Documentos de Académico
Documentos de Profesional
Documentos de Cultura
OBRA : "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
01.05.02.02 CONCRETO F'C= 175 kg/cm2 EN CANAL PLUVIAL m3 3.98 352.12 1,401.44
01.05.03.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 11.22 4.77 53.52
01.05.03.04 CONCRETO f'c=175 kg/cm2 PARA CAJA DE REUNION m3 0.21 352.12 73.95
03.02.01.01 ANCLAJE DE ACERO CORRUGADO FY=4200 KG/CM2 CON PLANCHA DE ACERO und 3.00 20.82 62.46
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
01.01.01 ALMACEN, OFICINA Y CASETA DE GUARDIANIA glb 1.00 1,800.00 1,800.00 1.00 1,800.00 1.00 1,800.00 100.00% 0.00 0.00 0.00
01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.6X2.40m m2 1.00 600.12 600.12 1.00 600.12 1.00 600.12 100.00% 0.00 0.00 0.00
01.01.03 CERCO PROVISIONAL DURANTE LA OBRA und 135.00 14.57 1,966.95 135.00 1,966.95 135.00 1,966.95 100.00% 0.00 0.00 0.00
01.02 SEGURIDAD Y SALUD OCUPACIONAL 6,682.49
01.02.01 EQUIPOS DE PROTECCION PERSONAL glb 30.00 150.60 4,518.00 27.00 4,066.20 3.00 451.80 30.00 4,518.00 100.00% 0.00 0.00 0.00
01.02.02 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb 1.00 338.88 338.88 0.80 271.10 0.20 67.78 1.00 338.88 100.00% 0.00 0.00 0.00
01.02.03 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 847.26 847.26 0.70 593.08 0.30 254.18 1.00 847.26 100.00% 0.00 0.00 0.00
01.02.04 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS glb 1.00 978.35 978.35 0.50 489.18 0.50 489.18 1.00 978.35 100.00% 0.00 0.00 0.00
01.03.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 4,500.00 4,500.00 0.80 3,600.00 0.80 3,600.00 80.00% 0.20 900.00 0.20
01.03.02 TRAZO, NIVELACION Y REPLANTEO m2 699.10 0.48 335.57 699.10 335.57 699.10 335.57 100.00% 0.00 0.00 0.00
01.03.03 TRAZO, NIVELACION Y REPLANTEO DURANTE LA OBRA m2 699.10 0.41 286.63 699.10 286.63 699.10 286.63 100.00% 0.00 0.00 0.00
01.04.01.01 LIMPIEZA DEL TERRENO MANUAL m2 865.13 0.21 181.68 865.13 181.68 865.13 181.68 100.00% 0.00 0.00 0.00
01.04.02.01 EXCAVACION CON MAQUINARIA PARA PLATAFORMA DE CAMPO DEPORTIVO m2 1,414.77 6.57 9,295.04 1,414.77 9,295.04 1,414.77 9,295.04 100.00% 0.00 0.00 0.00
01.04.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO DE CORTE m3 369.15 24.99 9,225.06 369.15 9,225.06 369.15 9,225.06 100.00% 0.00 0.00 0.00
01.04.02.03 ELIMINACION DE MATERIAL EXCEDENTE DM=1 km m3 1,399.13 4.00 5,596.52 1,399.13 5,596.52 1,399.13 5,596.52 100.00% 0.00 0.00 0.00
01.04.02.04 PERFILADO, NIVELADO Y COMPACTADO DEL TERRENO PARA CAMPO DEPORTIVO m3 865.13 2.04 1,764.87 865.13 1,764.87 865.13 1,764.87 100.00% 0.00 0.00 0.00
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
01.04.03.01.01 BASE COMPACTADA DE E=10CM CON MATERIAL PROPIO m2 699.10 1.28 894.85 699.10 894.85 699.10 894.85 100.00% 0.00 0.00 0.00
01.04.03.02.01 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO PARA CAMPO DEPORTIVO und 53.45 36.11 1,930.08 53.45 1,930.08 53.45 1,930.08 100.00% 0.00 0.00 0.00
01.04.03.02.02 CONCRETO F'C=210 kg/cm2 EN PAVIMENTO P/CAMPO DEPORTIVO m3 99.03 388.41 38,464.24 99.03 38,464.24 99.03 38,464.24 100.00% 0.00 0.00 0.00
01.04.03.02.03 ACABADO FROTACHADO EN CAMPO DEPORTIVO m2 504.00 4.12 2,076.48 504.00 2,076.48 504.00 2,076.48 100.00% 0.00 0.00 0.00
01.04.03.02.04 CURADO DE CONCRETO EN PAVIMENTO m2 634.87 0.06 38.09 634.87 38.09 634.87 38.09 100.00% 0.00 0.00 0.00
01.04.03.02.05 DEMARCACION DE LINEAS EN CAMPO DEPORTIVO m 364.86 4.12 1,503.22 364.86 1,503.22 364.86 1,503.22 100.00% 0.00 0.00 0.00
01.04.03.03.01 JUNTAS DE DILATACION m3 12.41 3.80 47.16 12.41 47.16 12.41 47.16 100.00% 0.00 0.00 0.00
01.04.03.03.02 JUNTAS DE CONTRACCION m2 71.50 5.19 371.09 71.50 371.09 71.50 371.09 100.00% 0.00 0.00 0.00
01.04.04.01.01 EXCAVACION EN TERRENO CONGLOMERADO m3 0.25 16.48 4.12 0.00 0.00 0.00 0.00 0.00% 0.25 4.12 1.00
01.04.04.01.02 CONCRETO f'c=140 kg/cm2 PARA DADO DE ANCLAJE m3 0.25 356.00 89.00 0.00 0.00 0.00 0.00 0.00% 0.25 89.00 1.00
01.04.04.01.03 SUMINISTRO Y COLOCACION DE ARCOS METALICOS Und 2.00 1,176.63 2,353.26 0.00 0.00 0.00 0.00 0.00% 2.00 2,353.26 1.00
01.04.04.02.01 ACCESORIOS PARA CAMPO DE VOLEY Und 1.00 130.77 130.77 0.00 0.00 0.00 0.00 0.00% 1.00 130.77 1.00
01.04.04.03.01 ACCESORIOS PARA CAMPO DE BASQUET Und 2.00 500.66 1,001.32 0.00 0.00 0.00 0.00 0.00% 2.00 1,001.32 1.00
01.05.01.01 EXCAVACION EN TERRENO CONGLOMERADO m3 11.99 16.48 197.60 0.00 0.00 4.20 69.22 4.20 69.22 35.03% 7.79 128.38 0.65
01.05.01.02 REFINE, NIVELACION Y COMPACTACION MANUAL m2 93.27 43.35 4,043.25 0.00 0.00 32.70 1,417.55 32.70 1,417.55 35.06% 60.57 2,625.71 0.65
01.05.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 14.99 10.30 154.40 0.00 0.00 5.25 54.08 5.25 54.08 35.03% 9.74 100.32 0.65
01.05.02.01 ENCOFRADO Y DESENCOFRADO EN CANAL PLUVIAL m2 119.92 38.86 4,660.09 0.00 0.00 42.05 1,634.06 42.05 1,634.06 35.06% 77.87 3,026.03 0.65
PRESUPUESTO DE DEDUCTIVO
OBRA : "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
01.05.02.02 CONCRETO F'C= 175 kg/cm2 EN CANAL PLUVIAL m3 6.33 352.12 2,228.92 0.00 0.00 2.22 781.71 2.22 781.71 35.07% 4.11 1,447.21 0.65
01.05.03.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 22.44 4.77 107.04 0.00 0.00 11.22 53.52 11.22 53.52 50.00% 11.22 53.52 0.50
01.05.03.03 ENCOFRADO Y DESENCOFRADO PARA CAJA DE REUNION m2 5.21 38.86 202.46 0.00 0.00 2.65 102.98 2.65 102.98 50.86% 2.56 99.48 0.49
01.05.03.04 CONCRETO f'c=175 kg/cm2 PARA CAJA DE REUNION m3 0.41 352.12 144.37 0.00 0.00 0.20 70.42 0.20 70.42 48.78% 0.21 73.95 0.51
01.05.04 CARPINTERIA METALICA 11,231.14
01.05.04.01 REJILLA DE METAL EN CANAL DE EVACUACION m 83.28 134.86 11,231.14 0.00 0.00 0.00 0.00 0.00% 83.28 11,231.14 1.00
01.06.01.01 TRAZO, NIVELACION Y REPLANTEO m2 17.01 0.48 8.16 8.90 4.27 8.11 3.89 17.01 8.16 100.00% 0.00 0.00 0.00
01.06.02.01 EXCAVACION EN TERRENO CONGLOMERADO m3 1.46 16.48 24.06 0.81 13.35 0.65 10.71 1.46 24.06 100.00% 0.00 0.00 0.00
01.06.02.02 RELLENO Y COMPACTACION CON MATERIAL PROPIO m3 0.72 4.39 3.16 0.00 0.00 0.72 3.16 0.72 3.16 100.00% 0.00 0.00 0.00
01.06.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 0.92 10.30 9.48 0.49 5.05 0.43 4.43 0.92 9.48 100.00% 0.00 0.00 0.00
01.06.03.01 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 404.35 4.68 1,892.36 0.00 0.00 0.00 0.00 0.00% 404.35 1,892.36 1.00
01.06.03.02 ENCOFRADO Y DESENCOFRADO EN GRADERIAS m2 19.24 38.86 747.67 0.00 0.00 0.00 0.00 0.00% 19.24 747.67 1.00
01.06.03.03 CONCRETO F'C= 175 kg/cm2 EN GRADERIAS m3 2.43 352.12 855.65 0.00 0.00 0.00 0.00 0.00% 2.43 855.65 1.00
01.06.03.04 CURADO DE CONCRETO EN GRADERIAS m2 17.01 0.06 1.02 0.00 0.00 0.00 0.00 0.00% 17.01 1.02 1.00
01.06.04.01 BARANDA METALICA EN GRADERIAS m 4.20 41.65 174.93 0.00 0.00 0.00 0.00 0.00% 4.20 174.93 1.00
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
02.01.01.01 TRAZO, NIVELACION Y REPLANTEO m2 10.22 1.44 14.72 10.22 14.72 10.22 14.72 100.00% 0.00 0.00 0.00
02.01.02 MOVIMIENTO DE TIERRAS 37.07
02.01.02.01 EXCAVACION EN TERRENO CONGLOMERADO m3 1.25 16.80 21.00 1.25 21.00 1.25 21.00 100.00% 0.00 0.00 0.00
02.01.02.02 ELIMINACION DE MATERIAL EXCEDENTE m3 1.56 10.30 16.07 1.56 16.07 1.56 16.07 100.00% 0.00 0.00 0.00
02.01.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 5.85 51.11 298.99 5.85 298.99 5.85 298.99 100.00% 0.00 0.00 0.00
02.01.03.03 CONCRETO SOBRECIMIENTOS MEZCLA 1:8 + 25% P.M. m3 0.44 288.54 126.96 0.44 126.96 0.44 126.96 100.00% 0.00 0.00 0.00
02.01.03.04 FALSO PISO DE CONCRETO 1:10 E=4" m2 8.00 37.09 296.72 8.00 296.72 8.00 296.72 100.00% 0.00 0.00 0.00
02.01.04.01.01 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 66.70 4.59 306.15 66.70 306.15 66.70 306.15 100.00% 0.00 0.00 0.00
02.01.04.01.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 12.69 43.48 551.76 6.69 290.88 6.00 260.88 12.69 551.76 100.00% 0.00 0.00 0.00
02.01.04.01.03 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS m3 0.53 389.57 206.47 0.23 89.60 0.30 116.87 0.53 206.47 100.00% 0.00 0.00 0.00
02.01.04.02.01 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 16.53 4.59 75.87 0.00 0.00 16.53 75.87 16.53 75.87 100.00% 0.00 0.00 0.00
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 7.23 41.75 301.85 0.00 0.00 7.23 301.85 7.23 301.85 100.00% 0.00 0.00 0.00
02.01.04.02.03 CONCRETO f'c=210 kg/cm2 PARA VIGAS m3 0.42 389.57 163.62 0.00 0.00 0.42 163.62 0.42 163.62 100.00% 0.00 0.00 0.00
02.02.01.01 MURO DE ALBAÑILERIA DE SOGA m2 29.65 52.69 1,562.26 0.00 0.00 29.65 1,562.26 29.65 1,562.26 100.00% 0.00 0.00 0.00
02.02.02.02 TARRAJEO EN COLUMNAS m2 5.09 23.14 117.78 0.00 0.00 0.00 0.00 0.00% 5.09 117.78 1.00
02.02.02.03 TARRAJEO EN VIGAS m2 3.99 23.14 92.33 0.00 0.00 0.00 0.00 0.00% 3.99 92.33 1.00
PRESUPUESTO DE DEDUCTIVO
OBRA : "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
02.02.02.04 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS m2 2.36 23.14 54.61 0.00 0.00 0.00 0.00 0.00% 2.36 54.61 1.00
02.02.04.01 CONTRAPISO DE E=40MM m2 8.24 22.31 183.83 0.00 0.00 0.00 0.00 0.00% 8.24 183.83 1.00
02.02.04.02 PISO DE CERAMICO DE 30X30CM m2 8.24 36.11 297.55 0.00 0.00 0.00 0.00 0.00% 8.24 297.55 1.00
02.02.05 ZOCALOS Y CONTRAZOCALOS 930.37
02.02.05.01 ZOCALO DE CERAMICA 25X40CM m2 18.48 36.83 680.62 0.00 0.00 0.00 0.00 0.00% 18.48 680.62 1.00
02.02.05.02 CONTRAZOCALO DE CERAMICA m 15.40 13.22 203.59 0.00 0.00 0.00 0.00 0.00% 15.40 203.59 1.00
02.02.05.03 CONTRAZOCALO DE CEMENTO PULIDO SIN COLOREAR h=0.20 m m 11.15 4.14 46.16 0.00 0.00 0.00 0.00 0.00% 11.15 46.16 1.00
02.02.06.01 SUMINISTRO Y COLOCACION DE PUERTA DE METAL und 2.00 330.35 660.70 0.00 0.00 0.00 0.00 0.00% 2.00 660.70 1.00
02.02.06.02 SUMINISTRO Y COLOCACION DE VENTANA DE METAL und 3.00 79.25 237.75 0.00 0.00 0.00 0.00 0.00% 3.00 237.75 1.00
02.02.06.03 SUMIN. Y COLOC. DE CORREAS DE METAL DE SECCION RECTANGULAR m2 14.45 38.28 553.15 0.00 0.00 0.00 0.00 0.00% 14.45 553.15 1.00
02.02.06.04 SUMIN. Y COLOCACION DE SISTEMA DE PROTECCION EN VENTANAS m2 0.59 26.44 15.60 0.00 0.00 0.00 0.00 0.00% 0.59 15.60 1.00
02.02.07.01 SUMINISTRO E INST. DE COBERTURA CON TEJA ANDINA m2 14.45 73.80 1,066.41 0.00 0.00 0.00 0.00 0.00% 14.45 1,066.41 1.00
02.02.08.01 BISAGRA CAPUCHINAS ALUMINIZADA PARA PUERTAS pza 6.00 9.38 56.28 0.00 0.00 0.00 0.00 0.00% 6.00 56.28 1.00
02.02.08.02 CERRADURA DOS GOLPES EN PUERTA CON TIRADOR pza 2.00 58.97 117.94 0.00 0.00 0.00 0.00 0.00% 2.00 117.94 1.00
02.02.09.01 VIDRIO SEMIDOBLE INCOLORO CRUDO m2 3.72 27.78 103.34 0.00 0.00 0.00 0.00 0.00% 3.72 103.34 1.00
02.03.02 SALIDA PARA CENTRO DE LUZ EN TECHO pto 2.00 29.08 58.16 0.00 0.00 0.00 0.00 0.00% 2.00 58.16 1.00
02.03.03 SALIDA PARA INTERRUPTOR UNIPOLAR DOBLE pto 2.00 35.98 71.96 0.00 0.00 0.00 0.00 0.00% 2.00 71.96 1.00
PRESUPUESTO DE DEDUCTIVO
OBRA : "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
02.03.04 SALIDA PARA TOMACORRIENTE DOBLE pto 2.00 55.89 111.78 0.00 0.00 0.00 0.00 0.00% 2.00 111.78 1.00
02.03.05 LUMINARIA TIPO FLUORESCENTE 40W CON ACCESORIOS und 2.00 72.32 144.64 0.00 0.00 0.00 0.00 0.00% 2.00 144.64 1.00
02.04 INSTALACIONES SANITARIAS 2,217.73
02.04.01.01 SALIDA DESAGUE DE PVC SAL Ø2" pto 3.00 13.80 41.40 0.00 0.00 0.00 0.00 0.00% 3.00 41.40 1.00
02.04.01.02 SALIDA DESAGUE DE PVC-SAL Ø4" pto 3.00 42.03 126.09 0.00 0.00 0.00 0.00 0.00% 3.00 126.09 1.00
02.04.01.03 SALIDA VENTILACION DE PVC-SAL Ø2" pto 2.00 30.69 61.38 0.00 0.00 0.00 0.00 0.00% 2.00 61.38 1.00
02.04.01.04 REGISTRO DE BRONCE Ø4" und 2.00 26.97 53.94 0.00 0.00 0.00 0.00 0.00% 2.00 53.94 1.00
02.04.01.05 CAJA DE REGISTRO DE DESAGUE 12"X24" und 1.00 76.97 76.97 0.00 0.00 0.00 0.00 0.00% 1.00 76.97 1.00
02.04.01.06 SUMIDERO DE BRONCE ROSCADO 2" und 2.00 50.17 100.34 0.00 0.00 0.00 0.00 0.00% 2.00 100.34 1.00
02.04.01.07 RED DE DERIVACION PARA DESAGUE PVC-SAL Ø2" m 3.20 7.49 23.97 0.00 0.00 0.00 0.00 0.00% 3.20 23.97 1.00
02.04.01.08 RED DE DERIVACION PARA DESAGUE PVC-SAL Ø4" m 6.00 18.43 110.58 0.00 0.00 0.00 0.00 0.00% 6.00 110.58 1.00
02.04.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 Ø1/2" pto 6.00 43.03 258.18 0.00 0.00 0.00 0.00 0.00% 6.00 258.18 1.00
02.04.02.02 RED DE DISTRIBUCION TUBERIA PVC-SAP Ø3/4" m 26.21 7.50 196.58 0.00 0.00 0.00 0.00 0.00% 26.21 196.58 1.00
02.04.02.03 RED DE DISTRIBUCION TUBERIA PVC-SAP Ø1/2" m 17.61 5.81 102.31 0.00 0.00 0.00 0.00 0.00% 17.61 102.31 1.00
02.04.02.04 VALVULA COMPUERTA DE Ø3/4" und 2.00 30.17 60.34 0.00 0.00 0.00 0.00 0.00% 2.00 60.34 1.00
02.04.03.01 SUMIN. Y COLOC. DE INODORO und 3.00 204.92 614.76 0.00 0.00 0.00 0.00 0.00% 3.00 614.76 1.00
02.04.03.02 SUMIN. Y COLOC. DE LAVATORIO DE PARED und 2.00 122.65 245.30 0.00 0.00 0.00 0.00 0.00% 2.00 245.30 1.00
02.04.03.03 SUMIN. Y COLOC. DE URINARIO und 1.00 145.59 145.59 0.00 0.00 0.00 0.00 0.00% 1.00 145.59 1.00
02.05 FLETE TERRESTRE 4,498.50
02.05.01 FLETE TERRESTRE PARA CAMERINOS Y SERVICIOS HIGIENICOS glb 1.00 4,498.50 4,498.50 0.50 2,249.25 0.30 1,349.55 0.80 3,598.80 80.00% 0.20 899.70 0.20
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
03.01.01.01 EXCAVACION MANUAL PARA TRIBUNAS m3 8.40 16.48 138.43 8.40 138.43 8.40 138.43 100.00% 0.00 0.00 0.00
03.01.01.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 2.36 25.84 60.98 2.36 60.98 2.36 60.98 100.00% 0.00 0.00 0.00
03.01.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 7.55 10.30 77.77 7.55 77.77 7.55 77.77 100.00% 0.00 0.00 0.00
03.01.02.01 SOLADO DE CONCRETO F'C=100KG/CM2 E=4" m2 8.40 23.04 193.54 8.40 193.54 8.40 193.54 100.00% 0.00 0.00 0.00
03.01.02.02 CONCRETO F'C= 175 kg/cm2 EN GRADERIAS m3 0.32 352.12 112.68 0.00 0.00 0.32 112.68 0.32 112.68 100.00% 0.00 0.00 0.00
03.01.03 CONCRETO ARMADO 12,911.67
03.01.03.01 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 524.99 4.59 2,409.70 245.00 1,124.55 279.99 1,285.15 524.99 2,409.70 100.00% 0.00 0.00 0.00
03.01.03.02 ENCOFRADO Y DESENCOFRADO EN TRIBUNAS m2 105.06 49.68 5,219.38 49.00 2,434.32 56.06 2,785.06 105.06 5,219.38 100.00% 0.00 0.00 0.00
03.01.03.03 CONCRETO f'c=210 kg/cm2 EN TRIBUNAS m3 13.13 402.33 5,282.59 6.10 2,454.21 7.03 2,828.38 13.13 5,282.59 100.00% 0.00 0.00 0.00
03.01.04.01 TARRAJEO EXTERIOR m2 75.37 23.99 1,808.13 0.00 0.00 55.37 1,328.33 55.37 1,328.33 73.46% 20.00 479.80 0.27
03.01.05.02 JUNTAS DE CONTRACCION m 13.80 5.19 71.62 0.00 0.00 13.80 71.62 13.80 71.62 100.00% 0.00 0.00 0.00
03.02.01.01 ANCLAJE DE ACERO CORRUGADO FY=4200 KG/CM2 CON PLANCHA DE ACERO und 28.00 20.82 582.96 14.00 291.48 14.00 291.48 50.00% 14.00 291.48 0.50
03.02.01.02 MALLA DE PROTECCION m 60.26 139.65 8,415.31 30.13 4,207.65 30.13 4,207.65 50.00% 30.13 4,207.65 0.50
03.02.01.03 PINTURA ANTOCORROSIVA PARA MALLA DE PROTECCION m 60.26 19.85 1,196.16 30.13 598.08 30.13 598.08 50.00% 30.13 598.08 0.50
03.03.01.01 EXCAVACION CON MAQUINARIA PARA MURO DE CONTENCION m3 250.17 5.72 1,430.97 250.17 1,430.97 250.17 1,430.97 100.00% 0.00 0.00 0.00
PRESUPUESTO DE DEDUCTIVO
OBRA : "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
03.03.01.02 RELLENO Y COMPACTACION CON MATERIAL PROPIO m3 300.12 3.64 1,092.44 300.12 1,092.44 300.12 1,092.44 100.00% 0.00 0.00 0.00
03.03.01.03 ELIMINACION DE MATERIAL EXCEDENTE m3 12.59 10.30 129.68 12.59 129.68 12.59 129.68 100.00% 0.00 0.00 0.00
03.03.02 CONCRETO SIMPLE 4,088.54
03.03.02.01 SOLADO PARA CIMENTOS E=4" MEZCLA 1:10 CEMENTO HORMIGON m2 136.33 29.99 4,088.54 136.33 4,088.54 136.33 4,088.54 100.00% 0.00 0.00 0.00
03.03.03.01.02 ENCOFRADO Y DESENCOFRADO EN ZAPATAS m2 47.48 46.99 2,231.09 47.48 2,231.09 47.48 2,231.09 100.00% 0.00 0.00 0.00
03.03.03.01.03 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS m3 54.53 370.63 20,210.45 54.53 20,210.45 54.53 20,210.45 100.00% 0.00 0.00 0.00
03.03.03.02.01 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 4,413.76 4.59 20,259.16 4,413.76 20,259.16 4,413.76 20,259.16 100.00% 0.00 0.00 0.00
03.03.03.02.02 ENCOFRADO Y DESENCOFRADO PANTALLA m2 452.63 44.24 20,024.35 452.63 20,024.35 452.63 20,024.35 100.00% 0.00 0.00 0.00
03.03.03.02.03 CONCRETO f'c=210 kg/cm2 EN PANTALLA m3 55.25 388.41 21,459.65 55.25 21,459.65 55.25 21,459.65 100.00% 0.00 0.00 0.00
03.03.04.01 JUNTAS DE DILATACION m 62.50 3.80 237.50 62.50 237.50 62.50 237.50 100.00% 0.00 0.00 0.00
03.03.04.02 JUNTAS DE CONTRACCION m 47.67 5.19 247.41 47.67 247.41 47.67 247.41 100.00% 0.00 0.00 0.00
03.03.05.01 FILTRO CON GRAVA DE Ø1"- Ø2" m3 20.84 118.62 2,472.04 20.84 2,472.04 20.84 2,472.04 100.00% 0.00 0.00 0.00
03.03.05.02 TUBERIA PVC SAP Ø3" PERFORADA PARA DRENAJE m 83.36 17.73 1,477.97 83.36 1,477.97 83.36 1,477.97 100.00% 0.00 0.00 0.00
03.04.01 FLETE TERRESTRE PARA TRIBUNAS, MURO DE CONCRETO ARMADO Y CERCO PERIMET glb 1.00 24,877.96 24,877.96 1.00 24,877.96 1.00 24,877.96 100.00% 0.00 0.00 0.00
04.01.02 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb 1.00 338.88 338.88 0.00 0.00 0.00 0.00 0.00% 1.00 338.88 1.00
PRESUPUESTO DE DEDUCTIVO
OBRA : "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
04.01.03 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 847.26 847.26 0.00 0.00 0.00 0.00 0.00% 1.00 847.26 1.00
04.02.01.01 LIMPIEZA DEL TERRENO MANUAL m2 900.00 0.52 468.00 900.00 468.00 900.00 468.00 100.00% 0.00 0.00 0.00
04.02.01.02 TRAZO, NIVELACION Y REPLANTEO m2 900.00 2.92 2,628.00 900.00 2,628.00 900.00 2,628.00 100.00% 0.00 0.00 0.00
04.02.02.02 NIVELACION Y APISONADO EN INTERIORES m2 36.22 4.39 159.01 36.22 159.01 36.22 159.01 100.00% 0.00 0.00 0.00
04.02.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO DE CORTE m3 18.62 66.40 1,236.37 18.62 1,236.37 18.62 1,236.37 100.00% 0.00 0.00 0.00
04.02.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 91.39 10.30 941.32 91.39 941.32 91.39 941.32 100.00% 0.00 0.00 0.00
04.02.03.01 SOLADO PARA ZAPATAS E=4", MEZCLA 1:12 C:H m2 33.75 24.27 819.11 33.75 819.11 33.75 819.11 100.00% 0.00 0.00 0.00
04.02.03.02 ENCOFRADO Y DESENCOFRADO EN SARDINEL m2 37.44 36.88 1,380.79 37.44 1,380.79 37.44 1,380.79 100.00% 0.00 0.00 0.00
04.02.03.03 CONCRETO f'c=210 kg/cm2 EN SARDINEL m3 5.62 364.39 2,047.87 5.62 2,047.87 5.62 2,047.87 100.00% 0.00 0.00 0.00
04.02.04.01.01 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 1,413.42 4.80 6,784.42 1,272.42 6,107.62 141.00 676.80 1,413.42 6,784.42 100.00% 0.00 0.00 0.00
04.02.04.01.02 CONCRETO f'c=210 kg/cm2 PARA ZAPATAS m3 19.35 364.60 7,055.01 17.42 6,351.33 1.93 703.68 19.35 7,055.01 100.00% 0.00 0.00 0.00
04.02.04.02 COLUMNAS 11,522.24
04.02.04.02.01 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 1,428.73 4.80 6,857.90 1,287.73 6,181.10 141.00 676.80 1,428.73 6,857.90 100.00% 0.00 0.00 0.00
04.02.04.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 57.44 36.88 2,118.39 51.73 1,907.80 5.71 210.58 57.44 2,118.39 100.00% 0.00 0.00 0.00
04.02.04.02.03 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS m3 7.04 361.64 2,545.95 6.34 2,292.80 0.70 253.15 7.04 2,545.95 100.00% 0.00 0.00 0.00
04.02.05.01.01 PLANCHA METALICA E=3/8" CON ANCLAJES DE FIERRO DE 5/8" und 16.00 117.96 1,887.36 14.00 1,651.44 2.00 235.92 16.00 1,887.36 100.00% 0.00 0.00 0.00
04.02.05.01.02 COLUMNA TUBO CUADRADO 8"x8"x5.6m und 16.00 536.86 8,589.76 0.00 0.00 0.00 0.00 0.00% 16.00 8,589.76 1.00
PRESUPUESTO DE DEDUCTIVO
OBRA : "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
04.02.05.02.01 VIGA TUBO RECTANGULAR 4"x4" m 64.00 33.77 2,161.28 0.00 0.00 0.00 0.00 0.00% 64.00 2,161.28 1.00
04.03 ARQUITECTURA 124,076.07
04.03.01.01 PINTURA ESMALTE EN COLUMNAS m2 15.36 8.25 126.72 0.00 0.00 0.00 0.00 0.00% 15.36 126.72 1.00
04.03.02.01.01 SUMINISTRO Y HABILITADO DE ARCO METALICO AM-01 und 8.00 4,487.87 35,902.96 0.00 0.00 0.00 0.00 0.00% 8.00 35,902.96 1.00
04.03.02.01.02 MONTAJE E INSTALACION DE ARCO METALICO AM-01 und 8.00 928.38 7,427.04 0.00 0.00 0.00 0.00 0.00% 8.00 7,427.04 1.00
04.03.02.01.03 MONTAJE E INSTALACION DE CORREAS m 650.00 25.58 16,627.00 0.00 0.00 0.00 0.00 0.00% 650.00 16,627.00 1.00
04.03.02.01.04 ARRIOSTRE DE ARCO METALICO 3/8" m 310.73 13.23 4,110.96 0.00 0.00 0.00 0.00 0.00% 310.73 4,110.96 1.00
04.03.02.02.01 COBERTURA METALICA EN FORMA DE ARCO m2 841.25 23.78 20,004.93 0.00 0.00 0.00 0.00 0.00% 841.25 20,004.93 1.00
04.03.02.02.02 COBERTURA EN FORMA DE ARCO TRASLUCIDO m2 52.50 57.88 3,038.70 0.00 0.00 0.00 0.00 0.00% 52.50 3,038.70 1.00
04.03.02.02.03 ACCESORIOS DE COBERTURA glb 1.00 7,523.50 7,523.50 0.00 0.00 0.00 0.00 0.00% 1.00 7,523.50 1.00
04.03.02.02.04 PINTURA DE ESTRUCTURAS METALICAS m2 484.88 10.14 4,916.68 0.00 0.00 0.00 0.00 0.00% 484.88 4,916.68 1.00
04.03.03.01.01 SALIDA DE REFLECTORES LED C/CABLE AWG TW 4.0MM(12)+ D PVC SAP 19MM (3/4") pto 8.00 104.73 837.84 0.00 0.00 0.00 0.00 0.00% 8.00 837.84 1.00
04.03.03.02.01 SALIDA PARA CORTO CIRCUITO C/CABLE AW TW 4.00MM(12)+D PVC SAP 19MM(3/4) pto 6.00 109.38 656.28 0.00 0.00 0.00 0.00 0.00% 6.00 656.28 1.00
AVANCE
PRESUPUESTO BASE (S/.) SALDO POR EJECUTAR
ACUMULADO ANTERIOR ACTUAL ACUMULADO
ITEM DESCRIPCION UNIDAD METRADO
COSTO SUB
VALORIZ. VALORIZ. VALORIZ. PORCENTAJE VALORIZ. PORCENTAJE
UNITARIO TOTAL METRADO METRADO METRADO METRADO
(S/.) (S/.) (S/.) (%) (S/.) (%)
(S/.) (S/.)
04.03.03.03.01 FUENTE DE LUZ UNA SOLA PASTILLA LED DE ALTO PODER PARA REFLECTORE 400W und 6.00 599.70 3,598.20 0.00 0.00 0.00 0.00 0.00% 6.00 3,598.20 1.00
04.03.04.01.01 TUBERIA PVC SAL DE Ø3" m 24.00 5.45 130.80 0.00 0.00 0.00 0.00 0.00% 24.00 130.80 1.00
04.03.04.01.02 CANALETA DE ZINC DE Ø6" m 68.00 24.68 1,678.24 0.00 0.00 0.00 0.00 0.00% 68.00 1,678.24 1.00
05.01 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 5,000.00 5,000.00 0.60 3,000.00 0.30 1,500.00 0.90 4,500.00 90.00% 0.10 500.00 0.10
TOTAL COSTO DIRECTO 494,034.66 294,925.93 31,944.82 326,870.76 167,163.90
GASTOS GENERALES 12.9687% 64,070.00 38,248.13 4,142.84 42,390.97 21,679.03
UTILIDAD 7.00% 34,582.43 20,644.82 2,236.14 22,880.97 11,701.46
…………………….. …………………….. …………………….. …………………….. ……………………..
SUB TOTAL 592,687.09 353,818.88 38,323.80 392,142.70 200,544.39
SUB TOTAL CON FACTOR DE RELACION 1.00000 592,687.09 353,818.88 38,323.80 392,142.70 200,544.39
IMPUESTO (IGV) 18.00% 106,683.68 63,687.40 6,898.28 70,585.68 36,098.00
============= ============= ============= ============= =============
TOTAL PRESUPUESTO 699,370.77 417,506.28 45,222.08 462,728.38 236,642.39
SUPERVISOR : Ing. ALBERTO TINOCO LEON MONTO CONTRATADO : S/. 699,370.77 Soles
INICIO OBRA : 18 DE SETIEMBRE DEL 2018 PLAZO DE EJECUCION : 120 DIAS CALENDARIOS
OBRA "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
SUPERVISOR : Ing. ALBERTO TINOCO LEON MONTO CONTRATADO : S/. 699,370.77 Soles
INICIO OBRA : 18 DE SETIEMBRE DEL 2018 PLAZO DE EJECUCION : 120 DIAS CALENDARIOS
SON: CUARENTA Y CINCO MIL DOS CIENTOS VEINTIDOS CON 08/100 SOLES
CONTROL ECONOMICO DE LAS VALORIZACIONES TRAMITADAS - CONTRATO PRINCIPAL
OBRA "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
SUPERVISOR : Ing. ALBERTO TINOCO LEON MONTO CONTRATADO : S/. 699,370.77 Soles
INICIO OBRA : 18 DE SETIEMBRE DEL 2018 PLAZO DE EJECUCION : 120 DIAS CALENDARIOS
PERIODO : DEL 01 AL 31 DE DICIEMBRE DEL 2018
Adelanto Directo -- -- -- - -- -- -- -- -- -- -- -- -- -- -- --
Adelanto Materiales -- -- -- - -- -- -- -- -- -- -- -- -- -- -- --
Valorizacion N° 01 001-Nº 000 Setiembre 2018 9/18/2018 - 9/30/2018 S/. -- S/. -- S/. 40,322.57 S/. -- S/. -- S/. -- S/. -- S/. -- S/. 40,322.57 S/. 7,258.06 S/. 47,580.63
Valorizacion N° 02 001-Nº 000 Octubre 2018 10/1/2018 - 10/31/2018 S/. -- S/. -- S/. 136,691.14 S/. -- S/. -- S/. -- S/. -- S/. -- S/. 136,691.14 S/. 24,604.41 S/. 161,295.55
Valorizacion N° 03 001-Nº 000 Noviembre 2018 11/1/2018 - 11/30/2018 S/. -- S/. -- S/. 176,805.19 S/. -- S/. -- S/. -- S/. -- S/. -- S/. 176,805.19 S/. 31,824.93 S/. 208,630.12
Valorizacion N° 04 001-Nº 000 Diciembre 2018 12/1/2018 - 12/31/2018 S/. -- S/. -- S/. 38,323.80 S/. -- S/. -- S/. -- S/. -- S/. -- S/. 38,323.80 S/. 6,898.28 S/. 45,222.08
Valorizacion N° 05 001-Nº 000 Enero 2019 1/1/2019 - 1/15/2019 S/. -- S/. -- '-- S/. -- S/. -- S/. -- S/. -- S/. -- S/. 0.00 S/. 0.00 S/. 0.00
SUPERVISOR : Ing. ALBERTO TINOCO LEON MONTO CONTRATADO : S/. 699,370.77 Soles
INICIO OBRA : 18 DE SETIEMBRE DEL 2018 PLAZO DE EJECUCION : 120 DIAS CALENDARIOS
100% 100.00%
92.61%
90%
% Avance Acumulado
80%
70% 66.16%
59.69%
60%
52.03%
50%
40%
29.86%
30%
20% 20.96%
10% 6.80%
6.34%
0%
Inicio de Obra: 18/09/2018 Val N º1: 30/09/ 2018 Val N º2: 31/10/2018 Val N º3: 30/11/2018 Val N º4: 31/12/2018 Val N º5: 15/01/2019
ACUMULADO EJECUTADO ACUMULADO PROGRAMADO
INICIO DE OBRA
OBRA "CREACION INFRAESTRUCTURA DEPORTIVA MULTIUSO EN HUAMAS DEL DISTRITO DE YANAMA-PROVINCIA DE YUNGAY-DEPARTAMENTO DE ANCASH"
UBICACIÓN : LOCALIDAD DE HUAMAS, DIST. DE YANAMA, PROV. DE YUNGAY, ANCASH
ENTIDAD : MUNICIPALIDAD DISTRITAL DE YUNGAY MODALIDAD DE EJECUCION : SUMA ALZADA
CONTRATISTA : CONSORCIO SAN MIGUEL VALOR REFERENCIAL : S/. 699,370.77 Soles
RESIDENTE : Ing. DANILO E. MONTORO VERGARA FACTOR DE RELACION : 1.00
SUPERVISOR : Ing. ALBERTO TINOCO LEON MONTO CONTRATADO : S/. 699,370.77 Soles
INICIO OBRA : 18 DE SETIEMBRE DEL 2018 PLAZO DE EJECUCION : 120 DIAS CALENDARIOS
PERIODO : DEL 01 AL 31 DE DICIEMBRE DEL 2018
VALORIZACION N° 01 Setiembre 2018 9/18/2018 - 9/30/2018 S/. 44,364.39 6.34% S/. 44,364.39 6.34% S/. 47,580.63 6.80% S/. 47,580.63 6.80% 0.46% OBRA ADELANTADA
VALORIZACION N° 02 Octubre 2018 10/1/2018 - 10/31/2018 S/. 102,270.27 14.62% S/. 146,634.66 20.96% S/. 161,295.55 23.06% S/. 208,876.18 29.86% 8.90% OBRA ADELANTADA
VALORIZACION N° 03 Noviembre 2018 11/1/2018 - 11/30/2018 S/. 217,263.45 31.07% S/. 363,898.11 52.03% S/. 208,630.12 29.83% S/. 208,630.12 59.69% 7.66% OBRA ADELANTADA
VALORIZACION N° 04 Diciembre 2018 12/1/2018 - 12/31/2018 S/. 283,778.27 40.58% S/. 647,676.38 92.61% S/. 45,222.08 6.47% S/. 45,222.08 66.16% -26.44% OBRA ATRAZADA