VALORIZACIÓN N° 12 DEL ADICIONAL DEDUCTIVO VINCULANTE DE OBRA Nº 01

CONTROL DE METRADOS EJECUTADOS


DEL 01/12/2022 AL 21/12/2022

METRADO METRADOS EJECUTADOS SALDO


PARTIDA DESCRIPCION UND %
BASE ANTERIOR ACTUAL ACUMULADO AVANCE METRADO

01 ADICIONAL VINCULANTE - SISTEMA DE AGUA POTABLE


01.01 LINEA DE CONDUCCION -
01.01.01 MOVIMIENTO DE TIERRAS -
01.01.01.01 EXCAVACIÓN A PULSO DE ZANJAS T.S.R, H=0.25M m 750.00 750.00 750.00 100.00% -
01.01.01.02 REFINE Y NIVELACION ZANJA T.S.R m 750.00 750.00 750.00 100.00% -
01.01.01.03 RELLENO COMP. DE ZANJA CON MAT. PROPIO SELECCIONADO m 750.00 750.00 750.00 100.00% -
01.01.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 15.00 15.00 15.00 100.00% -
01.01.02 TUBERIAS
01.01.02.01 SUMINISTRO E INSTALACION DE TUBERIA HDPE 1 1/2" m 750.00 750.00 750.00 100.00% -
01.02 RESERVORIO CIRCULAR ( V = 20 M3) 0.00
01.02.01 CERCO PERIMETRICO METALICO 0.00
01.02.01.01 CARPINTERIA METALICA 0.00
01.02.01.01.01 CERCO METALICO CON MALLA ELECTROSOLDADA EXAGONAL H=2.0 m 38.47 0.00 0.00% 38.47
01.02.01.01.02 POSTE METALICO F° G° 3PULG x 2.5mm, H=3.10m und 8.00 0.00 0.00% 8.00
01.02.01.01.03 PUERTA METALICA CON MALLA EXAGONAL D=1.0x2.0M GLB 1.00 0.00 0.00% 1.00
01.03 OTROS 0.00
01.03.01 FLETE TERRESTRE DESDE CHICLAYO GLB 1.00 1.00 1.00 100.00% -
01.03.02 FLETE RURAL AGUA P. GLB 1.00 1.00 1.00 100.00% -

1
VALORIZACIÓN N° 12 DEL ADICIONAL DEDUCTIVO VINCULANTE DE OBRA Nº 01
CONTROL DE METRADOS EJECUTADOS
DEL 01/12/2022 AL 21/12/2022

METRADO METRADOS EJECUTADOS SALDO


PARTIDA DESCRIPCION UND %
BASE ANTERIOR ACTUAL ACUMULADO AVANCE METRADO

02 ADICIONAL VINCULANTE - PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES


02.01 CERCO PERIMETRICO DE PTAR
02.01.01 CARPINTERIA METALICA
02.01.01.01 CERCO METALICO CON MALLA ELECTROSOLDADA EXAGON m 173.41 104.05 34.68 138.73 80.00% 34.68
02.01.01.02 POSTE METALICO F° G° 2PULG x 2.5mm, H=3.10m und 62.00 50.00 50.00 80.65% 12.00
02.01.01.03 PUERTA METALICA CON MALLA EXAGONAL D=1.05*2.0M GLB 1.00 0.00 0.00% 1.00
02.02 FLETE TERRESTRE 0.00
02.02.01 FLETE TERRESTRE - SISTEMA ALCANTARILLADO est 1.00 1.00 1.00 100.00% -

2
VALORIZACIÓN N° 12 DEL ADICIONAL DEDUCTIVO VINCULANTE DE OBRA Nº 01
CONTROL DE METRADOS EJECUTADOS
DEL 01/12/2022 AL 21/12/2022

METRADO METRADOS EJECUTADOS % SALDO


PARTIDA UND
BASE ANTERIOR ACTUAL ACUMULADO AVANCE METRADO

03 ADICIONAL VINCULANTE - UNIDADES BASICA DE SENEAMIENTO


03.01 FLETE 0.00 0.00
03.01.01 FLETE TERRESTRE UBS est 1.00 1.00 0.00 1.00 100.00% 0.00
03.01.02 FLETE RURAL UBS est 1.00 1.00 0.00 1.00 100.00% 0.00
03.02 MODULO DE SSHH - EDIFICACIONES 0.00
03.02.01 CUBIERTAS 0.00
03.02.01.01 COBERTURA DE PLANCHA CALAMINA N° 030-UBSm2 2,010.35 2,010.35 2,010.35 100.00% 0.00
03.02.02 CARPINTERIA DE MADERA 0.00
03.02.02.01 MARCO DE MADERA Y PUERTA TRIPLAY CONTR und 284.00 282.00 282.00 99.30% 2.00
03.02.02.02 VENTANA DE MADERA CON MALLA MOSQUITEROund 284.00 282.00 282.00 99.30% 2.00
03.03 SISTEMA DE TRATAMIENTO DE AGUAS RESIDUALES 0.00
03.03.01 POZO PERCOLADOR 0.00
03.03.01.01 CONCRETO ARMADO 0.00
03.03.01.01.01 TAPA DE CONCRETO PREFABRICADA F´c=175 k und 284.00 284.00 0.00 284.00 100.00% 0.00
03.03.01.02 ALBAÑILERIA 0.00 0.00 0.00
03.03.01.02.01 ASENTADO DE LADRILLO PARA POZO m2 2,158.49 2,158.49 0.00 2,158.49 100.00% 0.00

3
VALORIZACIÓN N° 12 DEL ADICIONAL DEDUCTIVO VINCULANTE DE OBRA Nº 01
CONTROL DE METRADOS EJECUTADOS

DEL 01/12/2022 AL 21/12/2022

METRADO METRADOS EJECUTADOS % SALDO


PARTIDA DESCRIPCION UND
BASE ANTERIOR ACTUAL ACUMULADO AVANCE METRADO

02 ADICIONAL VINCULANTE - PLANTA DE TRATAMIENTO DE AGUAS RES 0.00 0.00 0.00 0.00
02.01 CERCO PERIMETRICO DE PTAR 0.00 0.00 0.00 0.00
02.01.01 CARPINTERIA METALICA 0.00 0.00 0.00 0.00
02.01.01.01 CERCO METALICO CON MALLA ELECTROSOLDADA EXAGONAL H= 173.41 104.05 34.68 138.73 80.00% 34.68
02.01.01.02 POSTE METALICO F° G° 2PULG x 2.5mm, H=3.10m 62.00 50.00 50.00 80.65% 12.00
02.01.01.03 PUERTA METALICA CON MALLA EXAGONAL D=1.05*2.0M 1.00 0.00 0.00 0.00% 1.00
02.02 FLETE TERRESTRE 0.00 0.00 0.00 0.00
02.02.01 FLETE TERRESTRE - SISTEMA ALCANTARILLADO 1.00 1.00 0.00 1.00 100.00% 0.00

4
ADJUDICACIÓN : LP N° 002-2018-MDSJL/CS MODALIDAD DE EJECUCIÓN : PRECIO UNITARIO
OBRA PLAZO DE EJECUCIÓN : 50 DÍAS CALENDARIOS
: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"

ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS VALOR REFERENCIAL : S/. 945,597.93 Inc/IGV.
UBICACIÓN : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA FECHA BASE 10/25/2020
CONTRATISTA : CONSORCIO LICUPIS
SUPERVISOR : CONSORCIO YAKU

VALORIZACIÓN N° 12 DEL ADICIONAL DEDUCTIVO VINCULANTE DE OBRA Nº 01


DEL 01/12/2022 AL 21/12/2022

PRESUPUESTO BASE AVANCE


SALDOS
PARTIDA DESCRPCION UNID METRADO P.U. PARCIAL ANTERIOR ACTUAL ACUMULADO
(S/.) (S/.) METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL % METRADO PARCIAL %

01 ADICIONAL VINCULANTE - SISTEMA DE AGUA POTABLE 39,085.61 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03 OTROS 0.00 1,320.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00%
01.03.01 FLETE TERRESTRE DESDE CHICLAYO GLB 1.00 664.09 664.09 1.00 664.09 0.00 0.00 1.00 664.09 100.00% 0.00 0.00 0.00%
01.03.02 FLETE RURAL AGUA P. GLB 1.00 656.50 656.50 1.00 656.50 0.00 0.00 1.00 656.50 100.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00 0.00 0.00
02 ADICIONAL VINCULANTE - PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES 0.00 29,932.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00%
02.01 CERCO PERIMETRICO DE PTAR 0.00 28,149.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00%
02.01.01 CARPINTERIA METALICA 0.00 28,149.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00%
02.01.01.01 CERCO METALICO CON MALLA ELECTROSOLDADA EXAGONAL H=2.00m m 173.41 114.44 19,845.04 104.05 11,907.48 34.68 3,968.78 138.73 15,876.26 80.00% 34.68 3,968.78 20.00%
02.02 FLETE TERRESTRE 0.00 1,783.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00%
02.02.01 FLETE TERRESTRE - SISTEMA ALCANTARILLADO est 1.00 1,783.18 1,783.18 1.00 1,783.18 0.00 0.00 1.00 1,783.18 100.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00 0.00 0.00
03 ADICIONAL VINCULANTE - UNIDADES BASICA DE SENEAMIENTO 0.00 630,243.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01 FLETE 0.00 249,994.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00%
03.01.01 FLETE TERRESTRE UBS est 1.00 170,457.17 170,457.17 1.00 170,457.17 0.00 0.00 1.00 170,457.17 100.00% 0.00 0.00 0.00%
03.01.02 FLETE RURAL UBS est 1.00 79,537.50 79,537.50 1.00 79,537.50 0.00 0.00 1.00 79,537.50 100.00% 0.00 0.00 0.00%

COSTO DIRECTO DEL VALOR REFERENCIAL S/. 699,261.94 682,789.85 3,968.78 686,758.63 12,503.31
GASTOS GENERALES 10.0 % 10.00% S/. 69,926.19 68,278.99 396.87 68,675.86 1,250.33
UTILIDAD 4.6 % 4.60% S/. 32,166.05 31,408.33 182.56 31,590.90 575.15
SUB - TOTAL S/. 801,354.18 782,477.17 4,548.21 787,025.39 14,328.79
I.G.V. (18 % ) 18.00% S/. 144,243.75 140,845.89 818.68 141,664.57 2,579.18
TOTAL S/. 945,597.93 923,323.06 5,366.89 928,689.96 16,907.97
PORCENTAJE 100.00% 97.64% 0.57% 98.21% 1.79%
ADJUDICACIÓN : LP N° 002-2018-MDSJL/CS
: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS –
OBRA PROVINCIA DE CHOTA - REGION CAJAMARCA"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
UBICACIÓN : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
CONTRATISTA : CONSORCIO LICUPIS
SUPERVISOR : CONSORCIO YAKU

CONTROL DE VALORIZACIONES EJECUTADAS VS. PROGRAMADAS

PROGRAMADO (Sin. IGV) EJECUTADO (Sin. IGV) %


MES VALORIZACIÓN Nº AVANCE AVANCE PORCENTAJE AVANCE AVANCE PORCENTAJE EJEC./
MENSUAL ACUMULADO ACUMULADO MENSUAL ACUMULADO ACUMULADO PROG.

00
Oct-20 01 119,455.96 119,455.96 14.91% 119,455.96 119,455.96 14.91% 100.00%
Nov-20 02 152,730.41 272,186.37 33.97% 152,730.41 272,186.37 33.97% 100.00%
Dec-20 03 39,838.12 312,024.49 38.94% 39,838.12 312,024.49 38.94% 100.00%
Jan-21 0.00 312,024.49 38.94% 0.00 312,024.49 38.94% 100.00%
Feb-21 SUSPENSION 0.00 312,024.49 38.94% 0.00 312,024.49 38.94% 100.00%
Mar-21 POR LLUVIAS 0.00 312,024.49 38.94% 0.00 312,024.49 38.94% 100.00%
Apr-21 0.00 312,024.49 38.94% 0.00 312,024.49 38.94% 100.00%
May-21 0.00 312,024.49 38.94% 0.00 312,024.49 38.94% 100.00%
Jun-21 0.00 312,024.49 38.94% 0.00 312,024.49 38.94% 100.00%
Jul-21 04 37,042.84 349,067.33 43.56% 37,042.84 349,067.33 43.56% 100.00%
Aug-21 05 51,476.80 400,544.13 49.98% 51,476.80 400,544.13 49.98% 100.00%
Sep-21 06 78,350.28 478,894.41 59.76% 78,350.28 478,894.41 59.76% 100.00%
Oct-21 07 109,685.63 588,580.04 73.45% 109,685.63 588,580.04 73.45% 100.00%
Nov-21 08 39,451.60 628,031.64 78.37% 39,451.60 628,031.64 78.37% 100.00%
Dec-21 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
Jan-22 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
Feb-22 SUSPENSION 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
Mar-22 POR LLUVIAS 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
Apr-22 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
May-22 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
Jun-22 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
Jul-22 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
Aug-22 628,031.64 78.37% 0.00 628,031.64 78.37% 100.00%
Sep-22 09 66,128.33 694,159.97 86.62% 66,128.33 694,159.97 86.62% 100.00%
Oct-22 10 74,315.54 768,475.51 95.90% 74,315.54 768,475.51 95.90% 100.00%
Nov-22 11 16,439.34 784,914.85 97.95% 14,001.66 782,477.17 97.64% 99.69%
Dec-22 12 16,439.34 801,354.18 100.00% 4,548.21 787,025.38 98.21% 98.21%
TOTAL 801,354.18 787,025.38
ADJUDICACIÓN : LP N° 002-2018-MDSJL/CS
OBRA : "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS –
PROVINCIA DE CHOTA - REGION CAJAMARCA"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
UBICACIÓN : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
CONTRATISTA : CONSORCIO LICUPIS
SUPERVISOR : CONSORCIO YAKU
(% )

ADICIONAL DEDUCTIVO VINCULANTE DE OBRA N° 01


AV AN CE M E NS UA L AC UM U L AD O

GRÁFICO DEL AVANCE FÍSICO PROGRAMADO VS. AVANCE FÍSICO EJECUTADO


VALORIZACION ADIICIONAL DEDUCTIVO VINCUALNTE DE OBRA N° 01 - DEL 01/12/22 AL 21/12/22

110%
105% 100.00%
97.95%
100% 95.90%
98.21%
97.64%
95% 95.90%
90% 86.62%
85% 86.62%
78.37% 78.37% 78.37% 78.37%
80% 73.45% 78.37% 78.37% 78.37% 78.37% 78.37%
75% 73.45%
70%
65% 59.76%
60% 59.76%
55% 49.98%
50% 43.56% 49.98%
45% 38.94% 38.94% 38.94% 38.94% 43.56%
40% 33.97% 38.94% 38.94%38.94%
26-Oct20
35% 33.97%
30%
25%
20% 14.91% PROGR AMAD O

15% 14.91% EJ E C U TA DO

10%
Sep-20
5% 31 DIC.22
0% 0.00%
Sep-20 Nov-20 Jan-21 Mar-21 May-21 Jul-21 Sep-21 Nov-21 J an-22 Mar-22 May-22 Jul-22 Sep-22 Nov-22

PLAZO DE EJECUCIÓN (Meses)

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS (Sin/ IGV) PORCENTAJES MONTOS (Sin/ IGV) PORCENTAJES
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
Sep-20 0.00 0.00 0.00% 0.00% Sep-20 0.00 0.00 0.00% 0.00%
Oct-20 119,455.96 119,455.96 14.91% 14.91% Oct-20 119,455.96 119,455.96 14.91% 14.91%
Nov-20 152,730.41 272,186.37 19.06% 33.97% Nov-20 152,730.41 272,186.37 19.06% 33.97%
Dec-20 39,838.12 312,024.49 4.97% 38.94% Dec-20 39,838.12 312,024.49 4.97% 38.94%
Jan-21 0.00 312,024.49 0.00% 38.94% Jan-21 0.00 312,024.49 0.00% 38.94%
Feb-21 0.00 312,024.49 0.00% 38.94% Feb-21 0.00 312,024.49 0.00% 38.94%
Mar-21 0.00 312,024.49 0.00% 38.94% Mar-21 0.00 312,024.49 0.00% 38.94%
Apr-21 0.00 312,024.49 0.00% 38.94% Apr-21 0.00 312,024.49 0.00% 38.94%
May-21 0.00 312,024.49 0.00% 38.94% May-21 0.00 312,024.49 0.00% 38.94%
Jun-21 0.00 312,024.49 0.00% 38.94% Jun-21 0.00 312,024.49 0.00% 38.94%
Jul-21 37,042.84 349,067.33 4.62% 43.56% Jul-21 37,042.84 349,067.33 4.62% 43.56%
Aug-21 51,476.80 400,544.13 6.42% 49.98% Aug-21 51,476.80 400,544.13 6.42% 49.98%
Sep-21 78,350.28 478,894.41 9.78% 59.76% Sep-21 78,350.28 478,894.41 9.78% 59.76%
Oct-21 109,685.63 588,580.04 13.69% 73.45% Oct-21 109,685.63 588,580.04 13.69% 73.45%
Nov-21 39,451.60 628,031.64 4.92% 78.37% Nov-21 39,451.60 628,031.64 4.92% 78.37%
Dec-21 0.00 628,031.64 0.00% 78.37% Dec-21 0.00 628,031.64 0.00% 78.37%
Jan-22 0.00 628,031.64 0.00% 78.37% Jan-22 0.00 628,031.64 0.00% 78.37%
Feb-22 0.00 628,031.64 0.00% 78.37% Feb-22 0.00 628,031.64 0.00% 78.37%
Mar-22 0.00 628,031.64 0.00% 78.37% Mar-22 0.00 628,031.64 0.00% 78.37%
Apr-22 0.00 628,031.64 0.00% 78.37% Apr-22 0.00 628,031.64 0.00% 78.37%
May-22 0.00 628,031.64 0.00% 78.37% May-22 0.00 628,031.64 0.00% 78.37%
Jun-22 0.00 628,031.64 0.00% 78.37% Jun-22 0.00 628,031.64 0.00% 78.37%
Jul-22 0.00 628,031.64 0.00% 78.37% Jul-22 0.00 628,031.64 0.00% 78.37%
Aug-22 0.00 628,031.64 0.00% 78.37% Aug-22 0.00 628,031.64 0.00% 78.37%
Sep-22 66,128.33 694,159.97 8.25% 86.62% Sep-22 66,128.33 694,159.97 8.25% 86.62%
Oct-22 74,315.54 768,475.51 9.27% 95.90% Oct-22 74,315.54 768,475.51 9.27% 95.90%
Nov-22 16,439.34 784,914.85 2.05% 97.95% Nov-22 14,001.66 782,477.17 1.75% 97.64%
Dec-22 16,439.34 801,354.18 2.05% 100.00% Dec-22 4,548.21 787,025.38 0.57% 98.21%
TOTAL 801,354.18 100.00% TOTAL 787,025.38 98.21%
ADJUDICACIÓ : LP N° 002-2018-MDSJL/CS

OBRA : "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE
LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
UBICACIÓN : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
CONTRATISTA: CONSORCIO LICUPIS
SUPERVISOR : CONSORCIO YAKU
(S /.)
AV ANCE M E NS U AL ACUM U LADO

900,000 GRÁFICO DEL AVANCE FINANCIERO PROGRAMADO VS VANCE FINANCIERO EJECUTADO


VALORIZACION ADICIONAL DEDUCTIVO VINCUALNTE DE OBRA N° 01 - DEL 01/12/2022 AL 21/12/2022
801,354.18
784,914.85
800,000 768,475.51
787,025.38
782,477.17
768,475.51
694,159.97
700,000 694,159.97
628,031.64 628,031.64 628,031.64
588,580.04 628,031.64
628,031.64 628,031.64
628,031.64
600,000
588,580.04

500,000
478,894.41
478,894.41
400,544.13
400,000 400,544.13
349,067.33
312,024.49
312,024.49 312,024.49 349,067.33
300,000 272,186.37 312,024.49 312,024.49
312,024.49
272,186.37 P ROGRAMA DO

E J E CUTADO

200,000

119,455.96
119,455.96
100,000

26-Oct20
0.00 31 DIC.-
0 0.00 22
Sep-20 Nov-20 Jan-21 Mar-21 May-21 PLAZOSep-21
Jul-21 DE EJECUCIÓN
Nov-21 (Meses)
Jan-22 Mar-22 May-22 Jul-22 Sep-22 Nov-22

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS (Sin/ IGV) PORCENTAJES MONTOS (Sin/ IGV) PORCENTAJES
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
Sep-20 0.00 0.00 0.00% 0.00% Sep-20 0.00 0.00 0.00% 0.00%
Oct-20 119,455.96 119,455.96 14.91% 14.91% Oct-20 119,455.96 119,455.96 14.91% 14.91%
Nov-20 152,730.41 272,186.37 19.06% 33.97% Nov-20 152,730.41 272,186.37 19.06% 33.97%
Dec-20 39,838.12 312,024.49 4.97% 38.94% Dec-20 39,838.12 312,024.49 4.97% 38.94%
Jan-21 0.00 312,024.49 0.00% 38.94% Jan-21 0.00 312,024.49 0.00% 38.94%
Feb-21 0.00 312,024.49 0.00% 38.94% Feb-21 0.00 312,024.49 0.00% 38.94%
Mar-21 0.00 312,024.49 0.00% 38.94% Mar-21 0.00 312,024.49 0.00% 38.94%
Apr-21 0.00 312,024.49 0.00% 38.94% Apr-21 0.00 312,024.49 0.00% 38.94%
May-21 0.00 312,024.49 0.00% 38.94% May-21 0.00 312,024.49 0.00% 38.94%
Jun-21 0.00 312,024.49 0.00% 38.94% Jun-21 0.00 312,024.49 0.00% 38.94%
Jul-21 37,042.84 349,067.33 4.62% 43.56% Jul-21 37,042.84 349,067.33 4.62% 43.56%
Aug-21 51,476.80 400,544.13 6.42% 49.98% Aug-21 51,476.80 400,544.13 6.42% 49.98%
Sep-21 78,350.28 478,894.41 9.78% 59.76% Sep-21 78,350.28 478,894.41 9.78% 59.76%
Oct-21 109,685.63 588,580.04 13.69% 73.45% Oct-21 109,685.63 588,580.04 13.69% 73.45%
Nov-21 39,451.60 628,031.64 4.92% 78.37% Nov-21 39,451.60 628,031.64 4.92% 78.37%
Dec-21 0.00 628,031.64 0.00% 78.37% Dec-21 0.00 628,031.64 0.00% 78.37%
Jan-22 0.00 628,031.64 0.00% 78.37% Jan-22 0.00 628,031.64 0.00% 78.37%
Feb-22 0.00 628,031.64 0.00% 78.37% Feb-22 0.00 628,031.64 0.00% 78.37%
Mar-22 0.00 628,031.64 0.00% 78.37% Mar-22 0.00 628,031.64 0.00% 78.37%
Apr-22 0.00 628,031.64 0.00% 78.37% Apr-22 0.00 628,031.64 0.00% 78.37%
May-22 0.00 628,031.64 0.00% 78.37% May-22 0.00 628,031.64 0.00% 78.37%
Jun-22 0.00 628,031.64 0.00% 78.37% Jun-22 0.00 628,031.64 0.00% 78.37%
Jul-22 0.00 628,031.64 0.00% 78.37% Jul-22 0.00 628,031.64 0.00% 78.37%
Aug-22 0.00 628,031.64 0.00% 78.37% Aug-22 0.00 628,031.64 0.00% 78.37%
Sep-22 66,128.33 694,159.97 8.25% 86.62% Sep-22 66,128.33 694,159.97 8.25% 86.62%
Oct-22 74,315.54 768,475.51 9.27% 95.90% Oct-22 74,315.54 768,475.51 9.27% 95.90%
Nov-22 16,439.34 784,914.85 2.05% 97.95% Nov-22 14,001.66 782,477.17 1.75% 97.64%
Dec-22 16,439.34 801,354.18 2.05% 100.00% Dec-22 4,548.21 787,025.38 0.57% 98.21%
TOTAL 801,354.18 100.00% TOTAL 782,477.17 98.21%
ADJUDICACIÓN : LP N° 002-2018-MDSJL/CS MODALIDAD DE EJECUCIÓN : PRECIOS UNITARIOS
OBRA : "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PLAZO DE EJECUCIÓN : 50 DÍAS CALENDARIOS
ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS VALOR REFERENCIAL 5,056,090.99 Inc/IGV.
UBICACIÓN : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA MONTO OFERTADO 4,284,822.87 Inc/IGV.
CONTRATISTA : CONSORCIO LICUPIS FECHA BASE 10/25/2020
INSPECTOR : CONSORCIO YAKU FACTOR DE RELACIÓN 0.00000

CÁLCULO DEL FACTOR DE REAJUSTE " K "


FÓRMULA POLINÓMICA Nº 01 : (UNIDAD BASICA DE SANEAMIENTO)

(*) K = 0.561*(MOr/MOo) + 0.050*(AGr/AGo) + 0.051*(Cr/Co) + 0.086*(AMr/AMo) + 0.080*(Tr/To) + 0.073*(EIr/EIo) + 0.099*(Ir/Io)

(*) Fórmula de Expediente Inicial

ÍNDICE
NOV-2016 DIC-2016 Jan-17 Feb-17 Mar-17
% BASE
ÍNDICE DESCRIPCIÓN SÍMBOLO COEFIC.
INCIDENCIA (JUN-
ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF.
2016)

47 MANO DE OBRA INC. LEYES SOCIALES MO 0.561 100.000% 544.12 562.24 0.580 562.24 0.580 563.25 0.581 563.25 0.581 0.0000
05 AGREGADO GRUESO AG 0.050 100.000% 440.21 435.35 0.049 437.61 0.050 441.11 0.050 448.41 0.051 0.0000
21 CEMENTO PORTLAND TIPO I C 0.051 100.000% 462.57 462.57 0.051 462.57 0.051 462.57 0.051 459.40 0.051
02 ACERO CONSTRUCCION LISO AM 0.086 59.302% 471.28 484.88 0.088 484.81 0.087 477.63 0.087 468.50 0.086
43 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA 40.698% 695.66 700.57 698.83 706.95 705.84
72 TUBERIA PVC PARA AGUA T 0.080 100.000% 411.73 416.93 0.081 416.46 0.081 413.21 0.080 412.75 0.080 0.0000
49 MAQUINARIA Y EQUIPO IMPORTADO EI 0.073 100.000% 297.17 304.74 0.075 304.12 0.075 299.32 0.074 293.65 0.072
39 INDICE GENERAL DE PRECIOS AL CONSUMIDO I 0.099 100.000% 429.07 434.89 0.100 436.35 0.101 437.38 0.101 438.80 0.101 0.0000
1.000 K (Nov-16) 1.024 K (Dic-16) 1.025 K (Ene-17) 1.024 K (Feb-17) 1.022 K (Mar-17) 0.0000
ADJUDICACIÓN : LP N° 002-2018-MDSJL/CS

PROYECTO : "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"

ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS


UBICACIÓN : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
CONTRATISTA : CONSORCIO LICUPIS
SUPERVISIÓN : CONSORCIO YAKU

CONTROL DE AMORTIZACIÓN DEL ADELANTO DIRECTO


VALORIZACIÓN N° 12 DEL ADICIONAL DEDUCTIVO VINCULANTE DE OBRA Nº 01

DATOS GENERALES AMORTIZACIÓN DEL ADELANTO EN EFECTIVO DEL ADELANTO

MONTO CONTRATADO (Inc/IGV) S/. 10,992,284.17 VALORIZACIÓN AMORTIZACIÓN CARTA FIANZA MONTO (S/.) VIGENCIA
MONTO CONTRATADO (Sin/IGV) S/. 9,315,495.06 MES F.P. Nº 01 (%) F.P. Nº 01 ACUMUL. SALDO
CARTA FIANZA
ADELANTO SOLICITADO (Inc/IGV) S/. 1,099,228.42 #REF! 931,549.51 0.57% 5,287.16 5,287.16 926,262.35 N° 30035660 1,099,228.42 11-Jun-19
ADELANTO SOLICITADO (Sin/IGV) S/. 931,549.51 #REF! 931,549.51
#REF! 931,549.51
#REF! 931,549.51
ENTREGA DEL ADELANTO S/. (Sin / IGV) #REF! 931,549.51
ITEM PARCIAL ACUMULADO SALDO #REF! 931,549.51
1 931,549.51 931,549.51 0.00 Oct-20 931,549.51
Nov-20 931,549.51 OBSERVACIONES :
Dec-20 931,549.51 Carta Fianza emitida por LA POSITIVA SEGUROS
#REF! 931,549.51
#REF! 931,549.51
#REF! 931,549.51
LOS MONTOS EN EL CUADRO DE AMORTIZACIÓN
NO INCLUYEN EL IGV
5,287.16 0.00
ADJUDICACIÓN : LP N° 002-2018-MDSJL/CS
PROYECTO : "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS
UBICACIÓN : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA
CONTRATISTA : CONSORCIO LICUPIS
SUPERVISIÓN: : CONSORCIO YAKU

CONTROL DE AMORTIZACIÓN DEL ADELANTO DE MATERIALES


VALORIZACION N° 01

DATOS GENERALES AMORTIZACIÓN DEL ADELANTO EN EFECTIVO DEL ADELANTO


MONTO CONTRATADO (Inc/IGV) S/. 10,992,284.17 VALORIZACIÓN AMORTIZACIÓN CARTA FIANZA MONTO (S/.) VIGENCIA
MONTO CONTRATADO (Sin/IGV) S/. 9,315,495.06 MES F.P. Nº 01 (%) F.P. Nº 01 ACUMUL. SALDO
CARTA FIANZA
ADELANTO SOLICITADO (Inc/IGV) S/. 2,198,456.84 #REF! 1,863,099.03 0.57% 10,574.31 10,574.31 1,852,524.72 N° 30035661 2,198,456.84 7/9/2019
ADELANTO SOLICITADO (Sin/IGV) S/. 1,863,099.03 #REF!
#REF!
#REF!
ENTREGA DEL ADELANTO S/. (Sin / IGV) #REF!
ITEM PARCIAL ACUMULADO SALDO #REF!
1 1,863,099.03 1,863,099.03 0.00 Oct-20
Nov-20 OBSERVACIONES :
Dec-20 Carta Fianza emitida por LA POSITIVA SEGUROS
#REF!
LOS MONTOS EN EL CUADRO DE AMORTIZACIÓN #REF!
NO INCLUYEN EL IGV #REF!
10,574.31
ADJUDICACIÓN : LP N° 002-2018-MDSJL/CS
: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA POTABLE Y SANEAMIENTO DEL DISTRITO DE
OBRA SAN JUAN DE LICUPIS – PROVINCIA DE CHOTA - REGION CAJAMARCA"
ENTIDAD : MUNICIPALIDAD DISTRITAL DE SAN JUAN DE LICUPIS

UBICACIÓN : SAN JUAN DE LICUPIS - CHOTA - CAJAMARCA


CONTRATISTA : CONSORCIO LICUPIS
RESIDENTE : ING. JORGE ALEJANDRO GONZALEZ ZAVALA
SUPERVISION : CONSORCIO YAKU
SUPERVISOR : ING. FERNANDO EUSEBIO SUCLUPE CHAPOÑAN

VALORIZACIÓN N° 12 DEL ADICIONAL DEDUCTIVO VINCULANTE DE OBRA Nº 01


DEL 01/12/2022 AL 21/12/2022

ÍTEM CONCEPTO PARCIAL TOTAL

1.0.0 Valorización Adicional Deductivo Vinculante Nº 01


1.0.1 Valorización Contractual 4,548.21

1.1.0 Reintegros
1.1.1 Reajuste reconocido 0.00
1.1.2 Regularizacion del Reajuste 0.00

TOTAL MONTO BRUTO (A) 4,548.21

2.0.0 DESCUENTOS

TOTAL DESCUENTOS (B) 0.00

TOTAL NETO ( A-B) 4,548.21


I.G.V. 18.00% 818.68

TOTAL A CANCELAR AL CONTRATISTA S/. 5,366.89

SON: CINCO MIL TRESCIENTOS SESENTA Y SEIS CON 89/100 SOLES