CÁLCULO DE LOS REAJUSTES

OBRA:

ENTIDAD:
UBICACIÓN:
EJECUTA:
RESIDENTE:
SUPERVISOR:

1. PRESUPUESTO PRINCIPAL:

EJECUTADO (SIN IGV) PROGRAMADO (SIN IGV) "K" del mes de pago REAJUSTES (V*(K-1))
REAJUSTE
VAL
REAL PROG. REAL PROG. RECONOCIDO
REAL PROGRAMADO MES K REAL PROGRAM
ACUMULADO ACUMULADO ACUMULADO ACUMULADO

VAL 01 (FEB 2023) 349,205.70 349,205.70 104,694.17 104,694.17 Ene-23 1.029 10,126.97 10,126.97 3,036.13 3,036.13 10,126.97
VAL 02 (MAR 2023) 376,110.12 725,315.82 399,312.15 504,006.32 Feb-23 1.038 14,292.18 24,419.15 15,173.86 18,209.99 14,292.18
VAL 03 (ABR 2023) 178,104.58 903,420.40 398,074.69 902,081.01 Mar-23 1.039 6,946.08 31,365.23 15,524.91 33,734.90 6,946.08
VAL 04 (MAY 2023) 198,437.19 1,101,857.59 461,259.30 1,363,340.31 Abr-23 1.038 7,540.61 38,905.84 17,527.85 51,262.75 7,540.61
VAL 05 (JUN 2023) 0.00 1,101,857.59 416,159.29 1,779,499.60 0.000
VAL 06 (JUL 2023) 0.00 1,101,857.59 34,340.56 1,813,840.16 0.000
TOTAL 1,101,857.59 1,813,840.16 38,905.84 51,262.75 38,905.84

NOTA: LA OBRA ESTE MES HA CAIDO EN ATRASO POR LO QUE SE COMPARA LOS REAJUSTES ACUMULADOS SIENDO MENOR EL ACUMULADO EJECUTADO, POR LO QUE SE PAGA EL REAJUSTE REAL EJECUTADO