CONTROL MUESTRAS DE CONCRETO ENVIADAS A LABORATORIO


VERSION

MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DEL JR. FRANCISCO PIZARRO CUADRAS 01 A LA 07 Y JR. SAN MARTIN CUADRAS 01 A
PROYECTO: LA 04 DISTRITO DE MORALES, PROVINCIA DE SAN MARTIN-SAN MARTIN

Resistenc Valor Fechas de entrega reportes


Fecha
Muestra ia Tipo asentamie Elemento OBSERVACIONES
Vaciado esperada nto
3 dias 7 dias 14 dias 28 dias Testigos
LOSA DE FONDO DE CUNETA TIPO II DE 0.50x 0.90M EN LA Cdra. 07 DEL JR
1 11-oct-21 210 4" 5 1/2 FRANCISCO PIZARRO, LADO IZQUIERDO 14-Oct 18-Oct 25-Oct 8-Nov 6-Dec
MURO DE CUNETA TIPO II DE 0.50x 0.90M EN LA Cdra. 07 DEL JR FRANCISCO
2 12-oct-21 210 4" 6 3/8 PIZARRO, LADO IZQUIERDO 15-Oct 19-Oct 26-Oct 9-Nov 7-Dec
LOSA DE FONDO DE CUNETA TIPO I DE 0.50x 0.60M EN LA Cdra. 05 DEL JR
3 12-oct-21 210 4" 4 1/2 FRANCISCO PIZARRO, LADO IZQUIERDO 15-Oct 19-Oct 26-Oct 9-Nov 7-Dec
LOSA DE FONDO DE CUNETA TIPO I DE 0.50x 0.60M EN LA Cdra. 05 Y 04 DEL JR
4 13-oct-21 210 4" 5 1/2 FRANCISCO PIZARRO, LADO IZQUIERDO 16-Oct 20-Oct 27-Oct 10-Nov 8-Dec DENSIDAD DE CAMPO

MURO DE CUNETA TIPO I DE 0.50x 0.60M EN LA Cdra. 06 DEL JR FRANCISCO


5 13-oct-21 210 4" 5 4/5 PIZARRO, LADO IZQUIERDO 16-Oct 20-Oct 27-Oct 10-Nov 8-Dec
LOSA DE FONDO DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 06
6 13-oct-21 210 4" 6 3/5 Y 07 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 16-Oct 20-Oct 27-Oct 10-Nov 8-Dec DENSIDAD DE CAMPO

MURO DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 06 Y 07 DEL


7 14-oct-21 210 4" 5 2/7 JR FRANCISCO PIZARRO, LADO IZQUIERDO 17-Oct 21-Oct 28-Oct 11-Nov 9-Dec
LOSA DE FONDO DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 05
8 14-oct-21 210 4" 5 1/2 Y 06 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 17-Oct 21-Oct 28-Oct 11-Nov 9-Dec

9 14-oct-21 175 4" 5 5/7 VEREDA EN LA Cdra. 07 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 17-Oct 21-Oct 28-Oct 11-Nov 9-Dec DENSIDAD DE CAMPO

MURO DE CUNETA TIPO I DE 0.50x 0.60M EN LA Cdra. 05 DEL JR FRANCISCO


10 15-oct-21 210 4" 5 4/5 PIZARRO, LADO IZQUIERDO 18-Oct 22-Oct 29-Oct 12-Nov 10-Dec
LOSA SUPERIOR DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 06
11 15-oct-21 210 4" 5 2/7 Y 07 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 18-Oct 22-Oct 29-Oct 12-Nov 10-Dec
LOSA DE FONDO DE CUNETA TIPO I DE 0.50x 0.60M EN LA Cdra. 04 DEL JR
12 15-oct-21 210 4" 9 1/2 FRANCISCO PIZARRO, LADO DERECHO 18-Oct 22-Oct 29-Oct 12-Nov 10-Dec
LOSA DE FONDO DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 04 DEL JR
13 15-oct-21 210 4" 4 1/2 FRANCISCO PIZARRO, LADO DERECHO 18-Oct 22-Oct 29-Oct 12-Nov 10-Dec

14 15-oct-21 175 4" 8 3/5 VEREDA EN LA Cdra. 07 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 18-Oct 22-Oct 29-Oct 12-Nov 10-Dec DENSIDAD DE CAMPO

TECHO DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 05 Y 06 DEL


15 16-oct-21 210 4" 4 5/7 JR FRANCISCO PIZARRO, LADO IZQUIERDO 19-Oct 23-Oct 30-Oct 13-Nov 11-Dec

16 16-oct-21 175 4" 7 1/2 VEREDA EN LA Cdra. 06 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 19-Oct 23-Oct 30-Oct 13-Nov 11-Dec DENSIDAD DE CAMPO

MURO DE CUNETA TIPO I DE 0.50x 0.60M EN LA Cdra. 04 DEL JR FRANCISCO


17 16-oct-21 210 4" 4 5/7 PIZARRO, LADO DERECHO 19-Oct 23-Oct 30-Oct 13-Nov 11-Dec

18 18-oct-21 175 4" 5 2/7 VEREDA EN LA Cdra. 06 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 21-Oct 25-Oct 1-Nov 15-Nov 13-Dec
LOSA DE FONDO DE ALCANTARILLA TIPO II DE 0.80x 0.70M ENTRE LA Cdra. 07
19 18-oct-21 210 4" 7 1/2 Y AV. AVIACION, LADO IZQUIERDO 21-Oct 25-Oct 1-Nov 15-Nov 13-Dec

20 20-oct-21 175 4" 4 5/7 VEREDA EN LA Cdra. 05 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 23-Oct 27-Oct 3-Nov 17-Nov 15-Dec DENSIDAD DE CAMPO

LOSA SUPERIOR DE ALCANTARILLA TIPO II DE 0.80x 0.70M ENTRE LA Cdra. 07


21 20-oct-21 210 4" 4 5/7 Y AV. AVIACION, LADO IZQUIERDO 23-Oct 27-Oct 3-Nov 17-Nov 15-Dec
LOSA DE FONDO DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 05
20-oct-21 210 4" 5 2/7 DE FRANCISCO PIZARRO, PSJE FELIPE YAP/JR. 1 DE MAYO, LADO IZQUIERDO
DENSIDAD DE CAMPO
22 23-Oct 27-Oct 3-Nov 17-Nov 15-Dec
MURO DE CUNETA TIPO I DE 0.50x 0.60M EN LA Cdra. 03 DEL JR FRANCISCO
23 22-oct-21 210 4" 7 1/2 PIZARRO, LADO IZQUIERDO 25-Oct 29-Oct 5-Nov 19-Nov 17-Dec
LOSA DE FONDO DE CUNETA TIPO I DE 0.50x 0.60M EN LA Cdra. 07 DEL JR
24 22-oct-21 210 4" 4 5/7 FRANCISCO PIZARRO, LADO DERECHO 25-Oct 29-Oct 5-Nov 19-Nov 17-Dec DENSIDAD DE CAMPO

25 22-oct-21 175 4" 4 5/7 VEREDA EN LA Cdra. 05 Y 04 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 25-Oct 29-Oct 5-Nov 19-Nov 17-Dec DENSIDAD DE CAMPO

LOSA DE FONDO DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 02 DEL JR


26 23-oct-21 210 4" 4 5/7 FRANCISCO PIZARRO, LADO IZQUIERDO 26-Oct 30-Oct 6-Nov 20-Nov 18-Dec DENSIDAD DE CAMPO

27 25-oct-21 210 4" 5 2/7 ZAPATA DE MURO DE CONTENCION EN Cdra. 07 Y 06, LADO DERECHO
28-Oct 1-Nov 8-Nov 22-Nov 20-Dec DENSIDAD DE CAMPO

MURO DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 02 DEL JR FRANCISCO


28 25-oct-21 210 4" 7 1/2 PIZARRO, LADO IZQUIERDO 28-Oct 1-Nov 8-Nov 22-Nov 20-Dec
CODIGO
CONTROL MUESTRAS DE CONCRETO ENVIADAS A LABORATORIO
VERSION

MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DEL JR. FRANCISCO PIZARRO CUADRAS 01 A LA 07 Y JR. SAN MARTIN CUADRAS 01 A LA 04
PROYECTO: DISTRITO DE MORALES, PROVINCIA DE SAN MARTIN-SAN MARTIN

Fecha Resistencia Valor Fechas de entrega reportes


Muestra Tipo Elemento OBSERVACIONES
Vaciado esperada asentamiento
3 dias 7 dias 14 dias 28 dias Testigos
1 2-nov-21 175 4" 7 1/2 VEREDA EN LA Cdra. 02 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 5-Nov 9-Nov 16-Nov 30-Nov 28-Dec DENSIDAD DE CAMPO

LOSA DE FONDO DE ALCANTARILLA TIPO I DE 0.80x 0.60M EN LA Cdra. 07 y 06


2 2-nov-21 210 4" 6 3/8 DEL JR FRANCISCO PIZARRO, LADO DERECHO 5-Nov 9-Nov 16-Nov 30-Nov 28-Dec DENSIDAD DE CAMPO

LOSA DE FONDO DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR


3 3-nov-21 210 4" 5 1/2 FRANCISCO PIZARRO, LADO IZQUIERDO 6-Nov 10-Nov 17-Nov 1-Dec 29-Dec DENSIDAD DE CAMPO

MURO DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 06 Y 07 DEL


4 3-nov-21 210 4" 6 1/2 JR FRANCISCO PIZARRO, LADO DERECHO 6-Nov 10-Nov 17-Nov 1-Dec 29-Dec
VEREDA EN LA Cdra. 06 y Cdra. 05 DEL JR FRANCISCO PIZARRO, LADO
5 4-nov-21 175 4" 8 4/5 DERECHO 7-Nov 11-Nov 18-Nov 2-Dec 30-Dec DENSIDAD DE CAMPO

LOSA SUPERIOR DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 06


6 4-nov-21 210 4" 6 3/5 Y 07 DEL JR FRANCISCO PIZARRO, LADO DERECHO 7-Nov 11-Nov 18-Nov 2-Dec 30-Dec
MURO DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR FRANCISCO
7 5-nov-21 210 4" 6 1/7 PIZARRO, LADO IZQUIERDO 8-Nov 12-Nov 19-Nov 3-Dec 31-Dec
LOSA SUPERIOR DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 06
8 5-nov-21 210 4" 5 1/2 Y 05 DEL JR FRANCISCO PIZARRO, LADO DERECHO 8-Nov 12-Nov 19-Nov 3-Dec 31-Dec
LOSA DE FONDO DE ALCANTARILLA TIPO I DE 0.80x 0.60M EN LA Cdra. 05
5-nov-21 210 4" 6 5/7 DEL JR.FRANCISCO PIZARRO Y EL JR.1 DE MAYO , LADO DERECHO
9 8-Nov 12-Nov 19-Nov 3-Dec 31-Dec
MURO DE ALCANTARILLA TIPO I DE 0.80x 0.60M ENTRE LA Cdra. 05 Y 07 DEL
12 5-nov-21 210 4" 6 2/5 JR FRANCISCO PIZARRO, LADO DERECHO 8-Nov 12-Nov 19-Nov 3-Dec 31-Dec
LOSA DE FONDO DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR
13 8-nov-21 210 4" 7 1/3 SAN MARTIN, LADO IZQUIERDO 11-Nov 15-Nov 22-Nov 6-Dec 3-Jan DENSIDAD DE CAMPO

LOSA DE FONDO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA CDRA. 02


14 9-nov-21 210 4" 8 3/5 DEL JR SAN MARTIN, LADO IZQUIERDO 12-Nov 16-Nov 23-Nov 7-Dec 4-Jan

15 10-nov-21 175 4" 6 5/7 VEREDA EN LA Cdra. 04 DEL JR FRANCISCO PIZARRO, LADO DERECHO 13-Nov 17-Nov 24-Nov 8-Dec 5-Jan
LOSA DE FONDO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA CDRA. 03
16 10-nov-21 175 4" 7 1/2 DEL JR SAN MARTIN, LADO IZQUIERDO 13-Nov 17-Nov 24-Nov 8-Dec 5-Jan
LOSA SUPERIOR DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR.
17 10-nov-21 210 4" 6 5/7 SAN MARTIN, LADO IZQUIERDO 13-Nov 17-Nov 24-Nov 8-Dec 5-Jan
MURO DE CUNETA CON TAPA TIPO III DE 0.50x 0.60M EN LA Cdra. 02 DEL JR.
18 10-nov-21 210 4" 5 3/5 SAN MARTIN, LADO IZQUIERDO 13-Nov 17-Nov 24-Nov 8-Dec 5-Jan

19 11-nov-21 175 4" 7 1/2 MARTILLO N°14 EN LA Cdra. 04 DEL JR FRANCISCO PIZARRO, LADO DERECHO
14-Nov 18-Nov 25-Nov 9-Dec 6-Jan DENSIDAD DE CAMPO

MURO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA Cdra. 03 DEL JR. SAN
20 11-nov-21 210 4" 6 1/2 MARTIN, LADO IZQUIERDO 14-Nov 18-Nov 25-Nov 9-Dec 6-Jan
LOSA DE FONDO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA CDRA. 03
21 11-nov-21 210 4" 6 5/7 DEL JR SAN MARTIN, LADO DERECHO 14-Nov 18-Nov 25-Nov 9-Dec 6-Jan
MURO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA Cdra. 02 DEL JR. SAN
15-nov-21 210 4" 6 2/7 MARTIN, LADO DERECHO
22 18-Nov 22-Nov 29-Nov 13-Dec 10-Jan
MURO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA Cdra. 03 DEL JR. SAN
23 15-nov-21 210 4" 6 5/7 MARTIN, LADO IZQUIERDO 18-Nov 22-Nov 29-Nov 13-Dec 10-Jan
LOSA DE FONDO DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR
24 15-nov-21 210 4" 7 1/5 SAN MARTIN, LADO DERECHO 18-Nov 22-Nov 29-Nov 13-Dec 10-Jan DENSIDAD DE CAMPO

LOSA DE FONDO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA CDRA. 04


25 17-nov-21 210 4" 7 3/5 DEL JR SAN MARTIN, LADO DERECHO 20-Nov 24-Nov 1-Dec 15-Dec 12-Jan DENSIDAD DE CAMPO

MURO DE CUNETA CON TAPA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR.
26 17-nov-21 210 4" 6 4/5 SAN MARTIN, LADO DERECHO 20-Nov 24-Nov 1-Dec 15-Dec 12-Jan
MURO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA Cdra. 04 DEL JR. SAN
29 22-nov-21 210 4" 7 1/2 MARTIN, LADO IZQUIERDO 25-Nov 29-Nov 6-Dec 20-Dec 17-Jan
LOSA SUPERIOR DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR.
30 23-nov-21 210 4" 8 1/2 SAN MARTIN, LADO DERECHO 26-Nov 30-Nov 7-Dec 21-Dec 18-Jan

31 25-nov-21 175 4" 9 1/2 VEREDA EN LA Cdra. 01 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO
DENSIDAD DE CAMPO

LOSA DE FONDO DE CUNETA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR.
32 26-nov-21 213 4" 10 1/2 FRNCISCO PIZARRO, LADO DERECHO

33 26-nov-21 214 4" 11 1/2 VEREDA EN LA Cdra. 01 DEL JR. SAN MARTIN, LADO IZQUIERDO
DENSIDAD DE CAMPO
CODIGO
CONTROL MUESTRAS DE CONCRETO ENVIADAS A LABORATORIO
VERSION

MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DEL JR. FRANCISCO PIZARRO CUADRAS 01 A LA 07 Y JR. SAN MARTIN CUADRAS 01 A LA 04
PROYECTO: DISTRITO DE MORALES, PROVINCIA DE SAN MARTIN-SAN MARTIN

Fecha Resistencia Valor Fechas de entrega reportes


Muestra Tipo Elemento OBSERVACIONES
Vaciado esperada asentamiento
3 dias 7 dias 14 dias 28 dias Testigos
LOSA DE FONDO DE CUNETA CON TAPA TIPO III DE 0.50x 0.60M EN LA Cdra. 01
1 27-nov-21 210 4" 7 1/2 DEL JR FRANCISCO PIZARRO, LADO IZQUIERDO 30-Nov 4-Dec 11-Dec 25-Dec 22-Jan DENSIDAD DE CAMPO

MURO DE CUNETA CON TAPA TIPO III DE 0.50x 0.60M EN LA Cdra. 01 DEL JR
2 27-nov-21 210 4" 6 3/8 FRANCISCO PIZARRO, LADO DERECHO 30-Nov 4-Dec 11-Dec 25-Dec 22-Jan

3 27-nov-21 175 4" 5 1/2 VEREDA EN LA Cdra. 01 DEL JR SAN MARTIN, LADO IZQUIERDO
30-Nov 4-Dec 11-Dec 25-Dec 22-Jan DENSIDAD DE CAMPO

MURO DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M EN LA Cdra. 04 DEL JR SAN
4 1-dic-21 210 4" 6 1/2 MARTIN,, LADO DERECHO 4-Dec 8-Dec 15-Dec 29-Dec 26-Jan

5 1-dic-21 175 4" 8 4/5 MARTILLO N°07 EN LA Cdra. 01 DEL JR FRANCISCO PIZARRO, LADO DERECHO
4-Dec 8-Dec 15-Dec 29-Dec 26-Jan DENSIDAD DE CAMPO

6 1-dic-21 175 4" 6 3/5 VEREDA EN LA Cdra. 02 DEL JR SAN MARTIN, LADO DERECHO
4-Dec 8-Dec 15-Dec 29-Dec 26-Jan DENSIDAD DE CAMPO

LOSA SUPERIOR DE CUNETA CON TAPA TIPO III DE 0.50x 0.60M Cdra. 01 DEL
7 2-dic-21 210 4" 6 1/7 JR FRANCISCO PIZARRO, LADO DERECHO 5-Dec 9-Dec 16-Dec 30-Dec 27-Jan

8 3-dic-21 175 4" 5 1/2 MARTILLO N°04 EN LA Cdra. 07 DEL JR FRANCISCO PIZARRO, LADO DERECHO
6-Dec 10-Dec 17-Dec 31-Dec 28-Jan
9 3-dic-21 175 4" 6 5/7 MARTILLO N°04 EN LA Cdra. 06 DEL JR FRANCISCO PIZARRO, LADO DERECHO 6-Dec 10-Dec 17-Dec 31-Dec 28-Jan DENSIDAD DE CAMPO

10 3-dic-21 175 4" 6 2/5 VEREDA EN LA Cdra. 01 DEL JR SAN MARTIN, LADO DERECHO
6-Dec 10-Dec 17-Dec 31-Dec 28-Jan

11 4-dic-21 175 4" 7 1/3 MARTILLO N°11 EN LA Cdra. 05 DEL JR FRANCISCO PIZARRO, LADO DERECHO
7-Dec 11-Dec 18-Dec 1-Jan 29-Jan
MARTILLO N°10 EN LA Cdra. 04 DEL JR FRANCISCO PIZARRO, LADO
12 6-dic-21 175 4" 8 3/5 IZQUIERDO 9-Dec 13-Dec 20-Dec 3-Jan 31-Jan
LOSA SUPERIOR DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M Cdra. 02 DEL JR
13 11-dic-21 210 4" 6 5/7 SAN MRTIN, LADO DERECHO 14-Dec 18-Dec 25-Dec 8-Jan 5-Feb
LOSA SUPERIOR DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M Cdra. 02 DEL JR
14 11-dic-21 210 4" 7 1/2 SAN MRTIN, LADO IZQUIERDO 14-Dec 18-Dec 25-Dec 8-Jan 5-Feb

15 11-dic-21 175 4" 6 5/7 VEREDA EN LA Cdra. 02 DEL JR SAN MARTIN, LADO IZQUIERDO
14-Dec 18-Dec 25-Dec 8-Jan 5-Feb
LOSA DE FONDO DE CUNETA CON TAPA TIPO III DE 0.50x 0.60M EN LA Cdra. 01
16 13-dic-21 210 4" 6 5/7 DEL JR FRANCISCO PIZARRO, LADO DERECHO 16-Dec 20-Dec 27-Dec 10-Jan 7-Feb DENSIDAD DE CAMPO

LOSA SUPERIOR DE CUNETA SIN TAPA TIPO I DE 0.50x 0.60M Cdra. 03 DEL JR
17 13-dic-21 210 4" 6 5/7 SAN MRTIN, LADO IZQUIERDO 16-Dec 20-Dec 27-Dec 10-Jan 7-Feb

18 14-dic-21 175 4" 7 1/2 MARTILLO N°06 EN LA Cdra. 07 DEL JR FRANCISCO PIZARRO, LADO DERECHO
17-Dec 21-Dec 28-Dec 11-Jan 8-Feb
MARTILLO N°13 EN LA Cdra. 05 DEL JR FRANCISCO PIZARRO, LADO
19 14-dic-21 175 4" 6 1/2 IZQUIERDO 17-Dec 21-Dec 28-Dec 11-Jan 8-Feb
VEREDA EN LA Cdra. 03 DEL JR SAN MARTIN, LADO IZQUIERDO Y LADO
20 14-dic-21 175 4" 6 5/7 DERECHO 17-Dec 21-Dec 28-Dec 11-Jan 8-Feb

16-dic-21 175 4" 6 2/7 VEREDA EN LA Cdra. 04 DEL JR SAN MARTIN, LADO IZQUIERDO
21 19-Dec 23-Dec 30-Dec 13-Jan 10-Feb

23 17-dic-21 175 4" 6 5/7 VEREDA EN LA Cdra. 04 DEL JR SAN MARTIN, LADO DERECHO
20-Dec 24-Dec 31-Dec 14-Jan 11-Feb
CODIGO
CONTROL MUESTRAS DE CONCRETO ENVIADAS A LABORATORIO
VERSION

PROYECTO: “MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL URBANA DE LOS JIRONES: JR. MIGUEL GRAU CDRA 01 A LA 03, JR. FRANCISCO TORRES CDRA 01 A LA 08, JR. MOYOBAMBA CDRA 01 A LA 07, EMP. CARRETERA OASIS, EN LA
LOCALIDAD DE MORALES DEL DISTRITO DE MORALES - PROVINCIA DE S

Resistencia Fechas de entrega reportes


Muestra Fecha Vaciado esperada
Tipo Valor asentamiento Elemento OBSERVACIONES
3 dias 7 dias 14 dias 28 dias Testigos
Vaciado de concreto f’c= 175 kg/cm² en losa de fondo de cuneta de CUNETA ABIERTA 0.40x0.40M
1 25-ago-22 175 en Jr. Francisco Torres cdra. 08 – lado izquierdo, Jr. Francisco Torres cdra. 04 – lado izquierdo y Jr. 28-Aug 1-Sep 8-Sep 22-Sep 20-Oct ROTURA DE PROBETAS DE CONCRETO
Miguel Grau cdra. 02 – lado izquierdo.

Vaciado de concreto f’c= 175 kg/cm² en losa de fondo de cuneta de CUNETA ABIERTA 0.40x0.40M
2 26-ago-22 175 en Jr. Francisco Torres cdra. 04 – lado izquierdo y Jr. Miguel Grau cdra. 02 – lado izquierdo.
29-Aug 2-Sep 9-Sep 23-Sep 21-Oct ROTURA DE PROBETAS DE CONCRETO

Vaciado de concreto f’c= 175 kg/cm² en losa de fondo de cuneta de CUNETA ABIERTA 0.40x0.40M
en Jr. Francisco Torres cdra. 04 – lado derecho y Jr. Miguel Grau cdra. 02 – lado derecho. Vaciado
3 27-ago-22 175 de concreto f’c= 175 kg/cm² en muro de cuneta de CUNETA ABIERTA 0.40x0.40M en Jr. Francisco 30-Aug 3-Sep 10-Sep 24-Sep 22-Oct ROTURA DE PROBETAS DE CONCRETO
Torres cdra. 08 – lado izquierdo, Jr. Francisco Torres cdra. 04 – lado izquierdo y Jr. Miguel Grau
cdra. 02 – lado izquierdo.

Vaciado de concreto f’c= 175 kg/cm² en losa de fondo de cuneta de CUNETA ABIERTA 0.40x0.40M
en Jr. Francisco Torres cdra. 08 – lado derecho y Jr. Miguel Grau cdra. 02 – lado derecho. Vaciado
4 29-ago-22 175 de concreto f’c= 175 kg/cm² en muro de cuneta de CUNETA ABIERTA 0.40x0.40M en Jr. Francisco 1-Sep 5-Sep 12-Sep 26-Sep 24-Oct ROTURA DE PROBETAS DE CONCRETO
Torres cdra. 04 – lado derecho y Jr. Miguel Grau cdra. 02 – lado derecho.
MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DEL JR. FRACISCO PIZARRO CDRA. 01 AL 07 JR. SAN MARTIN CDRA. 01 AL 04, DISTRITO DE
MORALES, PROVINCIA SAN MARTIN

FECHA 1/15/2022
MAÑANA TARDE
INGRESO SALIDA INGRESO SALIDA
FIRMA FIRMA FIRMA FIRMA
N° DNI APELLIDOS Y NOMBRES CATEGORIA
7:00 AM 12:00 AM 13:30 PM 18:00 PM
1 70757135 ALEGRIA ZEGARRA ADREA SOLEDAD ING: AMBIENTAL

2 71891136 ARIAS CABALLERO DANIEL ING: CIVIL

3 73437941 CUBAS BECERRA LENIN ASIS. CONTROL DE CALIDAD

4 43722157 LIZARZABURO GARCIA KARLA ANGELICA ADMINISTRADORA

5 42081643 LIZARZABURO GARCIA ROXANA DEL PILAR ASIS. SOMA

6 1120621 LOZANO RAMIREZ RAMSES ING: CIVIL

7 47780516 PISCOYA HIDALGO JEAN CARLOS COTIZADOR

8 70349072 RIOS AREVALO MERY LUZ ENFERMERA

9 48707272 SAAVEDRA SORIA MAIRENA ARQUITECTA

10 74289838 TORRES DEL AGUILA ALEXIS APOYO SEGURIDAD

11 76675126 TORRES MACEDO ANGEL TOPOGRAFO

12 46759628 TORRES PAREDES GALO ALAIN TAREADOR

13 70167126 UBIDIA PINEDO LUCIA ESTHER ING: CIVIL

14 1148560 VASQUEZ RUIZ JACKSON CAPATAZ