S OL D E P ARAC AS HOJA ENTRADA

CLIENTE : LOS PORTALES SA OC


CONTRATA Ref VALORIZACION Nª 01
CONCEPTO PAISAJISMO VIVO SOL DE PARACAS II SETIEMBRE Fecha :
ATENCION Rev : 00

VALORIZACION 01
ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO ACTUAL SALDO POR EJECUTAR
ITEM DESCRIPCION UND CANT P. UNIT. (S/.) P. PARCIAL (S/.) P. PARCIAL (S/.)
CANT P. PARCIAL (S/.) % AVAN CANT P. PARCIAL (S/.) % AVAN CANT P. PARCIAL (S/.) % AVAN CANT P. PARCIAL (S/.) % AVAN
12,913.04

1.01 PERSONAL UND 5 S/ 1,500.00 7,500.00 0.00 0.00% 5.00 7500.00 100.00% 5.00 7500.00 100.00% 0.00 0.00 0.00%
1.02 ENCARGADO UND 1 S/ 2,350.00 2,350.00 0.00 0.00% 1.00 2350.00 100.00% 1.00 2350.00 100.00% 0.00 0.00 0.00%
1.03 COMBUSTIBLE Y NYLON MENSUAL 1 S/ 164.58 164.58 0.00 0.00% 1.00 164.58 100.00% 1.00 164.58 100.00% 0.00 0.00 0.00%
1.04 SUPERVISION Y MONITOREO PLAN COVID MES 1 S/ 700.00 700.00 0.00 0.00% 1.00 700.00 100.00% 1.00 700.00 100.00% 0.00 0.00 0.00%
1.05 SCTR MES 1 S/ 450.00 450.00 0.00 0.00% 1.00 450.00 100.00% 1.00 450.00 100.00% 0.00 0.00 0.00%
1.06 AGUA UND 2 S/ 17.80 35.60 0.00 0.00% 2.00 35.60 100.00% 2.00 35.60 100.00% 0.00 0.00 0.00%
1.07 YESO AGRICOLA UND 1 S/ 20.00 20.00 0.00 0.00% 1.00 20.00 100.00% 1.00 20.00 100.00% 0.00 0.00 0.00%
1.08 AZUFRE UND 1 S/ 98.00 98.00 0.00 0.00% 1.00 98.00 100.00% 1.00 98.00 100.00% 0.00 0.00 0.00%
1.09 SULFATO UND 3 S/ 70.00 210.00 0.00 0.00% 3.00 210.00 100.00% 3.00 210.00 100.00% 0.00 0.00 0.00%
1.10 UREA UND 1 S/ 200.00 200.00 0.00 0.00% 1.00 200.00 100.00% 1.00 200.00 100.00% 0.00 0.00 0.00%
ALQUILER D E 01 MOTOGUADAÑA - MOCHILA
1.11 DE FUMIGACION (1 SEMANA / MES , INCLUYE MES 1 S/ 1,184.86 1,184.86 0.00 0.00% 1.00 1184.86 100.00% 1.00 1184.86 100.00% 0.00 0.00 0.00%
MNTO)

COSTO DIRECTO (S/.) 12,913.04 S/ - S/ - S/ 12,913.04 S/ 1.00 S/ 12,913.04 S/ 1.00 S/ - S/ -


G.GENERALES 5.00% (S/.) 645.65 0.00 645.65 645.65 0.00
UTILIDAD 10.00% (S/.) 1,291.30 0.00 1291.30 1291.30 0.00
======= ======= ======= ======= =======
TOTAL PROPUESTA ECONOMICA (S/.) 14,850.00 0.00 14850.00 14850.00 0.00
DESCUENTO 0.00
======= ======= ======= ======= =======
PARCIAL 14,850.00 0.00 14850.00 14850.00 0.00
IGV 18.00% (S/.) 2,673.00 0.00 2673.00 2673.00 0.00
TOTAL A FACTURAR (S/.) 17,523.00 0.00 17523.00 17523.00 0.00
RETENCIÓN POR FONDO DE GARANTIA 0.00% - 0.00 0.00 0.00 0.00
TOTAL A PAGAR (S/.) 17,523.00 0.00 17523.00 17523.00 0.00

……………………………………………………… ……………………………………………………… ……………………………………………………… ………………………………………………………


0 0
GERENTE DE PLAZA Jefe de Proyecto Supervisor de obra Contratista

RESUMEN DE VALORIZACION MONTO VALORIZADO IGV (S/.) TOTAL A FACTURAR RETENCION MONTO A COBRAR (S/.)
TOTAL PRESPUESTO CONTRACTUAL 12913.04 2673.00 17523.00 0.00 17523.00
TOTAL PRESUPUESTO DE CIERRE 14850.00 2673.00 17523.00 0.00 17523.00

VALORIZACIONES
VAL 1 14850.00 2673.00 17523.00 0.00 17523.00
Saldo 0.00 0.00 0.00 0.00 0.00