Está en la página 1de 2

CRONOGRAMA DE ADQUISICIÓN DE INSUMOS

ACTIVIDAD: "MANTENIMIENTO DE LA PLANTA DE TRATAMIENTO DE AGUA RESIDUALES DEL CENTRO POBLADO DE LLUPA, DISTRITO DE INDEPENDENCIA-HUARAZ-ANCASH"

Caserio : LLUPA Provincia : HUARAZ


Distrito : INDEPENDENCIA Departamento : ANCASH

% AVANCE PARCIAL 55.75% 44.25%


% AVANCE ACUMULADO 55.75% 100.00%

Descripción Und Cantidad Precio S/. Parcial MES 01 MES 02


PEON hh 2,635.01 12.38 32,621.37 S/ 18,186.41 S/ 14,434.96
OPERADOR DE EQUIPO LIVIANO hh 41.35 13.76 569.02 S/ 317.23 S/ 251.79
OPERARIO hh 776.37 17.55 13,625.29 S/ 7,596.10 S/ 6,029.19
OFICIAL hh 234.65 13.76 3,228.80 S/ 1,800.06 S/ 1,428.74
TOPOGRAFO hh 4.07 17.55 71.34 S/ 39.77 S/ 31.57
CEMENTO PORTLAND TIPO I (42.5KG) bol 597.23 25.42 15,181.48 S/ 8,463.68 S/ 6,717.80
HORMIGON m³ 1.74 59.32 103.47 S/ 57.68 S/ 45.79
PIEDRA CHANCADA 1/2" m³ 34.75 69.80 2,425.72 S/ 1,352.34 S/ 1,073.38
ARENA GRUESA m³ 47.76 69.80 3,333.80 S/ 1,858.59 S/ 1,475.21
GRAVA PARA FILTRO DE 1"-2" m³ 99.81 177.97 17,762.74 S/ 9,902.73 S/ 7,860.01
TAPA DE CONCRETO ARMADO PARA BUZON INCLUYE MARCO FF und 6.00 220.70 1,324.20 S/ 738.24 S/ 585.96
CAL HIDRATADA DE 10kg bol 4.51 5.93 26.75 S/ 14.91 S/ 11.84
ESTACA DE MADERA und 12.74 1.50 19.11 S/ 10.65 S/ 8.46
PINTURA ESMALTE gal 0.62 28.81 17.84 S/ 9.95 S/ 7.89
ALAMBRE NEGRO RECOCIDO N° 16 kg 256.84 4.66 1,196.88 S/ 667.26 S/ 529.62
CLAVOS PARA MADERA C/C DE 3" kg 58.23 4.66 271.36 S/ 151.28 S/ 120.08
PERNO HEXAGONAL ROSCA CORRIENTE 3/4 X 12" und 18.00 5.93 106.74 S/ 59.51 S/ 47.23
MADERA TORNILLO INC.CORTE P/ENCOFRADO p² 980.20 7.67 7,518.13 S/ 4,191.36 S/ 3,326.77
MADERA ROLLIZA D=4" und 2.00 20.33 40.66 S/ 22.67 S/ 17.99
CARTEL DE OBRA DE 3.60Mx2.40M und 1.00 101.69 101.69 S/ 56.69 S/ 45.00
CASCO DE SEGURIDAD und 15.00 8.47 127.05 S/ 70.83 S/ 56.22
LENTES DE POLICARBONATO LUNA CLARA und 15.00 4.23 63.45 S/ 35.37 S/ 28.08
GUANTES DE CUERO par 15.00 7.62 114.30 S/ 63.72 S/ 50.58
GUANTES DE JEBE par 15.00 8.47 127.05 S/ 70.83 S/ 56.22
BOTAS DE CAUCHO par 15.00 22.88 343.20 S/ 191.33 S/ 151.87
BOTAS DE CUERO PUNTA DE ACERO par 4.00 38.35 153.40 S/ 85.52 S/ 67.88
TRAJE ESCAFANDRA EN PVC und 14.00 67.80 949.20 S/ 529.18 S/ 420.02
GUANTES MOSQUETEROS par 10.00 21.19 211.90 S/ 118.13 S/ 93.77
BOTAS DE HUELE TIPO FERRETERA par 15.00 23.73 355.95 S/ 198.44 S/ 157.51
RESPIRADOR DE MEDIA CARA DOBLE CARTUCHO und 10.00 21.19 211.90 S/ 118.13 S/ 93.77
RESPIRADOR PURIFICADOR Y CON SUMINISTRO DE AIRE und 10.00 93.22 932.20 S/ 519.70 S/ 412.50
MOSQUETEROS DE SEGURIDAD DE 3/4" und 4.00 46.62 186.48 S/ 103.96 S/ 82.52
LINEA DE VIDA VERTICAL und 4.00 76.27 305.08 S/ 170.08 S/ 135.00
ESLINGA CON ABSORVEDOR DE CHOQUE TUBULAR DOBLE TERMINAL EN "Y" CON MOSQUETERO DE 3/4" und 2.00 50.84 101.68 S/ 56.69 S/ 44.99
ARNES MULTIPROPOSITO PARA TRABAJOS EN ESPACIOS CONFINADOS und 5.00 127.12 635.60 S/ 354.35 S/ 281.25
LEJIA DESINFECTANTE DE 5 LT und 3.00 8.56 25.68 S/ 14.32 S/ 11.36
ALCOHOL EN GEL X 380 ML und 3.00 16.95 50.85 S/ 28.35 S/ 22.50
ALCOHOL 96° X 1000cc l 3.00 11.44 34.32 S/ 19.13 S/ 15.19
BALDE DE 18LT und 125.47 8.47 1,062.73 S/ 594.47 S/ 470.26
BOLSA ROJA DE 20X30 und 90.00 0.85 76.50 S/ 42.65 S/ 33.85
ESCOBA CON MANGO PVC und 3.00 5.08 15.24 S/ 8.50 S/ 6.74
MATERIALES DIDACTICOS gbl 1.00 169.49 169.49 S/ 94.49 S/ 75.00
CAPACITACION TECNICA gbl 1.00 1,500.00 1,500.00 S/ 836.25 S/ 663.75

Página 1
CRONOGRAMA DE ADQUISICIÓN DE INSUMOS

ACTIVIDAD: "MANTENIMIENTO DE LA PLANTA DE TRATAMIENTO DE AGUA RESIDUALES DEL CENTRO POBLADO DE LLUPA, DISTRITO DE INDEPENDENCIA-HUARAZ-ANCASH"

Caserio : LLUPA Provincia : HUARAZ


Distrito : INDEPENDENCIA Departamento : ANCASH

% AVANCE PARCIAL 55.75% 44.25%


% AVANCE ACUMULADO 55.75% 100.00%
CAPACITACION SOCIAL gbl 1.00 1,500.00 1,500.00 S/ 836.25 S/ 663.75
SOLDADURA CELLOCORD P 3/32" kg 704.40 16.95 11,939.58 S/ 6,656.32 S/ 5,283.26
TUBERIA DE FIERRO GALVANIZADO DE 2" m 229.40 16.49 3,782.88 S/ 2,108.96 S/ 1,673.92
TUBERIA PVC SAP DN=110mm CP-10 NTP ISO 4435 m 76.51 15.50 1,185.84 S/ 661.11 S/ 524.73
PEGAMENTO P/TUBERIA PVC 1/4 gln gln 5.47 63.56 347.45 S/ 193.70 S/ 153.75
TAPA DE CONCRETO ARMADO PARA BUZON INCLUYE MARCO FF und 16.00 84.74 1,355.84 S/ 755.88 S/ 599.96
ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60 kg 1,565.94 5.00 7,829.69 S/ 4,365.05 S/ 3,464.64
SERRUCHO und 15.00 16.95 254.25 S/ 141.74 S/ 112.51
ALAMBRE NEGRO RECOCIDO N° 8 kg 177.19 4.66 825.68 S/ 460.32 S/ 365.36
CLAVOS PARA MADERA C/C DE 2 1/2" kg 70.72 4.66 329.56 S/ 183.73 S/ 145.83
CLAVOS PARA MADERA C/C DE 4" kg 177.19 4.66 825.68 S/ 460.32 S/ 365.36
CINTA PLASTICA DE SEÑAL DE PELIGRO X 500M rll 2.00 27.19 54.38 S/ 30.32 S/ 24.06
SEÑALES DE ADVERTENCIA und 5.00 25.42 127.10 S/ 70.86 S/ 56.24
JABON LIQUIDO DE 250ml und 4.50 7.20 32.40 S/ 18.06 S/ 14.34
PAPEL TOALLA X 200M rll 3.00 8.20 24.60 S/ 13.71 S/ 10.89
CONTENEDOR DE COLOR VERDE und 2.00 37.20 74.40 S/ 41.48 S/ 32.92
CONTENEDOR DE COLOR AZUL und 2.00 37.20 74.40 S/ 41.48 S/ 32.92
CONTENEDOR DE COLOR NEGRO und 2.00 37.20 74.40 S/ 41.48 S/ 32.92
COMBA DE 25 LBS und 82.09 110.17 9,043.59 S/ 5,041.80 S/ 4,001.79
ANGULO DE FIERRO NEGRO DE 3/4"x3/4"x3/16" m 724.68 13.33 9,660.00 S/ 5,385.45 S/ 4,274.55
YEE PVC SAL 4" und 2.00 17.00 34.00 S/ 18.96 S/ 15.05
CODO PVC SAL 4" X 90° und 11.00 7.63 83.93 S/ 46.79 S/ 37.14
VALVULA CHECK und 1.00 97.45 97.45 S/ 54.33 S/ 43.12
BOTIQUIN CON MEDICAMENTOS BASICOS und 1.00 220.00 220.00 S/ 122.65 S/ 97.35
MASCARILLA QUIRURGICA cja 2.00 15.25 30.50 S/ 17.00 S/ 13.50
LADRILLO KK DE ARCILLA 9x14x24cm und 14,309.19 2.17 31,050.94 S/ 17,310.90 S/ 13,740.04
CLAVOS PARA MADERA C/C DE 3" kg 4.26 5.51 23.49 S/ 13.10 S/ 10.39
MALLA ALAMBRE F°G°N°10 COCADA 2"X2" m² 413.97 23.73 9,823.46 S/ 5,476.58 S/ 4,346.88
MATERIAL DE PRESTAMO ZARANDEADO m³ 1.49 29.66 44.06 S/ 24.56 S/ 19.50
PIEDRA GRANDE DE 8" m³ 2.92 50.85 148.69 S/ 82.89 S/ 65.80
CANDADO FORTE 50 MM. und 2.00 66.10 132.20 S/ 73.70 S/ 58.50
PUERTA DE F°G° CON MALLA OLIMPICA 2.05mx2.30m (DOBLE HOJA) und 2.00 296.91 593.82 S/ 331.05 S/ 262.77
THINNER gal 28.05 16.95 475.52 S/ 265.10 S/ 210.42
PINTURA ANTICORROSIVA gal 28.02 29.66 831.17 S/ 463.38 S/ 367.79
MEZCLADORA DE CONCRETO DE 9 -11P3 hm 48.14 29.66 1,427.92 S/ 796.07 S/ 631.85
VIBRADOR DE CONCRETO 4 HP 2.40" hm 35.89 21.18 760.08 S/ 423.74 S/ 336.34
ESTACION TOTAL INCL. PRISMAS JALONES TELESCOPICOS hm 4.09 21.20 86.63 S/ 48.30 S/ 38.33
BOMBA INDUSTRIAL PARA LODOS hm 163.29 45.00 7,346.20 S/ 4,095.51 S/ 3,250.69
EQUIPO DE SOLDAR hm 171.48 19.50 3,343.93 S/ 1,864.24 S/ 1,479.69
GRUPO ELECTROGENO hm 115.48 15.50 1,789.87 S/ 997.85 S/ 792.02
MOTOSIERRA hm 18.67 15.00 280.00 S/ 156.10 S/ 123.90
COMPACTADOR VIBTATORIO TIPO PLANCHA 4HP hm 56.73 29.66 1,682.72 S/ 938.12 S/ 744.60
COMPRESORA NEUMATICA 87HP 250-330 PCM hm 131.36 127.12 16,698.12 S/ 9,309.20 S/ 7,388.92
MOTOSOLDADORA DE 250 AMP. hm 1.33 16.95 22.60 S/ 12.60 S/ 10.00
COMPRESORA DE AIRE hm 45.74 25.42 1,162.84 S/ 648.28 S/ 514.56
HERRAMIENTAS MANUALES %mo 3.00 50,115.82 1,502.36 S/ 837.57 S/ 664.79
SC SERVICIO DE AGUA PARA OBRA m³ 14.23 2.00 28.45 S/ 15.86 S/ 12.59
SC MOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1.00 2,000.00 2,000.00 S/ 1,115.00 S/ 885.00
SC FLETE TERRESTRE glb 1.00 5,423.73 5,423.73 S/ 3,023.73 S/ 2,400.00
ALQUILER DE ALMACEN Y OFICINA mes 1.50 200.00 300.00 S/ 167.25 S/ 132.75
COSTO DIRECTO (S/.) S/ 244,088.04 S/ 136,079.97 S/ 108,008.07
ACUMULADO (S/.) S/ 136,079.97 S/ 244,088.04

Página 2