PRESUPUESTO OFICIAL
PROYECTO: CONSTRUCCION DE UNA CASA DE DOS NIVELES EN CALLE LAS FLORES BLOCK A # 5 Y AVENIDA LAS DALIAS COLONIA VISTA HERMOSA SAN MIGUEL
ELABORADO POR: ING. CARLOS, NORMA, JONAS FECHA: MAYO DEL 2011
355.23 $355.23
3,690.52 $3,690.52
716.12 $716.12
3,328.82 $3,328.82
1,679.79 $1,679.79
3,268.07 $3,268.07
966.49 $966.49
57.57 $57.57
5,643.40 $5,643.40
1,300.77 $1,300.77
1,041.95 $1,041.95
1,236.76 $1,236.76
1,018.63 $1,018.63
4,078.98 $4,078.98
2,381.55 $2,381.55
988.32 $988.32
527.85 $527.85
2,465.58 $2,465.58
1,377.00 $1,377.00
$36,123.40
18,793.40 $18,793.40
610.12 $610.12
$19,403.52
2,587.67 $2,587.67
1,130.74 $1,130.74
2,177.43 $2,177.43
$5,895.84
4,247.91 $4,247.91
731.28 $731.28
1,278.63 $1,278.63
2,828.29 $2,828.29
$9,086.11
6,231.60 $6,231.60
$6,231.60
7,686.36 $7,686.36
$7,686.36
1,212.74 $1,212.74
$1,212.74
1,564.89 $1,564.89
8,247.14 $8,247.14
262.73 $262.63
440.71 $440.71
233.79 $233.79
199.39 $199.39
80.15 $80.15
3,338.81 $3,338.81
84.29 $84.29
204.61 $204.61
142.46 $142.46
51.49 $51.49
89.85 $89.85
3,784.10 $3,784.10
$18,724.41
3,207.46 $3,207.46
$3,207.46
201.61 $201.61
$201.61
703.74 $703.74
$703.74
392.40 $392.40
$392.40
441.83 $441.83
257.08 $257.08
$698.91
$114,903.56 $114,903.56
FORMATO No. 7-A
OBRAS A LICITAR
PLAN DE OFERTA
PROYECTO: CONSTRUCCION DE UNA CASA DE DOS NIVELES EN LA CALLE LAS FLORES BLOCK A #5 Y AVENIDA LAS FLORES COLONIA VISTA HERMOSA SAN MIGUEL.
4460 comunidad
PROYECTO: CONSTRUCCION DE CENTRO DE DESARROLLO INFANTIL, EN CASERIO SANTA ROSA, CANTON, SAN MARCOS. MCPIO. DE SAN ANTONIO EL MOSCO, DPTO. DE SAN MIGUEL.
ELABORADO POR: ING. JOSE MARTIR DIAZ GUEVARA FECHA: FEBRERO DE 2010
IVA
VALOR DE LA OFERTA NUEVE MIL QUINIENTOS SESENTA 41/100 (IVA INCLUIDO) $10,676.43
FORMATO No. 7-C
APORTE DE COMUNIDAD
PROYECTO: CONSTRUCCION DE CENTRO DE DESARROLLO INFANTIL, EN CASERIO SANTA ROSA, CANTON, SAN MARCOS. MCPIO. DE SAN ANTONIO EL MOSCO, DPTO. DE SAN MIGUEL.
ELABORADO POR: ING. JOSE MARTIR DIAZ GUEVARA FECHA: FEBRERO DE 2010
IVA -
ASIGNACIÓN
1.1 - PERSONAL ASIGNADO SUELDO
HORAS MES HOMBRE SUB - TOTAL TOTAL
AL PROYECTO* MENSUAL
DIARIAS*
1.2 - PRESTACIONES
I.S.S.S. $ 3.00 $ 3.00
AFP $ 2.70 $ 2.70
Aguinaldo y Vacaciones $ - $ -
Indemnizaciones por Despido $ - $ -
Otros (Especifique)
COMPROMISO
1.4 CONSULTORIA DE MES DE
HORAS PRECIO MENSUAL SUB - TOTAL TOTAL
SUELOS Y MATERIALES* LABORATORIO
DIARIAS*
COMPROMISO
MESES
1.5 - SUBCONTRATOS* HORAS PRECIO MENSUAL SUB - TOTAL TOTAL
SUBCONTRATOS
DIARIAS*
TOTAL SUBCONTRATOS $ -
TOTAL DE COSTOS DIRECTOS ( 1.1 A 1.5 ) $ 140.70
2 - COSTOS INDIRECTOS
GASTO
2.2 - GASTOS ADMINISTRATIVOS MESES GASTOS SUB - TOTAL TOTAL
MENSUAL
MESES DE
PRECIO MENSUAL SUB - TOTAL TOTAL
2.3 - ALQUILERES ALQUILER
6 - I. V. A. ( 13. % ) $ 33.40
ASIGNACIÓN
1.1 - PERSONAL ASIGNADO SUELDO
HORAS MES HOMBRE SUB - TOTAL TOTAL
AL PROYECTO* MENSUAL
DIARIAS*
1.2 - PRESTACIONES
I.S.S.S. $ 90.00 $ 90.00
AFP $ 81.00 $ 81.00
COMPROMISO
1.4 CONSULTORIA DE MES DE
HORAS PRECIO MENSUAL SUB - TOTAL TOTAL
SUELOS Y MATERIALES* LABORATORIO
DIARIAS*
1- TÉCNICO DE LABORAT. $ -
VISITAS - PROGRAMADAS $ -
PERFORACIONES ESTÁNDAR *MTS.X C
TOTAL COSTOS DE LABORATORIOS SUELOS Y MATERIALES $ -
FORMATO N° 8 (5/10)
PRESUPUESTO DE SUPERVISION
PROYECTO: CENTRO DE DESARROLLO INFANTIL, CASERÍO SANTA ROSA, CANTÓN SAN MARCOS, MUNICIPIO DE SAN ANTONIO EL MOSCO,
DEPARTAMENTO DE SAN MIGUEL
COMPROMISO
MESES
1.5 - SUBCONTRATOS* HORAS PRECIO MENSUAL SUB - TOTAL TOTAL
SUBCONTRATOS
DIARIAS*
TOTAL SUBCONTRATOS
TOTAL DE COSTOS DIRECTOS ( 1.1 A 1.5 ) $ 2,599.00
2 - COSTOS INDIRECTOS
GASTO
2.2 - GASTOS ADMINISTRATIVOS MESES GASTOS SUB - TOTAL TOTAL
MENSUAL
MESES DE
PRECIO MENSUAL SUB - TOTAL TOTAL
2.3 - ALQUILERES ALQUILER
6 - I. V. A. ( 13. % ) $ 628.14
ASIGNACIÓN
1.1 - PERSONAL ASIGNADO SUELDO
HORAS MES HOMBRE SUB - TOTAL TOTAL
AL PROYECTO* MENSUAL
DIARIAS*
1.2 - PRESTACIONES
I.S.S.S. $ 3.00 $ 3.00
AFP $ 2.70 $ 2.70
COMPROMISO
1.4 CONSULTORIA DE MES DE
HORAS PRECIO MENSUAL SUB - TOTAL TOTAL
SUELOS Y MATERIALES* LABORATORIO
DIARIAS*
COMPROMISO
MESES
1.5 - SUBCONTRATOS* HORAS PRECIO MENSUAL SUB - TOTAL TOTAL
SUBCONTRATOS
DIARIAS*
TOTAL SUBCONTRATOS $ -
TOTAL DE COSTOS DIRECTOS ( 1.1 A 1.5 ) $ 205.00
2 - COSTOS INDIRECTOS
2.2 - GASTOS ADMINISTRATIVOS GASTO MENSUAL MESES GASTOS SUB - TOTAL TOTAL
MESES DE
PRECIO MENSUAL SUB - TOTAL TOTAL
2.3 - ALQUILERES ALQUILER
Otros (Especifique)
6 - I. V. A. ( 13. % ) $ 37.96
CUADRO RESUMEN