Id Modo Nombre de tarea Duración Comienzo Fin Predecesoras

Costo
de 01 ago '22 08 ago '22 15 ago '22 22 ago '22 29 ago '22 05 sep '22 12 sep '22 19 sep '22 26 sep '22 03 oct '22 10 oct '22 17 oct '22 24 oct '22 31 oct '22 07 nov '22 14 nov '22 21 nov '22 28 nov '22 05 dic '22 12 dic '22 19 dic '22 26 dic '22 02 ene '23 09 ene '23 16 ene '23 23 ene '23 30 ene '23
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
0 CREACION DEL MERCADO DE ABASTOS EN EL AA.HH. VILLA HERMOSA EN 184 días lun 01/08/22 mar 31/01/23 S/ 6,802,912.07
EL DISTRITO DE CASMA - PROVINCIA DE CASMA - DEPARTAMENTO DE
ANCASH
1 1 ESTRUCTURAS 184 días lun 01/08/22 mar 31/01/23 S/ 3,272,138.85
2 1.1 OBRAS PROVISIONALES 184 días lun 01/08/22 mar 31/01/23 S/ 159,929.46
3 1.1.1 ALMACEN, OFICINA Y CASETA DE GUARDIANIA 1 día lun 01/08/22 lun 01/08/22 5CC S/ 4,954.00
4 1.1.2 SERVICIOS HIGIENICOS PORTATILES 160 días lun 01/08/22 sáb 28/01/23 3CC S/ 5,228.40
5 1.1.3 CARTEL DE OBRA 3.60 X 2.40 M 1 día lun 01/08/22 lun 01/08/22 S/ 1,563.53
6 1.1.4 CONSUMO Y MANTENIMIENTO DE ENERGIA ELECTRICA 1 día lun 01/08/22 lun 01/08/22 3CC S/ 1,500.00
7 1.1.5 CERCO PROVISIONAL DE OBRA (H=2.50 M) 1 día lun 01/08/22 lun 01/08/22 5CC S/ 5,943.82
8 1.1.6 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO Y HERRAMIENTAS184 días lun 01/08/22 mar 31/01/23 5CC S/ 3,000.00
9 1.1.7 FLETE 180 días lun 01/08/22 sáb 28/01/23 5CC S/ 137,739.71
10 1.2 SEGURIDAD Y SALUD OCUPACIONAL, MITIGACION AMBIENTAL, 184 días lun 01/08/22 mar 31/01/23 S/ 69,830.88
MONITOREO ARQUEOLOGICO Y PLAN CONTROL DEL COVID-19
11 1.2.1 SEGURIDAD Y SALUD OCUPACIONAL 184 días lun 01/08/22 mar 31/01/23 S/ 19,546.02
12 1.2.1.1 ELABORACIÓN, IMPLEMENTACION Y ADMINISTRACION DEL 2 días mar 02/08/22 mié 03/08/22 3 S/ 300.00
PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO
13 1.2.1.2 EQUIPOS DE PROTECCION INDIVIDUAL 1 día mar 02/08/22 mar 02/08/22 12CCS/ 1,580.40
14 1.2.1.3 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD 184 días lun 01/08/22 mar 31/01/23 5CC S/ 4,465.62
15 1.2.1.4 CHARLAS DE CAPACITACION EN SEGURIDAD Y SALUD 183 días lun 01/08/22 lun 30/01/23 5CC S/ 7,200.00
16 1.2.1.5 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS EN 184 días lun 01/08/22 mar 31/01/23 3CC S/ 6,000.00
SEGURIDAD Y SALUD DURANTE EL TRABAJO
17 1.2.2 MITIGACIÓN E IMPACTO AMBIENTAL 183 días lun 01/08/22 lun 30/01/23 S/ 11,500.00
18 1.2.2.1 MANEJO DE ESCOMBROS Y MATERIAL EXCEDENTE 183 días lun 01/08/22 lun 30/01/23 5CC S/ 2,500.00
19 1.2.2.2 MANEJO DE CONCRETO EN OBRA 90 días lun 08/08/22 vie 18/11/22 42CCS/ 3,000.00
20 1.2.2.3 MANEJO DE AGREGADOS PETREOS (ARENAS, GRAVAS, 90 días lun 01/08/22 jue 10/11/22 33CCS/ 3,000.00
TRITURADOS O RECEBOS), LADRILLO Y PRODUCTOS DE ARCHILLA
21 1.2.2.4 MANEJO DE CAMPAMENTO Y ALMACEN 90 días mar 02/08/22 vie 11/11/22 3 S/ 3,000.00
22 1.2.3 VIGILANCIA PREVENCION Y CONTROL DEL COVID-19 184 días lun 01/08/22 mar 31/01/23 S/ 38,784.86
23 1.2.3.1 ELABORACION DEL PLAN PARA VIGILANCIA -PREVENCION - 1 día mar 02/08/22 mar 02/08/22 3 S/ 300.00
CONTROL DEL COVID-19
24 1.2.3.2 EQUIPOS DE PROTECION PERSONAL FRENTE A COVID 19 184 días lun 01/08/22 mar 31/01/23 5CC S/ 3,984.48
25 1.2.3.3 LIMPIEZA Y DESINFECCION EN OBRA FRENTE A COVID 19 184 días lun 01/08/22 mar 31/01/23 5CC S/ 4,014.21
26 1.2.3.4 EQUIPAMIENTO PARA LA VIGILANCIA DE LA SALUD 1 día mar 02/08/22 mar 02/08/22 23CCS/ 9,486.17
27 1.2.3.5 CAPACITACION EN SEGURIDAD Y SALUD 160 días lun 01/08/22 sáb 28/01/23 3CC S/ 3,000.00
28 1.2.3.6 PERSONAL DE SALUD (COVID 19) 162 días lun 01/08/22 mar 31/01/23 3CC S/ 18,000.00
29 1.3 MODULO I 94 días lun 01/08/22 mar 15/11/22 S/ 726,300.17
30 1.3.1 TRABAJOS PRELIMINARES 30 días lun 01/08/22 sáb 03/09/22 S/ 13,325.50
31 1.3.1.1 LIMPIEZA DE TERRENO MANUAL 30 días lun 01/08/22 sáb 03/09/22 7CC S/ 7,536.34
32 1.3.1.2 TRAZO Y REPLANTEO TOPOGRAFICO PRELIMINAR 15 días lun 01/08/22 mié 17/08/22 31CCS/ 5,789.16
33 1.3.2 MOVIMIENTO DE TIERRAS 42 días lun 01/08/22 vie 16/09/22 S/ 59,940.20
34 1.3.2.1 EXCAVACION DE ZANJAS PARA ZAPATAS 7 días lun 01/08/22 lun 08/08/22 32CCS/ 4,610.32
35 1.3.2.2 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION 7 días mar 02/08/22 mié 10/08/22 34CC+2 días
S/ 340.26
36 1.3.2.3 EXCAVACION DE ZANJAS PARA CIMENTOS 2 días jue 04/08/22 sáb 06/08/22 35CC+2 días
S/ 3,353.65
37 1.3.2.4 NIVELACION Y APISONADO 10 días jue 04/08/22 mar 16/08/22 32CC+4 días
S/ 4,362.68
38 1.3.2.5 AFIRMADO PARA PISOS Y VEREDAS, COMPACTACION 10 días mar 06/09/22 vie 16/09/22 39 S/ 23,282.60
C/EQUIPO, E=0.10M
39 1.3.2.6 RELLENO COMPACTADO CON MATERIAL PROPIO 3 días vie 02/09/22 mar 06/09/22 61;499;536
S/ 7,945.81
40 1.3.2.7 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día mar 06/09/22 mié 07/09/22 39 S/ 4,656.36
41 1.3.2.8 ELIMINACION DE MATERIAL EXCEDENTE 2 días mié 07/09/22 jue 08/09/22 40 S/ 11,388.52
42 1.3.3 OBRAS DE CONCRETO SIMPLE 43 días lun 08/08/22 lun 26/09/22 S/ 186,518.69
43 1.3.3.1 SOLADO 1 día lun 08/08/22 mar 09/08/22 S/ 128.21
44 1.3.3.1.1 SOLADO DE CONCRETO e=0.10m, C:H 1:12 1 día lun 08/08/22 mar 09/08/22 34 S/ 128.21
45 1.3.3.2 SOBRECIMIENTO 3 días vie 02/09/22 mar 06/09/22 S/ 1,784.02
46 1.3.3.2.1 SOBRECIMIENTO: C:H 1:6 + 25% P.M. 2" 1 día lun 05/09/22 mar 06/09/22 47 S/ 787.44
47 1.3.3.2.2 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO 2 días vie 02/09/22 lun 05/09/22 61 S/ 996.58
48 1.3.3.3 CIMIENTO CORRIDO 3 días mar 16/08/22 vie 19/08/22 S/ 60,169.07
49 1.3.3.3.1 CIMIENTO CORRIDO C:H 1:10 + 30% P.G. MAX. 8" 3 días mar 16/08/22 vie 19/08/22 70;74S/ 60,169.07
50 1.3.3.4 FALSO PISO 3 días vie 16/09/22 mar 20/09/22 S/ 100,143.88
51 1.3.3.4.1 FALSO PISO MEZCLA C:H 1:8 e=0.10m 3 días vie 16/09/22 mar 20/09/22 38 S/ 100,143.88
52 1.3.3.5 VEREDA 8 días vie 16/09/22 lun 26/09/22 S/ 24,293.51
53 1.3.3.5.1 VEREDA DE CONCRETO F'C=175 KG/CM2, E=10 CM 6 días vie 16/09/22 vie 23/09/22 38 S/ 22,576.73
SEMIPULIDO Y BRUÑADO INC. ENCOFRADO
54 1.3.3.5.2 CURADO DE VEREDAS 2 días vie 23/09/22 lun 26/09/22 53 S/ 810.53
55 1.3.3.5.3 JUNTAS ASFALTICAS E=1", DILATACION 2 días vie 23/09/22 lun 26/09/22 53 S/ 906.25
56 1.3.4 OBRAS DE CONCRETO ARMADO 86 días mar 09/08/22 mar 15/11/22 S/ 466,515.78
57 1.3.4.1 ZAPATAS 8 días mar 09/08/22 jue 18/08/22 S/ 83,927.71
58 1.3.4.1.1 ZAPATAS - CONCRETO F'C= 210 KG/CM2 3 días lun 15/08/22 jue 18/08/22 59 S/ 42,495.60
59 1.3.4.1.2 ZAPATAS - ACERO FY=4200 KG/CM2 5 días mar 09/08/22 lun 15/08/22 44 S/ 41,432.11
60 1.3.4.2 VIGAS DE CIMENTACION 12 días vie 19/08/22 vie 02/09/22 S/ 44,107.17
61 1.3.4.2.1 VIGA DE CIMENTACIÒN - CONCRETO F'C= 210 KG/CM2 5 días vie 26/08/22 vie 02/09/22 62 S/ 16,024.89
62 1.3.4.2.2 VIGA DE CIMENTACION - ACERO FY=4200 KG/CM2 7 días vie 19/08/22 vie 26/08/22 49 S/ 28,082.28
63 1.3.4.3 SOBRE CIMIENTO REFORZADO 7 días vie 02/09/22 vie 09/09/22 S/ 56,556.75
64 1.3.4.3.1 SOBRE CIMIENTO REFORZADO - CONCRETO F'C= 175 KG/CM2
3 días lun 05/09/22 jue 08/09/22 66CC+2
S/ 14,683.88
días
65 1.3.4.3.2 SOBRE CIMIENTO REFORZADO - ENCOFRADO Y 7 días vie 02/09/22 vie 09/09/22 61 S/ 30,125.75
DESENCOFRADO
66 1.3.4.3.3 SOBRE CIMIENTO REFORZADO - ACERO FY=4200 KG/CM22 días vie 02/09/22 lun 05/09/22 65CCS/ 11,747.12
67 1.3.4.4 COLUMNAS 43 días mar 09/08/22 mar 27/09/22 S/ 135,744.88
68 1.3.4.4.1 COLUMNAS - CONCRETO F'C= 210 KG/CM2 11 días lun 12/09/22 sáb 24/09/22 69CC+2 días
S/ 41,787.55
69 1.3.4.4.2 COLUMNAS - ENCOFRADO Y DESENCOFRADO 15 días vie 09/09/22 mar 27/09/22 63;70S/ 87,290.98
70 1.3.4.4.3 COLUMNAS - ACERO FY=4200 KG/CM2 5 días mar 09/08/22 lun 15/08/22 59CCS/ 6,666.35
71 1.3.4.5 PLACAS 12 días mié 10/08/22 mar 23/08/22 S/ 35,963.22
72 1.3.4.5.1 PLACAS - CONCRETO F'C= 210 KG/CM2 3 días mié 17/08/22 vie 19/08/22 73CC+1 día
S/ 9,665.17
73 1.3.4.5.2 PLACAS - ENCOFRADO Y DESENCOFRADO 7 días mar 16/08/22 mar 23/08/22 74 S/ 18,504.70
74 1.3.4.5.3 PLACAS - ACERO FY=4200 KG/CM2 5 días mié 10/08/22 mar 16/08/22 35 S/ 7,793.35
75 1.3.4.6 VIGAS 4 días lun 31/10/22 sáb 05/11/22 S/ 91,156.12
76 1.3.4.6.1 VIGAS - CONCRETO F'C= 210 KG/CM2 1 día jue 03/11/22 vie 04/11/22 78 S/ 23,765.08
77 1.3.4.6.2 VIGAS - ENCOFRADO Y DESENCOFRADO 4 días lun 31/10/22 sáb 05/11/22 246 S/ 37,503.26
78 1.3.4.6.3 VIGAS - ACERO FY=4200 KG/CM2 2 días lun 31/10/22 jue 03/11/22 77CCS/ 29,887.78
79 1.3.4.7 LOSA ALIGERADA 9 días sáb 05/11/22 mar 15/11/22 S/ 7,505.94
80 1.3.4.7.1 LOSA ALIGERADA - CONCRETO F'C= 210 KG/CM2 1 día lun 07/11/22 mar 08/11/22 83 S/ 1,522.58
81 1.3.4.7.2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO 9 días sáb 05/11/22 mar 15/11/22 77 S/ 2,691.48
82 1.3.4.7.3 LOSA ALIGERADA - LADRILLO HUECO 15 x 30 x 30 1 día sáb 05/11/22 sáb 05/11/22 81CCS/ 1,053.69
83 1.3.4.7.4 LOSA ALIGERADA - ACERO FY=4200 KG/CM2 1 día sáb 05/11/22 lun 07/11/22 82 S/ 2,238.19
84 1.3.4.8 MESA DE CONCRETO 4 días mar 27/09/22 vie 30/09/22 S/ 11,553.99
85 1.3.4.8.1 LOSA PARA LAVADERO - FC=175 KG/CM2 1 día mié 28/09/22 jue 29/09/22 86CC+1
S/ 2,414.06
día
86 1.3.4.8.2 LOSA PARA LAVADERO, ENCOFRADO Y DESENCOFRADO 3 días mar 27/09/22 vie 30/09/22 87 S/ 6,673.09
87 1.3.4.8.3 LOSA PARA LAVADERO - ACERO FY=4200 KG/CM2 1 día mar 27/09/22 mar 27/09/22 246CC
S/ 2,466.84
88 1.4 CISTERNA 24 días mar 02/08/22 sáb 27/08/22 S/ 27,984.51
89 1.4.1 TRABAJOS PRELIMINARES 2 días mar 02/08/22 mié 03/08/22 S/ 168.84
90 1.4.1.1 LIMPIEZA DE TERRENO MANUAL 1 día mar 02/08/22 mar 02/08/22 7 S/ 95.49
91 1.4.1.2 TRAZO Y REPLANTEO TOPOGRAFICO PRELIMINAR 1 día mar 02/08/22 mié 03/08/22 90 S/ 73.35
92 1.4.2 MOVIMIENTO DE TIERRAS 22 días mié 03/08/22 sáb 27/08/22 S/ 1,281.82
93 1.4.2.1 EXCAVACION MASIVA CON MAQUINARIA EN TERRENO NORMAL
1 día mié 03/08/22 jue 04/08/22 91 S/ 274.29
94 1.4.2.2 EXCAVACION DE ZANJAS PARA CIMENTOS 2 días jue 04/08/22 sáb 06/08/22 93 S/ 61.60
95 1.4.2.3 RELLENO COMPACTADO CON MATERIAL PROPIO 1 día mié 24/08/22 jue 25/08/22 113 S/ 13.23
96 1.4.2.4 NIVELACION Y APISONADO 1 día jue 25/08/22 vie 26/08/22 95 S/ 179.86
97 1.4.2.5 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día jue 25/08/22 vie 26/08/22 96CCS/ 160.37
98 1.4.2.6 ELIMINACION DE MATERIAL EXCEDENTE 1 día vie 26/08/22 sáb 27/08/22 97 S/ 592.47
99 1.4.3 OBRAS DE CONCRETO SIMPLE 7 días sáb 06/08/22 lun 15/08/22 S/ 3,143.15
100 1.4.3.1 SOLADO DE CONCRETO e=0.10m, C:H 1:12 1 día sáb 06/08/22 lun 08/08/22 94 S/ 680.23
101 1.4.3.2 DADOS DE CONCRETO F'C=175 KG/CM2 1 día lun 08/08/22 mar 09/08/22 100 S/ 7.55
102 1.4.3.3 BASE DE CONCRETO F'C=175 KG/CM2 1 día mar 09/08/22 mié 10/08/22 101 S/ 7.67
103 1.4.3.4 CIMIENTO CORRIDO C:H 1:10 + 30% P.G. MAX. 8" 1 día mié 10/08/22 jue 11/08/22 102 S/ 959.23
104 1.4.3.5 SOBRECIMIENTO: C:H 1:6 + 25% P.M. 2" 1 día vie 12/08/22 sáb 13/08/22 105FC-2 días
S/ 738.11
105 1.4.3.6 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO 3 días jue 11/08/22 lun 15/08/22 103 S/ 750.36
106 1.4.4 OBRAS DE CONCRETO ARMADO 9 días lun 15/08/22 mié 24/08/22 S/ 23,390.70
107 1.4.4.1 MUROS LATERALES 5 días lun 15/08/22 vie 19/08/22 S/ 14,017.15
108 1.4.4.1.1 MUROS LATERALES - CONCRETO F'C= 210 KG/CM2 1 día jue 18/08/22 vie 19/08/22 109FC-2 días
S/ 4,761.77
109 1.4.4.1.2 MUROS LATERALES - ENCOFRADO Y DESENCOFRADO 3 días mié 17/08/22 vie 19/08/22 110 S/ 6,715.75
110 1.4.4.1.3 MUROS LATERALES - ACERO FY=4200 KG/CM2 2 días lun 15/08/22 mié 17/08/22 105 S/ 2,539.63
111 1.4.4.2 LOSA MACIZA 4 días vie 19/08/22 mié 24/08/22 S/ 9,373.55
112 1.4.4.2.1 LOSA MACIZA - CONCRETO F'C= 210 KG/CM2 1 día lun 22/08/22 mar 23/08/22 113FC-2 días
S/ 4,415.91
113 1.4.4.2.2 LOSA MACIZA - ENCOFRADO Y DESENCOFRADO 3 días sáb 20/08/22 mié 24/08/22 114 S/ 1,342.31
114 1.4.4.2.3 LOSA MACIZA - ACERO FY=4200 KG/CM2 1 día vie 19/08/22 sáb 20/08/22 109 S/ 3,615.33
115 1.5 MODULO II 118 días lun 01/08/22 mié 14/12/22 S/ 1,651,988.01

Proyecto: CREACION DEL MERC Tarea División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso de tarea crítica
Fecha: mié 16/11/22 Progreso de tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica

Página 1
Id Modo Nombre de tarea Duración Comienzo Fin Predecesoras
Costo
de 01 ago '22 08 ago '22 15 ago '22 22 ago '22 29 ago '22 05 sep '22 12 sep '22 19 sep '22 26 sep '22 03 oct '22 10 oct '22 17 oct '22 24 oct '22 31 oct '22 07 nov '22 14 nov '22 21 nov '22 28 nov '22 05 dic '22 12 dic '22 19 dic '22 26 dic '22 02 ene '23 09 ene '23 16 ene '23 23 ene '23 30 ene '23
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
116 1.5.1 TRABAJOS PRELIMINARES 3 días lun 01/08/22 mié 03/08/22 S/ 3,959.74
117 1.5.1.1 LIMPIEZA DE TERRENO MANUAL 1 día lun 01/08/22 lun 01/08/22 7CC S/ 2,239.46
118 1.5.1.2 TRAZO Y REPLANTEO TOPOGRAFICO PRELIMINAR 2 días lun 01/08/22 mié 03/08/22 117 S/ 1,720.28
119 1.5.2 MOVIMIENTO DE TIERRAS 57 días mié 03/08/22 jue 06/10/22 S/ 73,405.14
120 1.5.2.1 EXCAVACION MASIVA CON MAQUINARIA EN TERRENO NORMAL
1 día mié 03/08/22 jue 04/08/22 118 S/ 10,508.45
121 1.5.2.2 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION 10 días vie 12/08/22 mar 23/08/22 122 S/ 124.50
122 1.5.2.3 EXCAVACION DE ZANJAS PARA CIMENTOS 7 días jue 04/08/22 vie 12/08/22 120 S/ 1,061.14
123 1.5.2.4 NIVELACION Y APISONADO 17 días jue 08/09/22 mar 27/09/22 143 S/ 13,027.20
124 1.5.2.5 AFIRMADO PARA PISOS Y VEREDAS, COMPACTACION 4 días mar 27/09/22 vie 30/09/22 123 S/ 6,673.66
C/EQUIPO, E=0.10M
125 1.5.2.6 RELLENO COMPACTADO CON MATERIAL PROPIO 3 días jue 25/08/22 lun 29/08/22 139 S/ 24,939.75
126 1.5.2.7 ACARREO MANUAL DE MATERIAL EXCEDENTE 3 días vie 30/09/22 mar 04/10/22 124 S/ 6,837.27
127 1.5.2.8 ELIMINACION DE MATERIAL EXCEDENTE 2 días mar 04/10/22 jue 06/10/22 126 S/ 10,233.17
128 1.5.3 OBRAS DE CONCRETO SIMPLE 53 días vie 12/08/22 mié 12/10/22 S/ 87,373.97
129 1.5.3.1 SOLADO 1 día vie 12/08/22 sáb 13/08/22 S/ 366.65
130 1.5.3.1.1 SOLADO DE CONCRETO e=0.10m, C:H 1:12 1 día vie 12/08/22 sáb 13/08/22 122 S/ 366.65
131 1.5.3.2 CIMIENTO CORRIDO 2 días lun 15/08/22 mié 17/08/22 S/ 52,956.58
132 1.5.3.2.1 CIMIENTO CORRIDO C:H 1:10 + 30% P.G. MAX. 8" 2 días lun 15/08/22 mié 17/08/22 138 S/ 52,956.58
133 1.5.3.3 FALSO PISO 9 días vie 30/09/22 mié 12/10/22 S/ 34,050.74
134 1.5.3.3.1 FALSO PISO MEZCLA C:H 1:8 e=0.10m 9 días vie 30/09/22 mié 12/10/22 124 S/ 34,050.74
135 1.5.4 OBRAS DE CONCRETO ARMADO 106 días sáb 13/08/22 mié 14/12/22 S/ 1,487,249.16
136 1.5.4.1 ZAPATAS 38 días sáb 13/08/22 lun 26/09/22 S/ 198,838.33
137 1.5.4.1.1 ZAPATAS - CONCRETO F'C= 210 KG/CM2 7 días sáb 17/09/22 lun 26/09/22 150;130
S/ 96,840.89
138 1.5.4.1.2 ZAPATAS - ACERO FY=4200 KG/CM2 1 día sáb 13/08/22 lun 15/08/22 130 S/ 101,997.44
139 1.5.4.2 VIGAS DE CIMENTACION 8 días mié 17/08/22 jue 25/08/22 S/ 70,112.26
140 1.5.4.2.1 VIGA DE CIMENTACIÒN - CONCRETO F'C= 210 KG/CM2 3 días sáb 20/08/22 mié 24/08/22 141FC-4
S/ 18,842.41
días
141 1.5.4.2.2 VIGA DE CIMENTACION - ENCOFRADO Y DESENCOFRADO 5 días vie 19/08/22 jue 25/08/22 142 S/ 22,282.75
142 1.5.4.2.3 VIGA DE CIMENTACION - ACERO FY=4200 KG/CM2 3 días mié 17/08/22 vie 19/08/22 132 S/ 28,987.10
143 1.5.4.3 SOBRE CIMIENTO REFORZADO 11 días jue 25/08/22 jue 08/09/22 S/ 37,850.21
144 1.5.4.3.1 SOBRE CIMIENTO REFORZADO - CONCRETO F'C= 175 KG/CM2
2 días lun 05/09/22 mié 07/09/22 145FC-3
S/ 12,527.41
días
145 1.5.4.3.2 SOBRE CIMIENTO REFORZADO - ENCOFRADO Y 4 días sáb 03/09/22 jue 08/09/22 146 S/ 18,900.06
DESENCOFRADO
146 1.5.4.3.3 SOBRE CIMIENTO REFORZADO - ACERO FY=4200 KG/CM27 días jue 25/08/22 sáb 03/09/22 141 S/ 6,422.74
147 1.5.4.4 COLUMNAS 88 días lun 15/08/22 mié 23/11/22 S/ 298,502.57
148 1.5.4.4.1 COLUMNAS - CONCRETO F'C= 210 KG/CM2 65 días vie 09/09/22 mar 22/11/22 149FC-66
S/ 60,323.83
días
149 1.5.4.4.2 COLUMNAS - ENCOFRADO Y DESENCOFRADO 67 días jue 08/09/22 mié 23/11/22 145 S/ 68,558.45
150 1.5.4.4.3 COLUMNAS - ACERO FY=4200 KG/CM2 30 días lun 15/08/22 sáb 17/09/22 138 S/ 169,620.29
151 1.5.4.5 COLUMNETA 79 días jue 25/08/22 jue 24/11/22 S/ 73,113.69
152 1.5.4.5.1 COLUMNETA - CONCRETO F'C= 175 KG/CM2 65 días sáb 10/09/22 jue 24/11/22 153FC-64
S/ 13,326.81
días
153 1.5.4.5.2 COLUMNETA - ENCOFRADO Y DESENCOFRADO 67 días jue 08/09/22 mié 23/11/22 145 S/ 45,653.74
154 1.5.4.5.3 COLUMNETA- ACERO FY=4200 KG/CM2 30 días jue 25/08/22 mié 28/09/22 146CC
S/ 14,133.14
155 1.5.4.6 PLACAS 89 días sáb 13/08/22 mié 23/11/22 S/ 337,845.25
156 1.5.4.6.1 PLACAS - CONCRETO F'C= 210 KG/CM2 65 días vie 09/09/22 mar 22/11/22 157FC-66
S/ 91,585.68
días
157 1.5.4.6.2 PLACAS - ENCOFRADO Y DESENCOFRADO 67 días jue 08/09/22 mié 23/11/22 145 S/ 125,337.98
158 1.5.4.6.3 PLACAS - ACERO FY=4200 KG/CM2 78 días sáb 13/08/22 jue 10/11/22 138CC
S/ 120,921.59
159 1.5.4.7 VIGAS 44 días vie 07/10/22 sáb 26/11/22 S/ 236,916.85
160 1.5.4.7.1 VIGAS - CONCRETO F'C= 210 KG/CM2 40 días mié 12/10/22 vie 25/11/22 161FC-41
S/ 63,488.37
días
161 1.5.4.7.2 VIGAS - ENCOFRADO Y DESENCOFRADO 42 días mar 11/10/22 sáb 26/11/22 162FC-28
S/ 89,523.72
días
162 1.5.4.7.3 VIGAS - ACERO FY=4200 KG/CM2 30 días vie 07/10/22 vie 11/11/22 149FC-40
S/ 83,904.76
días
163 1.5.4.8 VIGUETA 34 días mié 19/10/22 sáb 26/11/22 S/ 70,648.52
164 1.5.4.8.1 VIGUETA - CONCRETO F'C= 210 KG/CM2 30 días sáb 22/10/22 vie 25/11/22 165FC-31
S/ 3,875.57
días
165 1.5.4.8.2 VIGUETA - ENCOFRADO Y DESENCOFRADO 32 días vie 21/10/22 sáb 26/11/22 166FC-18
S/ 64,036.82
días
166 1.5.4.8.3 VIGUETA - ACERO FY=4200 KG/CM2 20 días mié 19/10/22 vie 11/11/22 153FC-30
S/ 2,736.13
días
167 1.5.4.9 LOSA ALIGERADA 55 días mar 11/10/22mié 14/12/22 S/ 142,535.41
168 1.5.4.9.1 LOSA ALIGERADA - CONCRETO F'C= 210 KG/CM2 40 días sáb 22/10/22 mié 07/12/22 169FC-44
S/ 40,579.23
días
169 1.5.4.9.2 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADO 55 días mar 11/10/22 mié 14/12/22 161CC
S/ 71,536.74
170 1.5.4.9.3 LOSA ALIGERADA - LADRILLO HUECO 15 x 30 x 30 30 días sáb 22/10/22 vie 25/11/22 171CC
S/ 27,683.31
171 1.5.4.9.4 LOSA ALIGERADA - ACERO FY=4200 KG/CM2 30 días sáb 22/10/22 vie 25/11/22 169FC-44
S/ 2,736.13
días
172 1.5.4.10 ESCALERA 67 días mié 17/08/22 mié 02/11/22 S/ 7,972.66
173 1.5.4.10.1 ESCALERA - CONCRETO F'C= 210 KG/CM2 48 días lun 05/09/22 vie 28/10/22 174FC-51
S/ 2,953.54
días
174 1.5.4.10.2 ESCALERA - ENCOFRADO Y DESENCOFRADO 52 días sáb 03/09/22 mié 02/11/22 175FC-30
S/ 3,685.56
días
175 1.5.4.10.3 ESCALERA - ACERO FY=4200 KG/CM2 45 días mié 17/08/22 jue 06/10/22 142CC
S/ 1,333.56
176 1.5.4.11 GRADAS 23 días mié 17/08/22 lun 12/09/22 S/ 1,191.96
177 1.5.4.11.1 GRADA - CONCRETO F'C= 175KG/CM2 20 días vie 19/08/22 sáb 10/09/22 178FC-21
S/ 474.67
días
178 1.5.4.11.2 GRADA - ENCOFRADO Y DESENCOFRADO 22 días jue 18/08/22 lun 12/09/22 179FC-14
S/ 589.99
días
179 1.5.4.11.3 GRADA - ACERO FY=4200 KG/CM2 15 días mié 17/08/22 sáb 03/09/22 142CC
S/ 127.30
180 1.5.4.12 CANALETA 9 días jue 25/08/22 mar 06/09/22 S/ 11,721.45
181 1.5.4.12.1 CANALETA- CONCRETO F'C= 175KG/CM2 5 días lun 29/08/22 lun 05/09/22 182FC-6
S/ 2,187.81
días
182 1.5.4.12.2 CANALETA- ENCOFRADO Y DESENCOFRADO 7 días sáb 27/08/22 mar 06/09/22 183 S/ 7,507.27
183 1.5.4.12.3 CANALETA- ACERO FY=4200 KG/CM2 2 días jue 25/08/22 sáb 27/08/22 139 S/ 2,026.37
184 1.6 EXTERIORES 144 días mar 02/08/22jue 12/01/23 S/ 636,105.82
185 1.6.1 TRABAJOS PRELIMINARES 58 días mar 02/08/22mié 05/10/22 S/ 31,245.08
186 1.6.1.1 LIMPIEZA DE TERRENO MANUAL 43 días mar 02/08/22 lun 19/09/22 7 S/ 12,319.00
187 1.6.1.2 TRAZO Y REPLANTEO TOPOGRAFICO PRELIMINAR 2 días lun 19/09/22 mié 21/09/22 186 S/ 9,463.04
188 1.6.1.3 TRAZO Y REPLANTEO TOPOGRAFICO DURANTE LA OBRA 13 días mié 21/09/22 mié 05/10/22 187 S/ 9,463.04
189 1.6.2 MOVIMIENTO DE TIERRAS 49 días mié 05/10/22 mié 30/11/22 S/ 215,590.83
190 1.6.2.1 CORTE MANUAL DE TERRENO A NIVEL DE SUBRASANTE H= 5 días vie 07/10/22 vie 14/10/22 191 S/ 6,926.73
0.25 M.
191 1.6.2.2 CONFORMACION A NIVEL DE SUBRASANTE C/EQUIPO 2 días mié 05/10/22 vie 07/10/22 188 S/ 69,267.74
192 1.6.2.3 EXCAVACION DE JARDINERA 4 días vie 07/10/22 jue 13/10/22 191 S/ 557.94
193 1.6.2.4 EXCAVACION DE ZANJAS PARA ZAPATAS 10 días mié 05/10/22 lun 17/10/22 188 S/ 637.41
194 1.6.2.5 EXCAVACION DE ZANJAS PARA CIMIENTOS CERCO PERIMETRICO
10 días mié 05/10/22 lun 17/10/22 188 S/ 8,349.19
195 1.6.2.6 EXCAVACION DE SARDINEL SUMERGIDO 10 días mié 05/10/22 lun 17/10/22 188 S/ 894.02
196 1.6.2.7 EXCAVACION DE SARDINEL PERALTADO 15 días mié 05/10/22 sáb 22/10/22 188 S/ 2,088.13
197 1.6.2.8 EXCAVACION DE MURO DE CONCRETO EN PATIO DE DESCARGA
10 días mié 05/10/22 lun 17/10/22 188 S/ 1,939.95
198 1.6.2.9 EXCAVACION DE ESTACIONAMIENTO 1 día mié 05/10/22 jue 06/10/22 188 S/ 7,216.63
199 1.6.2.10 AFIRMADO PARA PISOS Y VEREDAS, COMPACTACION 10 días sáb 05/11/22 mié 16/11/22 203FC-5
S/ 15,977.41
C/EQUIPO, E=0.10M días
200 1.6.2.11 CONFORMACION DE CAMA DE APOYO PARA ADOQUINES 13 días mié 16/11/22 mié 30/11/22 199 S/ 8,582.83
CON ARENA GRUESA
201 1.6.2.12 CONFORMACION DE SUB BASE GRANULAR E=0.20M 2 días lun 10/10/22 mié 12/10/22 202 S/ 26,379.29
202 1.6.2.13 CONFORMACION DE BASE GRANULAR E=0.15M 2 días jue 06/10/22 lun 10/10/22 198 S/ 21,807.49
203 1.6.2.14 RELLENO COMPACTADO CON MATERIAL PROPIO 30 días jue 06/10/22 jue 10/11/22 198 S/ 11,438.37
204 1.6.2.15 ACARREO MANUAL DE MATERIAL EXCEDENTE 10 días jue 10/11/22 mar 22/11/22 203 S/ 9,139.93
205 1.6.2.16 ELIMINACION DE MATERIAL EXCEDENTE 2 días mar 22/11/22 jue 24/11/22 204 S/ 24,387.77
206 1.6.3 OBRAS DE CONCRETO SIMPLE 38 días lun 17/10/22 mar 29/11/22 S/ 94,792.65
207 1.6.3.1 SOLADO 1 día lun 17/10/22 mar 18/10/22 S/ 571.62
208 1.6.3.1.1 SOLADO DE CONCRETO e=0.10m, C:H 1:12 1 día lun 17/10/22 mar 18/10/22 193 S/ 571.62
209 1.6.3.2 CIMIENTO CORRIDO 30 días lun 17/10/22 lun 21/11/22 S/ 32,546.95
210 1.6.3.2.1 CIMIENTO CORRIDO C:H 1:10 + 30% P.M EN CERCO 30 días lun 17/10/22 lun 21/11/22 194 S/ 28,547.48
PERIMETRICO
211 1.6.3.2.2 CIMIENTO CORRIDO C:H 1:10 + 30% P.G. MAX 8" EN 2 días lun 17/10/22 mié 19/10/22 197 S/ 3,999.47
MURO DE PATIO DE DESCARGA
212 1.6.3.3 FALSO PISO 5 días mié 16/11/22 mar 22/11/22 S/ 19,826.14
213 1.6.3.3.1 FALSO PISO MEZCLA C:H 1:8 e=0.10m 5 días mié 16/11/22 mar 22/11/22 199 S/ 19,826.14
214 1.6.3.4 VEREDA 12 días mié 16/11/22 mar 29/11/22 S/ 41,847.94
215 1.6.3.4.1 CONCRETO EN VEREDA F`C=175 KG/CM2 E=4" INC. BRUÑADO
6 días sáb 19/11/22 vie 25/11/22 217 S/ 32,577.95
216 1.6.3.4.2 CONCRETO EN VEREDA F`C=175 KG/CM2 INC. BRUÑADO2 días sáb 19/11/22 mar 22/11/22 217 S/ 6,196.63
217 1.6.3.4.3 ENCOFRADO Y DESENCOFRADO EN VEREDAS 3 días mié 16/11/22 sáb 19/11/22 199 S/ 1,894.09
218 1.6.3.4.4 CURADO DE VEREDAS 3 días vie 25/11/22 mar 29/11/22 215;216
S/ 1,179.27
219 1.6.4 OBRAS DE CONCRETO ARMADO 56 días lun 17/10/22 mié 21/12/22 S/ 116,376.93
220 1.6.4.1 ZAPATAS 15 días mar 18/10/22sáb 05/11/22 S/ 3,773.06
221 1.6.4.1.1 ZAPATAS - CONCRETO F'C= 210 KG/CM2 5 días sáb 29/10/22 sáb 05/11/22 222 S/ 2,815.61
222 1.6.4.1.2 ZAPATAS - ACERO FY=4200 KG/CM2 10 días mar 18/10/22 sáb 29/10/22 208 S/ 957.45
223 1.6.4.2 SOBRE CIMIENTO REFORZADO 26 días lun 21/11/22 mié 21/12/22 S/ 11,998.96
224 1.6.4.2.1 SOBRE CIMIENTO REFORZADO - CONCRETO F'C= 175 14 días vie 02/12/22 mar 20/12/22 225FC-15
S/ 4,037.16
KG/CM2 EN PATIO DE DESCARGA días
225 1.6.4.2.2 SOBRE CIMIENTO REFORZADO - ENCOFRADO Y 16 días jue 01/12/22 mié 21/12/22 226 S/ 3,501.12
DESENCOFRADO
226 1.6.4.2.3 SOBRE CIMIENTO REFORZADO - ACERO FY=4200 KG/CM210 días lun 21/11/22 jue 01/12/22 210 S/ 4,460.68
227 1.6.4.3 COLUMNAS 14 días mar 18/10/22vie 04/11/22 S/ 7,437.52
228 1.6.4.3.1 COLUMNAS EN PERIMETRO - CONCRETO F'C= 210 KG/CM2
3 días lun 31/10/22 vie 04/11/22 229FC-3
S/ 1,701.17
días
229 1.6.4.3.2 COLUMNAS EN PERIMETRO - ENCOFRADO Y DESENCOFRADO
4 días sáb 29/10/22 vie 04/11/22 230 S/ 4,385.77
230 1.6.4.3.3 COLUMNAS EN PERIMETRO - ACERO FY=4200 KG/CM2 10 días mar 18/10/22 sáb 29/10/22 222CC
S/ 1,350.58
231 1.6.4.4 SARDINEL PERALTADO 6 días sáb 22/10/22 sáb 29/10/22 S/ 75,111.46
232 1.6.4.4.1 SARDINEL PERALTADO - CONCRETO F'C= 175 KG/CM2 2 días mié 26/10/22 vie 28/10/22 233FC-3
S/ 30,465.84
días

Proyecto: CREACION DEL MERC Tarea División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso de tarea crítica
Fecha: mié 16/11/22 Progreso de tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica

Página 2
Id Modo Nombre de tarea Duración Comienzo Fin Predecesoras
Costo
de 01 ago '22 08 ago '22 15 ago '22 22 ago '22 29 ago '22 05 sep '22 12 sep '22 19 sep '22 26 sep '22 03 oct '22 10 oct '22 17 oct '22 24 oct '22 31 oct '22 07 nov '22 14 nov '22 21 nov '22 28 nov '22 05 dic '22 12 dic '22 19 dic '22 26 dic '22 02 ene '23 09 ene '23 16 ene '23 23 ene '23 30 ene '23
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
233 1.6.4.4.2 SARDINEL PERALTADO - ENCOFRADO Y DESENCOFRADO 4 días mar 25/10/22 sáb 29/10/22 234 S/ 35,121.25
234 1.6.4.4.3 SARDINEL PERALTADO - ACERO FY=4200 KG/CM2 2 días sáb 22/10/22 mar 25/10/22 196 S/ 9,524.37
235 1.6.4.5 SARDINEL SUMERGIDO 30 días lun 17/10/22 lun 21/11/22 S/ 18,055.93
236 1.6.4.5.1 SARDINEL SUMERGIDO - CONCRETO F'C= 175 KG/CM2 15 días vie 04/11/22 lun 21/11/22 237 S/ 12,498.07
237 1.6.4.5.2 SARDINEL SUMERGIDO - ACERO FY=4200 KG/CM2 15 días lun 17/10/22 vie 04/11/22 195 S/ 5,557.86
238 1.6.5 OTROS 50 días mié 16/11/22 jue 12/01/23 S/ 178,100.33
239 1.6.5.1 ELEMENTO PREFABRICADO DE CONCRETO TIPO H 20 días mié 21/12/22 jue 12/01/23 225 S/ 77,084.80
240 1.6.5.2 IMPRIMACION ASFALTICA 1 día vie 18/11/22 sáb 19/11/22 241 S/ 13,601.11
241 1.6.5.3 CARPETA ASFALTICA EN CALIENTE DE 2" 2 días mié 16/11/22 vie 18/11/22 199 S/ 85,172.63
242 1.6.5.4 JUNTAS ASFALTICAS E=1", DILATACION 1 día mar 29/11/22 mié 30/11/22 214 S/ 2,241.79
243 2 ARQUITECTURA 154 días mar 09/08/22mar 31/01/23 S/ 2,769,317.89
244 2.1 MODULO I 111 días mar 09/08/22jue 15/12/22 S/ 1,896,876.80
245 2.1.1 MUROS Y TABIQUES DE ALBAÑILERIA 45 días mar 27/09/22jue 17/11/22 S/ 189,455.43
246 2.1.1.1 MURO DE SOGA LADRILLO K-K, MEZCLA C:A 1:5 30 días mar 27/09/22 lun 31/10/22 69 S/ 169,581.29
247 2.1.1.2 MURO DE CABEZA LADRILLO K-K, MEZCLA C:A 1:5 20 días mar 27/09/22 mié 19/10/22 69 S/ 18,480.46
248 2.1.1.3 TABIQUERIA DE MELAMINE TIPO RH, PARA BAÑOS SEGUN DISEÑO
1 día mié 16/11/22 jue 17/11/22 249 S/ 1,393.68
249 2.1.2 REVOQUES ENLUCIDOS Y MOLDURAS 14 días lun 31/10/22 mié 16/11/22 S/ 186,357.06
250 2.1.2.1 TARRAJEO EN MURO INTERIOR C:A 1:5 e=1.5cm 8 días lun 31/10/22 mié 09/11/22 246 S/ 95,159.12
251 2.1.2.2 TARRAJEO EN MURO EXTERIOR C:A 1:5 e=1.5cm 7 días lun 31/10/22 mar 08/11/22 246 S/ 17,744.87
252 2.1.2.3 TARRAJEO DE COLUMNAS Y COLUMNETAS C:A 1:5 7 días lun 31/10/22 mar 08/11/22 246 S/ 21,620.28
253 2.1.2.4 TARRAJEO DE VIGAS C:A 1:5 3 días sáb 05/11/22 mar 08/11/22 75 S/ 22,934.29
254 2.1.2.5 VESTIDURA DE DERRAMES, E=0.15 M 3 días sáb 05/11/22 mar 08/11/22 75 S/ 9,910.38
255 2.1.2.6 TARRAJEO RAYADO C:A 1:5 6 días lun 31/10/22 lun 07/11/22 246 S/ 16,829.95
256 2.1.2.7 TARRAJEO EN CIELORRASOS C/ MEZCLA C:A / 1:5 1 día mar 15/11/22 mié 16/11/22 79 S/ 2,158.17
257 2.1.3 ZOCALOS Y CONTRAZOCALOS 10 días lun 07/11/22 vie 18/11/22 S/ 83,750.93
258 2.1.3.1 ZOCALOS 10 días lun 07/11/22 vie 18/11/22 S/ 66,140.92
259 2.1.3.1.1 ZOCALO DE PORCELANATO 60 X 60, H=1.80 M 10 días lun 07/11/22 vie 18/11/22 255 S/ 43,435.02
260 2.1.3.1.2 ENCHAPE DE PIEDRA LAJA COLOR MARRON OSCURO 7 días lun 07/11/22 mar 15/11/22 255 S/ 20,256.55
261 2.1.3.1.3 ENCHAPE DE PIEDRA LAJA COLOR MARRON CLARO 3 días lun 07/11/22 jue 10/11/22 260CC
S/ 2,037.13
262 2.1.3.1.4 ACABADO CON MICROCEMENTO COLOR BLANCO 1 día lun 07/11/22 mar 08/11/22 255 S/ 412.22
263 2.1.3.2 CONTRAZOCALOS 3 días mar 08/11/22vie 11/11/22 S/ 17,610.01
264 2.1.3.2.1 CONTRAZOCALO DE PORCELANATO 60 X 60 , H=0.10 M 2 días mié 09/11/22 vie 11/11/22 250 S/ 13,490.58
265 2.1.3.2.2 CONTRAZOCALO DE PORCELANATO 60 X 60 , H=0.40 M 2 días mar 08/11/22 jue 10/11/22 251 S/ 4,119.43
266 2.1.4 PISOS Y PAVIMENTOS 19 días mar 20/09/22mié 12/10/22 S/ 276,793.06
267 2.1.4.1 CONTRAPISO DE 48 MM 1 día mar 20/09/22 mié 21/09/22 51 S/ 84,499.09
268 2.1.4.2 PISO PORCELANATO ALTO TRANSITO, 60x60cm 18 días mié 21/09/22 mié 12/10/22 267 S/ 192,293.97
269 2.1.5 COBERTURAS 10 días jue 24/11/22 lun 05/12/22 S/ 405,132.30
270 2.1.5.1 FALSO CIELO DE DRYWALL 2 días jue 24/11/22 vie 25/11/22 275 S/ 46,574.32
271 2.1.5.2 COBERTURA DE POLIPROPILENO E=1.2 MM 1 día jue 24/11/22 jue 24/11/22 275 S/ 31,677.34
272 2.1.5.3 MALLA METALICA CUADRADA 1/2" 2 días jue 24/11/22 vie 25/11/22 275 S/ 15,459.36
273 2.1.5.4 COBERTURA DE ALUZINC TR4 (CALAMINON) 5 días mar 29/11/22 lun 05/12/22 291 S/ 311,421.28
274 2.1.6 CARPINTERIA DE MADERA 7 días mié 16/11/22 jue 24/11/22 S/ 15,320.20
275 2.1.6.1 SOPORTE DE MADERA P/COBERTURA DE POLIPROPILENO 7 días mié 16/11/22 jue 24/11/22 249 S/ 10,206.72
276 2.1.6.2 PUERTA CONTRAPLACADA DE TRIPLAY C/MARCO DE 1 día mié 16/11/22 jue 17/11/22 249 S/ 3,393.80
MADERA INC.ACABADOS
277 2.1.6.3 PUERTAS DE MELAMINE DE 18MM" 1 día jue 17/11/22 vie 18/11/22 248 S/ 1,719.68
278 2.1.7 CARPINTERIA METALICA 99 días mar 09/08/22mar 29/11/22 S/ 632,988.63
279 2.1.7.1 SUM. E INT. DE PORTON 5.00X4.00M METALICO C/PERFILES 4 días mié 16/11/22 lun 21/11/22 249 S/ 7,200.00
DE A°G° INCL. CERRAJERIA Y PINTURA
280 2.1.7.2 SUM. E INT. DE PORTON 5.00X3.50M METALICO C/PERFILES 4 días mié 16/11/22 lun 21/11/22 249 S/ 14,000.00
DE A°G° INCL. CERRAJERIA Y PINTURA
281 2.1.7.3 SUM. E INT. DE PORTON 4.00X3.50M METALICO C/PERFILES 4 días mié 16/11/22 lun 21/11/22 249 S/ 5,800.00
DE A°G° INCL. CERRAJERIA Y PINTURA
282 2.1.7.4 SUM. E INST. DE PORTON METALICO 3.60X3.20M TIPO 3 días mié 16/11/22 sáb 19/11/22 249 S/ 19,000.00
CADENA INC. CERRAJERIA Y PINTURA
283 2.1.7.5 SUM. E INST. DE PORTON METALICO 2.70X3.20M TIPO 3 días mié 16/11/22 sáb 19/11/22 249 S/ 212,400.00
CADENA INC. CERRAJERIA Y PINTURA
284 2.1.7.6 SUM. E INST. DE PORTON METALICO 2.60X3.20M TIPO 3 días mié 16/11/22 sáb 19/11/22 249 S/ 14,000.00
CADENA INC. CERRAJERIA Y PINTURA
285 2.1.7.7 SUM. E INST. DE PORTON METALICO 2.55X3.20M TIPO 2 días mié 16/11/22 vie 18/11/22 249 S/ 24,500.00
CADENA INC. CERRAJERIA Y PINTURA
286 2.1.7.8 SUM. E INST. DE PORTON METALICO 2.43X3.20M TIPO 2 días mié 16/11/22 vie 18/11/22 249 S/ 3,200.00
CADENA INC. CERRAJERIA Y PINTURA
287 2.1.7.9 SUMINISTRO DE TIJERAL PRIMARIO. INC. ANTICORROSIVO Y 2 días mié 16/11/22 vie 18/11/22 249 S/ 99,740.74
PINTURA
288 2.1.7.10 MONTAJE DE TIJERAL METALICO PRINCIPAL 7 días vie 18/11/22 vie 25/11/22 287 S/ 34,136.96
289 2.1.7.11 CORREA TUBO REC. LAC NEGRO 3"x2", E=3.0mm 2 días mié 16/11/22 vie 18/11/22 287CC
S/ 115,521.47
290 2.1.7.12 MONTAJE DE CORREA METALICA 5 días vie 18/11/22 jue 24/11/22 289 S/ 1,165.50
291 2.1.7.13 ARRIOSTRE PARA TIJERAL CON FIERRO LISO Ø5/8" CRUZ 3 días vie 25/11/22 mar 29/11/22 288 S/ 30,393.82
SAN ANDRES
292 2.1.7.14 SUMINITRO E INSTALACION DE PROTECTOR METALICO 3 días mié 16/11/22 sáb 19/11/22 249 S/ 7,849.28
TIPO 01 INC. ANTICORROSIVO Y PINTURA
293 2.1.7.15 SUMINITRO E INSTALACION DE PROTECTOR METALICO 3 días mié 16/11/22 sáb 19/11/22 249 S/ 5,911.50
TIPO 02 INCL. ANTICORROSIVO Y PINTURA
294 2.1.7.16 SUMINITRO E INSTALACION DE PROTECTOR METALICO 3 días mié 16/11/22 sáb 19/11/22 249 S/ 1,801.96
TIPO 03 INCL. ANTICORROSIVO Y PINTURA
295 2.1.7.17 SUMINITRO E INSTALACION DE PROTECTOR METALICO 3 días mié 16/11/22 sáb 19/11/22 249 S/ 1,720.98
TIPO 04 INCL. ANTICORROSIVO Y PINTURA
296 2.1.7.18 SUMINITRO E INSTALACION DE PROTECTOR METALICO 3 días mié 16/11/22 sáb 19/11/22 249 S/ 1,720.98
TIPO 05 INCL. ANTICORROSIVO Y PINTURA
297 2.1.7.19 MALLA DE PROTECCION CERCO PERIMETRICO 3 días mar 09/08/22 vie 12/08/22 101 S/ 6,702.75
298 2.1.7.20 REJILLA METALICA DE ACERO GALVANIZADO P/ CUNETA 1 día mar 20/09/22 mié 21/09/22 267CC
S/ 26,222.69
299 2.1.8 CERRAJERIA 2 días mié 16/11/22 vie 18/11/22 S/ 1,425.00
300 2.1.8.1 BISAGRA CAPUCHINA ALUMINIZADA DE 3" X4" 1 día mié 16/11/22 jue 17/11/22 276CC
S/ 369.12
301 2.1.8.2 BISAGRA CANGREJO DE 35MM 1 día jue 17/11/22 vie 18/11/22 277CC
S/ 159.84
302 2.1.8.3 CERRADURA POMO 1 día mié 16/11/22 jue 17/11/22 300CC
S/ 295.96
303 2.1.8.4 CERROJO TIPO PERSA INL. JALADOR 1 día jue 17/11/22 vie 18/11/22 301CC
S/ 600.08
304 2.1.9 VIDRIOS, CRISTALES Y SIMILARES 1 día mié 16/11/22 jue 17/11/22 S/ 3,332.11
305 2.1.9.1 VENTANA DE SISTEMA DIRECTO CRISTAL TEMPLADO 1 día mié 16/11/22 jue 17/11/22 249 S/ 3,332.11
INCOLORO DE 6mm
306 2.1.10 PINTURAS 5 días lun 05/12/22 mar 13/12/22 S/ 78,563.12
307 2.1.10.1 PINTURA LATEX 2 MANOS EN MUROS 5 días lun 05/12/22 mar 13/12/22 273 S/ 63,950.11
308 2.1.10.2 PINTURA LATEX 2 MANOS EN COLUMNAS 3 días lun 05/12/22 sáb 10/12/22 273 S/ 8,349.20
309 2.1.10.3 PINTURA LATEX 2 MANOS EN VIGAS 1 día lun 05/12/22 mar 06/12/22 273 S/ 6,263.81
310 2.1.11 MISCELANEOS 2 días mar 13/12/22jue 15/12/22 S/ 1,250.00
311 2.1.11.1 LETRAS DECORATIVAS 1 día mar 13/12/22 mié 14/12/22 307 S/ 500.00
312 2.1.11.2 PLACA RECORDATORIA 1 día mar 13/12/22 mié 14/12/22 307 S/ 250.00
313 2.1.11.3 LIMPIEZA FINAL DE OBRA 1 día mié 14/12/22 jue 15/12/22 312 S/ 500.00
314 2.1.12 SEÑALIZACION Y EVACUACION 1 día mar 13/12/22mié 14/12/22 S/ 5,036.06
315 2.1.12.1 SEÑAL INDICATIVA DE AFORO 1 día mar 13/12/22 mié 14/12/22 307 S/ 190.04
316 2.1.12.2 SEÑAL DE UBICACIÓN DE BOTIQUIN DE PRIMEROS AUXILIOS1 día mar 13/12/22 mié 14/12/22 307 S/ 47.51
317 2.1.12.3 SEÑAL INDICATIVA DE SALIDA 1 día mar 13/12/22 mié 14/12/22 307 S/ 2,565.54
318 2.1.12.4 SEÑAL INDICATIVA DE EXTINTOR 1 día mar 13/12/22 mié 14/12/22 307 S/ 1,757.87
319 2.1.12.5 SEÑAL INDICATIVA DE PROHIBIDO FUMAR 1 día mar 13/12/22 mié 14/12/22 307 S/ 237.55
320 2.1.12.6 SEÑAL INDICATIVA DE PELIGRO DE ALTO VOLTAJE 1 día mar 13/12/22 mié 14/12/22 307 S/ 47.51
321 2.1.12.7 SEÑAL INDICATIVA DE UBICACIÓN DE POZO A TIERRA 1 día mar 13/12/22 mié 14/12/22 307 S/ 47.51
322 2.1.12.8 SEÑAL INDICATIVA DE SS.HH 1 día mar 13/12/22 mié 14/12/22 307 S/ 142.53
323 2.1.13 EQUIPOS Y OTROS 2 días mar 13/12/22jue 15/12/22 S/ 17,472.90
324 2.1.13.1 SUMINSTRO E INSTALACION DE EXTINTOR PQS-(POLVO 1 día mar 13/12/22 mié 14/12/22 307 S/ 5,932.21
QUIMICO SECO)
325 2.1.13.2 SUMINISTRO DE BALANZA DE MESA CAP.:40KG 1 día mar 13/12/22 mié 14/12/22 307 S/ 6,504.48
326 2.1.13.3 PINTURA DE TRAFICO AMARILLO 2 días mar 13/12/22 jue 15/12/22 307 S/ 5,036.21
327 2.2 CISTERNA 22 días mar 09/08/22sáb 03/09/22 S/ 20,061.48
328 2.2.1 REVOQUES ENLUCIDOS Y MOLDURAS 4 días sáb 27/08/22 vie 02/09/22 S/ 3,568.26
329 2.2.1.1 TARRAJEO EN MURO EXTERIOR C:A 1:5 e=1.5cm 1 día jue 01/09/22 vie 02/09/22 331 S/ 800.22
330 2.2.1.2 TARRAJEO C/IMPERMEABILIZANTE C:A 1:3 e=20mm 1 día sáb 27/08/22 lun 29/08/22 98 S/ 2,249.64
331 2.2.1.3 TARRAJEO C/IMPERMEABILIZANTE C:A 1:3 e=25mm 2 días lun 29/08/22 jue 01/09/22 330 S/ 518.40
332 2.2.2 CARPINTERIA METALICA 21 días mar 09/08/22vie 02/09/22 S/ 16,220.47
333 2.2.2.1 SUM. E INST. DE PUERTA METALICA 1.10X2.20M TIPO REJA 2 días vie 12/08/22 lun 15/08/22 297 S/ 1,344.76
INC. CERRAJERIA Y PINTURA
334 2.2.2.2 SUMI. E INST. DE TAPA METALICA 0.60x0.60M C/MARCO 1 día jue 01/09/22 vie 02/09/22 329CC
S/ 713.22
INCL. CERRAJERIA Y PINTURA
335 2.2.2.3 SUMI. E INST. DE TAPA METALICA 0.30X0.30M C/MARCO 1 día jue 01/09/22 vie 02/09/22 329CC
S/ 304.11
INCL. CERRAJERIA Y PINTURA
336 2.2.2.4 SUMI. E INST. DE TAPA METALICA 0.60x0.30M C/MARCO 1 día jue 01/09/22 vie 02/09/22 329CC
S/ 290.72
INCL. CERRAJERIA Y PINTURA
337 2.2.2.5 SUMINISTRO E INSTALACION DE ESCALERA DE GATO 1 día mié 17/08/22 jue 18/08/22 110 S/ 3,991.10
L=4.35M DE F°G°

Proyecto: CREACION DEL MERC Tarea División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso de tarea crítica
Fecha: mié 16/11/22 Progreso de tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica

Página 3
Id Modo Nombre de tarea Duración Comienzo Fin Predecesoras
Costo
de 01 ago '22 08 ago '22 15 ago '22 22 ago '22 29 ago '22 05 sep '22 12 sep '22 19 sep '22 26 sep '22 03 oct '22 10 oct '22 17 oct '22 24 oct '22 31 oct '22 07 nov '22 14 nov '22 21 nov '22 28 nov '22 05 dic '22 12 dic '22 19 dic '22 26 dic '22 02 ene '23 09 ene '23 16 ene '23 23 ene '23 30 ene '23
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
338 2.2.2.6 TUBO METALICO RECTANGULAR GALVANIZADA 50X100X5 1 día mar 09/08/22 mié 10/08/22 297CC
S/ 1,822.02
mm H=2.24
339 2.2.2.7 TUBO METALICO CUADRADA GALVANIZADA 20 x 20 x 2 mm 3 días mar 09/08/22 vie 12/08/22 338CC
S/ 5,234.64
340 2.2.2.8 VARILLA ROSCADA INOX. D 10 mm L 280 mm 1 día mar 09/08/22 mié 10/08/22 339CC
S/ 1,119.80
341 2.2.2.9 PLATINA GALVANIZADA AL PIE DE MONTANTE 2 días mié 10/08/22 vie 12/08/22 340 S/ 1,400.10
200X200X10MM INCL ANCLAJE
342 2.2.3 PINTURAS 1 día vie 02/09/22 sáb 03/09/22 S/ 272.75
343 2.2.3.1 PINTURA LATEX 2 MANOS EN MUROS 1 día vie 02/09/22 sáb 03/09/22 329 S/ 272.75
344 2.3 MODULO II 128 días jue 08/09/22 mar 31/01/23 S/ 649,272.52
345 2.3.1 MUROS Y TABIQUES DE ALBAÑILERIA 122 días jue 08/09/22 mar 24/01/23 S/ 63,482.91
346 2.3.1.1 MURO DE SOGA LADRILLO K-K, MEZCLA C:A 1:5 70 días jue 08/09/22 vie 25/11/22 145 S/ 61,537.09
347 2.3.1.2 TABIQUERIA DE MELAMINE TIPO RH, PARA BAÑOS SEGUN DISEÑO
1 día lun 23/01/23 mar 24/01/23 385 S/ 1,945.82
348 2.3.2 REVOQUES ENLUCIDOS Y MOLDURAS 30 días mié 14/12/22 lun 16/01/23 S/ 208,079.14
349 2.3.2.1 TARRAJEO EN MURO INTERIOR C:A 1:5 e=1.5cm 25 días mié 14/12/22 mar 10/01/23 169 S/ 19,694.02
350 2.3.2.2 TARRAJEO EN MURO EXTERIOR C:A 1:5 e=1.5cm 15 días mié 14/12/22 vie 30/12/22 169 S/ 21,900.18
351 2.3.2.3 TARRAJEO DE COLUMNAS Y COLUMNETAS C:A 1:5 25 días mié 14/12/22 mar 10/01/23 169 S/ 70,590.20
352 2.3.2.4 TARRAJEO DE VIGAS C:A 1:5 25 días mié 14/12/22 mar 10/01/23 169 S/ 37,460.03
353 2.3.2.5 VESTIDURA DE DERRAMES, E=0.15 M 25 días mié 14/12/22 mar 10/01/23 169 S/ 1,174.61
354 2.3.2.6 TARRAJEO RAYADO C:A 1:5 15 días mié 14/12/22 vie 30/12/22 169 S/ 4,569.41
355 2.3.2.7 TARRAJEO EN CIELORRASOS C/ MEZCLA C:A / 1:5 5 días mar 10/01/23 lun 16/01/23 349 S/ 51,604.35
356 2.3.2.8 TARRAJEO EN ESCALERA 3 días jue 05/01/23 lun 09/01/23 349FC-4 días
S/ 1,086.34
357 2.3.3 ZOCALOS Y CONTRAZOCALOS 16 días vie 30/12/22 mar 17/01/23 S/ 24,604.98
358 2.3.3.1 ZOCALOS 5 días vie 30/12/22 mié 04/01/23 S/ 15,754.10
359 2.3.3.1.1 ZOCALO DE PORCELANATO 60 X 60 5 días vie 30/12/22 mié 04/01/23 354 S/ 15,754.10
360 2.3.3.2 CONTRAZOCALOS 16 días vie 30/12/22 mar 17/01/23 S/ 8,850.88
361 2.3.3.2.1 CONTRAZOCALO DE PORCELANATO 60 X 60 , H=0.10 M 16 días vie 30/12/22 mar 17/01/23 354 S/ 8,850.88
362 2.3.4 PISOS Y PAVIMENTOS 8 días mar 10/01/23jue 19/01/23 S/ 114,955.85
363 2.3.4.1 CONTRAPISO DE 48 MM 3 días mar 10/01/23 vie 13/01/23 349 S/ 21,857.61
364 2.3.4.2 PISO PORCELANATO ALTO TRANSITO, 60x60cm 5 días vie 13/01/23 jue 19/01/23 363 S/ 93,098.24
365 2.3.5 CARPINTERIA DE MADERA 2 días lun 23/01/23 mié 25/01/23 S/ 25,796.60
366 2.3.5.1 PUERTA 2 HOJAS CONTRAPLACADA CON MARCO Y 1 día lun 23/01/23 mar 24/01/23 385 S/ 2,200.00
ESTRUCTURA DE MADERA TORNILLO (2.45X3.75)
367 2.3.5.2 PUERTA 2 HOJAS CONTRAPLACADA C/ ESTRUCTURA DE 1 día lun 23/01/23 mar 24/01/23 385 S/ 2,600.00
MADERA TORNILLO G° 180 (2.3X3.75)
368 2.3.5.3 PUERTA 1 HOJAS CONTRAPLACADA CON MARCO Y 1 día lun 23/01/23 mar 24/01/23 385 S/ 5,750.00
ESTRUCTURA DE MADERA TORNILLO (1X3.75)
369 2.3.5.4 PUERTA 1 HOJAS CONTRAPLACADA CON MARCO Y 1 día lun 23/01/23 mar 24/01/23 385 S/ 1,150.00
ESTRUCTURA DE MADERA TORNILLO (0.9X4.15)
370 2.3.5.5 PUERTA 1 HOJAS CONTRAPLACADA CON MARCO Y 1 día lun 23/01/23 mar 24/01/23 385 S/ 3,400.00
ESTRUCTURA DE MADERA TORNILLO (0.8X4.15)
371 2.3.5.6 PUERTA DE MELAMINA RH 18MM CON CANTO GRUESO (0.6X1.70)
1 día mar 24/01/23 mié 25/01/23 376 S/ 944.87
372 2.3.5.7 PUERTA 2 HOJAS CONTRAPLACADA CON MARCO Y 1 día lun 23/01/23 mar 24/01/23 385 S/ 4,400.00
ESTRUCTURA DE MADERA TORNILLO (2.00X2.80)
373 2.3.5.8 PUERTA 1 HOJAS CONTRAPLACADA CON MARCO Y 1 día lun 23/01/23 mar 24/01/23 385 S/ 900.00
ESTRUCTURA DE MADERA TORNILLO (0.90X2.80)
374 2.3.5.9 PUERTA 1 HOJAS CONTRAPLACADA CON MARCO Y 1 día lun 23/01/23 mar 24/01/23 385 S/ 900.00
ESTRUCTURA DE MADERA TORNILLO (1X2.80)
375 2.3.5.10 PUERTA 1 HOJAS CONTRAPLACADA CON MARCO Y 1 día lun 23/01/23 mar 24/01/23 385 S/ 800.00
ESTRUCTURA DE MADERA TORNILLO (0.80X2.80)
376 2.3.5.11 MURO DE MELAMINA DE 18MM TIPO RH 1 día lun 23/01/23 mar 24/01/23 385 S/ 2,751.73
377 2.3.6 CERRAJERIA 2 días lun 23/01/23 mié 25/01/23 S/ 3,137.15
378 2.3.6.1 BISAGRA CAPUCHINA ALUMINIZADA DE 3" X4" 1 día lun 23/01/23 mar 24/01/23 366CC;367CC;368CC;369CC;370CC
S/ 1,753.32
379 2.3.6.2 BISAGRA CANGREJO DE 35MM 1 día mar 24/01/23 mié 25/01/23 371CC
S/ 119.88
380 2.3.6.3 CERRADURA POMO 1 día lun 23/01/23 mar 24/01/23 366CC;367CC;368CC;369CC;370CC
S/ 813.89
381 2.3.6.4 CERROJO TIPO PERSA INL. JALADOR 1 día mar 24/01/23 mié 25/01/23 371CC
S/ 450.06
382 2.3.7 VIDRIOS, CRISTALES Y SIMILARES 5 días mié 25/01/23 mar 31/01/23 S/ 13,777.88
383 2.3.7.1 VENTANA SISTEMA DIRECTO CRISTAL TEMPLADO INCOLORO 5 días mié 25/01/23 mar 31/01/23 377 S/ 13,777.88
DE 6mm S/ DISEÑO
384 2.3.8 PINTURAS 7 días lun 16/01/23 lun 23/01/23 S/ 69,910.27
385 2.3.8.1 PINTURA LATEX 2 MANOS EN MUROS 7 días lun 16/01/23 lun 23/01/23 348 S/ 18,712.43
386 2.3.8.2 PINTURA LATEX 2 MANOS EN COLUMNAS 7 días lun 16/01/23 lun 23/01/23 348 S/ 27,260.12
387 2.3.8.3 PINTURA LATEX 2 MANOS EN VIGAS 7 días lun 16/01/23 lun 23/01/23 348 S/ 10,231.08
388 2.3.8.4 PINTURA LATEX 2 MANOS EN CIELO RAZO 7 días lun 16/01/23 lun 23/01/23 348 S/ 13,706.64
389 2.3.9 PANELES AISLANTES 2 días lun 23/01/23 mié 25/01/23 S/ 89,095.77
390 2.3.9.1 PANEL AISLANTE TIPO SANWICH C/LAMINA ALUZINC 2 días lun 23/01/23 mié 25/01/23 385 S/ 65,798.45
INTERIOR DE POLIURATANO ALTA DENSIDAD E=100MM
391 2.3.9.2 PANEL AISLANTE EN CIELO RASO 2 días lun 23/01/23 mié 25/01/23 388 S/ 23,297.32
392 2.3.10 EQUIPAMIENTO Y OTROS 7 días lun 23/01/23 mar 31/01/23 S/ 36,431.97
393 2.3.10.1 SEÑALIZACION Y EVACUACION 1 día lun 23/01/23 mar 24/01/23 S/ 3,610.76
394 2.3.10.1.1 SEÑAL INDICATIVA DE AFORO 1 día lun 23/01/23 mar 24/01/23 385 S/ 285.06
395 2.3.10.1.2 SEÑAL DE UBICACIÓN DE BOTIQUIN DE PRIMEROS AUXILIOS
1 día lun 23/01/23 mar 24/01/23 385 S/ 142.53
396 2.3.10.1.3 SEÑAL INDICATIVA DE SALIDA 1 día lun 23/01/23 mar 24/01/23 385 S/ 1,662.85
397 2.3.10.1.4 SEÑAL INDICATIVA DE EXTINTOR 1 día lun 23/01/23 mar 24/01/23 385 S/ 665.14
398 2.3.10.1.5 SEÑAL INDICATIVA DE PROHIBIDO FUMAR 1 día lun 23/01/23 mar 24/01/23 385 S/ 380.08
399 2.3.10.1.6 SEÑAL INDICATIVA DE PELIGRO DE ALTO VOLTAJE 1 día lun 23/01/23 mar 24/01/23 385 S/ 285.06
400 2.3.10.1.7 SEÑAL INDICATIVA DE SS.HH 1 día lun 23/01/23 mar 24/01/23 385 S/ 190.04
401 2.3.10.2 EQUIPAMIENTO 5 días mié 25/01/23 mar 31/01/23 S/ 32,821.21
402 2.3.10.2.1 SUMINSTRO E INSTALACION DE EXTINTOR PQS-(POLVO 2 días vie 27/01/23 lun 30/01/23 383CC+2
S/ 2,130.80
QUIMICO SECO) días
403 2.3.10.2.2 PINTURA DE TRAFICO AMARILLO 3 días mié 25/01/23 sáb 28/01/23 383CC
S/ 484.50
404 2.3.10.2.3 CAMILLA RECLINABLE DE METAL 1.80X0.60m H=0.70m 1 día lun 30/01/23 mar 31/01/23 402 S/ 640.00
405 2.3.10.2.4 BIOMBO DE METAL 3 CUERPOS 1 día lun 30/01/23 mar 31/01/23 402 S/ 249.15
406 2.3.10.2.5 CONTENEDOR DE BASURA CAP. 85 LITROS DE 1 día lun 30/01/23 mar 31/01/23 402 S/ 3,148.60
POLIETILENO CON RUEDAS PLASTICAS
407 2.3.10.2.6 SILLA CON TAPIZ: CUERINA/ ESTRUCTURA: METAL Y 1 día lun 30/01/23 mar 31/01/23 402 S/ 1,417.76
PROPILENO/ RESISTENCIA: 150KG
408 2.3.10.2.7 ESCRITORIO DE OFICINA EN MELAMINA E 18MM (0.70X1.40)
1 día lun 30/01/23 mar 31/01/23 402 S/ 1,099.44
409 2.3.10.2.8 SILLA CON RESPALDAR Y ASIENTO TAPIZADO EN TELA 1 día lun 30/01/23 mar 31/01/23 402 S/ 3,126.06
CON ESTRUCTURA DE METAL DE 4 PATAS CON TAPONES
ANTIDESLIZANTES
410 2.3.10.2.9 ANAQUEL METALICO DE (0.90X0.45), H=1.80m 1 día lun 30/01/23 mar 31/01/23 402 S/ 1,253.70
411 2.3.10.2.10 BALANZA DE PLATAFORMA ELECTRONICA DE 1TN 1 día lun 30/01/23 mar 31/01/23 402 S/ 438.98
412 2.3.10.2.11 COCHE DE CARGA DE 300KG 1 día lun 30/01/23 mar 31/01/23 402 S/ 677.20
413 2.3.10.2.12 CASILLERO CON 15 COMPARTIMIENTO, 1 día lun 30/01/23 mar 31/01/23 402 S/ 2,644.00
PROFUNDIDAD DE 0.40M Y H=1.80
414 2.3.10.2.13 INCUBADORA DE LABORATORIO CAP:53LT Y DIM: 55X48X68
1 día lun 30/01/23 mar 31/01/23 402 S/ 2,490.00
415 2.3.10.2.14 BALANZA DE MESA CAP:40KG 1 día lun 30/01/23 mar 31/01/23 402 S/ 271.02
416 2.3.10.2.15 PUERTA DE REFRIGERACION CON PROTECCION DE 1 día lun 30/01/23 mar 31/01/23 402 S/ 4,250.00
ALUMINIO BATIENTE 1X2.1M
417 2.3.10.2.16 PUERTA DE REFRIGERACION CON PROTECCION DE 1 día lun 30/01/23 mar 31/01/23 402 S/ 8,500.00
ALUMINIO BATIENTE 1.2X2.1M
418 2.4 EXTERIORES 67 días sáb 29/10/22 sáb 14/01/23 S/ 203,107.09
419 2.4.1 REVOQUES ENLUCIDOS Y MOLDURAS 52 días sáb 29/10/22 jue 29/12/22 S/ 21,151.62
420 2.4.1.1 TARRAJEO EN EXTERIORES CERCO PERIMETRICO C:A 1:5 7 días mié 21/12/22 jue 29/12/22 225 S/ 13,953.59
e=1.5cm
421 2.4.1.2 TARRAJEO EN EXTERIORES EN COLUMNAS 2 días vie 04/11/22 sáb 05/11/22 227 S/ 605.14
422 2.4.1.3 TARRAJEO EN EXTERIORES EN GRADAS 1 día sáb 29/10/22 lun 31/10/22 231 S/ 218.49
423 2.4.1.4 TARRAJEO EN EXTERIORES EN SARDINEL 3 días sáb 29/10/22 jue 03/11/22 231 S/ 2,075.91
424 2.4.1.5 TARRAJEO EN EXTERIORES EN JARDINERA CIRCULAR 3 días sáb 29/10/22 jue 03/11/22 231 S/ 4,298.49
425 2.4.2 PINTURAS 64 días jue 03/11/22 sáb 14/01/23 S/ 7,935.79
426 2.4.2.1 PINTURA LATEX 2 MANOS EN CIMIENTO DE CERCO PERIMETRICO
15 días jue 29/12/22 sáb 14/01/23 420 S/ 5,961.13
427 2.4.2.2 PINTURA EN EXTERIORES EN COLUMNAS 1 día sáb 05/11/22 lun 07/11/22 421 S/ 233.69
428 2.4.2.3 PINTURA EN EXTERIORES EN SARDINEL 2 días jue 03/11/22 sáb 05/11/22 423 S/ 566.97
429 2.4.2.4 PINTURA EN EXTERIORES EN JARDINERA CIRCULAR 3 días jue 03/11/22 sáb 05/11/22 424 S/ 1,174.00
430 2.4.3 PISOS Y PAVIMENTOS 33 días mar 22/11/22vie 30/12/22 S/ 96,602.95
431 2.4.3.1 CONTRAPISO DE 48 MM 1 día mar 22/11/22 mié 23/11/22 213 S/ 6,732.35
432 2.4.3.2 PISO PORCELANATO ALTO TRANSITO, 60x60cm 15 días mié 23/11/22 lun 12/12/22 431 S/ 15,320.76
433 2.4.3.3 PISO DE ADIQUIN COLOR ROJO DE 20X10X6 cm 25 días mié 30/11/22 vie 30/12/22 200 S/ 74,549.84
434 2.4.4 CARPINTERIA METALICA 2 días lun 07/11/22 mar 08/11/22 S/ 59,500.00
435 2.4.4.1 SUM. E INT. DE PORTON 6.00X4.00M METALICO C/PERFILES 2 días lun 07/11/22 mar 08/11/22 421 S/ 42,500.00
DE A°G° INCL. CERRAJERIA Y PINTURA
436 2.4.4.2 SUM. E INT. DE PORTON 8.50X4.00M METALICO C/PERFILES 2 días lun 07/11/22 mar 08/11/22 421 S/ 8,500.00
DE A°G° INCL. CERRAJERIA Y PINTURA
437 2.4.4.3 SUM. E INT. DE PORTON 10.00X4.00M METALICO C/PERFILES 2 días lun 07/11/22 mar 08/11/22 421 S/ 8,500.00
DE A°G° INCL. CERRAJERIA Y PINTURA
438 2.4.5 EQUIPAMIENTO 2 días vie 30/12/22 lun 02/01/23 S/ 11,136.87
439 2.4.5.1 BANCAS DE FIERRO Y MADERA SEGÚN DISEÑO 2 días vie 30/12/22 lun 02/01/23 430 S/ 11,136.87
440 2.4.6 AREA VERDE Y PLANTA HORNAMENTALES 11 días lun 07/11/22 vie 18/11/22 S/ 6,779.86
441 2.4.6.1 PREPARACION DE TERRENO PARA SEMBRADO 4 días lun 07/11/22 jue 10/11/22 429 S/ 493.66
442 2.4.6.2 SEMBRADO DE GRASS NATURAL 6 días jue 10/11/22 jue 17/11/22 441 S/ 4,096.80
443 2.4.6.3 SEMBRADO DE PLANTAS ORNAMENTALES 4 días jue 10/11/22 mar 15/11/22 441 S/ 1,389.40
444 2.4.6.4 CONSERVACION Y RIEGO DE JARDINES HASTA ENTREGA DE OBRA
1 día jue 17/11/22 vie 18/11/22 442;443
S/ 800.00
Proyecto: CREACION DEL MERC Tarea División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso de tarea crítica
Fecha: mié 16/11/22 Progreso de tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica

Página 4
Id Modo Nombre de tarea Duración Comienzo Fin Predecesoras
Costo
de 01 ago '22 08 ago '22 15 ago '22 22 ago '22 29 ago '22 05 sep '22 12 sep '22 19 sep '22 26 sep '22 03 oct '22 10 oct '22 17 oct '22 24 oct '22 31 oct '22 07 nov '22 14 nov '22 21 nov '22 28 nov '22 05 dic '22 12 dic '22 19 dic '22 26 dic '22 02 ene '23 09 ene '23 16 ene '23 23 ene '23 30 ene '23
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
445 3 INSTALACIONES SANITARIAS 151 días sáb 06/08/22 mié 25/01/23 S/ 154,570.18
446 3.1 MODULO I 87 días mar 16/08/22mié 23/11/22 S/ 87,353.06
447 3.1.1 APARATOS SANITARIOS Y ACCESORIOS 11 días vie 30/09/22 vie 14/10/22 S/ 19,191.53
448 3.1.1.1 SUMINISTRO E INSTALACION DE APARATOS SANITARIOS 11 días vie 30/09/22 vie 14/10/22 S/ 19,191.53
449 3.1.1.1.1 INODORO CON FLUXOMETRO BLANCO 2 días mié 12/10/22 vie 14/10/22 268 S/ 10,804.59
450 3.1.1.1.2 URINARIO CON FLUXOMETRO BLANCO 1 día mié 12/10/22 jue 13/10/22 268 S/ 3,222.96
451 3.1.1.1.3 LAVATORIO OVALIN BLANCO COMERCIAL 1 día mié 12/10/22 jue 13/10/22 268 S/ 1,833.02
452 3.1.1.1.4 LAVADERO DE ACERO INOXIDABLE 1 POZA 1 día vie 30/09/22 sáb 01/10/22 84 S/ 3,330.96
453 3.1.2 SUMINISTRO E INSTALACION DE ACCESORIOS SANITARIOS 81 días vie 19/08/22 lun 21/11/22 S/ 7,309.03
454 3.1.2.1 PAPELERA METALICA 3 días jue 17/11/22 lun 21/11/22 248 S/ 709.65
455 3.1.2.2 JABONERA TIPO BOLA 1 día sáb 19/11/22 sáb 19/11/22 259 S/ 367.20
456 3.1.2.3 ESPEJO BISELADO 0.90 x 1.85m 1 día mié 12/10/22 jue 13/10/22 268 S/ 346.52
457 3.1.2.4 ESPEJO BISELADO 0.90 x 0.60m 1 día mié 12/10/22 jue 13/10/22 268 S/ 56.19
458 3.1.2.5 LLAVE DE RIEGO CON GRIFO DE 1/2" 1 día sáb 20/08/22 lun 22/08/22 466 S/ 236.32
459 3.1.2.6 LLAVE TEMPORIZADA PICO LARGO DE 1/2 " PESADO 1 día jue 13/10/22 vie 14/10/22 451 S/ 843.90
460 3.1.2.7 GRIFO CON PALANCA DE 1/2" PESADO 1 día jue 13/10/22 vie 14/10/22 451 S/ 116.48
461 3.1.2.8 GRIFO CUELLO DE GANSO 1/2" 1 día sáb 01/10/22 lun 03/10/22 452 S/ 1,092.48
462 3.1.2.9 MEDIDOR DE AGUA 1" (PROVEDOR) INC. ACCESORIOS 1 día vie 19/08/22 sáb 20/08/22 467 S/ 272.33
463 3.1.2.10 MEDIDOR DE AGUA 1/2" (PROVEDOR) INCL. ACCESORIOS 3 días sáb 20/08/22 mié 24/08/22 466 S/ 3,267.96
464 3.1.3 SISTEMA DE AGUA FRIA 9 días mar 16/08/22jue 25/08/22 S/ 17,483.16
465 3.1.3.1 SALIDAS DE AGUA FRIA 3 días jue 18/08/22 sáb 20/08/22 S/ 3,321.45
466 3.1.3.1.1 SALIDA DE AGUA FRIA - Ø 1/2" PVC C-10 3 días jue 18/08/22 sáb 20/08/22 472 S/ 2,303.64
467 3.1.3.1.2 SALIDA DE AGUA FRIA - Ø 1" PVC C-10 2 días jue 18/08/22 vie 19/08/22 474 S/ 1,017.81
468 3.1.3.2 REDES DE DISTRIBUCION Y ALIMENTACION 2 días mar 16/08/22jue 18/08/22 S/ 6,278.96
469 3.1.3.2.1 SUMINISTRO E INSTALACION DE TUB Ø 2" PVC - SAP 2 días mar 16/08/22 jue 18/08/22 37 S/ 990.33
470 3.1.3.2.2 SUMINISTRO E INSTALACION DE TUB Ø 1 1/2" PVC - SAP 2 días mar 16/08/22 jue 18/08/22 469CC
S/ 818.79
471 3.1.3.2.3 SUMINISTRO E INSTALACION DE TUB Ø 1 1/4" PVC - SAP 2 días mar 16/08/22 jue 18/08/22 469CC
S/ 338.28
472 3.1.3.2.4 SUMINISTRO E INSTALACION DE TUB Ø 1" PVC - SAP 2 días mar 16/08/22 jue 18/08/22 471CC
S/ 791.29
473 3.1.3.2.5 SUMINISTRO E INSTALACION DE TUB Ø 3/4" PVC - SAP 2 días mar 16/08/22 jue 18/08/22 470CC
S/ 1,512.90
474 3.1.3.2.6 SUMINISTRO E INSTALACION DE TUB Ø 1/2" PVC - SAP 2 días mar 16/08/22 jue 18/08/22 473CC
S/ 1,827.37
475 3.1.3.3 ACCESORIOS DE REDES DE AGUA 2 días mar 16/08/22jue 18/08/22 S/ 3,142.74
476 3.1.3.3.1 CODO DE 90º PVC - SAP Ø 1/2" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 464.40
477 3.1.3.3.2 CODO DE 90º PVC - SAP Ø 3/4" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 82.75
478 3.1.3.3.3 CODO DE 90º PVC - SAP Ø 1" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 596.02
479 3.1.3.3.4 CODO DE 90º PVC - SAP Ø 1 1/4" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 23.06
480 3.1.3.3.5 CODO DE 90º PVC - SAP Ø 2" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 71.84
481 3.1.3.3.6 TEE DE PVC - SAP Ø 3/4" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 283.92
482 3.1.3.3.7 TEE DE PVC - SAP Ø 1" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 432.64
483 3.1.3.3.8 TEE DE PVC - SAP Ø 1 1/4" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 65.54
484 3.1.3.3.9 TEE DE PVC - SAP Ø 1 1/2" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 131.08
485 3.1.3.3.10 TEE DE PVC - SAP Ø 2" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 76.44
486 3.1.3.3.11 REDUCCION DE PVC - SAP Ø 2" A 1 1/2" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 25.15
487 3.1.3.3.12 REDUCCION DE PVC - SAP Ø 2" A 1 1/4" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 53.90
488 3.1.3.3.13 REDUCCION DE PVC - SAP Ø 1 1/4" A 1" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 78.78
489 3.1.3.3.14 REDUCCION DE PVC - SAP Ø 1 1/4" A 3/4" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 25.65
490 3.1.3.3.15 REDUCCION DE PVC - SAP Ø 1 1/2" A 1/2" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 26.84
491 3.1.3.3.16 REDUCCION DE PVC - SAP Ø 1 1/2" A 3/4" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 107.56
492 3.1.3.3.17 REDUCCION DE PVC - SAP Ø 3/4" A 1/2" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 446.88
493 3.1.3.3.18 REDUCCION DE PVC - SAP Ø 1" A 1/2" 2 días mar 16/08/22 jue 18/08/22 468CC
S/ 150.29
494 3.1.3.4 VALVULAS Y LLAVES 1 día jue 18/08/22 vie 19/08/22 S/ 2,704.01
495 3.1.3.4.1 VALVULA ESFERICA DE BRONCE PESADA 1" 1 día jue 18/08/22 vie 19/08/22 472 S/ 921.15
496 3.1.3.4.2 VALVULA ESFERICA DE BRONCE PESADA 1/2" 1 día jue 18/08/22 vie 19/08/22 474 S/ 924.32
497 3.1.3.4.3 VALVULA ESFERICA DE BRONCE PESADA 3/4" 1 día jue 18/08/22 vie 19/08/22 473 S/ 858.54
498 3.1.3.5 OTROS 1 día mié 24/08/22 jue 25/08/22 S/ 666.54
499 3.1.3.5.1 PRUEBA HIDRAULICA PARA AGUA FRIA 1 día mié 24/08/22 jue 25/08/22 462;463
S/ 666.54
500 3.1.3.6 PIEZAS VARIAS 2 días jue 18/08/22 vie 19/08/22 S/ 1,369.46
501 3.1.3.6.1 CAJA DE CONCRETO PARA VALVULA 0.30x0.35 1 día jue 18/08/22 vie 19/08/22 494CC
S/ 455.04
502 3.1.3.6.2 TAPA METALICA 2 días jue 18/08/22 vie 19/08/22 501CC
S/ 914.42
503 3.1.4 SISTEMA DE DESAGUE Y VENTILACION 6 días mar 16/08/22lun 22/08/22 S/ 27,637.34
504 3.1.4.1 SALIDA DE DESAGUE Y VENTILACION 2 días jue 18/08/22 vie 19/08/22 S/ 2,464.71
505 3.1.4.1.1 SALIDA DE DESAGUE EN PVC SAP D=4" 2 días jue 18/08/22 vie 19/08/22 511 S/ 721.71
506 3.1.4.1.2 SALIDA DE DESAGUE EN PVC SAP D=2" 2 días jue 18/08/22 vie 19/08/22 509 S/ 683.40
507 3.1.4.1.3 SALIDA DE DESAGUE EN PVC SAP D=3" 1 día jue 18/08/22 vie 19/08/22 510 S/ 1,059.60
508 3.1.4.2 REDES DE DISTRIBUCION 2 días mar 16/08/22jue 18/08/22 S/ 18,162.06
509 3.1.4.2.1 RED DE DISTRIBUCION DE TUB. PVC-SAP D=2" 2 días mar 16/08/22 jue 18/08/22 512CC
S/ 1,257.20
510 3.1.4.2.2 RED DE DISTRIBUCION DE TUB. PVC-SAP D=3" 2 días mar 16/08/22 jue 18/08/22 512CC
S/ 3,183.52
511 3.1.4.2.3 RED DE DISTRIBUCION DE TUB. PVC-SAP D=4" 2 días mar 16/08/22 jue 18/08/22 512CC
S/ 1,686.28
512 3.1.4.2.4 RED DE DISTRIBUCION DE TUB. PVC-SAP D=6" 2 días mar 16/08/22 jue 18/08/22 37 S/ 11,581.44
513 3.1.4.2.5 MONTANTE Y/O VENTILACION DE TUB. PVC-SAP D=2" 1 día mar 16/08/22 mié 17/08/22 512CC
S/ 453.62
514 3.1.4.3 ADITAMIENTOS VARIOS 3 días mar 16/08/22vie 19/08/22 S/ 3,763.76
515 3.1.4.3.1 CODO SANITARIA PVC 45° - SAP DE 2'' 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 19.45
516 3.1.4.3.2 CODO SANITARIA PVC 90° - SAP DE 2'' 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 57.93
517 3.1.4.3.3 CODO SANITARIA PVC 45° - SAP DE 3'' 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 178.22
518 3.1.4.3.4 CODO SANITARIA PVC 45° - SAP DE 4'' 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 220.22
519 3.1.4.3.5 CODO SANITARIA PVC 45° - SAP DE 6'' 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 95.00
520 3.1.4.3.6 CODO SANITARIA PVC 90° - SAP DE 6'' 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 284.88
521 3.1.4.3.7 YEE SANITARIA PVC - SAP DE Ø 2" 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 188.09
522 3.1.4.3.8 YEE SANITARIA PVC - SAP DE Ø 3" - Ø 2" 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 423.84
523 3.1.4.3.9 YEE SANITARIA PVC - SAP DE Ø 3" 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 423.02
524 3.1.4.3.10 YEE DOBLE PVC - SAP DE Ø 2" 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 53.58
525 3.1.4.3.11 YEE SANITARIA PVC - SAP DE Ø 4" 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 383.50
526 3.1.4.3.12 YEE SANITARIA PVC - SAP DE Ø 4" - Ø 2" 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 33.26
527 3.1.4.3.13 YEE SANITARIA PVC - SAP DE Ø 6" - Ø 4" 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 524.44
528 3.1.4.3.14 SUMIDEROS DE BRONCE DE 2" PROVISION Y COLOCACION 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 632.00
529 3.1.4.3.15 REGISTRO ROSCADO DE BRONCE DE 4" PROVISION Y 2 días mar 16/08/22 jue 18/08/22 508CC
S/ 184.38
COLOCACION
530 3.1.4.3.16 SOMBRERO DE VENTILACION 2" PVC SAP 2 días mié 17/08/22 vie 19/08/22 513 S/ 61.95
531 3.1.4.4 CAJA DE INSPECCION 3 días jue 18/08/22 sáb 20/08/22 S/ 1,840.33
532 3.1.4.4.1 CAJAS DE INSPECCION DE CONCRETO 12''×24'' H.PROM=0,60
3 días
m jue 18/08/22 sáb 20/08/22 512 S/ 1,100.95
533 3.1.4.4.2 CAJAS DE INSPECCION DE CONCRETO 18''×24'' H.PROM=0,60
3 días
m jue 18/08/22 sáb 20/08/22 512 S/ 492.92
534 3.1.4.4.3 CAJAS DE INSPECCION DE CONCRETO 24''×24'' H.PROM=0,60
3 días
m jue 18/08/22 sáb 20/08/22 512 S/ 246.46
535 3.1.4.5 OTROS 6 días mar 16/08/22lun 22/08/22 S/ 1,406.48
536 3.1.4.5.1 PRUEBA HIDRAULICA DE ESCORRENTIA DE TUB. DESAGUE1 día sáb 20/08/22 lun 22/08/22 531 S/ 879.60
537 3.1.4.5.2 EMPALME Y/O CONEXIÓN A RED PROYECTADA INC. 1 día mar 16/08/22 mié 17/08/22 508CC
S/ 526.88
ACCESORIOS.
538 3.1.5 SISTEMA DE DRENAJE PLUVIAL 87 días mar 16/08/22mié 23/11/22 S/ 15,732.00
539 3.1.5.1 RED COLECTORA 7 días mar 16/08/22mar 23/08/22 S/ 7,007.23
540 3.1.5.1.1 EXCAVACION MANUAL DE ZANJAS 2 días mar 16/08/22 jue 18/08/22 37 S/ 1,208.59
541 3.1.5.1.2 RELLENO Y COMPACTADO CON MATERIAL PROPIO 1 día vie 19/08/22 vie 19/08/22 544 S/ 1,769.83
542 3.1.5.1.3 ACARREO MANUAL DE MATERIAL EXCEDENTE 2 días sáb 20/08/22 lun 22/08/22 541 S/ 60.44
543 3.1.5.1.4 ELIMINACION DE MATERIAL EXCEDENTE 1 día lun 22/08/22 mar 23/08/22 542 S/ 171.21
544 3.1.5.1.5 RED DE DRENAJE PLUVIAL C/TUBERIA DE PVC-CP- Ø 6" 1 día jue 18/08/22 vie 19/08/22 512 S/ 3,797.16
545 3.1.5.2 OBRAS DE CONCRETO 2 días mar 27/09/22mié 28/09/22 S/ 397.46
546 3.1.5.2.1 FALSA COLUMNA - CONCRETO FC=175 KG/CM2 1 día mar 27/09/22 mar 27/09/22 547CC
S/ 266.86
547 3.1.5.2.2 FALSA COLUMNAS - ENCOFRADO Y DESENCOFRADO NORMAL 2 días mar 27/09/22 mié 28/09/22 69;552
S/ 130.60
548 3.1.5.3 REVOQUES ENLUCIDOS Y MOLDURAS 1 día mié 28/09/22 jue 29/09/22 S/ 77.32
549 3.1.5.3.1 FALSA COLUMNA - TARRAJEO 1 día mié 28/09/22 jue 29/09/22 547 S/ 77.32
550 3.1.5.4 SUMINISTRO DE TUBERIAS 84 días jue 18/08/22 mar 22/11/22 S/ 4,345.73
551 3.1.5.4.1 CANALETA GALVANIZADA D=6'' 2 días sáb 19/11/22 mar 22/11/22 288CC+1 día
S/ 3,880.51
552 3.1.5.4.2 MONTANTES Y/O BAJADAS PLUVIALES CON TUB. PVC -CP 1 día jue 18/08/22 vie 19/08/22 544CC
S/ 465.22
DE Ø 4"
553 3.1.5.5 ACCESORIOS 2 días jue 18/08/22 vie 19/08/22 S/ 3,380.60
554 3.1.5.5.1 CODO SANITARIA PVC 45° - SAP DE 4'' 1 día jue 18/08/22 vie 19/08/22 552CC
S/ 201.76
555 3.1.5.5.2 CODO SANITARIA PVC 90° - SAP DE 4'' 1 día jue 18/08/22 vie 19/08/22 552CC
S/ 104.00
556 3.1.5.5.3 SUJETADORES PARA TUBERIA PLUVIALES DE Ø 4" 1 día vie 19/08/22 vie 19/08/22 552 S/ 2,272.40
557 3.1.5.5.4 ABRAZADERA DE 4" 1 día vie 19/08/22 vie 19/08/22 552 S/ 802.44
558 3.1.5.6 OTROS 1 día mar 22/11/22mié 23/11/22 S/ 523.66
559 3.1.5.6.1 PRUEBA HIDRAULICA PARA SISTEMA DE DRENAJE 1 día mar 22/11/22 mié 23/11/22 551 S/ 523.66
560 3.2 CISTERNA 113 días sáb 06/08/22 jue 15/12/22 S/ 14,595.35
561 3.2.1 TUBERIA SALIDA (IMPULSION Y SUCCION) 30 días sáb 06/08/22 vie 09/09/22 S/ 8,106.62
562 3.2.1.1 REDES DE DISTRIBUCIÓN 27 días sáb 06/08/22 mié 07/09/22 S/ 577.24
563 3.2.1.1.1 TUBERIA FG 2 1/2 " 18 días mié 17/08/22 mié 07/09/22 110 S/ 39.62
564 3.2.1.1.2 TUBERIA PVC 2" 1 día sáb 06/08/22 lun 08/08/22 94 S/ 480.81
565 3.2.1.1.3 TUBERIA FG 2" 1 día mar 06/09/22 mar 06/09/22 343 S/ 43.57
566 3.2.1.1.4 TUBERIA FG 1" 1 día mar 06/09/22 mar 06/09/22 565CC
S/ 13.24
567 3.2.1.2 ACCESORIOS DE REDES 3 días mar 06/09/22jue 08/09/22 S/ 1,937.81
568 3.2.1.2.1 UNION DRESSER TIPO MAXI F°G° 2 " 2 días mar 06/09/22 jue 08/09/22 565 S/ 213.54
569 3.2.1.2.2 TEE° F°G° PN 16 2 1/2 " 1 día mié 07/09/22 jue 08/09/22 563 S/ 186.56
570 3.2.1.2.3 CODO 90° F°G° PN 16 2 1/2 " 1 día mié 07/09/22 jue 08/09/22 563 S/ 154.77
571 3.2.1.2.4 CABEZAL DE SUCCION F°G° PN 16 2 1/2 " 1 día mié 07/09/22 jue 08/09/22 563 S/ 101.02
572 3.2.1.2.5 CABEZAL DE SUCCION F°G° PN 16 2 " 1 día mar 06/09/22 mié 07/09/22 565 S/ 154.27
Proyecto: CREACION DEL MERC Tarea División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso de tarea crítica
Fecha: mié 16/11/22 Progreso de tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica

Página 5
Id Modo Nombre de tarea Duración Comienzo Fin Predecesoras
Costo
de 01 ago '22 08 ago '22 15 ago '22 22 ago '22 29 ago '22 05 sep '22 12 sep '22 19 sep '22 26 sep '22 03 oct '22 10 oct '22 17 oct '22 24 oct '22 31 oct '22 07 nov '22 14 nov '22 21 nov '22 28 nov '22 05 dic '22 12 dic '22 19 dic '22 26 dic '22 02 ene '23 09 ene '23 16 ene '23 23 ene '23 30 ene '23
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
573 3.2.1.2.6 CANASTILLA DE SUCCION BRONCE PN 16 2 1/2" 1 día mar 06/09/22 mié 07/09/22 565 S/ 81.18
574 3.2.1.2.7 ACOPLES FLEXIBLES FºGº PN 10 2 1/2 " 1 día mar 06/09/22 mié 07/09/22 565 S/ 390.30
575 3.2.1.2.8 REDUCCION F°G° 2 1/2" A 2" 1 día mar 06/09/22 mié 07/09/22 565 S/ 39.38
576 3.2.1.2.9 UNION UNIVERSAL F°G° PN 16 1" 1 día mar 06/09/22 mar 06/09/22 566CC
S/ 109.41
577 3.2.1.2.10 TEE° F°G° PN 16 2 " 1 día mar 06/09/22 mar 06/09/22 565CC
S/ 184.00
578 3.2.1.2.11 CODO 90° F°G° PN 16 2 " 1 día mar 06/09/22 mar 06/09/22 565CC
S/ 89.16
579 3.2.1.2.12 CODO 90° F°G° PN 16 1 " 1 día mar 06/09/22 mar 06/09/22 566CC
S/ 39.32
580 3.2.1.2.13 NIPLE F°G° CON BRIDA ROMPE AGUA R (L=0.40 M) CON 1 día mar 06/09/22 mar 06/09/22 566CC
S/ 48.92
ROSCA AMBOS LADOS 1"
581 3.2.1.2.14 TEE PVC DE 2 " SAP 1 día mar 06/09/22 mar 06/09/22 565CC
S/ 38.22
582 3.2.1.2.15 CODO DE 90º PVC - SAP Ø 2" 1 día mar 06/09/22 mar 06/09/22 565CC
S/ 107.76
583 3.2.1.3 VALVULAS Y LLAVES 2 días mar 06/09/22jue 08/09/22 S/ 2,789.09
584 3.2.1.3.1 VALVULA DE COMPUERTA DE CIERRE ESFERICO 1 día mié 07/09/22 jue 08/09/22 563 S/ 1,207.95
C/MANIJA PN 16 2 1/2 "
585 3.2.1.3.2 VALVULA DE RETENCION BRONCE ROSCADO C/RESORTE 1 día mié 07/09/22 jue 08/09/22 584CC
S/ 430.06
PN 16 2 1/2 "
586 3.2.1.3.3 VALVULA DE AIRE TRIPLE EFECTO 2" 2 días mar 06/09/22 jue 08/09/22 565 S/ 215.80
587 3.2.1.3.4 VALVULA DE COMPUERTA DE CIERRE ESFERICO 1 día mar 06/09/22 mié 07/09/22 565 S/ 400.18
C/MANIJA PN 16 2"
588 3.2.1.3.5 VALVULA DE COMPUERTA DE CIERRE ESFERICO 1 día mar 06/09/22 mié 07/09/22 566 S/ 206.84
C/MANIJA PN 16 1"
589 3.2.1.3.6 VALVULA CHECK 2" TIPO VERTICAL 1 día mar 06/09/22 mié 07/09/22 565 S/ 328.26
590 3.2.1.4 EQUIPOS 3.19 días mar 06/09/22vie 09/09/22 S/ 2,802.48
591 3.2.1.4.1 ELECTROBOMBA CENTRIFUGA VERTICAL MULTIETAPICAS 3 días mié 07/09/22 vie 09/09/22 562 S/ 1,697.48
DE 1HP
592 3.2.1.4.2 TANQUE PULMON 20GAL CON MENBRANA 1 día mié 07/09/22 jue 08/09/22 591CC
S/ 270.56
593 3.2.1.4.3 MANOMETRO RANGO: O A 300 PSI 3 días mar 06/09/22 vie 09/09/22 566 S/ 834.44
594 3.2.2 TUBERIA DE ENTRADA 28 días sáb 06/08/22 jue 08/09/22 S/ 647.83
595 3.2.2.1 REDES DE DISTRIBUCIÓN 1 día sáb 06/08/22 lun 08/08/22 S/ 100.28
596 3.2.2.1.1 TUBERIA PVC 1 1/2" 1 día sáb 06/08/22 lun 08/08/22 94 S/ 100.28
597 3.2.2.2 ACCESORIOS DE REDES 24 días lun 08/08/22 lun 05/09/22 S/ 265.73
598 3.2.2.2.1 TEE F°G° 1 1/2" X 1 1/2" 1 día sáb 03/09/22 lun 05/09/22 343 S/ 71.26
599 3.2.2.2.2 REDUCCION PVC 1 1/2" A 1" 1 día lun 08/08/22 mar 09/08/22 596 S/ 18.36
600 3.2.2.2.3 UNION UNIVERSAL PVC 1" 1 día lun 08/08/22 mar 09/08/22 596 S/ 41.06
601 3.2.2.2.4 NIPLE PVC R (L=0.10 M) CON ROSCA AMBOS LADOS 1 1/2"1 día lun 08/08/22 mar 09/08/22 596 S/ 49.95
602 3.2.2.2.5 CODO 45° PVC 1 1/2" SAP 1 día lun 08/08/22 mar 09/08/22 596 S/ 72.62
603 3.2.2.2.6 ADAPTADOR UNION PRESION ROSCA PVC 1 1/2" 1 día lun 08/08/22 mar 09/08/22 596 S/ 12.48
604 3.2.2.3 VALVULAS Y LLAVES 27 días lun 08/08/22 jue 08/09/22 S/ 281.82
605 3.2.2.3.1 VALVULA DE COMPUERTA DE CIERRE ESFERICO 27 días lun 08/08/22 jue 08/09/22 596 S/ 121.22
C/MANIJA 1 /2" EN BRONCE
606 3.2.2.3.2 VALVULA FLOTADORA DE BRONCE 1 1/2" 1 día mar 06/09/22 mié 07/09/22 590CC
S/ 160.60
607 3.2.3 TUBERIA DE LIMPIA 1 día vie 26/08/22 sáb 27/08/22 S/ 1,466.25
608 3.2.3.1 REDES DE DISTRIBUCIÓN 1 día vie 26/08/22 sáb 27/08/22 S/ 64.68
609 3.2.3.1.1 TUBERIA F°G° 2" 1 día vie 26/08/22 sáb 27/08/22 96 S/ 64.68
610 3.2.3.2 ACCESORIOS DE REDES 1 día vie 26/08/22 sáb 27/08/22 S/ 269.58
611 3.2.3.2.1 CODO 90° F°G° 2" 1 día vie 26/08/22 sáb 27/08/22 609CC
S/ 92.58
612 3.2.3.2.2 NIPLE F°G° R (L=0.10 M) CON ROSCA AMBOS LADOS 2" 1 día vie 26/08/22 sáb 27/08/22 609CC
S/ 29.48
613 3.2.3.2.3 TAPON F°G°ROSCADO HEMBRA 2" 1 día vie 26/08/22 sáb 27/08/22 609CC
S/ 22.76
614 3.2.3.2.4 NIPLE F°G° CON BRIDA ROMPE AGUA R (L=0.30 M) CON 1 día vie 26/08/22 sáb 27/08/22 609CC
S/ 62.23
ROSCA A UN LADO 2"
615 3.2.3.2.5 NIPLE F°G° CON BRIDA ROMPE AGUA R (L=0.40 M) CON 1 día vie 26/08/22 sáb 27/08/22 609CC
S/ 62.53
ROSCA A UN LADO 2"
616 3.2.3.3 VALVULAS Y LLAVES 1 día vie 26/08/22 sáb 27/08/22 S/ 437.64
617 3.2.3.3.1 VALVULA DE COMPUERTA DE CIERRE ESFERICO C/MANIJA12"
día vie 26/08/22 sáb 27/08/22 609CC
S/ 437.64
618 3.2.3.4 EQUIPOS 1 día vie 26/08/22 sáb 27/08/22 S/ 694.35
619 3.2.3.4.1 BOMBA SUMIDERO DESAGUES 1 día vie 26/08/22 sáb 27/08/22 609CC
S/ 694.35
620 3.2.4 TUBERIA REBOSE 19 días sáb 06/08/22 sáb 27/08/22 S/ 468.39
621 3.2.4.1 CODO 90° F°G° CON MALLA SOLDADA 2" 1 día vie 26/08/22 sáb 27/08/22 609CC
S/ 44.63
622 3.2.4.2 NIPLE F°G° CON BRIDA ROMPE AGUA R (L=0.40 M) CON 1 día vie 26/08/22 sáb 27/08/22 609CC
S/ 155.29
ROSCA A UN LADO 2"
623 3.2.4.3 CODO 45° PVC DE 3" 1 día sáb 06/08/22 lun 08/08/22 624CC
S/ 41.66
624 3.2.4.4 TUBERIA PVC S/P PN 10 3" 1 día sáb 06/08/22 lun 08/08/22 94 S/ 226.81
625 3.2.5 TUBERIA DE VENTILACION 25 días sáb 06/08/22 lun 05/09/22 S/ 1,397.40
626 3.2.5.1 CODO 90° PVC 3" 1 día sáb 06/08/22 lun 08/08/22 624CC
S/ 239.12
627 3.2.5.2 NIPLE F°G° CON BRIDA ROMPE AGUA R (L=0.40 M) CON 1 día sáb 03/09/22 lun 05/09/22 343 S/ 157.54
ROSCA A UN LADO 3"
628 3.2.5.3 NIPLE F°G° R (L=0.50 M) CON ROSCA A UN LADO 3" 1 día sáb 03/09/22 lun 05/09/22 343 S/ 175.70
629 3.2.5.4 NIPLE F°G° R (L=0.10 M) CON ROSCA AMBOS LADOS 3" 1 día sáb 03/09/22 lun 05/09/22 343 S/ 98.36
630 3.2.5.5 CODO 90º FºGº 6" 1 día sáb 03/09/22 lun 05/09/22 343 S/ 421.60
631 3.2.5.6 NIPLE FºGº (L=0.50M.) CON ROSCA A UN LADO 6" 1 día sáb 03/09/22 lun 05/09/22 343 S/ 115.91
632 3.2.5.7 NIPLE Fº Gº (L=0.15M.) CON ROSCA AMBOS LADOS 6" 1 día sáb 03/09/22 lun 05/09/22 343 S/ 189.17
633 3.2.6 ACCESORIOS PARA BOMBA 1 día mar 06/09/22mié 07/09/22 S/ 135.24
634 3.2.6.1 REDUCCION EXCENTRICA 2 1/2" A 2" 1 día mar 06/09/22 mié 07/09/22 573CC
S/ 70.62
635 3.2.6.2 REDUCCION CONCENTRICA 2 1/2" A 2" 1 día mar 06/09/22 mié 07/09/22 573CC
S/ 64.62
636 3.2.7 TANQUE ELEVADO 1 día mié 14/12/22 jue 15/12/22 S/ 2,373.62
637 3.2.7.1 TANQUE ELEVADO DE 2500 LITROS INC/ ACC. 1 día mié 14/12/22 jue 15/12/22 167 S/ 2,373.62
638 3.3 MODULO II 106 días mar 27/09/22mié 25/01/23 S/ 47,170.40
639 3.3.1 APARATOS SANITARIOS Y ACCESORIOS 1 día jue 19/01/23 vie 20/01/23 S/ 12,588.34
640 3.3.1.1 SUMINISTRO E INSTALACION DE APARATOS SANITARIOS 1 día jue 19/01/23 vie 20/01/23 S/ 12,588.34
641 3.3.1.1.1 INODORO CON FLUXOMETRO BLANCO 1 día jue 19/01/23 vie 20/01/23 364 S/ 7,203.06
642 3.3.1.1.2 URINARIO CON FLUXOMETRO BLANCO 1 día jue 19/01/23 vie 20/01/23 364 S/ 2,148.64
643 3.3.1.1.3 LAVATORIO OVALIN BLANCO COMERCIAL 1 día jue 19/01/23 vie 20/01/23 364 S/ 1,571.16
644 3.3.1.1.4 LAVADERO DE ACERO INOXIDABLE 1 POZA 1 día jue 19/01/23 vie 20/01/23 364 S/ 1,665.48
645 3.3.2 SUMINISTRO E INSTALACION DE ACCESORIOS SANITARIOS 6 días jue 19/01/23 mié 25/01/23 S/ 2,741.06
646 3.3.2.1 PAPELERA METALICA 1 día mar 24/01/23 mié 25/01/23 376 S/ 315.40
647 3.3.2.2 JABONERA TIPO BOLA 1 día jue 19/01/23 vie 20/01/23 364 S/ 146.88
648 3.3.2.3 ESPEJO BISELADO 0.90 x 1.85m 1 día jue 19/01/23 vie 20/01/23 364 S/ 346.52
649 3.3.2.4 ESPEJO BISELADO 0.90 x 0.60m 1 día jue 19/01/23 vie 20/01/23 364 S/ 112.38
650 3.3.2.5 DUCHA BARU C/BRAZO Y CANOPLA ICL. LLAVE TIPO 1 día jue 19/01/23 vie 20/01/23 364 S/ 80.30
BARVARO PESADO
651 3.3.2.6 LLAVE TEMPORIZADA PICO LARGO DE 1/2 " PESADO 1 día vie 20/01/23 sáb 21/01/23 643 S/ 843.90
652 3.3.2.7 GRIFO CUELLO DE GANSO 1/2" 1 día vie 20/01/23 sáb 21/01/23 644 S/ 546.24
653 3.3.2.8 GRIFO CON PALANCA DE 1/2" PESADO 1 día vie 20/01/23 sáb 21/01/23 643 S/ 349.44
654 3.3.3 SISTEMA DE AGUA FRIA 103 días mar 27/09/22sáb 21/01/23 S/ 9,773.63
655 3.3.3.1 SALIDA DE AGUA FRIA 70 días vie 30/09/22 mié 21/12/22 S/ 2,299.62
656 3.3.3.1.1 SALIDA DE AGUA FRIA - Ø 1/2" PVC C-10 70 días vie 30/09/22 mié 21/12/22 662CC
S/ 1,621.08
657 3.3.3.1.2 SALIDA DE AGUA FRIA - Ø 1" PVC C-10 1 día vie 30/09/22 sáb 01/10/22 661 S/ 678.54
658 3.3.3.2 REDES DE DISTRIBUCION Y ALIMENTACION 74 días mar 27/09/22mié 21/12/22 S/ 3,237.63
659 3.3.3.2.1 SUMINISTRO E INSTALACION DE TUB Ø 2" PVC - SAP 1 día vie 30/09/22 sáb 01/10/22 124 S/ 268.45
660 3.3.3.2.2 SUMINISTRO E INSTALACION DE TUB Ø 1 1/2" PVC - SAP 2 días mar 27/09/22 mié 28/09/22 124CC
S/ 873.94
661 3.3.3.2.3 SUMINISTRO E INSTALACION DE TUB Ø 1" PVC - SAP 2 días mié 28/09/22 vie 30/09/22 660 S/ 876.74
662 3.3.3.2.4 SUMINISTRO E INSTALACION DE TUB Ø 1/2" PVC - SAP 70 días vie 30/09/22 mié 21/12/22 661 S/ 1,218.50
663 3.3.3.3 ACCESORIOS DE REDES DE AGUA 74 días mar 27/09/22mié 21/12/22 S/ 1,839.83
664 3.3.3.3.1 CODO DE 90º PVC - SAP Ø 1/2" 70 días vie 30/09/22 mié 21/12/22 662CC
S/ 495.36
665 3.3.3.3.2 CODO DE 90º PVC - SAP Ø 1" 1 día mié 28/09/22 jue 29/09/22 661CC
S/ 333.07
666 3.3.3.3.3 CODO DE 90º PVC - SAP Ø 1 1/2" 70 días mar 27/09/22 vie 16/12/22 660CC
S/ 50.70
667 3.3.3.3.4 CODO DE 90º PVC - SAP Ø 2" 1 día vie 30/09/22 sáb 01/10/22 659CC
S/ 71.84
668 3.3.3.3.5 TEE DE PVC - SAP Ø 1/2" 70 días vie 30/09/22 mié 21/12/22 662CC
S/ 165.15
669 3.3.3.3.6 TEE DE PVC - SAP Ø 1" 1 día mié 28/09/22 jue 29/09/22 661CC
S/ 189.28
670 3.3.3.3.7 TEE DE PVC - SAP Ø 1 1/2" 1 día mar 27/09/22 mar 27/09/22 660CC
S/ 196.62
671 3.3.3.3.8 TEE DE PVC - SAP Ø 2" 1 día vie 30/09/22 sáb 01/10/22 659CC
S/ 38.22
672 3.3.3.3.9 REDUCCION DE PVC - SAP Ø 2" A 1 1/2" 1 día mar 27/09/22 mar 27/09/22 660CC
S/ 25.15
673 3.3.3.3.10 REDUCCION DE PVC - SAP Ø 1 1/2" A 1" 1 día mié 28/09/22 jue 29/09/22 661CC
S/ 67.68
674 3.3.3.3.11 REDUCCION DE PVC - SAP Ø 1 1/2" A 1/2" 5 días vie 30/09/22 jue 06/10/22 662CC
S/ 106.80
675 3.3.3.3.12 REDUCCION DE PVC - SAP Ø 1" A 1/2" 1 día vie 30/09/22 sáb 01/10/22 662CC
S/ 99.96
676 3.3.3.4 VALVULAS Y LLAVES 71 días vie 30/09/22 jue 22/12/22 S/ 1,235.52
677 3.3.3.4.1 VALVULA ESFERICA DE BRONCE PESADA 1" 1 día vie 30/09/22 sáb 01/10/22 661 S/ 736.92
678 3.3.3.4.2 VALVULA ESFERICA DE BRONCE PESADA 1/2" 1 día mié 21/12/22 jue 22/12/22 662 S/ 115.54
679 3.3.3.4.3 VALVULA ESFERICA DE BRONCE PESADA 2" 1 día sáb 01/10/22 lun 03/10/22 659 S/ 383.06
680 3.3.3.5 OTROS 2 días vie 20/01/23 sáb 21/01/23 S/ 598.31
681 3.3.3.5.1 PRUEBA HIDRAULICA PARA AGUA FRIA 1 día vie 20/01/23 sáb 21/01/23 640 S/ 337.68
682 3.3.3.5.2 FALSA COLUMNA DE 15X15cm EN FIBROCEMENTO INCL. 1 día sáb 21/01/23 sáb 21/01/23 681 S/ 260.63
PINTURA
683 3.3.3.6 PIEZAS VARIAS 1 día sáb 21/01/23 sáb 21/01/23 S/ 562.72
684 3.3.3.6.1 TAPA METALICA 1 día sáb 21/01/23 sáb 21/01/23 681 S/ 562.72
685 3.3.4 SISTEMA DE DESAGUE Y VENTILACION 101 días mar 27/09/22vie 20/01/23 S/ 21,083.34
686 3.3.4.1 SALIDA DE DESAGUE Y VENTILACION 70 días mar 27/09/22vie 16/12/22 S/ 2,386.20
687 3.3.4.1.1 SALIDA DE DESAGUE EN PVC SAP D=4" 1 día mié 28/09/22 jue 29/09/22 693 S/ 481.14
688 3.3.4.1.2 SALIDA DE DESAGUE EN PVC SAP D=2" 70 días mar 27/09/22 vie 16/12/22 691CC
S/ 1,640.16
689 3.3.4.1.3 SALIDA DE DESAGUE EN PVC SAP D=3" 1 día mié 28/09/22 jue 29/09/22 692 S/ 264.90
690 3.3.4.2 REDES DE DISTRIBUCION 70 días mar 27/09/22vie 16/12/22 S/ 12,284.22

Proyecto: CREACION DEL MERC Tarea División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso de tarea crítica
Fecha: mié 16/11/22 Progreso de tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica

Página 6
Id Modo Nombre de tarea Duración Comienzo Fin Predecesoras
Costo
de 01 ago '22 08 ago '22 15 ago '22 22 ago '22 29 ago '22 05 sep '22 12 sep '22 19 sep '22 26 sep '22 03 oct '22 10 oct '22 17 oct '22 24 oct '22 31 oct '22 07 nov '22 14 nov '22 21 nov '22 28 nov '22 05 dic '22 12 dic '22 19 dic '22 26 dic '22 02 ene '23 09 ene '23 16 ene '23 23 ene '23 30 ene '23
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
691 3.3.4.2.1 RED DE DISTRIBUCION DE TUB. PVC-SAP D=2" 70 días mar 27/09/22 vie 16/12/22 693CC
S/ 2,354.97
692 3.3.4.2.2 RED DE DISTRIBUCION DE TUB. PVC-SAP D=3" 2 días mar 27/09/22 mié 28/09/22 693CC
S/ 1,072.74
693 3.3.4.2.3 RED DE DISTRIBUCION DE TUB. PVC-SAP D=4" 2 días mar 27/09/22 mié 28/09/22 694CC
S/ 1,247.72
694 3.3.4.2.4 RED DE DISTRIBUCION DE TUB. PVC-SAP D=6" 2 días mar 27/09/22 mié 28/09/22 124CC
S/ 6,544.59
695 3.3.4.2.5 MONTANTE Y/O VENTILACION DE TUB. PVC-SAP D=2" 2 días mié 28/09/22 vie 30/09/22 694 S/ 1,064.20
696 3.3.4.3 ADITAMIENTOS VARIOS 101 días mar 27/09/22vie 20/01/23 S/ 2,192.43
697 3.3.4.3.1 CODO SANITARIA PVC 45° - SAP DE 2'' 70 días mar 27/09/22 vie 16/12/22 691CC
S/ 155.60
698 3.3.4.3.2 CODO SANITARIA PVC 90° - SAP DE 2'' 70 días mar 27/09/22 vie 16/12/22 691CC
S/ 347.58
699 3.3.4.3.3 CODO SANITARIA PVC 45° - SAP DE 3'' 2 días mar 27/09/22 mié 28/09/22 692CC
S/ 50.92
700 3.3.4.3.4 CODO SANITARIA PVC 45° - SAP DE 4'' 2 días mar 27/09/22 mié 28/09/22 693CC
S/ 125.84
701 3.3.4.3.5 CODO SANITARIA PVC 45° - SAP DE 6'' 2 días mar 27/09/22 mié 28/09/22 694CC
S/ 47.50
702 3.3.4.3.6 YEE SANITARIA PVC - SAP DE Ø 2" 1 día mar 27/09/22 mar 27/09/22 691CC
S/ 376.18
703 3.3.4.3.7 YEE SANITARIA PVC - SAP DE Ø 4" - Ø3" 1 día mar 27/09/22 mar 27/09/22 693CC
S/ 42.75
704 3.3.4.3.8 YEE SANITARIA PVC - SAP DE Ø 3" 1 día mar 27/09/22 mar 27/09/22 692CC
S/ 65.08
705 3.3.4.3.9 YEE SANITARIA PVC - SAP DE Ø 4" 1 día mar 27/09/22 mar 27/09/22 694CC
S/ 76.70
706 3.3.4.3.10 YEE SANITARIA PVC - SAP DE Ø 4" - Ø 2" 1 día mar 27/09/22 mar 27/09/22 694CC
S/ 299.34
707 3.3.4.3.11 SUMIDEROS DE BRONCE DE 2" PROVISION Y COLOCACION
1 día jue 19/01/23 vie 20/01/23 364 S/ 276.50
708 3.3.4.3.12 REGISTRO ROSCADO DE BRONCE DE 4" PROVISION Y 1 día jue 19/01/23 vie 20/01/23 364 S/ 245.84
COLOCACION
709 3.3.4.3.13 SOMBRERO DE VENTILACION 2" PVC SAP 1 día jue 19/01/23 vie 20/01/23 364 S/ 82.60
710 3.3.4.4 CAJA DE INSPECCION 2 días mar 27/09/22mié 28/09/22 S/ 2,280.71
711 3.3.4.4.1 CAJAS DE INSPECCION DE CONCRETO 12''×24'' H.PROM=0,60
2 días
m mar 27/09/22 mié 28/09/22 694CC
S/ 1,541.33
712 3.3.4.4.2 CAJAS DE INSPECCION DE CONCRETO 18''×24'' H.PROM=0,60
1 díam mar 27/09/22 mar 27/09/22 694CC
S/ 492.92
713 3.3.4.4.3 CAJAS DE INSPECCION DE CONCRETO 24''×24'' H.PROM=0,60
1 díam mar 27/09/22 mar 27/09/22 694CC
S/ 246.46
714 3.3.4.5 OTROS 71 días mar 27/09/22sáb 17/12/22 S/ 1,939.78
715 3.3.4.5.1 PRUEBA HIDRAULICA DE ESCORRENTIA DE TUB. DESAGUE1 día vie 16/12/22 sáb 17/12/22 687;688
S/ 724.85
716 3.3.4.5.2 EMPALME Y/O CONEXIÓN A RED PROYECTADA INC. 1 día mar 27/09/22 mar 27/09/22 694CC
S/ 526.88
ACCESORIOS.
717 3.3.4.5.3 FALSA COLUMNA DE 15X15cm EN FIBROCEMENTO INCL. 3 días mié 14/12/22 vie 16/12/22 169 S/ 688.05
PINTURA
718 3.3.5 SISTEMA DE DRENAJE PLUVIAL 2 días mar 06/12/22sáb 10/12/22 S/ 984.03
719 3.3.5.1 RED DE DISTRIBUCION 1 día mar 06/12/22mié 07/12/22 S/ 734.55
720 3.3.5.1.1 RED DE DRENAJE PLUVIAL C/TUBERIA DE PVC- Ø 4 1 día mar 06/12/22 mié 07/12/22 169FC-5 días
S/ 734.55
721 3.3.5.2 ACCESORIOS 1 día mar 06/12/22mié 07/12/22 S/ 183.79
722 3.3.5.2.1 CODO SANITARIA PVC 45° - SAP DE 4'' 1 día mar 06/12/22 mié 07/12/22 720CC
S/ 25.22
723 3.3.5.2.2 CODO SANITARIA PVC 90° - SAP DE 4'' 1 día mar 06/12/22 mié 07/12/22 720CC
S/ 52.00
724 3.3.5.2.3 YEE PVC 90° - SAP DE 4'' 1 día mar 06/12/22 mié 07/12/22 720CC
S/ 38.35
725 3.3.5.2.4 SUMIDERO DE BRONCE DE 4" 1 día mar 06/12/22 mié 07/12/22 720CC
S/ 68.22
726 3.3.5.3 OTROS 1 día mié 07/12/22 sáb 10/12/22 S/ 65.69
727 3.3.5.3.1 PRUEBA HIDRUALICA PARA SISTEMA DE DRENAJE 1 día mié 07/12/22 sáb 10/12/22 720 S/ 65.69
728 3.4 EXTERIORES 8 días mié 05/10/22 sáb 15/10/22 S/ 5,451.37
729 3.4.1 SUMINISTRO E INSTALACION DE ACCESORIOS SANITARIOS 1 día jue 13/10/22 vie 14/10/22 S/ 349.44
730 3.4.1.1 GRIFO CON PALANCA DE 1/2" PESADO 1 día jue 13/10/22 vie 14/10/22 745CC
S/ 349.44
731 3.4.2 SISTEMA DE AGUA FRIA 1 día mié 12/10/22 jue 13/10/22 S/ 255.96
732 3.4.2.1 SALIDAS DE AGUA FRIA 1 día mié 12/10/22 jue 13/10/22 S/ 255.96
733 3.4.2.1.1 SALIDA DE AGUA FRIA - Ø 1/2" PVC C-10 1 día mié 12/10/22 jue 13/10/22 743 S/ 255.96
734 3.4.3 REDES DE DISTRIBUCION Y ALIMENTACION 4 días mié 05/10/22 mar 11/10/22 S/ 3,153.60
735 3.4.3.1 SUMINISTRO E INSTALACION DE TUB Ø 2" PVC - SAP 2 días mié 05/10/22 vie 07/10/22 188 S/ 1,473.94
736 3.4.3.2 SUMINISTRO E INSTALACION DE TUB Ø 3/4" PVC - SAP 4 días mié 05/10/22 mar 11/10/22 188 S/ 1,679.66
737 3.4.4 ACCESORIOS DE REDES DE AGUA 5 días mié 05/10/22 mié 12/10/22 S/ 439.48
738 3.4.4.1 CODO DE 90º PVC - SAP Ø 3/4" 1 día mié 05/10/22 jue 06/10/22 736CC
S/ 115.85
739 3.4.4.2 CODO DE 90º PVC - SAP Ø 2" 1 día mié 05/10/22 jue 06/10/22 735CC
S/ 107.76
740 3.4.4.3 TEE DE PVC - SAP Ø 3/4" 1 día mié 05/10/22 jue 06/10/22 736CC
S/ 40.56
741 3.4.4.4 TEE DE PVC - SAP Ø 2" 1 día mié 05/10/22 jue 06/10/22 735CC
S/ 76.44
742 3.4.4.5 REDUCCION DE PVC - SAP Ø 2" A 3/4" 1 día vie 07/10/22 lun 10/10/22 735 S/ 29.63
743 3.4.4.6 REDUCCION DE PVC - SAP Ø 3/4" A 1/2" 1 día mar 11/10/22 mié 12/10/22 736 S/ 69.24
744 3.4.5 VALVULAS Y LLAVES 5 días vie 07/10/22 vie 14/10/22 S/ 729.68
745 3.4.5.1 VALVULA CONTROL ESFERICA DE BRONCE 1/2" 1 día jue 13/10/22 vie 14/10/22 733 S/ 346.62
746 3.4.5.2 VALVULA ESFERICA DE BRONCE PESADA 2" 1 día vie 07/10/22 lun 10/10/22 735 S/ 383.06
747 3.4.6 OTROS 1 día vie 14/10/22 sáb 15/10/22 S/ 295.69
748 3.4.6.1 PRUEBA HIDRAULICA PARA AGUA FRIA 1 día vie 14/10/22 sáb 15/10/22 730 S/ 295.69
749 3.4.7 PIEZAS VARIAS 1 día mié 05/10/22 jue 06/10/22 S/ 227.52
750 3.4.7.1 CAJA DE CONCRETO PARA VALVULA 0.30x0.35 1 día mié 05/10/22 jue 06/10/22 188 S/ 227.52
751 4 INSTALACIONES ELECTRICAS 159 días mié 03/08/22 mar 31/01/23 S/ 606,885.15
752 4.1 MODULO I 106 días mar 16/08/22jue 15/12/22 S/ 228,451.38
753 4.1.1 SALIDA PARA ALUMBRADO , TOMACORRIENTES , FUERZAS Y 100 días jue 18/08/22 lun 12/12/22 S/ 50,105.56
SEÑALES DEBILES
754 4.1.1.1 SALIDAS PARA ALUMBRADO 2 días jue 24/11/22 vie 25/11/22 269CC
S/ 8,662.50
755 4.1.1.2 SALIDAS PARA ALUMBRADO COLGANTE 2 días jue 24/11/22 vie 25/11/22 269CC
S/ 2,931.20
756 4.1.1.3 SALIDAS DE TOMACORRIENTES MONOFASICO DOBLE C0N 1 día jue 18/08/22 vie 19/08/22 763CC
S/ 17,155.19
PUESTA TIERRA
757 4.1.1.4 SALIDAS PARA INTERRUPTORES SIMPLES 1 día mar 27/09/22 mar 27/09/22 246CC
S/ 6,398.10
758 4.1.1.5 SALIDAS PARA INTERRUPTORES DOBLES 1 día mar 27/09/22 mar 27/09/22 246CC
S/ 816.30
759 4.1.1.6 SALIDAS PARA EQ. SONIDO 1 día mar 27/09/22 mar 27/09/22 246CC
S/ 12,962.91
760 4.1.1.7 SALIDAS PARA LUZ DE EMERGENCIA 1 día sáb 10/12/22 lun 12/12/22 764 S/ 1,179.36
761 4.1.2 CANALIZACIONES, CONDUCTOS O TUBERIAS 99 días jue 18/08/22 sáb 10/12/22 S/ 42,871.48
762 4.1.2.1 TUBERIA PVC SAP Ø 40 MM 3 días mar 27/09/22 jue 29/09/22 246CC
S/ 7,114.41
763 4.1.2.2 TUBERIA PVC SAP Ø 20 MM 2 días jue 18/08/22 vie 19/08/22 778 S/ 24,098.93
764 4.1.2.3 TUBERIA EMT Ø 20 MM 3 días lun 05/12/22 sáb 10/12/22 269 S/ 9,429.86
765 4.1.2.4 CURVAS PARA TUBERIA ELECTRICA PVC 3 días mar 27/09/22 jue 29/09/22 246CC
S/ 2,228.28
766 4.1.3 CONDUCTORES Y CABLES 2 días sáb 10/12/22 mar 13/12/22 S/ 38,660.88
767 4.1.3.1 CABLE N2XOH 10 MM2 1 día sáb 10/12/22 lun 12/12/22 761 S/ 11,292.34
768 4.1.3.2 CABLE NH-80 2.5 MM2 2 días sáb 10/12/22 mar 13/12/22 761 S/ 14,407.55
769 4.1.3.3 CABLE NH-80 4 MM2 2 días sáb 10/12/22 mar 13/12/22 761 S/ 12,960.99
770 4.1.4 SUMINISTRO E INSTALACION DE LUMINARIAS 1 día mar 13/12/22mié 14/12/22 761 S/ 13,363.26
771 4.1.4.1 SUMINISTRO E INSTALACION DE LUMINARIA LED 23W 1 día mar 13/12/22 mié 14/12/22 768 S/ 6,754.50
772 4.1.4.2 SUMINISTRO E INSTALACION DE LUMINARIA TIPO GONDOLA 1 día mar 13/12/22 mié 14/12/22 768 S/ 4,594.56
1x36 W
773 4.1.4.3 SUMINISTRO E INTALACION DE LUZ DE EMERGENCIA LED 3H 1 día mar 13/12/22 mié 14/12/22 769 S/ 2,014.20
774 4.1.5 TABLEROS Y SUBTABLEROS 47 días mié 19/10/22 mié 14/12/22 S/ 49,980.13
775 4.1.5.1 SUM. E INST. DE TABLERO DE DISTRIBUCION 18 POLOS 1 día mié 19/10/22 jue 20/10/22 247 S/ 25,588.92
776 4.1.5.2 SUM. E INST. DE MEDIDORES 2 días lun 12/12/22 mié 14/12/22 767 S/ 24,391.21
777 4.1.6 MOVIMIENTO DE TIERRAS 7 días mar 16/08/22mar 23/08/22 S/ 17,579.69
778 4.1.6.1 EXCAVACION PARA CABLE SUBTERRANEO 2 días mar 16/08/22 jue 18/08/22 37 S/ 10,953.04
779 4.1.6.2 RELLENO CON MATERIAL PROPIO 1 día sáb 20/08/22 sáb 20/08/22 780 S/ 4,441.76
780 4.1.6.3 PROTECCION Y SEÑALIZACION DE CABLE SUBTERRANEO 2 días jue 18/08/22 vie 19/08/22 763CC
S/ 714.48
781 4.1.6.4 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día sáb 20/08/22 lun 22/08/22 779 S/ 383.73
782 4.1.6.5 ELIMINACION DE MATERIAL EXCEDENTE 1 día lun 22/08/22 mar 23/08/22 781 S/ 1,086.68
783 4.1.7 DISPOSITIVO DE MANIOBRA Y PROTECCION 3 días lun 12/12/22 jue 15/12/22 S/ 15,390.38
784 4.1.7.1 INTERRUPTOR TERMOMAGNETICO 3x50A 1 día lun 12/12/22 mar 13/12/22 767 S/ 104.21
785 4.1.7.2 INTERRUPTOR TERMOMAGNETICO 2x16A 1 día mar 13/12/22 mié 14/12/22 768 S/ 5,202.94
786 4.1.7.3 INTERRUPTOR TERMOMAGNETICO 2x20A 1 día mar 13/12/22 mié 14/12/22 769 S/ 4,852.18
787 4.1.7.4 INTERRUPTOR TERMOMAGNETICO 2x32A 1 día mié 14/12/22 jue 15/12/22 776 S/ 4,471.21
788 4.1.7.5 INTERRUPTOR DIFERENCIAL 3x50A 1 día lun 12/12/22 mar 13/12/22 784CC
S/ 133.88
789 4.1.7.6 INTERRUPTOR DIFERENCIAL 3x32A 1 día mié 14/12/22 jue 15/12/22 787CC
S/ 117.76
790 4.1.7.7 INTERRUPTOR DIFERENCIAL 3x16A 1 día mar 13/12/22 mié 14/12/22 785CC
S/ 508.20
791 4.1.8 PRUEBAS ELECTRICAS 1 día jue 15/12/22 jue 15/12/22 S/ 500.00
792 4.1.8.1 PRUEBAS ELECTRICAS 1 día jue 15/12/22 jue 15/12/22 783 S/ 500.00
793 4.2 CISTERNA 120 días mié 03/08/22 lun 19/12/22 S/ 12,930.02
794 4.2.1 SALIDA PARA ALUMBRADO , TOMACORRIENTES , FUERZAS Y 1 día lun 08/08/22 mar 09/08/22 S/ 75.86
SEÑALES DEBILES
795 4.2.1.1 SALIDAS PARA ELECTROBOMBA 1HP 1 día lun 08/08/22 mar 09/08/22 797 S/ 75.86
796 4.2.2 CANALIZACIONES, CONDUCTOS O TUBERIAS 2 días vie 05/08/22 lun 08/08/22 S/ 2,691.92
797 4.2.2.1 TUBERIA PVC SAP Ø 40 MM 2 días vie 05/08/22 lun 08/08/22 802 S/ 2,596.08
798 4.2.2.2 CURVAS PARA TUBERIA ELECTRICA PVC 1 día vie 05/08/22 sáb 06/08/22 797CC
S/ 95.84
799 4.2.3 CONDUCTORES Y CABLES 4 días mar 13/12/22vie 16/12/22 S/ 4,085.72
800 4.2.3.1 CABLE N2XOH Ø 6 MM2 4 días mar 13/12/22 vie 16/12/22 788 S/ 4,085.72
801 4.2.4 MOVIMIENTO DE TIERRAS 10 días mié 03/08/22 lun 15/08/22 S/ 4,391.74
802 4.2.4.1 EXCAVACION PARA CABLE SUBTERRANEO 2 días mié 03/08/22 vie 05/08/22 91 S/ 2,736.29
803 4.2.4.2 RELLENO CON MATERIAL PROPIO 2 días mié 10/08/22 vie 12/08/22 804 S/ 1,109.60
804 4.2.4.3 PROTECCION Y SEÑALIZACION DE CABLE SUBTERRANEO 2 días lun 08/08/22 mié 10/08/22 797 S/ 178.51
805 4.2.4.4 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día vie 12/08/22 sáb 13/08/22 803 S/ 95.87
806 4.2.4.5 ELIMINACION DE MATERIAL EXCEDENTE 1 día sáb 13/08/22 lun 15/08/22 805 S/ 271.47
807 4.2.5 DISPOSITIVO DE MANIOBRA Y PROTECCION 1 día vie 16/12/22 sáb 17/12/22 S/ 205.05
808 4.2.5.1 INTERRUPTOR TERMOMAGNETICO 3x20A 1 día vie 16/12/22 sáb 17/12/22 800 S/ 87.29
809 4.2.5.2 INTERRUPTOR DIFERENCIA 3x20A 1 día vie 16/12/22 sáb 17/12/22 808CC
S/ 117.76
810 4.2.6 CAJA DE PASO - BUZONES 10 días mié 03/08/22 lun 15/08/22 S/ 979.73
811 4.2.6.1 EXCAVACION PARA BUZON DE CONCRETO (CAJA DE PASO) 1 día mié 03/08/22 jue 04/08/22 802CC
S/ 100.58

812 4.2.6.2 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día vie 12/08/22 sáb 13/08/22 805CC
S/ 14.09
813 4.2.6.3 ELIMINACION DE MATERIAL EXCEDENTE 1 día sáb 13/08/22 lun 15/08/22 812 S/ 62.42

Proyecto: CREACION DEL MERC Tarea División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso de tarea crítica
Fecha: mié 16/11/22 Progreso de tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica

Página 7
Id Modo Nombre de tarea Duración Comienzo Fin Predecesoras
Costo
de 01 ago '22 08 ago '22 15 ago '22 22 ago '22 29 ago '22 05 sep '22 12 sep '22 19 sep '22 26 sep '22 03 oct '22 10 oct '22 17 oct '22 24 oct '22 31 oct '22 07 nov '22 14 nov '22 21 nov '22 28 nov '22 05 dic '22 12 dic '22 19 dic '22 26 dic '22 02 ene '23 09 ene '23 16 ene '23 23 ene '23 30 ene '23
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J
814 4.2.6.4 MANHOLES DE PASE DE CONCRETO 1 día jue 04/08/22 vie 05/08/22 811 S/ 802.64
815 4.2.7 PRUEBAS ELECTRICAS 1 día sáb 17/12/22 lun 19/12/22 S/ 500.00
816 4.2.7.1 PRUEBAS ELECTRICAS 1 día sáb 17/12/22 lun 19/12/22 807 S/ 500.00
817 4.3 MODULO II 128 días jue 08/09/22 mar 31/01/23 S/ 258,242.32
818 4.3.1 SALIDA PARA ALUMBRADO , TOMACORRIENTES , FUERZAS Y 69 días jue 08/09/22 vie 25/11/22 S/ 12,496.28
SEÑALES DEBILES
819 4.3.1.1 SALIDAS PARA ALUMBRADO 30 días sáb 22/10/22 vie 25/11/22 826CC
S/ 6,545.00
820 4.3.1.2 SALIDAS DE TOMACORRIENTES MONOFASICO DOBLE C0N 30 días jue 08/09/22 jue 13/10/22 825CC
S/ 2,030.20
PUESTA TIERRA
821 4.3.1.3 SALIDAS PARA INTERRUPTORES SIMPLES 30 días sáb 22/10/22 vie 25/11/22 826CC
S/ 1,563.98
822 4.3.1.4 SALIDAS PARA INTERRUPTORES DOBLES 30 días sáb 22/10/22 vie 25/11/22 826CC
S/ 489.78
823 4.3.1.5 SALIDAS PARA LUZ DE EMERGENCIA 30 días sáb 22/10/22 vie 25/11/22 827CC
S/ 1,867.32
824 4.3.2 CANALIZACIONES, CONDUCTOS O TUBERIAS 69 días jue 08/09/22 vie 25/11/22 S/ 32,671.21
825 4.3.2.1 TUBERIA PVC SAP Ø 40 MM 65 días jue 08/09/22 mar 22/11/22 844 S/ 7,592.45
826 4.3.2.2 TUBERIA PVC SAP Ø 20 MM 30 días sáb 22/10/22 vie 25/11/22 170CC
S/ 8,114.51
827 4.3.2.3 TUBERIA EMT Ø 20 MM 30 días sáb 22/10/22 vie 25/11/22 170CC
S/ 7,691.20
828 4.3.2.4 TUBERIA PVC SAP Ø 50 MM 1 día jue 08/09/22 vie 09/09/22 844 S/ 394.27
829 4.3.2.5 TUBERIA PVC SAP Ø 75 MM 1 día jue 08/09/22 vie 09/09/22 844 S/ 3,344.02
830 4.3.2.6 CURVAS PARA TUBERIA ELECTRICA PVC 60 días jue 08/09/22 mié 16/11/22 844 S/ 5,534.76
831 4.3.3 CONDUCTORES Y CABLES 13 días lun 16/01/23 lun 30/01/23 S/ 27,935.07
832 4.3.3.1 CABLE N2XOH 10 MM2 6 días lun 16/01/23 sáb 21/01/23 348 S/ 7,228.13
833 4.3.3.2 CABLE N2XOH Ø 6 MM2 8 días lun 16/01/23 mar 24/01/23 348 S/ 6,964.12
834 4.3.3.3 CABLE N2XOH Ø 16 MM2 4 días lun 16/01/23 vie 20/01/23 348 S/ 5,842.69
835 4.3.3.4 CABLE NH-80 2.5 MM2 13 días lun 16/01/23 lun 30/01/23 348 S/ 6,316.01
836 4.3.3.5 CABLE NH-80 4 MM2 3 días lun 16/01/23 jue 19/01/23 348 S/ 1,584.12
837 4.3.4 SUMINISTRO E INSTALACION DE LUMINARIAS 11 días jue 19/01/23 mar 31/01/23 S/ 11,268.31
838 4.3.4.1 SUMINISTRO E INSTALACION DE LUMINARIA LED 23W 1 día lun 30/01/23 mar 31/01/23 835 S/ 2,401.60
839 4.3.4.2 SUMINISTRO E INSTALACION DE LUMINARIA TIPO 1 día lun 30/01/23 mar 31/01/23 835 S/ 5,677.56
HERMETICO 1X36W
840 4.3.4.3 SUMINISTRO E INSTALACION DE LUZ DE EMERGENCIA LED 1 día jue 19/01/23 vie 20/01/23 836 S/ 3,189.15
3H
841 4.3.5 TABLEROS Y SUBTABLEROS 2 días vie 25/11/22 lun 28/11/22 S/ 609.26
842 4.3.5.1 SUM. E INST. DE TABLERO DE DISTRIBUCION 18 POLOS 2 días vie 25/11/22 lun 28/11/22 346 S/ 609.26
843 4.3.6 MOVIMIENTO DE TIERRAS 69 días jue 08/09/22 jue 24/11/22 S/ 14,539.81
844 4.3.6.1 EXCAVACION PARA CABLE SUBTERRANEO 1 día jue 08/09/22 jue 08/09/22 123CC
S/ 9,059.03
845 4.3.6.2 RELLENO CON MATERIAL PROPIO 1 día mar 22/11/22 mié 23/11/22 825;828;829;830
S/ 3,673.68
846 4.3.6.3 PROTECCION Y SEÑALIZACION DE CABLE SUBTERRANEO 60 días vie 09/09/22 mié 16/11/22 825CC;828CC;829CC;830CC
S/ 590.94
847 4.3.6.4 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día mié 23/11/22 jue 24/11/22 845 S/ 317.38
848 4.3.6.5 ELIMINACION DE MATERIAL EXCEDENTE 1 día jue 24/11/22 jue 24/11/22 847 S/ 898.78
849 4.3.7 DISPOSITIVO DE MANIOBRA Y PROTECCION 11 días jue 19/01/23 mar 31/01/23 S/ 2,441.64
850 4.3.7.1 INTERRUPTOR TERMOMAGNETICO 3x60A 1 día sáb 21/01/23 lun 23/01/23 832 S/ 134.68
851 4.3.7.2 INTERRUPTOR TERMOMAGNETICO 2x16A 1 día lun 30/01/23 mar 31/01/23 835 S/ 350.76
852 4.3.7.3 INTERRUPTOR TERMOMAGNETICO 3x20A 1 día jue 19/01/23 vie 20/01/23 836 S/ 174.58
853 4.3.7.4 INTERRUPTOR TERMOMAGNETICO 3x32A 1 día mar 24/01/23 mié 25/01/23 833 S/ 180.54
854 4.3.7.5 INTERRUPTOR TERMOMAGNETICO 3x63A 1 día sáb 21/01/23 lun 23/01/23 832 S/ 134.68
855 4.3.7.6 INTERRUPTOR DIFERENCIAL 3x63A 1 día sáb 21/01/23 lun 23/01/23 854CC
S/ 133.88
856 4.3.7.7 INTERRUPTOR DIFERENCIAL 3x32A 1 día mar 24/01/23 mié 25/01/23 853CC
S/ 353.28
857 4.3.7.8 INTERRUPTOR DIFERENCIAL 3x16A 1 día lun 30/01/23 mar 31/01/23 851CC
S/ 609.84
858 4.3.7.9 INTERRUPTOR DIFERENCIAL 3x60A 1 día sáb 21/01/23 lun 23/01/23 850CC
S/ 133.88
859 4.3.7.10 INTERRUPTOR DIFERENCIAL 3x20A 1 día jue 19/01/23 vie 20/01/23 852CC
S/ 235.52
860 4.3.8 CAJA DE PASO - BUZONES 3 días jue 08/09/22 sáb 10/09/22 S/ 862.15
861 4.3.8.1 EXCAVACION PARA BUZON DE CONCRETO (CAJA DE PASO) 1 día jue 08/09/22 jue 08/09/22 123CC
S/ 75.33

862 4.3.8.2 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día vie 09/09/22 vie 09/09/22 861 S/ 10.56
863 4.3.8.3 ELIMINACION DE MATERIAL EXCEDENTE 1 día vie 09/09/22 sáb 10/09/22 862 S/ 46.78
864 4.3.8.4 MANHOLES DE PASE DE CONCRETO 1 día jue 08/09/22 vie 09/09/22 861 S/ 601.98
865 4.3.8.5 CAJA DE PASO 4X4X2" 1 día jue 08/09/22 vie 09/09/22 861 S/ 127.50
866 4.3.9 INSTALACIONES MECANICAS 15 días mar 10/01/23jue 26/01/23 S/ 154,918.59
867 4.3.9.1 INSTALACIONES MECANICAS EN EQUIPOS FRIGORIFICOS 3 días lun 23/01/23 jue 26/01/23 389CC
S/ 95,254.20
868 4.3.9.2 INSTALACIÓN DE CAJA DE FILTROS PARA EQUIPO DE 1 día lun 23/01/23 mar 24/01/23 389CC
S/ 12,300.00
INYECCIÓN DE AIRE
869 4.3.9.3 SUMINISTRO DE MONTACARGAS ACERO INOXIDABLE 1500 5 días mar 10/01/23 lun 16/01/23 349 S/ 47,364.39
KG, 2.20 X 2.00 X 2.40 M
870 4.3.10 PRUEBAS ELECTRICAS 1 día jue 19/01/23 vie 20/01/23 S/ 500.00
871 4.3.10.1 PRUEBAS ELECTRICAS 1 día jue 19/01/23 vie 20/01/23 849CC
S/ 500.00
872 4.4 EXTERIOR 83 días mié 12/10/22 sáb 14/01/23 S/ 107,261.43
873 4.4.1 SALIDA PARA ALUMBRADO , TOMACORRIENTES , FUERZAS Y 26 días vie 21/10/22 lun 21/11/22 S/ 2,887.50
SEÑALES DEBILES
874 4.4.1.1 SALIDA PARA REFLECTOR LED APPLETON 240W 220V - 2 días vie 21/10/22 lun 24/10/22 910 S/ 673.75
POSTES
875 4.4.1.2 SALIDA PARA REFLECTOR LED APPLETON 240W 220V - 5 días mar 15/11/22 lun 21/11/22 877 S/ 2,213.75
CERCO PERIMETRAL
876 4.4.2 CANALIZACIONES, CONDUCTOS O TUBERIAS 30 días mié 12/10/22 mar 15/11/22 S/ 17,223.54
877 4.4.2.1 TUBERIA PVC SAP Ø 40 MM 30 días mié 12/10/22 mar 15/11/22 201 S/ 17,223.54
878 4.4.3 CONDUCTORES Y CABLES 2 días mar 15/11/22jue 17/11/22 S/ 23,158.28
879 4.4.3.1 CABLE N2XOH 10 MM2 2 días mar 15/11/22 jue 17/11/22 877 S/ 11,113.74
880 4.4.3.2 CABLE N2XOH Ø 4 MM2 2 días mar 15/11/22 jue 17/11/22 877 S/ 11,285.47
881 4.4.3.3 CABLE N2XOH Ø 35 MM2 2 días mar 15/11/22 jue 17/11/22 877 S/ 759.07
882 4.4.4 SUMINISTRO E INSTALACION DE LUMINARIAS 73 días vie 21/10/22 vie 13/01/23 S/ 16,027.68
883 4.4.4.1 SUMINISTRO E INTASLACION DE REFLECTOR LED APPLETON 1 día vie 21/10/22 sáb 22/10/22 910 S/ 7,729.05
240W 220V - POSTES
884 4.4.4.2 SUMINISTRO E INTASLACION DE REFLECTOR LED APPLETON 1 día jue 12/01/23 vie 13/01/23 239 S/ 8,298.63
240W 220V - PERIMETRO
885 4.4.5 TABLEROS Y SUBTABLEROS 1 día vie 04/11/22 sáb 05/11/22 S/ 304.63
886 4.4.5.1 SUM. E INST. DE TABLERO DE DISTRIBUCION 18 POLOS 1 día vie 04/11/22 sáb 05/11/22 229 S/ 304.63
887 4.4.6 MOVIMIENTO DE TIERRAS 18 días mié 12/10/22 mié 02/11/22 S/ 29,138.68
888 4.4.6.1 EXCAVACION PARA CABLE SUBTERRANEO 2 días mié 12/10/22 vie 14/10/22 201 S/ 18,154.90
889 4.4.6.2 RELLENO CON MATERIAL PROPIO 3 días mar 25/10/22 vie 28/10/22 890 S/ 7,362.35
890 4.4.6.3 PROTECCION Y SEÑALIZACION DE CABLE SUBTERRANEO 12 días mié 12/10/22 mar 25/10/22 877CC
S/ 1,184.30
891 4.4.6.4 ACARREO MANUAL DE MATERIAL EXCEDENTE 2 días vie 28/10/22 lun 31/10/22 889 S/ 636.03
892 4.4.6.5 ELIMINACION DE MATERIAL EXCEDENTE 1 día lun 31/10/22 mié 02/11/22 891 S/ 1,801.10
893 4.4.7 DISPOSITIVO DE MANIOBRA Y PROTECCION 1 día vie 13/01/23 sáb 14/01/23 S/ 682.18
894 4.4.7.1 INTERRUPTOR AUTOMATICO TRIPOLARES COMPACT NSX 1 día vie 13/01/23 sáb 14/01/23 882 S/ 272.08
250H - 3X175/250A
895 4.4.7.2 INTERRUPTOR TERMOMAGNETICO 3x20A 1 día vie 13/01/23 sáb 14/01/23 882 S/ 174.58
896 4.4.7.3 INTERRUPTOR DIFERENCIAL 3x20A 1 día vie 13/01/23 sáb 14/01/23 882 S/ 235.52
897 4.4.8 CAJA DE PASO - BUZONES 8 días mié 12/10/22 jue 20/10/22 S/ 3,184.26
898 4.4.8.1 EXCAVACION PARA BUZON DE CONCRETO (CAJA DE PASO) 3 días mié 12/10/22 sáb 15/10/22 201 S/ 326.98

899 4.4.8.2 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día sáb 15/10/22 lun 17/10/22 898 S/ 45.82
900 4.4.8.3 ELIMINACION DE MATERIAL EXCEDENTE 1 día lun 17/10/22 lun 17/10/22 899 S/ 202.88
901 4.4.8.4 MANHOLES DE PASE DE CONCRETO 3 días lun 17/10/22 jue 20/10/22 900 S/ 2,608.58
902 4.4.9 PRUEBAS ELECTRICAS 1 día lun 21/11/22 mar 22/11/22 S/ 500.00
903 4.4.9.1 PRUEBAS ELECTRICAS 1 día lun 21/11/22 mar 22/11/22 875 S/ 500.00
904 4.4.10 POZO A TIERRA 4 días mié 12/10/22 lun 17/10/22 S/ 1,110.23
905 4.4.10.1 EXCAVACION PARA POZO TIERRA 0.6 X 0.6 1 día mié 12/10/22 jue 13/10/22 201 S/ 41.39
906 4.4.10.2 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día vie 14/10/22 sáb 15/10/22 908 S/ 5.80
907 4.4.10.3 ELIMINACION DE MATERIAL EXCEDENTE 1 día sáb 15/10/22 lun 17/10/22 906 S/ 49.28
908 4.4.10.4 POZO DE PUESTA A TIERRA 1 día jue 13/10/22 vie 14/10/22 905 S/ 713.76
909 4.4.10.5 PRUEBA DE RESISTENCIA DE POZO A TIERRA 1 día vie 14/10/22 sáb 15/10/22 908 S/ 300.00
910 4.4.11 POSTE DE C.A.C. DE H=9M 9 días mié 12/10/22 vie 21/10/22 S/ 13,044.45
911 4.4.11.1 EXCAVACION PARA POSTES DE C.A.C. 2 días mié 12/10/22 vie 14/10/22 201 S/ 160.59
912 4.4.11.2 ACARREO MANUAL DE MATERIAL EXCEDENTE 1 día mar 18/10/22 mié 19/10/22 915 S/ 22.50
913 4.4.11.3 ELIMINACION DE MATERIAL EXCEDENTE 1 día mié 19/10/22 jue 20/10/22 912 S/ 53.09
914 4.4.11.4 SOLADO DE CONCRETO E=10CM C:H 1:12 EN CIMIENTO DE 1 día vie 14/10/22 sáb 15/10/22 911 S/ 11.02
POSTES
915 4.4.11.5 CONCRETO F'C=175 KG/CM2 EN CIMIENTO DE POSTE 3 días sáb 15/10/22 mar 18/10/22 916CC
S/ 1,754.69
916 4.4.11.6 SUMINISTRO E INSTALACION DE POSTES DE C.A.C. H=9M 3 días sáb 15/10/22 mar 18/10/22 914 S/ 10,542.56

917 4.4.11.7 PRUEBA DE RESISTENCIA DE POSTE DE C.A.C. 1 día jue 20/10/22 vie 21/10/22 913 S/ 500.00

Proyecto: CREACION DEL MERC Tarea División Resumen Agrupar por síntesis Tarea crítica resumida Progreso resumido Hito externo Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Fecha límite Progreso de tarea crítica
Fecha: mié 16/11/22 Progreso de tarea Hito Resumen del proyecto Tarea resumida Hito resumido Tareas externas Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Tarea crítica