GERENCIA DE ESTUDIOS Y PROYECTOS

CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA


TICONA MAMANI ALEJANDRO RICHARD
Actividad :
COSTO DIRECTO 422,986.67
Fecha 01/01/2023
Plazo :

Mes 1 Mes 2 Mes 3 Mes 4


Item Descripción Parcial (S/.)
Parcial (S/.) % Parcial (S/.) % Parcial (S/.) % Parcial (S/.) %
1 VIVIENDA MULTIFAMILIAR DE 07 NIVELES S/ 422,986.67 112,178.79 26.52% 117,979.06 27.89% 177,164.60 41.88% 15,664.22 3.70%
2 MOVIMIENTO DE TIERRAS S/ 32,713.03 32,713.03 100.00%
3 EXCAVACION MASIVA PARA SEMISOTANO, C/EQ S/ 5,608.44 5,608.44 100.00%
4 EXCAVACION PARA CALZADURAS, MANUAL S/ 6,777.55 6,777.55 100.00%
5 EXCAVACION DE ZANJAS PARA CIMIENTO, MANUAL S/ 3,681.58 3,681.58 100.00%
6 EXCAVACION MASIVA PARA CISTERNA, C/EQ S/ 3,056.38 3,056.38 100.00%
7 RELLENO COMPACTADO CON MATERIAL PROPIO S/ 3,220.50 3,220.50 100.00%
8 ELIMINACION DE MATERIAL EXCEDENTE C/EQ S/ 10,368.58 10,368.58 100.00%
9 OBRAS DE CONCRETO SIMPLE S/ 45,361.38 39,860.97 87.87% 5,500.41 12.13%
10 CONCRETO EN FALSO PISO f´c = 100 Kg/cm2 S/ 9,614.93 9,614.93 100.00%
11 CONCRETO PARA CALZADURA f'c=100 kg/cm2 S/ 22,001.65 16,501.24 75.00% 5,500.41 25.00%
12 ENCOFRADO Y DESENCOFRADO DE CALZADURA S/ 13,744.80 13,744.80 100.00%
13 OBRAS DE CONCRETO ARMADO S/ 322,986.23 36,466.48 11.29% 108,921.90 33.72% 161,933.63 50.14% 15,664.22 4.85%
14 CIMENTACION ARMADA S/ 16,630.86 3,238.76 19.47% 13,392.10 80.53%
15 CONCRETO f'c=210 kg/cm2 EN CIMIENTOS S/ 9,419.10 9,419.10 100.00%
16 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS S/ 2,500.84 2,500.84 100.00%
17 ACERO DE REFUERZO fy=4200 kg/cm2 EN CIMIENTOS S/ 4,710.92 3,238.76 68.75% 1,472.16 31.25%
18 COLUMNAS DE CONCRETO S/ 86,332.62 67,713.35 78.43% 18,619.27 21.57%
19 CONCRETO f'c=210 kg/cm2 EN COLUMNAS S/ 17,950.99 3,205.53 17.86% 14,745.46 82.14%
20 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS S/ 22,538.52 18,664.71 82.81% 3,873.81 17.19%
21 ACERO DE REFUERZO fy=4200 kg/cm2 EN COLUMNAS S/ 45,843.11 45,843.11 100.00%
22 VIGAS DE CONCRETO S/ 96,819.16 33,227.72 34.32% 21,455.94 22.16% 42,135.50 43.52%
23 CONCRETO f'c=210 kg/cm2 EN VIGAS S/ 20,506.58 20,506.58 100.00%
24 ENCOFRADO Y DESENCOFRADO DE VIGAS S/ 34,177.08 33,227.72 97.22% 949.36 2.78%
25 ACERO DE REFUERZO fy=4200 kg/cm2 EN VIGAS S/ 42,135.50 42,135.50 100.00%
26 LOSAS ALIGERADAS S/ 96,655.93 96,655.93 100.00%
27 CONCRETO f'c=210 kg/cm2 EN LOSAS ALIGERADAS S/ 17,641.15 17,641.15 100.00%
28 ENCOFRADO Y DESENCOFRADO DE LOSAS ALIGERADAS S/ 46,704.98 46,704.98 100.00%
29 ACERO DE REFUERZO fy=4200 kg/cm2 EN LOSAS ALIGERADAS S/ 6,154.19 6,154.19 100.00%
30 LADRILLO DE ARCILLA HUECO 15X30X30cm S/ 26,155.61 26,155.61 100.00%
31 ESCALERAS S/ 26,547.66 6,360.51 23.96% 4,522.93 17.04% 15,664.22 59.00%
32 CONCRETO F'C=210 KG/CM2 ESCALERAS S/ 6,360.51 6,360.51 100.00%
33 ENCOFRADO Y DESENCOFRADO NORMAL ESCALERAS S/ 4,189.65 4,189.65 100.00%
34 ACERO CORRUGADO FY=4200 KG/CM2 EN PLACAS S/ 15,997.50 333.28 2.08% 15,664.22 97.92%
35 ALBAÑILERIA S/ 21,926.03 3,138.31 14.31% 3,556.75 16.22% 15,230.97 69.47%

36 MURO DE LADRILLO KK DE ARCILLA - SOGA 9X14X24CM. 1:4 X 1.5 CM S/ 15,230.97 15,230.97 100.00%

37 MURO DE LADRILLO PANDERETA 9X11X23CM. 1:4 X 1.5 CM S/ 6,695.06 3,138.31 46.88% 3,556.75 53.12%

COSTO DIRECTO 422,986.67 112,178.79 117,979.06 177,164.60 15,664.22


%AVANZADO PARCIAL 26.52% 27.89% 41.88% 3.70%
%AVANZADO ACUMULADO 26.52% 54.41% 96.30% 100.00%

GRÁFICA DE GASTO PROGRAMADO (%)