D=200 mm C 5-7.5 UF ISO 4422 INC. ANILLO ML 11,012.28 4.20 46,302.97
TUBERIA DE PVC PARA AGUA D=160 mm C 5-7.5 UF ISO 4422 INC. ANILLO I ML 3,000.00 0.88 2,655.00
GEOMENBRANA HPDE e=1.50mm - Inc. Accesorios M2 9,790.83 2.85 27,903.87
CEMENTO PORTLAND TIPO I (42.5KG) BOL 15,999.11 42.50 679,962.18
MADERA P2 16,496.56 1.48 24,414.91
OTROS MATERIALES KG 500.00 1.00 500.00

TOTAL KG 859,903.95

DESCRIPCION CANT. TOTAL FLETE POR KG TOTAL


FLETE POR PESO 859,903.95 0.100 85,990.00
COSTO TOTAL FLETE RURAL : S/. 85,990.00