LOSAS Y VEREDAS SEM 25 Classic Schedule Layout 24-Jul-23 11:15

Activity ID Activity Name Original BL Project BL Project Start Finish Performance Schedule % Labor Units BL Project Actual Remaining At Completion February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023
Duration Start Finish % Complete Complete % Complete Labor Units Labor Units Labor Units Labor Units
29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24
BCHT01-8 LOSAS Y VEREDAS SEM 25 286 01-Dec-22 21-Jul-23 01-Dec-22 A 12-Sep-23 0% 0% 64.77% 31608 27371 14886 42256 12-Sep-23, BCHT01-8 LOSAS Y V

BCHT01-8.1 HITOS DEL CONTRATO 54 19-May-23 21-Jul-23 21-Jul-23 12-Sep-23 0% 0% 0% 0 0 0 0 12-Sep-23, BCHT01-8.1 HITOS DE

A1360 Fecha de entrega en Vigencia 0 19-May-23 21-Jul-23* 0% 100% 0% 0 0 0 0 Fecha de entrega en Vigencia, 21-Jul-23*
A1370 Inicio de la gestión de movilización (KOM) 0 19-May-23 21-Jul-23* 0% 100% 0% 0 0 0 0 Inicio de la gestión de movilización (KOM), 21-Jul-23*
A1371 Movilización (inicio de la inducción en sitio) 0 19-May-23 21-Jul-23* 0% 100% 0% 0 0 0 0 Movilización (inicio de la inducción en sitio), 21-Jul-23*
A1390 Inicio de Obras 0 19-May-23 21-Jul-23* 0% 100% 0% 0 0 0 0 Inicio de Obras, 21-Jul-23*
A1392 Liberación de area Stage 3-sector 1 0 20-May-23 22-Jul-23* 0% 100% 0% 0 0 0 0 Liberación de area Stage 3-sector 1, 22-Jul-23*
A1394 Liberación de area Stage 3-sector 2 0 02-Jun-23 24-Jul-23* 0% 100% 0% 0 0 0 0 Liberación de area Stage 3-sector 2, 24-Jul-23*
A1396 Liberación de area Stage 3-sector 3 0 23-Jun-23 11-Aug-23* 0% 100% 0% 0 0 0 0 Liberación de area Stage 3-sector 3, 11-Aug-23*
A1398 Liberación de area Stage 5 0 20-May-23 21-Jul-23* 0% 100% 0% 0 0 0 0 Liberación de area Stage 5, 21-Jul-23*
A1399 Liberación de area Stage 4 0 19-May-23 21-Jul-23* 0% 100% 0% 0 0 0 0 Liberación de area Stage 4, 21-Jul-23*
A1400 Fin de veredas y escaleras Stage 1 y 2 0 05-Jul-23 24-Aug-23 0% 100% 0% 0 0 0 0 Fin de veredas y escaleras Stage 1 y 2,
A1410 Fin de Losas Deportivas 0 07-Jul-23 28-Aug-23 0% 100% 0% 0 0 0 0 Fin de Losas Deportivas,
A1420 Fin de veredas y escaleras Stage 3 0 02-Jul-23 02-Sep-23 0% 100% 0% 0 0 0 0 Fin de veredas y escaleras Stage 3,
A1425 Fin de veredas y escaleras Stage 5 0 20-Jun-23 15-Aug-23 0% 100% 0% 0 0 0 0 Fin de veredas y escaleras Stage 5,
A1427 Fin de veredas y escaleras Stage 4 0 06-Jul-23 25-Aug-23 0% 100% 0% 0 0 0 0 Fin de veredas y escaleras Stage 4,
A1430 Fin de los trabajos (Términos sustancial) 0 07-Jul-23 02-Sep-23 0% 100% 0% 0 0 0 0 Fin de los trabajos (Términos sustancial),
A1440 Fin de Desmovilización del Sitio de los Trab ajos 0 21-Jul-23 12-Sep-23 0% 0% 0% 0 0 0 0 Fin de Desmovilización del Sitio de l
BCHT01-8.8 GESTIÓN ADMINISTRATIVA 56 01-Dec-22 26-Jan-23 01-Dec-22 A 26-Jan-23 A 0% 0% 0% 0 0 0 26-Jan-23
0 A, BCHT01-8.8 GESTIÓN ADMINISTRATIVA

BCHT01-8.8.1 GESTIÓN DEL TALENTO HUMANO 29 01-Dec-22 30-Dec-22 01-Dec-22 A 30-Dec-22 A 0% 0% 0% 0 30-Dec-22
0 A, BCHT01-8.8.1
0 GESTIÓN
0 DEL TALENTO HUMANO
BCHT01-8.8.2 GESTIÓN DE SEGURIDAD 14 01-Dec-22 15-Dec-22 01-Dec-22 A 15-Dec-22 A 0% 0% 0% 0 0 0 0
BCHT01-8.8.3 GESTIÓN DE LOGISTICA 8 06-Dec-22 14-Dec-22 06-Dec-22 A 14-Dec-22 A 0% 0% 0% 0 0 0 0
BCHT01-8.8.4 GESTIÓN DE PROYECTO 27 30-Dec-22 26-Jan-23 30-Dec-22 A 26-Jan-23 A 0% 0% 0% 0 0 0 26-Jan-23
0 A, BCHT01-8.8.4 GESTIÓN DE PROYECTO
BCHT01-8.9 PRE-CONSTRUCCIÓN 37 26-Jan-23 03-Mar-23 26-Jan-23 A 03-Mar-23 A 0% 0% 0% 0 0 0 0 03-Mar-23 A, BCHT01-8. 9 PRE-CONSTRUCC IÓN

BCHT01-8.9.1 ACTVIDADES PRELIMINARES 37 26-Jan-23 03-Mar-23 26-Jan-23 A 03-Mar-23 A 0% 0% 0% 0 0 0 0 03-Mar-23 A, BCHT01-8. 9.1 ACTVIDADES PRELIMINARES
BCHT01-8.10 PROCURA 184 07-Feb-23 24-Jun-23 07-Feb-23 A 09-Aug-23 0% 0% 0% 0 0 0 0 09-Aug-23, BCHT01-8.10 PROCURA

BCHT01-8.10.1 MATERIALES 184 07-Feb-23 24-Jun-23 07-Feb-23 A 09-Aug-23 0% 0% 0% 0 0 0 0 09-Aug-23, BCHT01-8.10.1 MATERIALES
BCHT01-8.10.1.1 ETAPAS 1&2 178 07-Feb-23 14-Jun-23 07-Feb-23 A 03-Aug-23 0% 0% 0% 0 0 0 0 03-Aug-23, BCHT01-8.10.1.1 ETAPAS 1&2
A2660 Suministro y Habilitación de Fierro (Cajamarca) 43 07-Feb-23 21-Mar-23 07-Feb-23 A 21-Mar-23 A 100% 100% 0% 0 0 0 0 Suministro y Habilitación de Fierro (Cajamarca)
A2670 Transporte de Fierro a Obra 37 13-Feb-23 21-Mar-23 13-Feb-23 A 21-Mar-23 A 100% 100% 0% 0 0 0 0 Transporte de Fierro a Obra
A2680 Suministro y Habilitación de Acero (Cajamarca ) 57 21-Feb-23 18-Apr-23 21-Feb-23 A 18-Apr-23 A 100% 100% 0% 0 0 0 0 Suministro y Habilitación de Acero (Cajamarca)
A2690 Transporte de Acero a Obra 83 19-Apr-23 11-May-23 19-Apr-23 A 24-Jul-23 0% 100% 0% 0 0 0 0 Transporte de Acero a Obra
A2720 Suministro y Habilitación de Malla Olimpica 5 26-May-23 09-Jun-23 25-Jul-23 29-Jul-23 0% 100% 0% 0 0 0 0 Suministro y Habilitación de Malla Olimpica
A2730 Transporte de Malla Olimpica 5 10-Jun-23 14-Jun-23 30-Jul-23 03-Aug-23 0% 100% 0% 0 0 0 0 Transporte de Malla Olimpica
BCHT01-8.10.1.2 ETAPAS 3@5 162 01-Mar-23 24-Jun-23 01-Mar-23 A 09-Aug-23 0% 0% 0% 0 0 0 0 09-Aug-23, BCHT01-8.10.1.2 ETAPAS 3@5
A2700 Suministro y Habilitación de Fierro (Cajamarca) 143 01-Mar-23 03-Jun-23 01-Mar-23 A 23-Jul-23 80% 100% 0% 0 0 0 0 Suministro y Habilitación de Fierro (Cajamarca)
A2710 Transporte de Fierro a Obra 2 19-May-23 07-Jun-23 21-Jul-23 22-Jul-23 0% 100% 0% 0 0 0 0 Transporte de Fierro a Obra
A2760 Suministro y Habilitación de Acero (Cajamarca ) 7 29-May-23 17-Jun-23 31-Jul-23 06-Aug-23 0% 100% 0% 0 0 0 0 Suministro y Habilitación de Acero (Cajamarca)
A2770 Transporte de Acero a Obra 3 18-Jun-23 24-Jun-23 07-Aug-23 09-Aug-23 0% 100% 0% 0 0 0 0 Transporte de Acero a Obra
BCHT01-8.11 CONSTRUCCIÓN 224 01-Feb-23 21-Jul-23 01-Feb-23 A 12-Sep-23 0% 0% 64.77% 31608 27371 14886 42256 12-Sep-23, BCHT01-8.11 CONSTR
A1830 Liberación de área para Construcción 0 01-Feb-23 01-Feb-23 A 100% 100% 0% 0 0 0 0 Liberación de área para Construcción, 01-Feb-23 A
BCHT01-8.11.1 ETAPAS 1&2 187 04-Feb-23 05-Jul-23 04-Feb-23 A 24-Aug-23 0% 0% 81.99% 12773 10486 2304 12790 24-Aug-23, BCHT01-8.11.1 ETAPAS 1&2
BCHT01-8.11.1.4 TR AZO Y REPLANTEO 168 04-Feb-23 29-Jun-23 04-Feb-23 A 01-Aug-23 0% 0% 92.46% 24 22 2 24 01-Aug-23, BCHT01-8.11.1.4 TRAZO Y REPLANTEO
A2800 Trazo y Replanteo 168 04-Feb-23 29-Jun-23 04-Feb-23 A 01-Aug-23 92.46% 100% 92.46% 24 22 2 24 Trazo y Replanteo
BCHT01-8.11.1.1 ETAPA 1: SECTOR ACOMODACIÓN 158 05-Mar-23 05-Jul-23 05-Mar-23 A 21-Aug-23 0% 0% 80.83% 8921 7224 1714 8938 21-Aug-23, BCHT01-8.11.1.1 ETAPA 1: SECTOR ACOMODAC
BCHT01-8.11.1.1.1 SECTOR 1: ACOMODACIÓN 129 05-Mar-23 10-Jun-23 05-Mar-23 A 26-Jul-23 0% 0% 99.4% 4922 4908 30 4938 26-Jul-23, BCHT01-8.11.1.1.1 SECTOR 1: ACOMODACIÓN
BCHT01-8.11.1.1.1.1 MOVIMIENTO DE TIERRAS 5 05-Mar-23 10-Mar-23 05-Mar-23 A 10-Mar-23 A 0% 0% 100% 325 325 0 325 10-Mar-23 A, BCHT01-8.11.1.1.1.1 MOVIMIENTO DE TIERRAS
A1840 Excavación local para veredas 6 05-Mar-23 10-Mar-23 05-Mar-23 A 10-Mar-23 A 100% 100% 100% 325 325 0 325 Excavación local para veredas
BCHT01-8.11.1.1.1.2 CAPAS GRANULARES 57 08-Mar-23 04-May-23 08-Mar-23 A 04-May-23 A 0% 0% 0% 0 0 0 0 04-May-23 A, BCHT01-8.11.1.1.1.2 CAPAS GRANULARES
A1860 Colocación de Base granular para veredas 57 08-Mar-23 04-May-23 08-Mar-23 A 04-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas
BCHT01-8.11.1.1.1.3 CONCR ETO 125 09-Mar-23 10-Jun-23 09-Mar-23 A 26-Jul-23 0% 0% 99.36% 4597 4583 30 4613 26-Jul-23, BCHT01-8.11.1.1.1.3 CONCRETO
A1880 Construcción Veredas Tipo 1 120 09-Mar-23 20-May-23 09-Mar-23 A 21-Jul-23 99.55% 100% 99.66% 2890 2880 10 2890 Construcción Veredas Tipo 1
A1881 Construcción Escalera Tipo 2 88 11-Apr-23 20-May-23 11-Apr-23 A 21-Jul-23 88.67% 100% 96.56% 372 375 13 388 Construcción Escalera Tipo 2
A1882 Construcción Escalera Tipo 3 89 11-Apr-23 20-May-23 11-Apr-23 A 22-Jul-23 97.24% 100% 100% 373 373 0 373 Construcción Escalera Tipo 3
A1890 Construcción Rampa 2 90 13-Apr-23 10-Jun-23 13-Apr-23 A 26-Jul-23 85.01% 100% 99.32% 962 955 7 962 Construcción Rampa 2
97 24-Apr-23
BCHT01-8.11.1.1.2 SECTOR 4: AUXILIARES (TOPICO, ADMINISTRACIÓN) 17-Jun-23 24-Apr-23 A 02-Aug-23 0% 0% 83.16% 1736 1444 292 1736 02-Aug-23, BCHT01-8.11.1.1.2 SECTOR 4: AUXILIARES (TOPICO, ADMINISTRACIÓN
BCHT01-8.11.1.1.2.1 MOVIMIENTO DE TIERRAS 75 24-Apr-23 20-May-23 24-Apr-23 A 22-Jul-23 0% 0% 98.03% 110 108 2 110 22-Jul-23, BCHT01-8.11.1.1.2.1 MOVIMIENTO DE TIERRAS
A1910 Excavación local para veredas 75 24-Apr-23 20-May-23 24-Apr-23 A 22-Jul-23 97.31% 100% 98.03% 110 108 2 110 Excavación local para veredas
BCHT01-8.11.1.1.2.2 CAPAS GRANULARES 6 28-Apr-23 03-May-23 28-Apr-23 A 03-May-23 A 0% 0% 0% 0 0 0 0 03-May-23 A, BCHT01-8.11.1.1.2.2 CAPAS GRANULARES
A1930 Colocación de Base granular para veredas 6 28-Apr-23 03-May-23 28-Apr-23 A 03-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas
BCHT01-8.11.1.1.2.3 CONCR ETO 91 30-Apr-23 17-Jun-23 30-Apr-23 A 02-Aug-23 0% 0% 82.15% 1626 1336 290 1626 02-Aug-23, BCHT01-8.11.1.1.2.3 CONCRETO
A1945 Construcción Rampa 3 61 09-May-23 27-May-23 09-May-23 A 23-Jul-23 62.55% 100% 99.07% 565 560 5 565 Construcción Rampa 3
A1950 Construcción Veredas Tipo 1 80 30-Apr-23 17-Jun-23 30-Apr-23 A 29-Jul-23 87.66% 100% 93.71% 700 656 44 700 Construcción Veredas Tipo 1
A1980 Construcción Rampa Policlinico 4 13-Jun-23 16-Jun-23 19-Jul-23 A 02-Aug-23 33% 100% 33.24% 361 120 241 361 Construcción Rampa Policlinico
BCHT01-8.11.1.1.4 SECTOR 5: AUXILIARES (LAVANDERÍA) 95 06-May-23 05-Jul-23 06-May-23 A 21-Aug-23 0% 0% 38.52% 2263 872 1392 2264 21-Aug-23, BCHT01-8.11.1.1.4 SECTOR 5: AUXILIARES (LAVA
BCHT01-8.11.1.1.4.1 MOVIMIENTO DE TIERRAS 82 06-May-23 24-Jun-23 06-May-23 A 07-Aug-23 0% 0% 36.31% 165 60 105 165 07-Aug-23, BCHT01-8.11.1.1.4.1 MOVIMIENTO DE TIERRAS
A2350 Excavación local para veredas 82 06-May-23 24-Jun-23 06-May-23 A 07-Aug-23 35% 100% 36.31% 165 60 105 165 Excavación local para veredas
BCHT01-8.11.1.1.4.2 CAPAS GRANULARES 1 19-May-23 21-May-23 10-May-23 A 11-May-23 A 0% 0% 0% 0 0 0 0 11-May-23 A, BCHT01-8.11.1.1.4.2 CAPAS GRANULARES
A2360 Colocación de Base granular para veredas 1 19-May-23 21-May-23 10-May-23 A 11-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas
BCHT01-8.11.1.1.4.3 CONCR ETO 83 21-Jun-23 05-Jul-23 18-May-23 A 21-Aug-23 0% 0% 38.7% 2098 812 1286 2098 21-Aug-23, BCHT01-8.11.1.1.4.3 CONCRETO
A2370 Construcción Veredas Tipo 1 77 21-Jun-23 28-Jun-23 18-May-23 A 14-Aug-23 34.19% 100% 40.32% 1049 423 626 1049 Construcción Veredas Tipo 1
A2380 Construcción Veredas Tipo 2 83 28-Jun-23 05-Jul-23 18-May-23 A 21-Aug-23 34.15% 100% 37.08% 1049 389 660 1049 Construcción Veredas Tipo 2
BCHT01-8.11.1.3 ETAPA 2: ACOMODACIÓN 124 17-Mar-23 17-Jun-23 17-Mar-23 A 24-Aug-23 0% 0% 84.62% 3828 3239 589 3828 24-Aug-23, BCHT01-8.11.1.3 ETAPA 2: ACOMODACIÓN
BCHT01-8.11.1.3.4 SECTOR 2: ACOMODACIÓN 124 17-Mar-23 17-Jun-23 17-Mar-23 A 24-Aug-23 0% 0% 84.62% 3828 3239 589 3828 24-Aug-23, BCHT01-8.11.1.3.4 SECTOR 2: ACOMODACIÓ
BCHT01-8.11.1.3.4.1 MOVIMIENTO DE TIERRAS 113 17-Mar-23 20-May-23 17-Mar-23 A 21-Jul-23 0% 0% 98% 276 271 6 276 21-Jul-23, BCHT01-8.11.1.3.4.1 MOVIMIENTO DE TIERRAS
A2400 Excavación local para veredas 113 17-Mar-23 20-May-23 17-Mar-23 A 21-Jul-23 98% 100% 98% 276 271 6 276 Excavación local para veredas
BCHT01-8.11.1.3.4.2 CAPAS GRANULARES 9 27-Apr-23 06-May-23 27-Apr-23 A 06-May-23 A 0% 0% 0% 0 0 0 0 06-May-23 A, BCHT01-8.11.1.3.4.2 CAPAS GRANULARES
A2410 Colocación de Base granular para veredas 9 27-Apr-23 06-May-23 27-Apr-23 A 06-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas
BCHT01-8.11.1.3.4.3 CONCR ETO 100 10-Apr-23 17-Jun-23 10-Apr-23 A 24-Aug-23 0% 0% 83.58% 3552 2969 583 3552 24-Aug-23, BCHT01-8.11.1.3.4.3 CONCRETO
A2420 Construcción Veredas Tipo 1 89 10-Apr-23 20-May-23 10-Apr-23 A 21-Jul-23 99.22% 100% 100% 1858 1858 0 1858 Construcción Veredas Tipo 1
A2430 Construcción Escalera Tipo 1 68 02-May-23 27-May-23 02-May-23 A 22-Jul-23 74.67% 100% 98.86% 157 155 2 157 Construcción Escalera Tipo 1
A2440 Construcción Rampa 1 71 12-May-23 17-Jun-23 09-May-23 A 24-Aug-23 51.2% 100% 62.19% 1537 956 581 1537 Construcción Rampa 1
BCHT01-8.11.4 ETAPAS 3@5 137 18-Apr-23 08-Jul-23 18-Apr-23 A 02-Sep-23 0% 0% 71.48% 10671 11699 4668 16367 02-Sep-23, BCHT01-8.11.4 ETAPAS 3@5
BCHT01-8.11.4.1 ETAPA 3: AUXILIARES 92 03-May-23 29-Jun-23 03-May-23 A 14-Aug-23 0% 0% 78.22% 4133 3233 900 4133 14-Aug-23, BCHT01-8.11.4.1 ETAPA 3: AUXILIARES
BCHT01-8.11.4.1.5 SECTOR 1: ENTRENAMIENTO Y RECREACIÓN 92 03-May-23 29-Jun-23 03-May-23 A 14-Aug-23 0% 0% 69.71% 2919 2035 884 2919 14-Aug-23, BCHT01-8.11.4.1.5 SECTOR 1: ENTRENAMIENTO Y REC
BCHT01-8.11.4.1.5.2 MOVIMIENTO DE TIERRAS 68 03-May-23 03-Jun-23 03-May-23 A 23-Jul-23 0% 0% 98.78% 484 478 6 484 23-Jul-23, BCHT01-8.11.4.1.5.2 MOVIMIENTO DE TIERRAS
A2125 Escarificado, nivelación y compactación de subrasante 67 03-May-23 03-Jun-23 03-May-23 A 22-Jul-23 65.12% 100% 97.65% 98 96 2 98 Escarificado, nivelación y compactación de subrasante
A2130 Excavación local para veredas 67 04-May-23 03-Jun-23 04-May-23 A 23-Jul-23 95.49% 100% 99.07% 386 382 4 386 Excavación local para veredas
BCHT01-8.11.4.1.5.3 CAPAS GRANULARES 2 26-May-23 13-Jun-23 09-May-23 A 10-May-23 A 0% 0% 0% 0 0 0 0 10-May-23 A, BCHT01-8.11.4.1.5.3 CAPAS GRANULARES
A2140 Colocación de Base granular para veredas 1 26-May-23 30-May-23 09-May-23 A 10-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas

Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
LOSAS Y VEREDAS SEM 25 Classic Schedule Layout 24-Jul-23 11:15
Activity ID Activity Name Original BL Project BL Project Start Finish Performance Schedule % Labor Units BL Project Actual Remaining At Completion February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023
Duration Start Finish % Complete Complete % Complete Labor Units Labor Units Labor Units Labor Units
29 05 12 19 26 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24
A2210 Colocación de Base granular para camino 2 30-May-23 13-Jun-23 09-May-23 A 10-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para camino
BCHT01-8.11.4.1.5.4 CONCR ETO 84 11-May-23 29-Jun-23 11-May-23 A 14-Aug-23 0% 0% 63.94% 2435 1557 878 2435 14-Aug-23, BCHT01-8.11.4.1.5.4 CONCRETO
A2160 Construcción Veredas Tipo 1 61 11-May-23 03-Jun-23 11-May-23 A 24-Jul-23 91.42% 100% 99.6% 1049 1045 4 1049 Construcción Veredas Tipo 1
A2170 Construcción Rampa 1 78 15-Jun-23 29-Jun-23 17-May-23 A 14-Aug-23 29.84% 100% 36.94% 1386 512 874 1386 Construcción Rampa 1
BCHT01-8.11.4.1.1 SECTOR 2: SEGURIDAD Y ALMACÉN 64 12-May-23 17-Jun-23 09-May-23 A 25-Jul-23 0% 0% 98.65% 1214 1198 16 1214 25-Jul-23, BCHT01-8.11.4.1.1 SECTOR 2: SEGURIDAD Y ALMACÉN
BCHT01-8.11.4.1.1.1 MOVIMIENTO DE TIERRAS 53 02-Jun-23 02-Jun-23 19-May-23 A 24-Jul-23 0% 0% 95.61% 165 158 7 165 24-Jul-23, BCHT01-8.11.4.1.1.1 MOVIMIENTO DE TIERRAS
A2480 Excavación local para veredas 53 02-Jun-23 02-Jun-23 19-May-23 A 24-Jul-23 92.16% 100% 95.61% 165 158 7 165 Excavación local para veredas
BCHT01-8.11.4.1.1.2 CAPAS GRANULARES 1 12-May-23 14-May-23 09-May-23 A 10-May-23 A 0% 0% 0% 0 0 0 0 10-May-23 A, BCHT01-8.11.4.1.1.2 CAPAS GRANULARES
A2490 Colocación de Base granular para veredas 1 12-May-23 14-May-23 09-May-23 A 10-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas
BCHT01-8.11.4.1.1.3 CONCR ETO 64 12-May-23 17-Jun-23 09-May-23 A 25-Jul-23 0% 0% 99.13% 1049 1040 9 1049 25-Jul-23, BCHT01-8.11.4.1.1.3 CONCRETO
A2500 Construcción Veredas Tipo 1 64 12-May-23 17-Jun-23 09-May-23 A 25-Jul-23 90.98% 100% 99.13% 1049 1040 9 1049 Construcción Veredas Tipo 1
BCHT01-8.11.4.5 ETAPA 1@2 : LOSAS DEPORTIVAS 134 18-Apr-23 08-Jul-23 18-Apr-23 A 30-Aug-23 0% 0% 83.42% 4453 8466 1683 10149 30-Aug-23, BCHT01-8.11.4.5 ETAPA 1@2 : LOSAS
BCHT01-8.11.4.5.6 SECTOR 3: CANCHAS MULTIUSOS 118 04-May-23 08-Jul-23 04-May-23 A 30-Aug-23 0% 0% 82.4% 3608 7666 1638 9304 30-Aug-23, BCHT01-8.11.4.5.6 SECTOR 3: CANC
BCHT01-8.11.4.5.6.1 MOVIMIENTO DE TIERRAS 54 03-Jun-23 21-Jun-23 01-Jun-23 A 05-Aug-23 0% 0% 99.84% 158 5844 10 5854 05-Aug-23, BCHT01-8.11.4.5.6.1 MOVIMIENTO DE TIERRAS
A2020 Excavación local para zapatas cerco 42 03-Jun-23 05-Jun-23 01-Jun-23 A 26-Jul-23 32.78% 100% 81.12% 27 22 5 27 Excavación local para zapatas cerco
A2030 Relleno para zapatas cerco 23 16-Jun-23 17-Jun-23 02-Jul-23 A 05-Aug-23 18.38% 100% 69.4% 14 10 4 14 Relleno para zapatas cerco
A2032 Nivelación de canchas 25 17-Jun-23 21-Jun-23 13-Jun-23 A 25-Jul-23 97.98% 100% 100% 117 5812 0 5812 Nivelación de canchas
BCHT01-8.11.4.5.6.2 CAPAS GRANULARES 73 14-May-23 24-Jun-23 09-May-23 A 26-Jul-23 0% 0% 66.29% 151 100 51 151 26-Jul-23, BCHT01-8.11.4.5.6.2 CAPAS GRANULARES
A2035 Colocación de Sub base granular 0 14-May-23 18-May-23 09-May-23 A 10-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Sub base granular
A2040 Colocación de Base granular canchas 3 21-Jun-23 24-Jun-23 19-Jul-23 A 26-Jul-23 0% 100% 66.29% 151 100 51 151 Colocación de Base granular canchas
BCHT01-8.11.4.5.6.3 CONCR ETO 81 04-May-23 08-Jul-23 04-May-23 A 20-Aug-23 0% 0% 86.23% 1384 1194 191 1385 20-Aug-23, BCHT01-8.11.4.5.6.3 CONCRETO
A2070 Concreto fundación cerco 79 04-May-23 17-Jun-23 04-May-23 A 03-Aug-23 75.68% 100% 95.82% 225 216 9 225 Concreto fundación cerco
A2071 Concreto para canchas 28 15-May-23 08-Jul-23 27-Jun-23 A 20-Aug-23 76.76% 100% 84.36% 1159 978 181 1159 Concreto para canchas
BCHT01-8.11.4.5.6.4 ELEMENTOS DE CONTROL Y SEGURIDAD 83 16-Jun-23 05-Jul-23 09-Jun-23 A 30-Aug-23 0% 0% 26.81% 1701 456 1245 1701 30-Aug-23, BCHT01-8.11.4.5.6.4 ELEMENTOS DE
A2080 Construcción Cerco perimetral canchas 52 16-Jun-23 25-Jun-23 09-Jun-23 A 13-Aug-23 19.7% 100% 28.23% 1615 456 1159 1615 Construcción Cerco perimetral canchas
A2090 Suministro e instalación de equipamiento deportivo canchas 10 26-Jun-23 05-Jul-23 21-Aug-23 30-Aug-23 0% 100% 0% 86 0 86 86 Suministro e instalación de equipamiento deportivo ca
BCHT01-8.11.4.5.6.5 SISTEMAS DE ILU MINACIÓ N DE CANCHAS 88 26-Jun-23 07-Jul-23 25-May-23 A 20-Aug-23 0% 0% 33.66% 214 72 142 214 20-Aug-23, BCHT01-8.11.4.5.6.5 SISTEMAS DE ILUMINACIÓN
A2110 Concreto Fundación Poste 69 26-Jun-23 02-Jul-23 25-May-23 A 15-Aug-23 60.17% 100% 90.38% 80 72 8 80 Concreto Fundación Poste
A2115 Poste de iluminación de acero galvanizado 3 03-Jul-23 05-Jul-23 16-Aug-23 18-Aug-23 0% 100% 0% 102 0 102 102 Poste de iluminación de acero galvanizado
A2120 Conexión a Tablero co n Tapa atornillada tipo Crouse-Hinds Mod WJB10806
2 06-Jul-23 07-Jul-23 19-Aug-23 20-Aug-23 0% 100% 0% 32 0 32 32 Conexión a Tablero co n Tapa atornillada tipo Crouse-Hinds Mod W
BCHT01-8.11.4.5.1 SECTOR 4: ACCESOS VEHICULARES 132 18-Apr-23 23-Jun-23 18-Apr-23 A 28-Aug-23 0% 0% 94.68% 845 800 45 845 28-Aug-23, BCHT01-8.11.4.5.1 SECTOR 4: ACCESO
BCHT01-8.11.4.5.1.1 MOVIMIENTO DE TIERRAS 1 18-Apr-23 19-Apr-23 18-Apr-23 A 19-Apr-23 A 0% 0% 0% 0 0 0 0 19-Apr-23 A, BCHT01-8.11.4.5.1.1 MOVIMIENTO DE TIERRAS
A2450 Escarificado, nivelación y compactación de subrasante 1 18-Apr-23 19-Apr-23 18-Apr-23 A 19-Apr-23 A 100% 100% 0% 0 0 0 0 Escarificado, nivelación y compactación de subrasante
BCHT01-8.11.4.5.1.2 CAPAS GRANULARES 1 19-Apr-23 19-Apr-23 19-Apr-23 A 19-Apr-23 A 0% 0% 100% 800 800 0 800 19-Apr-23 A, BCHT01-8.11.4.5.1.2 CAPAS GRANULARES
A2460 Construcción de Base granular para camino 1 19-Apr-23 19-Apr-23 19-Apr-23 A 19-Apr-23 A 100% 100% 100% 800 800 0 800 Construcción de Base granular para camino
BCHT01-8.11.4.5.1.3 ELEMENTOS DE CONTROL Y SEGURIDAD 8 16-Jun-23 23-Jun-23 20-Aug-23 28-Aug-23 0% 0% 0% 45 0 45 45 28-Aug-23, BCHT01-8.11.4.5.1.3 ELEMENTOS DE C
A2470 Señalética vertical 8 16-Jun-23 23-Jun-23 20-Aug-23 28-Aug-23 0% 100% 0% 45 0 45 45 Señalética vertical
BCHT01-8.11.4.4 SECTOR 3: ZONA DE ESTACIONAMIENTO 117 28-May-23 02-Jul-23 09-May-23 A 02-Sep-23 0% 0% 0% 2085 0 2085 2085 02-Sep-23, BCHT01-8.11.4.4 SECTOR 3: ZON
BCHT01-8.11.4.4.1 MOVIMIENTO DE TIERRAS 6 23-Jun-23 24-Jun-23 11-Aug-23 16-Aug-23 0% 0% 0% 275 0 275 275 16-Aug-23, BCHT01-8.11.4.4.1 MOVIMIENTO DE TIE RRAS
A2510 Excavación local para veredas 6 23-Jun-23 24-Jun-23 11-Aug-23 16-Aug-23 0% 100% 0% 275 0 275 275 Excavación local para veredas
BCHT01-8.11.4.4.2 CAPAS GRANULAR ES 5 28-May-23 29-May-23 09-May-23 A 10-May-23 A 0% 0% 0% 0 0 0 0 10-May-23 A, BCHT01-8.11.4.4.2 CAPAS GRANULARES
A2520 Colocación de Base granular para veredas 5 28-May-23 29-May-23 09-May-23 A 10-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas
BCHT01-8.11.4.4.3 CONCRETO 5 25-Jun-23 26-Jun-23 12-Aug-23 16-Aug-23 0% 0% 0% 614 0 614 614 16-Aug-23, BCHT01-8.11.4.4.3 CONCRETO
A2530 Concreto Fundación Bolardos 5 25-Jun-23 26-Jun-23 12-Aug-23 16-Aug-23 0% 100% 0% 614 0 614 614 Concreto Fundación Bolardos
BCHT01-8.11.4.4.4 ELEMENTOS DE CONTROL Y SEGURIDAD 19 27-Jun-23 02-Jul-23 15-Aug-23 02-Sep-23 0% 0% 0% 1195 0 1195 1195 02-Sep-23, BCHT01-8.11.4.4.4 ELEMENTOS D
A2540 Suministro e Instalación de Bolardos 10 27-Jun-23 28-Jun-23 15-Aug-23 24-Aug-23 0% 100% 0% 1157 0 1157 1157 Suministro e Instalación de Bolardos
A2550 Demarcación 5 29-Jun-23 30-Jun-23 25-Aug-23 29-Aug-23 0% 100% 0% 34 0 34 34 Demarcación
A2560 Señaletica Vertica l 4 01-Jul-23 02-Jul-23 30-Aug-23 02-Sep-23 0% 100% 0% 4 0 4 4 Señaletica Vertical
BCHT01-8.11.7 ETAPA 4: MODULOS 108 11-May-23 06-Jul-23 09-May-23 A 25-Aug-23 0% 0% 75.15% 4463 3021 999 4020 25-Aug-23, BCHT01-8.11.7 ETAPA 4: MODULOS
BCHT01-8.11.7.4 SECTOR 1: MODULOS 18 AL 12 108 11-May-23 06-Jul-23 09-May-23 A 25-Aug-23 0% 0% 75.15% 4463 3021 999 4020 25-Aug-23, BCHT01-8.11.7.4 SECTOR 1: MODULOS 18 A
BCHT01-8.11.7.4.1 MOVIMIENTO DE TIERRAS 51 19-May-23 20-May-23 17-May-23 A 21-Jul-23 0% 0% 98.94% 551 545 6 551 21-Jul-23, BCHT01-8.11.7.4.1 MOVIMIENTO DE TIERRAS
A2570 Excavación local para veredas 51 19-May-23 20-May-23 17-May-23 A 21-Jul-23 95.37% 100% 98.94% 551 545 6 551 Excavación local para veredas
BCHT01-8.11.7.4.2 CAPAS GRANULAR ES 2 17-May-23 25-May-23 09-May-23 A 10-May-23 A 0% 0% 0% 0 0 0 0 10-May-23 A, BCHT01-8.11.7.4.2 CAPAS GRANULARES
A2580 Colocación de Base granular para veredas 2 17-May-23 25-May-23 09-May-23 A 10-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas
BCHT01-8.11.7.4.3 CONCRETO 106 11-May-23 06-Jul-23 11-May-23 A 25-Aug-23 0% 0% 71.37% 3912 2476 993 3469 25-Aug-23, BCHT01-8.11.7.4.3 CONCRETO
A2599 Construcción Veredas Tipo 1 72 11-May-23 01-Jul-23 11-May-23 A 25-Jul-23 83.44% 100% 90.1% 3191 2476 272 2748 Construcción Veredas Tipo 1
A2600 Construcción Rampa 4 10 25-Jun-23 06-Jul-23 15-Aug-23 25-Aug-23 0% 100% 0% 721 0 721 721 Construcción Rampa 4
BCHT01-8.11.6 ETAPA 5: MODULOS 98 20-May-23 24-Jun-23 09-May-23 A 15-Aug-23 0% 0% 84.01% 2577 2165 412 2577 15-Aug-23, BCHT01-8.11.6 ETAPA 5: MODULOS
BCHT01-8.11.6.1 SECTOR 2: MODULOS 11 AL 6 98 20-May-23 24-Jun-23 09-May-23 A 15-Aug-23 0% 0% 84.01% 2577 2165 412 2577 15-Aug-23, BCHT01-8.11.6.1 SECTOR 2: MODULOS 11 AL 6
BCHT01-8.11.6.1.1 MOVIMIENTO DE TIERRAS 37 20-May-23 24-May-23 01-Jun-23 A 23-Jul-23 0% 0% 91.31% 551 503 48 551 23-Jul-23, BCHT01-8.11.6.1.1 MOVIMIENTO DE TIERRAS
A2610 Excavación local para veredas 37 20-May-23 24-May-23 01-Jun-23 A 23-Jul-23 88.02% 100% 91.31% 551 503 48 551 Excavación local para veredas
BCHT01-8.11.6.1.2 CAPAS GRANULAR ES 2 18-Jun-23 24-Jun-23 09-May-23 A 10-May-23 A 0% 0% 0% 0 0 0 0 10-May-23 A, BCHT01-8.11.6.1.2 CAPAS GRANULARES
A2620 Colocación de Base granular para veredas 2 18-Jun-23 24-Jun-23 09-May-23 A 10-May-23 A 100% 100% 0% 0 0 0 0 Colocación de Base granular para veredas
BCHT01-8.11.6.1.3 CONCRETO 90 08-Jun-23 20-Jun-23 17-May-23 A 15-Aug-23 0% 0% 82.02% 2026 1662 364 2026 15-Aug-23, BCHT01-8.11.6.1.3 CONCRETO
A2630 Construcción Veredas Tipo 1 70 17-Jun-23 17-Jun-23 17-May-23 A 26-Jul-23 88.03% 100% 95.02% 1749 1662 87 1749 Construcción Veredas Tipo 1
A2640 Construcción Escalera Tipo 4 10 08-Jun-23 14-Jun-23 27-Jul-23 05-Aug-23 0% 100% 0% 120 0 120 120 Construcción Escalera Tipo 4
A2650 Construcción Escalera Tipo 5 10 14-Jun-23 20-Jun-23 05-Aug-23 15-Aug-23 0% 100% 0% 157 0 157 157 Construcción Escalera Tipo 5
BCHT01-8.11.3 PARTIDAS ADICIONALES 38 08-Jun-23 07-Jul-23 20-Jul-23 A 29-Aug-23 0% 0% 0% 1123 0 6502 6502 29-Aug-23, BCHT01-8.11.3 PARTIDAS ADICIONALE
A2810 Preparación de superficie de concreto estructural, con medios manuales
28 08-Jun-23 05-Jul-23 23-Jul-23 19-Aug-23 0% 100% 0% 400 0 400 400 Preparación de superficie de concreto estructural, con medios manu
A2820 Escalera para ingreso a modulos tipo 01 18 08-Jun-23 27-Jun-23 20-Jul-23 A 13-Aug-23 0% 100% 0% 102 0 2146 2146 Escalera para ingreso a modulos tipo 01
A2830 Escalera para ingreso a modulos tipo 02 7 18-Jun-23 02-Jul-23 20-Jul-23 A 20-Aug-23 0% 100% 0% 22 0 476 476 Escalera para ingreso a modulos tipo 02
A2840 Escalera para ingreso a modulos tipo 03 9 26-Jun-23 06-Jul-23 21-Aug-23 29-Aug-23 0% 100% 0% 62 0 1535 1535 Escalera para ingreso a modulos tipo 03
A2850 Suministro e Instalación de Grass Sintético H=0.05m 8 29-Jun-23 07-Jul-23 21-Aug-23 28-Aug-23 0% 100% 0% 538 0 538 538 Suministro e Instalación de Grass Sintético H=0.05m
A2860 Losa para ambulancia 24 06-Aug-23 29-Aug-23 0% 0% 0% 0 0 1408 1408 Losa para ambulancia
BCHT01-8.11.2 POST-CONSTRUCCION Y CIERRE 14 07-Jul-23 21-Jul-23 30-Aug-23 12-Sep-23 0% 0% 0% 0 0 0 0 12-Sep-23, BCHT01-8.11.2 POST-
BCHT01-8.11.2.1 PRESENTACIÓN FINAL Y ACEPTACION 11 07-Jul-23 18-Jul-23 30-Aug-23 09-Sep-23 0% 0% 0% 0 0 0 0 09-Sep-23, BCHT01-8.11.2.1 PRESEN
A2280 Presentación Final de Dossier de Calidad 2 07-Jul-23 09-Jul-23 30-Aug-23 31-Aug-23 0% 100% 0% 0 0 0 0 Presentación Final de Dossier de Calidad
A2290 Producción y Entrega de Planos Finales 3 10-Jul-23 12-Jul-23 01-Sep-23 04-Sep-23 0% 100% 0% 0 0 0 0 Producción y Entrega de Planos Finales
A2300 Aceptación por Bechtel 6 13-Jul-23 18-Jul-23 04-Sep-23 09-Sep-23 0% 100% 0% 0 0 0 0 Aceptación por Bechtel
BCHT01-8.11.2.2 INICIO DE DESMOVILIZACIO N 5 16-Jul-23 21-Jul-23 08-Sep-23 12-Sep-23 0% 0% 0% 0 0 0 0 12-Sep-23, BCHT01-8.11.2.2 INICI
A2310 Fin de Desmovilización del Sitio de los Trab ajos 5 16-Jul-23 21-Jul-23 08-Sep-23 12-Sep-23 0% 91.67% 0% 0 0 0 0 Fin de Desmovilización del Sitio de l

Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation