Predecesoras 01 oct '23 08 oct '23 15 oct '23 22 oct '23 29 oct '23 05 nov '23 12 nov '23 19 nov '23 26 nov '23 03 dic '23 10 dic '23 17 dic '23 24 dic '23 31 dic '23 07 ene '24 14 ene '24 21 ene '24 28 ene '24 04 feb '24 11 feb '24 18 feb '24 25 feb '24 03 mar '24 10 mar '24 17 mar '24 24 mar '24 31 mar '24 07 abr '24 14 abr '24 21 abr '24 28 abr '24 05 may '24 12 may '24 19 may '24 26 may '24
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
1 1 AMPLIACION Y MEJORAMIENTO DE LA 240 días lun 02/10/23 mié 29/05/24
CAPACIDAD RESOLUTIVA DEL PUESTO DE
SALUD, NIVEL I-3 CHINCHE TINGO, LOCALIDAD
DE CHINCHE TINGO, DISTRITO DE YANAHUANCA,
PROVINCIA DE DANIEL
ALCIDES CARRION - PASCO
2 1.1 OBRAS PROVISIONALES, TRABAJOS 196 días lun 02/10/23 lun 15/04/24
PRELIMINARES, SEGURIDAD Y SALUD
3 1.1.1 OBRAS PROVISIONALES Y TRABAJOS 35 días lun 02/10/23 lun 06/11/23
PRELIMINARES
5 1.1.1.1.1 ALMACEN Y OFICINA PARA OBRA 1 día lun 02/10/23 mar 03/10/23
(ALQUILER)
7 1.1.1.1.3 VESTUARIO PERSONAL OBRA 1 día mar 03/10/23 mié 04/10/23 6CC
(ALQUILER)
8 1.1.1.1.4 SERVICIOS HIGIENICOS PORTATIL 1 día mar 03/10/23 mié 04/10/23 7CC
(ALQUILER)
9 1.1.1.1.5 CERCO PROVISIONAL DE OBRA 2 días mar 03/10/23 jue 05/10/23 8CC
C/TRIPLAY 6mm H=3.60m
10 1.1.1.1.6 CARTEL DE OBRA DE 4.80M X 3.60M. 1 día jue 05/10/23 vie 06/10/23 9
12 1.1.1.2.1 PAGO POR CONSUMO DE AGUA 1 día vie 06/10/23 sáb 07/10/23 10
13 1.1.1.2.2 PAGO POR CONSUMO DE 1 día vie 06/10/23 sáb 07/10/23 12CC
ELECTRICIDAD
20 1.1.1.4.2 TRAZO, NIVELES Y REPLANTEO 30 días sáb 07/10/23 lun 06/11/23 19CC
DURANTE EL PROCESO
27 1.1.2.1.5 RECURSOS PARA RESPUESTAS 1 día mar 03/10/23 mié 04/10/23 24CC
ANTE EMERGENCIAS EN SEGURIDAD
Y SALUD DURANTE EL TRABAJO
30 1.1.3.1 LIMPIEZA PERMANENTE DE OBRA 107 días lun 09/10/23 mié 24/01/24 19
31 1.1.3.2 LIMPIEZA FINAL DE OBRA 5 días mié 10/04/24 lun 15/04/24 132
40 1.2.2.1.1.2 EXCAVACION MASIVA PARA LOSA 1 día jue 19/10/23 vie 20/10/23 39
DE CIMENTACION
52 1.2.2.4.1 NIVELACION INTERIOR Y APISONADO 6 días vie 03/11/23 jue 09/11/23 46CC
58 1.2.3.1.1 CONCRETO f'c=175 kg/cm2 PARA 9 días vie 24/11/23 dom 03/12/23 59
CIMIENTO CORRIDO
61 1.2.3.2.1 CONCRETO f'c=175 kg/cm2 PARA 6 días mié 25/10/23 mar 31/10/23 50
SOLADOS
63 1.2.3.3.1 CONCRETO f'c=175 kg/cm2 PARA 6 días mar 31/10/23 lun 06/11/23 61
FALSO PISO
64 1.2.4 OBRAS DE CONCRETO ARMADO 174 días vie 20/10/23 jue 11/04/24
66 1.2.4.1.1 CONCRETO f'c=280 kg/cm2 PARA 21 días lun 20/11/23 lun 11/12/23 67
LOSA DE CIMENTACION
67 1.2.4.1.2 ACERO Fy= 4200 Kg/cm² PARA LOSA 20 días mar 31/10/23 lun 20/11/23 61
DE CIMENTACION
69 1.2.4.2.1 CONCRETO f'c=210 kg/cm2 PARA 1 día lun 13/11/23 mar 14/11/23 70
VIGAS DE CIMENTACION
71 1.2.4.2.3 ACERO Fy= 4200 Kg/cm² PARA VIGAS 11 días mar 31/10/23 sáb 11/11/23 67CC
DE CIMENTACION
73 1.2.4.3.1 CONCRETO f'c=175 kg/cm2 PARA 3 días dom 28/01/24 mié 31/01/24 74
SOBRECIMIENTOS ARMADOS
75 1.2.4.3.3 ACERO Fy= 4200 Kg/cm² PARA 12 días lun 11/12/23 sáb 23/12/23 66
SOBRECIMIENTOS ARMADOS
77 1.2.4.4.1 CONCRETO f'c=280 Kg/cm² PARA 2 días mar 02/01/24 jue 04/01/24 78
PLACAS
79 1.2.4.4.3 ACERO Fy= 4200 Kg/cm² PARA 18 días lun 20/11/23 vie 08/12/23 67
PLACAS
82 1.2.4.5.1.1 CONCRETO f'c=280 Kg/cm² PARA 9 días dom 03/12/23 mar 12/12/23 83
COLUMNAS
84 1.2.4.5.1.3 ACERO Fy= 4200 Kg/cm² PARA 13 días mar 31/10/23 lun 13/11/23 71CC
COLUMNAS
86 1.2.4.5.2.1 CONCRETO f'c=175 Kg/cm² PARA 11 días jue 28/03/24 lun 08/04/24 87
COLUMNAS DE CONFINAMIENTO
88 1.2.4.5.2.3 ACERO Fy= 4200 Kg/cm² PARA 14 días sáb 24/02/24 sáb 09/03/24 141;142;143
COLUMNAS DE CONFINAMIENTO
91 1.2.4.6.1.1 CONCRETO f'c=280 Kg/cm² PARA 11 días lun 25/03/24 vie 05/04/24 93
VIGAS
93 1.2.4.6.1.3 ACERO Fy= 4200 Kg/cm² PARA 46 días jue 08/02/24 lun 25/03/24 92
VIGAS
95 1.2.4.6.2.1 CONCRETO f'c=175 Kg/cm² PARA 3 días lun 08/04/24 jue 11/04/24 97
VIGAS DE CONFINAMIENTO
97 1.2.4.6.2.3 ACERO Fy= 4200 Kg/cm² PARA 8 días dom 31/03/24 lun 08/04/24 96
VIGAS DE CONFINAMIENTO
100 1.2.4.7.1.1 CONCRETO f'c=210 Kg/cm² PARA 9 días vie 26/01/24 dom 04/02/24 102
LOSA MACIZA
102 1.2.4.7.1.3 ACERO Fy= 4200 Kg/cm² PARA 20 días sáb 06/01/24 vie 26/01/24 101
LOSA MACIZA
104 1.2.4.8.1 CONCRETO f'c=210 Kg/cm² PARA 2 días jue 22/02/24 sáb 24/02/24 106
ESCALERAS
Proyecto: PROGRAMACIÓN CH Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha límite División crítica Progreso manual
Fecha: mié 02/08/23 División Resumen Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Hito externo Tareas críticas Progreso
Página 1
Id Modo de EDT Nombre de tarea Duración Comienzo Fin Predecesoras 01 oct '23 08 oct '23 15 oct '23 22 oct '23 29 oct '23 05 nov '23 12 nov '23 19 nov '23 26 nov '23 03 dic '23 10 dic '23 17 dic '23 24 dic '23 31 dic '23 07 ene '24 14 ene '24 21 ene '24 28 ene '24 04 feb '24 11 feb '24 18 feb '24 25 feb '24 03 mar '24 10 mar '24 17 mar '24 24 mar '24 31 mar '24 07 abr '24 14 abr '24 21 abr '24 28 abr '24 05 may '24 12 may '24 19 may '24 26 may '24
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
105 1.2.4.8.2 ENCOFRADO Y DESENCOFRADO 11 días dom 04/02/24 jue 15/02/24 100
NORMAL PARA ESCALERAS
106 1.2.4.8.3 ACERO Fy= 4200 Kg/cm² PARA 7 días jue 15/02/24 jue 22/02/24 105
ESCALERAS
108 1.2.4.9.1 CONCRETO f'c=280 Kg/cm² PARA 1 día jue 23/11/23 vie 24/11/23 109
CISTERNA
109 1.2.4.9.2 ENCOFRADO Y DESENCOFRADO 14 días jue 09/11/23 jue 23/11/23 110
NORMAL PARA CISTERNA
110 1.2.4.9.3 ACERO Fy= 4200 Kg/cm² PARA 9 días mar 31/10/23 jue 09/11/23 41
CISTERNA
111 1.2.4.10 MURO DE CONTENCIÓN 138 días vie 20/10/23 mié 06/03/24
112 1.2.4.10.1 CONCRETO f'c=210 Kg/cm² PARA 9 días lun 26/02/24 mié 06/03/24 113
MURO DE CONTENCIÓN
113 1.2.4.10.2 ENCOFRADO Y DESENCOFRADO 65 días sáb 23/12/23 lun 26/02/24 114
NORMAL PARA MURO DE
CONTENCIÓN
114 1.2.4.10.3 ACERO Fy= 4200 Kg/cm² PARA MURO 64 días vie 20/10/23 sáb 23/12/23 40
DE CONTENCIÓN
116 1.2.4.11.1 CONCRETO f'c=210 Kg/cm² PARA 1 día jue 14/03/24 vie 15/03/24 117
VEREDAS
117 1.2.4.11.2 ENCOFRADO Y DESENCOFRADO 1 día mié 13/03/24 jue 14/03/24 118
NORMAL PARA VEREDAS
118 1.2.4.11.3 ACERO Fy= 4200 Kg/cm² PARA 3 días dom 10/03/24 mié 13/03/24 120
VEREDAS
120 1.2.4.12.1 CONCRETO f'c=175 Kg/cm² PARA 1 día sáb 09/03/24 dom 10/03/24 121
SARDINELES
121 1.2.4.12.2 ENCOFRADO Y DESENCOFRADO 2 días jue 07/03/24 sáb 09/03/24 122
NORMAL PARA SARDINELES
122 1.2.4.12.3 ACERO Fy= 4200 Kg/cm² PARA 1 día mié 06/03/24 jue 07/03/24 112
SARDINELES
124 1.2.4.13.1 CONCRETO f'c=210 Kg/cm² PARA 1 día mar 19/03/24 mié 20/03/24 126
RAMPAS
125 1.2.4.13.2 ENCOFRADO Y DESENCOFRADO 1 día vie 15/03/24 sáb 16/03/24 116
NORMAL PARA RAMPAS
126 1.2.4.13.3 ACERO Fy= 4200 Kg/cm² PARA 3 días sáb 16/03/24 mar 19/03/24 125
RAMPAS
128 1.2.5.1 TIJERAL DE MADERA DE ESTRUCTURA 6 días lun 01/04/24 dom 07/04/24 91CC+7 días
3" x 6"
129 1.2.5.2 CORREAS DE MADERA DE 2" x 3" 2 días dom 07/04/24 mar 09/04/24 128
131 1.2.6.1 TUBO METALICO DE 2"X2" 1 día mar 09/04/24 mié 10/04/24 129
132 1.2.6.2 TUBO METALICO DE 2"X2" 1 día mar 09/04/24 mié 10/04/24 131CC
134 1.2.7.1 JUNTA DE DILTACION DE 1" CON SELLO 6 días mié 27/03/24 mar 02/04/24 124FC+7 días
ASFALTICO
135 1.2.7.2 JUNTA SISMICA DE 1" (POLIESTIRENO) 4 días vie 27/10/23 mar 31/10/23 84CF
136 1.2.7.3 SUMINISTRO Y COLOCACIÓN DE WATER 1 día jue 23/11/23 vie 24/11/23 108CC
STOP DE 4"
137 1.2.7.4 ESCALERA METÁLICA TIPO GATA 1 día vie 24/11/23 sáb 25/11/23 136
139 1.3.1 MUROS Y TABIQUES DE ALBAÑILERIA 20 días dom 04/02/24 sáb 24/02/24
140 1.3.1.1 MUROS DE LADRILLO KING KONG DE 20 días dom 04/02/24 sáb 24/02/24
ARCILLA (A MAQUINA O
ARTESANALMENTE)
141 1.3.1.1.1 MUROS DE LADRILLO KING KONG DE 20 días dom 04/02/24 sáb 24/02/24 100
ARCILLA (A MAQUINA) DE SOGA
MEZCLA C:A 1:4, TIPO IV PARA
TARRAJEO
142 1.3.1.1.2 MUROS DE LADRILLO KING KONG DE 20 días dom 04/02/24 sáb 24/02/24 141CC
ARCILLA (A MAQUINA) DE CABEZA
MEZCLA C:A 1:4, TIPO IV PARA
TARRAJEO
143 1.3.1.1.3 MUROS DE LADRILLO KK MAQ. TIPO 15 días dom 04/02/24 lun 19/02/24 142CC
IV SOGA MEZCLA C:A 1:4 CARAVISTA
144 1.3.1.2 MUROS CON EL SISTEMA DE 1 día lun 19/02/24 mar 20/02/24
CONSTRUCCION EN SECO (SISTEMA
DRYWALL O SIMILAR)
145 1.3.1.2.1 TABIQUE SISTEMA DRYWALL 1 día lun 19/02/24 mar 20/02/24 143
INTERIOR - TI PLACA DE
FIBROCEMENTO 8mm
146 1.3.2 REVOQUES Y REVESTIMIENTOS 148 días vie 24/11/23 sáb 20/04/24
147 1.3.2.1 TARRAJEO RAYADO PRIMARIO 33 días sáb 24/02/24 jue 28/03/24
148 1.3.2.1.1 TARRAJEO RAYADO PRIMARIO 33 días sáb 24/02/24 jue 28/03/24 141;142;143
P/RECIBIR ENCHAPE C:A 1:5, e=1.5
CM
150 1.3.2.2.1 TARRAJEO FROTACHADO DE MUROS 15 días sáb 24/02/24 dom 10/03/24 141;142;143
INTERIORES C/MORT C:A 1:5, e=1.5
CM
151 1.3.2.2.2 TARRAJEO DE COLUMNAS C/MORT 20 días sáb 24/02/24 vie 15/03/24 150CC
C:A 1:5, e=1.5 CM
152 1.3.2.2.3 TARRAJEO DE VIGAS C/MORT C:A 9 días vie 15/03/24 dom 24/03/24 151
1:5, e=1.5 CM
153 1.3.2.2.4 SOLAQUEADO DE MUROS 35 días mié 06/03/24 mié 10/04/24 112
154 1.3.2.2.5 SOLAQUEO DE COLUMNAS 7 días vie 15/03/24 vie 22/03/24 151
155 1.3.2.2.6 SOLAQUEO DE VIGAS 10 días dom 24/03/24 mié 03/04/24 152
157 1.3.2.3.1 TARRAJEO FROTACHADO DE MUROS 15 días dom 10/03/24 lun 25/03/24 150
EXTERIORES C/MORT C:A 1:5, e=1.5
CM
159 1.3.2.4.1 VESTIDURA DE DERRAMES E = 0.15 10 días mié 03/04/24 sáb 13/04/24 155
m
161 1.3.2.5.1 BRUÑAS DE 1cm x 1 cm 17 días mié 03/04/24 sáb 20/04/24 159CC
162 1.3.2.6 TARRAJEO EN FONDO DE ESCALERA 22 días sáb 24/02/24 dom 17/03/24
163 1.3.2.6.1 TARRAJEO FONDO DE ESCALERAS 22 días sáb 24/02/24 dom 17/03/24 104
MEZC. C:A 1:5, e=1.5 cm
165 1.3.2.7.1 FORJADO DE GRADAS Y ESCALERAS 7 días dom 17/03/24 dom 24/03/24 163
DE CEMENTO FROTACHADO
166 1.3.2.7.2 FORJADO DE DESCANSO CON 4 días dom 17/03/24 jue 21/03/24 165CC
CEMENTO FROTACHADO
167 1.3.2.7.3 REVESTIMIENTO DE GRADAS Y 11 días dom 17/03/24 jue 28/03/24 166CC
ESCALERAS CON CEMENTO
SEMIPULIDO
168 1.3.2.7.4 REVESTIMIENTO DE DESCANSO DE 4 días dom 17/03/24 jue 21/03/24 167CC
ESCALERA CON CEMENTO
SEMIPULIDO BRUÑADO
169 1.3.2.7.5 REVESTIMIENTO DE CANALETA CON 25 días jue 21/03/24 lun 15/04/24 168
CEMENTO PULIDO E
IMPERMEABILIZADO
170 1.3.2.7.6 REVESTIMIENTO DE CISTERNA CON 6 días vie 24/11/23 jue 30/11/23 108
CEMENTO PULIDO
IMPERMEABILIZADO Y JUNTAS
WATER STOP
171 1.3.2.7.7 REVESTIMIENTO DE PARAPERO EN 4 días mié 20/03/24 dom 24/03/24 124
TANQUE ELEVADO CON CEMENTO
SEMIPULIDO
173 1.3.3.1 CIELORRASO CON MEZCLA 17 días dom 04/02/24 mié 21/02/24
174 1.3.3.1.1 CIELORASO CON MEZCLA C:A 1:5, E 17 días dom 04/02/24 mié 21/02/24 100
= 1.5 cm
176 1.3.3.2.1 FALSO CIELORASO TIPO A - 16 días dom 04/02/24 mar 20/02/24 100
BALDOSA DE FIBRA MINERAL
MICROPERFORADA CON ACABADO
DE PINTURA DE 0.61X0.61X5/8" (15,9
mms), BORDE RECTO, R.H. MIN DE
99% Y CALOR 49°C, SISTEMA DE
SUSPENSIÓN ANTISISMICA RX HEAVY
DUTY PRELUDE XL 15/16" COLOR
BLANCO O SIMILAR.
177 1.3.3.2.2 FALSO CIELORASO TIPO B - 1 día dom 04/02/24 lun 05/02/24 176CC
BALDOSA DE FIBRA MINERAL CLASE
5, BORDE RECTO DE 0.61x0.61m x
5/8"(15,9mms), RESISTENTE A LA
HUMEDAD MIN. DE 99% Y CALOR DE
49°C, SISTEMA DE SUSPENSIÓN
ANTISISMICA RX HEAVY DUTY
PRELUDE XL 15/16" COLOR BLANCO
O SIMILAR.
178 1.3.3.2.3 FALSO CIELORASO TIPO C - 2 días dom 04/02/24 mar 06/02/24 177CC
BALDOSA DE FIBRA MINERAL CLASE
5, BORDE RECTO DE 0.61x0.61m x
5/8", CON SIST. DE SUSPENSIÓN
ESPECIAL CLEAN ROOM, RES. A LA
HUMEDAD MIN. DE 99% Y CALOR
49°C, SIST. DE SUSP. ANTISISMICA DE
ALUMINIO DE 1-1/2", BLANCO O
SIMILAR.
179 1.3.3.2.4 FALSO CIELORASO TIPO D - 1 día dom 04/02/24 lun 05/02/24 178CC
BALDOSA DE FIBRA MINERAL SIN
PERFORACIONES, BORDE RECTO DE
0.61x0.61m x 5/8"(15,9mms),R.H. MIN
DE 99% Y AL CALOR DE 49°C, SIST.
SUSPENSIÓN ANTISISMICO RX
HEAVY DUTY PRELUDE XL 15/16"
COLOR BLANCO O SIMILAR.
180 1.3.3.2.5 FALSO CIELORASO TIPO E - SISTEMA 2 días dom 04/02/24 mar 06/02/24 179CC
PLYROCK CON PLANCHA DE
FIBROCEMENTO SIN SILICE DE 8mm,
BORDE REBAJADO, JUNTA RÍGIDA
INVISIBLE, ACABADO CON PINTURA
ACRILICA MATE BASE AGUA O
SIMILAR.
181 1.3.3.2.6 FALSO CIELORASO TIPO G - SISTEMA 8 días dom 04/02/24 lun 12/02/24 180CC
DRYWALL CON PLANCHA DE YESO
REGULAR DE 1/2" DE ESPESOR,
ACABADO CON PINTURA LATEX
VINÍLICA BASE AGUA.
182 1.3.4 PISOS Y PAVIMENTOS 173 días lun 06/11/23 sáb 27/04/24
187 1.3.4.2.1.1 PISO PORCELANATO 18 días lun 25/03/24 vie 12/04/24 157
ANTIDESLIZANTE PEI-4 60 cm x 60
cm
188 1.3.4.2.1.2 PISO DE PORCELANA DOBLE 9 días lun 25/03/24 mié 03/04/24 187CC
CARGA ANTIDESLIZANTE PEI-4 DE
0.6 X 0.6
Proyecto: PROGRAMACIÓN CH Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha límite División crítica Progreso manual
Fecha: mié 02/08/23 División Resumen Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Hito externo Tareas críticas Progreso
Página 2
Id Modo de EDT Nombre de tarea Duración Comienzo Fin Predecesoras 01 oct '23 08 oct '23 15 oct '23 22 oct '23 29 oct '23 05 nov '23 12 nov '23 19 nov '23 26 nov '23 03 dic '23 10 dic '23 17 dic '23 24 dic '23 31 dic '23 07 ene '24 14 ene '24 21 ene '24 28 ene '24 04 feb '24 11 feb '24 18 feb '24 25 feb '24 03 mar '24 10 mar '24 17 mar '24 24 mar '24 31 mar '24 07 abr '24 14 abr '24 21 abr '24 28 abr '24 05 may '24 12 may '24 19 may '24 26 may '24
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
190 1.3.4.2.2.1 PISO CEMENTO SEMIPULIDO CON 5 días mié 03/04/24 lun 08/04/24 188
ENDURECEDOR Y BRUÑADO
e=1cm.
191 1.3.4.2.2.2 PISO DE CEMENTO SEMI PULIDO 12 días mié 03/04/24 lun 15/04/24 190CC
CON ENDURECEDOR +
CONTRAZOCALO DE CEMENTO
SEMI PULIDO
193 1.3.4.2.3.1 TIPO I - PISO EN ROLLO VINÍLICO 6 días lun 15/04/24 dom 21/04/24 191
MIPOLAM TROPLAN CON
TRATAMIENTO EVERCARE DE 2mm
DE ESPESOR y 2m DE ANCHO
INSTALADO CON CORDÓN DE
SOLDADURA MIMETIZADO CON EL
PISO + CONTRAZÓCALO
SANITARIO CON SUBIDA DE
RODAPIE COMPLETA CON COVE
FORMER DE 2
194 1.3.4.2.3.2 TIPO Ia - PISO EN ROLLO VINÍLICO 12 días lun 15/04/24 sáb 27/04/24 193CC
MIPOLAM COSMO CON
TRATAMIENTO EVERCARE DE 2mm
DE ESPESOR y 2m DE ANCHO
INSTALADO CON CORDÓN DE
SOLDADURA MIMETIZADO CON EL
PISO + CONTRAZÓCALO
SANITARIO DE 10cm DEL MISMO
MATERIAL CON SUBIDA DE
RODAPIÉ COMPLETA CON C
195 1.3.4.2.3.3 TIPO III - PISO EN ROLLO VINÍLICO 12 días lun 15/04/24 sáb 27/04/24 194CC
MIPOLAM AFFINITY CON
TRATAMIENTO EVERCARE DE 2mm
DE ESPESOR y 2m DE ANCHO
INSTALADO CON CORDÓN DE
SOLDADURA MIMETIZADO CON EL
PISO + CONTRAZÓCALO
SANITARIO DE 10cm DEL MISMO
MATERIAL CON SUBIDA DE
RODAPIÉ COMPLETA C
196 1.3.4.2.3.4 TIPO VIII - PISO ACÚSTICO EN 4 días lun 15/04/24 vie 19/04/24 195CC
ROLLO VINÍLICO TARALAY
IMPRESSION COMFORT CON
TRATAMIENTO PROTECSOL2 DE
3.35mm DE ESPESOR y 2m DE
ANCHO + CONTRAZÓCALO
SANITARIO DE 10cm DEL MISMO
MATERIAL CON SUBIDA DE
RODAPIÉ COMPLETA CON COVE
FORMER DE 26X100mm+ REVES
198 1.3.4.3.1 VEREDA CON ACABADO DE 10 días vie 15/03/24 lun 25/03/24 116
CEMENTO SEMIPULIDO Y BRUÑADO
199 1.3.4.3.2 RAMPA DE CONCRETO ACABADO EN 2 días mié 20/03/24 vie 22/03/24 124
CEMENTO SEMIPULIDO Y BRUÑADO
@ 0.10M
200 1.3.4.3.3 PAVIMENTO DE CONCRETO F'C = 210 1 día vie 22/03/24 sáb 23/03/24 199
Kg/cm2, CON ACABADO DE CEMENTO
FROTACHADO
204 1.3.5.1.1.1 ZOCALO DE PORCELANATO 60 cm 7 días vie 19/04/24 vie 26/04/24 196
x 60 cm
209 1.3.5.2.2.1 CONTRAZOCALO SANITARIO 1 día vie 19/04/24 sáb 20/04/24 207CC
TERRAZO PULLIDO H=0.10 m
210 1.3.5.2.3 PROTECTOR DE CAMILLAS 265:292 2 días sáb 20/04/24 lun 22/04/24
211 1.3.5.2.3.1 CONTRAZOCALO COVE FORMER 1 día sáb 20/04/24 dom 21/04/24 209
DE 26x100mm + REVESTIMIENTO
VINILICO FLEXIBLE e=2mm,
H=0.10m
212 1.3.5.2.3.2 CONTRAZOCALO COVER FORMER 2 días sáb 20/04/24 lun 22/04/24 211CC
DE 38x38mm + REVESTIMIENTO
VINILICO, ROLLO DE 2mm,
CONDUCTOR DE LA
ELECTRICIDAD ESTATICA.
213 1.3.5.2.3.3 CONTRAZOCALO COVER FORMER 2 días sáb 20/04/24 lun 22/04/24 212CC
DE 26x100mm + REVESTIMIENTO
VINILICO, ALTO TRANSITO, EN
ROLLO DE 3.35mm.DE LA
ELECTRICIDAD ESTATICA.
216 1.3.6.1.1 CUBIERTA DE CEMENTO PULIDO + 14 días dom 04/02/24 dom 18/02/24 100
IMPERMEABILIZANTE HIDROFUGO
CON BICAPA DE MANTO ASFALTICO Y
AISLAMIENTO
218 1.3.6.2.1 TEJA ANDINA DE FIBROCEMENTO 10 días dom 04/02/24 mié 14/02/24 100
1.14 X 0.72
219 1.3.6.2.2 CUMBRERA TEJA ANDINA DE 9 días mié 14/02/24 vie 23/02/24 218
FIBROCEMENTO 0.35X 0.70
220 1.3.6.2.3 TIRAFON PARA CUMBRERA TEJA 20 días mié 14/02/24 mar 05/03/24 219CC
ANDINA 125 MM CON ARANDELA Y
TAPA DE PLÁSTICO
223 1.3.7.1.1 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 159
MDF LAMINADO E=4MM, CON
REFUERZO PARA CERRADURA Y
BISAGRAS. P-1 (2.00 X 2.50) 2 HOJAS
224 1.3.7.1.2 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 223CC
MDF LAMINADO E=4MM, CON
REFUERZO PARA CERRADURA Y
BISAGRAS. P-2 (1.20 X 2.10) 1 HOJA
225 1.3.7.1.3 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 224CC
MDF LAMINADO E=4MM, CON
REFUERZO PARA CERRADURA Y
BISAGRAS. P-3 (1.00 X 2.10) 1 HOJA
226 1.3.7.1.4 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 225CC
MDF LAMINADO E=4MM, CON
REFUERZO PARA CERRADURA Y
BISAGRAS. P-4 (0.90 X 2.10) 1 HOJA
227 1.3.7.1.5 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 226CC
MDF LAMINADO E=4MM, CON
REFUERZO PARA CERRADURA Y
BISAGRAS. P-5 (0.80 X 2.00) 1 HOJA
228 1.3.7.1.6 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 227CC
MDF LAMINADO E=4MM, CON
REFUERZO PARA CIERRAPUERTAS
CERRADURA Y BISAGRAS,
EXTERIORES. P-6 (2.00 X 2.10) 2
HOJAS
229 1.3.7.1.7 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 228CC
MDF LAMINADO E=4MM, CON
REFUERZO PARA CERRADURA Y
BISAGRAS. P-7 (1.80 X 2.10) 2 HOJAS
230 1.3.7.1.8 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 229CC
MDF LAMINADO E=6MM, CON
REFUERZO PARA CERRADURA Y
BISAGRAS, EXTERIORES. P-9 (1.00 X
2.10) 1 HOJA
231 1.3.7.1.9 PUERTAS CONTRAPLACADA CON 3 días sáb 13/04/24 mar 16/04/24 230CC
MDF LAMINADO E=6MM, CON
REFUERZO PARA CERRADURA Y
BISAGRAS, EXTERIORES. P-10 (1.50 X
2.10) 2 HOJAS
232 1.3.8 CARPINTERIA METALICA Y HERRERIA 36 días dom 24/03/24 lun 29/04/24
234 1.3.8.1.1 PUERTA METALICA P-8 (3.00 X 2.82) 2 1 día mar 16/04/24 mié 17/04/24 231
hojas
236 1.3.8.2.1 V-1 VENTANA DE ALUMINIO, 12 días mié 17/04/24 lun 29/04/24 234
C/CRISTAL TEMPLADO INCOLORO
6mm, INC. ACCESORIOS (0.60 x 1.62m)
237 1.3.8.2.2 V-2 VENTANA DE ALUMINIO, 10 días mié 17/04/24 sáb 27/04/24 236CC
C/CRISTAL TEMPLADO INCOLORO
6mm, INC. ACCESORIOS (0.60 x 0.70m)
238 1.3.8.2.3 V-3 VENTANA DE ALUMINIO, 1 día mié 17/04/24 jue 18/04/24 237CC
C/CRISTAL TEMPLADO INCOLORO
6mm, INC. ACCESORIOS (1.20 x 1.82m)
239 1.3.8.2.4 V-4 VENTANA DE ALUMINIO, 1 día mié 17/04/24 jue 18/04/24 238CC
C/CRISTAL TEMPLADO INCOLORO
6mm, INC. ACCESORIOS (0.75 x 1.82m)
240 1.3.8.2.5 V-5 VENTANA DE ALUMINIO, 2 días mié 17/04/24 vie 19/04/24 239CC
C/CRISTAL TEMPLADO INCOLORO
6mm, INC. ACCESORIOS (0.85 x 1.82m)
241 1.3.8.2.6 V-6 VENTANA DE ALUMINIO, 2 días mié 17/04/24 vie 19/04/24 240CC
C/CRISTAL TEMPLADO INCOLORO
6mm, INC. ACCESORIOS (1.25 x 1.82m)
242 1.3.8.3 PUERTAS Y MANPARAS DE ALUMINIO 9 días vie 19/04/24 dom 28/04/24
DE ALUMINIO
243 1.3.8.3.1 P-11 VIDRIO TEMPLADO e=10mm, CON 7 días vie 19/04/24 vie 26/04/24 241
MARCO DE ALUMINIO 2 HOJAS. INC.
ACCESORIOS (1.20m x 2.82m.)
244 1.3.8.3.2 M-02 MAMPARA DE ALUMINIO C/ 5 días vie 19/04/24 mié 24/04/24 243CC
CRISTAL TEMPLADO INCOLORO DE
10mm. INC. ACCESORIOS (0.75m x
2.82m.)
Proyecto: PROGRAMACIÓN CH Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha límite División crítica Progreso manual
Fecha: mié 02/08/23 División Resumen Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Hito externo Tareas críticas Progreso
Página 3
Id Modo de EDT Nombre de tarea Duración Comienzo Fin Predecesoras 01 oct '23 08 oct '23 15 oct '23 22 oct '23 29 oct '23 05 nov '23 12 nov '23 19 nov '23 26 nov '23 03 dic '23 10 dic '23 17 dic '23 24 dic '23 31 dic '23 07 ene '24 14 ene '24 21 ene '24 28 ene '24 04 feb '24 11 feb '24 18 feb '24 25 feb '24 03 mar '24 10 mar '24 17 mar '24 24 mar '24 31 mar '24 07 abr '24 14 abr '24 21 abr '24 28 abr '24 05 may '24 12 may '24 19 may '24 26 may '24
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
245 1.3.8.3.3 M-03 MAMPARA DE ALUMINIO C/ 9 días vie 19/04/24 dom 28/04/24 244CC
CRISTAL TEMPLADO INCOLORO DE
10mm. INC. ACCESORIOS (2.95m x
2.82m.)
246 1.3.8.3.4 M-04 MAMPARA DE ALUMINIO C/ 8 días vie 19/04/24 sáb 27/04/24 245CC
CRISTAL TEMPLADO INCOLORO DE
10mm. INC. ACCESORIOS (2.52m x
2.82m.)
248 1.3.8.4.1 AGARRADERA PARA 3 días vie 26/04/24 lun 29/04/24 204
DISCAPACITADOS EN INODOROS; Ø =
1 1/2"
249 1.3.8.5 ELEMENTOS METÁLICOS ESPECIALES 3 días dom 24/03/24 mié 27/03/24
250 1.3.8.5.1 ESCALERA TIPO GATO CON 3 días dom 24/03/24 mié 27/03/24 171
PROTECCION Fe Ø2", PINTADO CON
ANTICORROSIVA Y ESMALTE
253 1.3.9.1.1 CERRADURA TIPO A 1 día mar 16/04/24 mié 17/04/24 231
254 1.3.9.1.2 CERRADURA TIPO B 5 días mar 16/04/24 dom 21/04/24 253CC
255 1.3.9.1.3 CERRADURA TIPO E 1 día mar 16/04/24 mié 17/04/24 254CC
256 1.3.9.1.4 CERRADURA TIPO P 1 día mar 16/04/24 mié 17/04/24 255CC
257 1.3.10 VIDRIOS CRISTALES Y SIMILARES 5 días vie 19/04/24 mié 24/04/24
259 1.3.10.1.1 VIDRIO TEMPLADO e=10mm, (1.20 m. x 5 días vie 19/04/24 mié 24/04/24 241
2.82 m.)
260 1.3.10.1.2 VIDRIO TEMPLADO e=10mm, (0.75 m. x 5 días vie 19/04/24 mié 24/04/24 259CC
2.82 m.)
261 1.3.10.1.3 VIDRIO TEMPLADO e=10mm, (2.95 m. x 5 días vie 19/04/24 mié 24/04/24 260CC
2.82 m.)
262 1.3.10.1.4 VIDRIO TEMPLADO e=10mm, (2.52 m. x 5 días vie 19/04/24 mié 24/04/24 261CC
2.82 m.)
263 1.3.10.1.5 CRISTAL INCOLORO e=6mm, (0.60 m. x 5 días vie 19/04/24 mié 24/04/24 262CC
1.62 m.)
264 1.3.10.1.6 CRISTAL INCOLORO e=6mm, (0.60 m. x 5 días vie 19/04/24 mié 24/04/24 263CC
0.70 m.)
265 1.3.10.1.7 CRISTAL INCOLORO e=6mm, (1.20 m. x 5 días vie 19/04/24 mié 24/04/24 264CC
1.82 m.)
266 1.3.10.1.8 CRISTAL INCOLORO e=6mm, (0.75 m. x 5 días vie 19/04/24 mié 24/04/24 265CC
1.82 m.)
267 1.3.10.1.9 CRISTAL INCOLORO e=6mm, (0.85 m. x 5 días vie 19/04/24 mié 24/04/24 266CC
1.82 m.)
268 1.3.10.1.10 CRISTAL INCOLORO e=6mm, (1.25 m. x 5 días vie 19/04/24 mié 24/04/24 267CC
1.82 m.)
271 1.3.11.1.1 PINTURA CIELORASOS C/ PINTURA A 5 días mié 21/02/24 lun 26/02/24 174
BASE ALQUIDICA CON ACABADO
OLEOMATE Y DE RAPIDO SECADO (2
MANOS) C/ IMPRIMANTE
272 1.3.11.2 PINTURA DE MUROS INTERIORES 25 días dom 10/03/24 jue 04/04/24
273 1.3.11.2.1 PINTURA MUROS INTERIORES C/ 25 días dom 10/03/24 jue 04/04/24 150
EMPASTADO Y PINTURA OLEOMATE
(2 MANOS)
274 1.3.11.3 PINTURA DE MUROS EXTERIORES 15 días lun 25/03/24 mar 09/04/24
275 1.3.11.3.1 PINTURA MUROS EXTERIORES C/ 15 días lun 25/03/24 mar 09/04/24 157
PINTURA PREMIUN BASE AGUA TIPO
LATEX CON NANO PARTICULAS
ANTIBACTERIALES, DE ALTA
RESISTENCIA A RAYOS UV BAJO VOC
(2 MANOS), C/ IMPRIMANTE
277 1.3.11.4.1 PINTURA PAVIMENTOS 1 día mar 09/04/24 mié 10/04/24 275
DEMARCACION DE FRANJAS, ANCHO
= 0.50 M C/ PINTURA A BASE DE
POLIMEROS ACRILICOS ALTA
RESISTENCIA AL TRAFICO Y
RETROREFLECTIVAS - 2 MANOS
278 1.3.11.4.2 PINTURA PAVIMENTOS 1 día mar 09/04/24 mié 10/04/24 277CC
DEMARCACION DE FRANJAS, ANCHO
= 0.10 M C/ PINTURA A BASE DE
POLIMEROS ACRILICOS ALTA
RESISTENCIA AL TRAFICO Y
RETROREFLECTIVAS - 2 MANOS
279 1.3.11.4.3 PINTURA PAVIMENTOS 1 día mar 09/04/24 mié 10/04/24 278CC
DEMARCACION DE FRANJAS, ANCHO
= 0.20 M C/ PINTURA A BASE DE
POLIMEROS ACRILICOS ALTA
RESISTENCIA AL TRAFICO Y
RETROREFLECTIVAS - 2 MANOS
280 1.3.12 VARIOS, LIMPIEZA, JARDINERIA 199 días lun 02/10/23 jue 18/04/24
282 1.3.12.1.1 PASAMANOS, h=0.90m 11 días dom 10/03/24 jue 21/03/24 120
283 1.3.12.1.2 ESPEJOS PARA SS.HH. (0.60 x 0.80) 1 día jue 21/03/24 vie 22/03/24 282
284 1.3.12.1.3 PARED COMPLEMENTARIA 1 día vie 22/03/24 sáb 23/03/24 283
MELAMINE SS.HH.
285 1.3.12.2 LIMPIEZA PERMANENTE DE OBRA 192 días lun 09/10/23 jue 18/04/24
286 1.3.12.2.1 LIMPIEZA PERMANENTE DE OBRA 14 días lun 09/10/23 lun 23/10/23 30CC
287 1.3.12.2.2 LIMPIEZA FINAL DE OBRA 8 días mié 10/04/24 jue 18/04/24 31CC
289 1.3.12.3.1 PROVISION Y SEMBRIO DE GRASS 3 días lun 02/10/23 jue 05/10/23
292 1.3.13.1.1 SI - 01 INDICATIVO DE SS.HH. 1 día mié 10/04/24 jue 11/04/24 279
(0.60X0.30m) ADOSADO
293 1.3.13.1.2 SI - 02 IDENTIFICATIVO (1.20 x 0.30m) 2 días jue 11/04/24 sáb 13/04/24 292
COLGANTE
295 1.3.13.2.1 SEÑALES ADHESIVAS 3 días sáb 13/04/24 mar 16/04/24 293
296 1.4 INSTALACIONES ELECTRICAS 196 días lun 02/10/23 lun 15/04/24
298 1.4.1.1 TRAZO Y REPLANTEO 4 días sáb 24/02/24 mié 28/02/24 141
300 1.4.2.1 EXCAVACION Y RELLENO DE ZANJA 9 días mié 28/02/24 vie 08/03/24 298
(0.70 X 0.6 M)
301 1.4.2.2 COMPACTACION Y ELIMINACION DE 9 días mié 03/04/24 vie 12/04/24 311
MATERIAL EXCEDENTE
302 1.4.2.3 EXCAVACION DE POZO PARA PUESTA A 1 día mié 28/02/24 jue 29/02/24 300CC
TIERRA
304 1.4.3.1 TUBERIAS DE PVC- SAP DE 100 MM. 2 días vie 08/03/24 dom 10/03/24 300
DIAMETRO
305 1.4.3.2 TUBERIAS DE PVC- SAP DE 25 MM. 2 días vie 08/03/24 dom 10/03/24 304CC
DIAMETRO
306 1.4.3.3 TUBERIAS DE PVC- SAP DE 20 MM. 15 días vie 08/03/24 sáb 23/03/24 305CC
DIAMETRO
308 1.4.4.1 CONDUCTOR DE Cu. N2XH 3 -1 x 72 1 día sáb 23/03/24 dom 24/03/24 306
MM2. ALIMENTADOR
309 1.4.4.2 CONDUCTOR DE Cu. N2XH 3 -1 x 6 MM2. 1 día sáb 23/03/24 dom 24/03/24 308CC
ALIMENTADOR
310 1.4.4.3 CONDUCTOR DE Cu. LSOH 4 MM2. 1 día dom 24/03/24 lun 25/03/24 309
311 1.4.4.4 CONDUCTOR DE Cu. LSOH 2.5 MM2. 10 días dom 24/03/24 mié 03/04/24 310CC
313 1.4.5.1 BUZON DE REGISTRO DE C.A. DE 700 x 1 día jue 29/02/24 vie 01/03/24 302
700 mm
314 1.4.6 EQUIPOS DE ALUMBRADO INTERIOR 196 días lun 02/10/23 lun 15/04/24
315 1.4.6.1 LUMINARIA EMPOTRADA CON 9 días sáb 06/04/24 lun 15/04/24 325
FLUORESCENTES RECTOS T8 4 x 18 W
316 1.4.6.2 LUMINARIA EMPOTRADA CON 9 días sáb 06/04/24 lun 15/04/24 315CC
FLUORESCENTES RECTOS T8 3 x 36 W
317 1.4.6.3 SISTEMA DE LUCES DE EMERGENCIA 2 días lun 02/10/23 mié 04/10/23
319 1.4.7.1 TABLERO GENERAL (TG) 1 día dom 24/03/24 lun 25/03/24 308
320 1.4.7.2 SUBTABLERO DE DISTRIBUCION 1 día lun 25/03/24 mar 26/03/24 319
321 1.4.7.3 SUBTABLERO DE CONTROL 1 día lun 25/03/24 mar 26/03/24 320CC
322 1.4.8 SALIDAS DE PARED - INTERRUPTORES 16 días mar 26/03/24 jue 11/04/24
323 1.4.8.1 SALIDA DE PARED P/INTERRUPTOR 16 días mar 26/03/24 jue 11/04/24 321
SIMPLE, CAJA RECTANGULAR
324 1.4.9 SALIDA PARA TOMACORRIENTES 11 días mar 26/03/24 sáb 06/04/24
325 1.4.9.1 SALIDA P/TOMACORRIENTE BIPOLAR 11 días mar 26/03/24 sáb 06/04/24 323CC
DOBLE C/TOMA TIERRA, PARED
327 1.4.10.1 POZO DE TIERRA SISTEMA RED 3 días vie 01/03/24 lun 04/03/24 313
NORMAL
329 1.4.11.1 GRUPO ELECTROGENO (DIESEL) 1 día lun 25/03/24 mar 26/03/24 319
250KVA
330 1.5 INSTALACIONES SANITARIAS 208 días lun 02/10/23 sáb 27/04/24
331 1.5.1 APARATOS SANITARIOS Y ACCESORIOS 34 días mar 19/03/24 lun 22/04/24
333 1.5.1.1.1 INODORO TIPO TOP PIEC FLUXO O 11 días jue 04/04/24 lun 15/04/24 347
SIMILAR CON GRIFERIA
334 1.5.1.1.2 LAVATORIO OVALIN TIPO SONET O 10 días jue 04/04/24 dom 14/04/24 333CC
SIMILAR PARA EMPOTRAR CON
GRIFERIA CON TEMPORIZADOR
335 1.5.1.1.3 LAVADERO DE ACERO INOXIDABLE 1 10 días jue 04/04/24 dom 14/04/24 334CC
POZAS
336 1.5.1.1.4 URINARIO TIPO CADET O SIMILAR 5 días jue 04/04/24 mar 09/04/24 335CC
CON FLUXOMETRO
338 1.5.1.2.1 LLAVE PARA LAVATORIO 2 días dom 14/04/24 mar 16/04/24 334
339 1.5.1.2.2 LLAVE PARA LAVADERO DE ACERO 1 día dom 14/04/24 lun 15/04/24 335
INOXIDABLE
340 1.5.1.2.3 DUCHAS DE EMERGENCIA 3 días mar 09/04/24 vie 12/04/24 336
341 1.5.1.2.4 MEZCLADORA PARA LAVATORIO 1 día dom 14/04/24 lun 15/04/24 334
342 1.5.1.2.5 MEZCLADORA PARA LAVADERO 2 días dom 14/04/24 mar 16/04/24 335
343 1.5.1.2.6 MEZCLADORA PARA DUCHA 1 día vie 12/04/24 sáb 13/04/24 340
345 1.5.1.3.1 JABONERA CROMADA CON 6 días mar 16/04/24 lun 22/04/24 342
DISPENSADOR PARA JABON LIQUIDO
347 1.5.1.4.1 COLOCACION DE APARATOS 10 días lun 25/03/24 jue 04/04/24 349
SANITARIOS
349 1.5.1.5.1 COLOCACION DE GRIFERIAS 6 días mar 19/03/24 lun 25/03/24 352
Proyecto: PROGRAMACIÓN CH Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha límite División crítica Progreso manual
Fecha: mié 02/08/23 División Resumen Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Hito externo Tareas críticas Progreso
Página 4
Id Modo de EDT Nombre de tarea Duración Comienzo Fin Predecesoras 01 oct '23 08 oct '23 15 oct '23 22 oct '23 29 oct '23 05 nov '23 12 nov '23 19 nov '23 26 nov '23 03 dic '23 10 dic '23 17 dic '23 24 dic '23 31 dic '23 07 ene '24 14 ene '24 21 ene '24 28 ene '24 04 feb '24 11 feb '24 18 feb '24 25 feb '24 03 mar '24 10 mar '24 17 mar '24 24 mar '24 31 mar '24 07 abr '24 14 abr '24 21 abr '24 28 abr '24 05 may '24 12 may '24 19 may '24 26 may '24
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
350 1.5.2 SISTEMA DE DESAGUE 63 días sáb 24/02/24 sáb 27/04/24
352 1.5.2.1.1 SALIDA DE DESAGUE DE PVC 2" 14 días mar 05/03/24 mar 19/03/24 358
353 1.5.2.1.2 SALIDA DE DESAGUE DE PVC 4" 7 días mar 05/03/24 mar 12/03/24 352CC
354 1.5.2.1.3 SALIDA DE VENTILACION DE PVC 2" 5 días mar 05/03/24 dom 10/03/24 353CC
356 1.5.2.2.1 RED DE DISTRIBUCION PVC-UF DN 3 días sáb 24/02/24 mar 27/02/24 141
1600MM
357 1.5.2.2.2 RED DE DISTRIBUCION PVC SAP 8 días sáb 24/02/24 dom 03/03/24 356CC
PARA DESAGUE 4"
358 1.5.2.2.3 RED DE DISTRIBUCION PVC SAP 10 días sáb 24/02/24 mar 05/03/24 357CC
PARA DESAGUE 2"
359 1.5.2.2.4 RED DE DISTRIBUCION PVC SAP 2 días sáb 24/02/24 lun 26/02/24 358CC
PARA VENTILACION 2"
362 1.5.2.3.1.1 CODO PVC-SAP 2" * 90º 3 días mar 05/03/24 vie 08/03/24 358
363 1.5.2.3.1.2 CODO PVC-SAP 2" * 45º 2 días mar 05/03/24 jue 07/03/24 362CC
364 1.5.2.3.1.3 CODO PVC-SAP 4" * 90º 1 día mar 05/03/24 mié 06/03/24 363CC
365 1.5.2.3.1.4 CODO PVC-SAP 4" * 45º 1 día mar 05/03/24 mié 06/03/24 364CC
366 1.5.2.3.1.5 CODO SANITARIO PVC-SAP 4" * 1 día mar 05/03/24 mié 06/03/24 365CC
90º CON REDUCCION A 2"
368 1.5.2.3.2.1 TEE PVC-SAP DE 2" 1 día mié 06/03/24 jue 07/03/24 366
369 1.5.2.3.2.2 TEE PVC-SAP DE 4" 1 día mié 06/03/24 jue 07/03/24 368CC
371 1.5.2.3.3.1 YEE PVC-SAP DE 2" 2 días jue 07/03/24 sáb 09/03/24 369
372 1.5.2.3.3.2 YEE PVC-SAP DE 4" 2 días jue 07/03/24 sáb 09/03/24 371CC
373 1.5.2.3.3.3 YEE PVC-SAP DE 4" A 2" 2 días jue 07/03/24 sáb 09/03/24 372CC
375 1.5.2.4.1 SUMIDERO DE BRONCE 2" 2 días lun 22/04/24 mié 24/04/24 345
376 1.5.2.4.2 REGISTRO DE BRONCE 2" 1 día lun 22/04/24 mar 23/04/24 375CC
377 1.5.2.4.3 REGISTRO DE BRONCE 4" 2 días lun 22/04/24 mié 24/04/24 376CC
378 1.5.2.4.4 REDUCCION PVC SAP DE 4" A 2" 1 día lun 22/04/24 mar 23/04/24 377CC
379 1.5.2.4.5 CAJA DE RGISTRO DE 18"X24" 5 días lun 22/04/24 sáb 27/04/24 378CC
380 1.5.3 SISTEMA DE DRENAJE PLUVIAL 8 días mar 05/03/24 mié 13/03/24
382 1.5.3.1.1 RED DE DISTRIBUCION PVC SAP 8 días mar 05/03/24 mié 13/03/24 358
PARA DESAGUE 4"
384 1.5.3.2.1 CODO PVC-SAP 4" * 90º 1 día mar 05/03/24 mié 06/03/24 382CC
385 1.5.3.2.2 TEE PVC-SAP DE 4" 5 días mar 05/03/24 dom 10/03/24 384CC
387 1.5.4.1 TRAMPA DE GRASA EN COCINA 1 día mié 13/03/24 jue 14/03/24 382
388 1.5.5 SISTEMA DE AGUA FRIA 200 días lun 02/10/23 vie 19/04/24
389 1.5.5.1 SALIDAS DE AGUA FRIA 14 días lun 02/10/23 lun 16/10/23
390 1.5.5.1.1 SALIDA DE AGUA FRIA PVC C-10 Ø 14 días lun 02/10/23 lun 16/10/23
1/2"
391 1.5.5.1.2 SALIDA DE AGUA FRIA PVC C-10 Ø 1" 6 días lun 02/10/23 dom 08/10/23
392 1.5.5.2 REDES DEL SISTEMA DE AGUA 37 días sáb 24/02/24 lun 01/04/24
393 1.5.5.2.1 TRAZO NIVEL Y REPLANTEO PARA 1 día sáb 24/02/24 dom 25/02/24 141
AGUA
394 1.5.5.2.2 EXCAVACION DE ZANJA TN TUBERIA 1 día dom 25/02/24 lun 26/02/24 393
PARA AGUA
395 1.5.5.2.3 REFINE, NIVELACION Y 2 días lun 26/02/24 mié 28/02/24 394
CONFORMACION DE FONDOS PARA
AGUA
396 1.5.5.2.4 CAMA DE APOYO PARA TUBERÍAS 2 días mié 28/02/24 vie 01/03/24 395
(E=10CM)
397 1.5.5.2.5 RELLENO Y COMPACTACION DE 1 día dom 31/03/24 lun 01/04/24 402
ZANJA TUBERIA PARA AGUA
398 1.5.5.2.6 TUBERIA PVC SAP C-10 D=3/4" 1 día vie 01/03/24 sáb 02/03/24 396
(REDES DE ALIMENTADOR)
399 1.5.5.2.7 TUBERIA PVC SAP C-10 D=11/2" 9 días sáb 02/03/24 lun 11/03/24 398
(ALIMENTACION - IMPULSION)
400 1.5.5.2.8 TUBERIA PVC SAP C-10 D=1" 10 días lun 11/03/24 jue 21/03/24 399
(DISTRIBUCION)
401 1.5.5.2.9 TUBERIA PVC SAP C-10 D=1/2" 8 días jue 21/03/24 vie 29/03/24 400
(DISTRIBUCION)
402 1.5.5.2.10 TUBERIA PVC SAP C-10 D=2" 2 días vie 29/03/24 dom 31/03/24 401
(REVOSE Y LIMPIEZA SUCCION)
403 1.5.5.3 ACCESORIOS DE REDES DE AGUA 48 días sáb 02/03/24 vie 19/04/24
404 1.5.5.3.1 ACCESORIOS DE REDES DE AGUA 33 días sáb 02/03/24 jue 04/04/24
405 1.5.5.3.1.1 CODO DE COBRE 1 1/2" X 90º 1 día sáb 02/03/24 dom 03/03/24 399CC
406 1.5.5.3.1.2 CODO DE COBRE 1" x 90º 5 días lun 11/03/24 sáb 16/03/24 400CC
407 1.5.5.3.1.3 CODO DE COBRE 1/2" x 90º 4 días jue 21/03/24 lun 25/03/24 401CC
408 1.5.5.3.1.4 REDUCCION DE COBRE 1 1/2" - 1 día dom 03/03/24 lun 04/03/24 405
1/2"
409 1.5.5.3.1.5 TEE DE COBRE 1/2" 1 día lun 25/03/24 mar 26/03/24 407
410 1.5.5.3.1.6 TEE DE COBRE 1" 3 días sáb 16/03/24 mar 19/03/24 406
411 1.5.5.3.1.7 TEE DE COBRE 1 1/2" 1 día dom 03/03/24 lun 04/03/24 405
412 1.5.5.3.1.8 REDUCCION DE COBRE 1 1/2" - 1" 1 día lun 04/03/24 mar 05/03/24 411
413 1.5.5.3.1.9 REDUCCION DE COBRE 1" - 1/2" 2 días mar 19/03/24 jue 21/03/24 410
414 1.5.5.3.1.10 UNION UNIVERSAL PVC SAP Ø 1 3 días jue 21/03/24 dom 24/03/24 413
1/2"
415 1.5.5.3.1.11 UNION UNIVERSAL PVC SAP Ø 1" 3 días dom 24/03/24 mié 27/03/24 414
416 1.5.5.3.1.12 UNION UNIVERSAL PVC SAP Ø 1/2" 1 día mié 27/03/24 jue 28/03/24 415
417 1.5.5.3.1.13 UNION UNIVERSAL PVC SAP Ø 2" 1 día jue 28/03/24 vie 29/03/24 416
418 1.5.5.3.1.14 UNION UNIVERSAL PVC SAP Ø 3/4" 1 día vie 29/03/24 sáb 30/03/24 417
419 1.5.5.3.1.15 NIPLE ROSCADO PVC SAP Ø 1 1/2" 1 día sáb 30/03/24 dom 31/03/24 418
X3
420 1.5.5.3.1.16 ADAPTADOR CON ROSCA PVC 1 día dom 31/03/24 lun 01/04/24 419
SAP Ø 1 1/2"
421 1.5.5.3.1.17 CANASTILLA PVC SAP Ø 1 1/2" 1 día lun 01/04/24 mar 02/04/24 420
422 1.5.5.3.1.18 SOMBRERO DE VENTILACION PVC 1 día mar 02/04/24 mié 03/04/24 421
SAL Ø 2"
423 1.5.5.3.1.19 VALVULA FLOTADOR 1 día mié 03/04/24 jue 04/04/24 422
425 1.5.5.3.2.1 TUBERIA DE F° G° DE 2" 1 día dom 31/03/24 lun 01/04/24 402
426 1.5.5.3.2.2 CODO DE F° G° 2" X 90° 1 día dom 31/03/24 lun 01/04/24 425CC
427 1.5.5.3.2.3 TEE DE F° G° 2" x 2" 1 día lun 01/04/24 mar 02/04/24 426
428 1.5.5.3.2.4 UNION UNIVERSAL F° GVDO Ø2" 2 días lun 01/04/24 mié 03/04/24 427CC
429 1.5.5.3.2.5 VALVULA DE PIE Ø2" 1 día mié 03/04/24 jue 04/04/24 428
430 1.5.5.3.2.6 VALVULA COMP. DE BRONCE DE 1 día jue 04/04/24 vie 05/04/24 429
2"
431 1.5.5.3.2.7 VALVULA CHECK Ø 2" 1 día vie 05/04/24 sáb 06/04/24 430
(IMPULSION)
432 1.5.5.3.2.8 VALVULA ESFERICA DE PASO 1 1 día sáb 06/04/24 dom 07/04/24 431
1/2" PVC
433 1.5.5.3.2.9 VALVULA ESFERICA DE PASO 1" 4 días dom 07/04/24 jue 11/04/24 432
PVC
434 1.5.5.3.2.10 VALVULA ESFERICA DE PASO 1/2" 1 día jue 11/04/24 vie 12/04/24 433
PVC
435 1.5.5.3.2.11 VALVULA ESFERICA DE PASO 3/4" 1 día vie 12/04/24 sáb 13/04/24 434
PVC
437 1.5.5.3.3.1 PRUEBA HIDRAULICA DE AGUA 4 días sáb 13/04/24 mié 17/04/24 435
POTABLE TUB. PVC
438 1.5.5.3.4 EQUIPOS Y OTRAS INSTALACIONES 2 días mié 17/04/24 vie 19/04/24
439 1.5.5.3.4.1 BOMBA DE AGUA C=1.91 LTS/SEG. 1 día mié 17/04/24 jue 18/04/24 437
POT=1.5.00 HP
440 1.5.5.3.4.2 SISTEMA HIDRONEUMATICO 1 día jue 18/04/24 vie 19/04/24 439
441 1.5.6 SISTEMA DE AGUA CALIENTE 21 días lun 01/04/24 lun 22/04/24
442 1.5.6.1 SALIDAS DE AGUA CALIENTE 4 días dom 14/04/24 jue 18/04/24
443 1.5.6.1.1 SALIDA DE AGUA CALIENTE CPVC 4 días dom 14/04/24 jue 18/04/24 451
C-10 Ø 1/2"
444 1.5.6.2 REDES DE DISTRIBUCION DE AGUA 4 días lun 01/04/24 vie 05/04/24
CALIENTE
445 1.5.6.2.1 TUBERIA CPVC PRESION Ø 1/2" 4 días lun 01/04/24 vie 05/04/24 425
446 1.5.6.3 ACCESORIOS DE REDES DE AGUA 4 días vie 05/04/24 mar 09/04/24
CALIENTE
447 1.5.6.3.1 CODO CPVC 1/2"x 90º 3 días vie 05/04/24 lun 08/04/24 445
448 1.5.6.3.2 TEE CPVC 1/2"x1/2" 1 día lun 08/04/24 mar 09/04/24 447
449 1.5.6.4 VALVULAS DE AGUA CALIENTE 5 días mar 09/04/24 dom 14/04/24
450 1.5.6.4.1 VALVULA COMP. DE BRONCE DE 1/2" 2 días mar 09/04/24 jue 11/04/24 448
451 1.5.6.4.2 UNION UNIVERSAL CPVC SAP Ø 1/2" 3 días jue 11/04/24 dom 14/04/24 450
452 1.5.6.5 EQUIPOS DE PRODUCCION DE AGUA 4 días jue 18/04/24 lun 22/04/24
CALIENTE
453 1.5.6.5.1 SUMINISTRO E INSTALACION DE 4 días jue 18/04/24 lun 22/04/24 443
THERMA ELECTRICAS -50 LITROS
454 1.6 SISTEMA CONTRA INCENDIO 187 días lun 02/10/23 sáb 06/04/24
456 1.6.1.1 TRAZO NIVEL Y REPLANTEO PARA ACI 1 día sáb 24/02/24 dom 25/02/24 141
457 1.6.1.2 EXCAVACION DE ZANJA TN TUBERIA 1 día dom 25/02/24 lun 26/02/24 456
PARA ACI
458 1.6.1.3 REFINE, NIVELACION Y 1 día lun 26/02/24 mar 27/02/24 457
CONFORMACION DE FONDOS PARA ACI
459 1.6.1.4 CAMA DE APOYO PARA TUBERIAS 1 día mar 27/02/24 mié 28/02/24 458
(E=10CM) PARA ACI
460 1.6.1.5 RELLENO Y COMPACTACION DE ZANJA 1 día vie 05/04/24 sáb 06/04/24 478
TUBERIA PARA ACI
461 1.6.2 RED DE DISTRIBUCIÓN SISTEMA CONTRA 7 días mié 28/02/24 mié 06/03/24
INCENDIO
462 1.6.2.1 TUBERIA DE ACERO SCHEDULE 40 Ø 4" 6 días mié 28/02/24 mar 05/03/24 459
(ALIMENTADOR - MONTANTE)
463 1.6.2.2 TUBERIA DE ACERO SCHEDULE 40 Ø 2" 1 día mar 05/03/24 mié 06/03/24 462
(DISTRIBUCION COLGANTE)
464 1.6.3 ACCESORIOS RED DE SIST. CONTRA 1 día mar 05/03/24 mié 06/03/24
INCENDIO
465 1.6.3.1 CODO SCHEDULE 40 4 x 90° UNION 1 día mar 05/03/24 mié 06/03/24 463CC
ROSCADA
466 1.6.3.2 CODO SCHEDULE 40 2 x 90° UNION 1 día mar 05/03/24 mié 06/03/24 465CC
ROSCADA
467 1.6.3.3 TEE SCHEDULE 40 4" UNIÓN ROSCADA 1 día mar 05/03/24 mié 06/03/24 466CC
468 1.6.3.4 TEE SCHEDULE 40 2" UNION 1 día mar 05/03/24 mié 06/03/24 467CC
ROSCADA03.06.02.01 TEE ACERO
SCHEDULE 40 4" x 4"
470 1.6.4.1 GABINETE CONTRA INCENDIO 5 días lun 02/10/23 sáb 07/10/23
471 1.6.5 VÁLVULAS DE SISTEMA CONTRA 1 día mié 06/03/24 jue 07/03/24
INCENDIO
472 1.6.5.1 UNIÓN SIAMESA 4" 1 día mié 06/03/24 jue 07/03/24 468
Proyecto: PROGRAMACIÓN CH Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha límite División crítica Progreso manual
Fecha: mié 02/08/23 División Resumen Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Hito externo Tareas críticas Progreso
Página 5
Id Modo de EDT Nombre de tarea Duración Comienzo Fin Predecesoras 01 oct '23 08 oct '23 15 oct '23 22 oct '23 29 oct '23 05 nov '23 12 nov '23 19 nov '23 26 nov '23 03 dic '23 10 dic '23 17 dic '23 24 dic '23 31 dic '23 07 ene '24 14 ene '24 21 ene '24 28 ene '24 04 feb '24 11 feb '24 18 feb '24 25 feb '24 03 mar '24 10 mar '24 17 mar '24 24 mar '24 31 mar '24 07 abr '24 14 abr '24 21 abr '24 28 abr '24 05 may '24 12 may '24 19 may '24 26 may '24
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V
473 1.6.6 INSTALACIONES ESPECIALES 28 días jue 07/03/24 jue 04/04/24
474 1.6.6.1 SUMINISTRO E INSTALACIÓN DE 5 días jue 07/03/24 mar 12/03/24 472
SOPORTE DE TUBERÍAS (TECHO)
475 1.6.6.2 EQUIPO DE BOMBEO CONTRA INCENDIO 20 días mar 12/03/24 lun 01/04/24 474
476 1.6.6.3 ACCESORIOS VARIOS EN CUARTO DE 3 días lun 01/04/24 jue 04/04/24 475
BOMBAS
477 1.6.7 PRUEBA HIDRÁULICA Y DESINFECCIÓN DE 1 día jue 04/04/24 vie 05/04/24
SCI
478 1.6.7.1 PRUEBA HIDRÁULICA DE AGUA 1 día jue 04/04/24 vie 05/04/24 476
POTABLE TUB.
480 1.7.1 CAPACITACION Y SENSIBILIZACION DE 1 día dom 28/04/24 lun 29/04/24 482CF
OBRA
482 1.8.1 EQUIPAMIENTO C.S. CHINCHE 30 días lun 29/04/24 mié 29/05/24 248
483 1.9 PLAN DE MANEJO AMBIENTAL 212 días mar 03/10/23 jue 02/05/24
484 1.9.1 PROGRAMA DE MANEJO DE RESIDUOS 212 días mar 03/10/23 jue 02/05/24
SÓLIDOS Y LÍQUIDOS
485 1.9.1.1 PROGRAMA DE MANEJO DE RESIDUOS 29 días mar 03/10/23 mié 01/11/23
SÓLIDOS Y LÍQUIDOS
487 1.9.1.1.2 MANEJO DE RESIDUOS SÓLIDOS 6 días mar 17/10/23 lun 23/10/23 486
COMUNIDADES (RECOJO, TRASLADO,
TRANSPORTE Y DISPOSICIÓN FINAL)
488 1.9.1.1.3 MANEJO Y DISPOSICIÓN FINAL DE 3 días lun 23/10/23 jue 26/10/23 487
RESIDUOS PELIGROSOS.
489 1.9.1.1.4 MANEJO DE RESIDUOS LÍQUIDOS (04 6 días jue 26/10/23 mié 01/11/23 488
BAÑOS PORTÁTILES) (LIMPIEZA Y
DISPOSICIÓN FINAL DE RESIDUOS
LÍQUIDOS)
491 1.9.1.2.1 SUBPROGRAMA DE SEGURIDAD VIAL 6 días mar 03/10/23 lun 09/10/23 486CC
Y SEÑALIZACIÓN AMBIENTAL
493 1.9.1.3.1 ESPECIALISTA EN SEGURIDAD Y 6 días lun 09/10/23 dom 15/10/23 491
SALUD OCUPACIONAL
494 1.9.1.3.2 CONTINGENCIA ANTE EVENTOS 1 día lun 09/10/23 mar 10/10/23 493CC
NATURALES, INCENDIOS, ETC.
495 1.9.1.3.3 EQUIPOS DE EMERGENCIAS 1 día lun 09/10/23 mar 10/10/23 494CC
497 1.9.1.4.1 MONITOREO DE CALIDAD DE RUIDO 6 días jue 19/10/23 mié 25/10/23 39
AMBIENTAL (1 ESTACIÓN DE
MONITOREO EN LA ZONA DEL
PROYECTO)
498 1.9.1.4.2 MONITOREO DE LA CALIDAD DEL 3 días mié 25/10/23 sáb 28/10/23 497
AIRE (1 ESTACIÓN DE MONITOREO
EN LA ZONA DEL PROYECTO)
499 1.9.1.5 PROGRAMA DE ASUNTOS SOCIALES 3 días lun 29/04/24 jue 02/05/24
500 1.9.1.5.1 MEDIDAS DE PARTICIPACIÓN 3 días lun 29/04/24 jue 02/05/24 480
CIUDADANA Y RELACIONES
COMUNITARIAS
501 1.9.1.6 PLAN DE CIERRE Y/O ABANDONO 159 días jue 23/11/23 mar 30/04/24
503 1.9.1.6.2 LIMPIEZA DE ÁREAS INTERVENIDAS 1 día vie 24/11/23 sáb 25/11/23 502
504 1.9.1.6.3 RETIRO DE INSTALACIONES 1 día lun 29/04/24 mar 30/04/24 482CC
Proyecto: PROGRAMACIÓN CH Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha límite División crítica Progreso manual
Fecha: mié 02/08/23 División Resumen Tarea inactiva Resumen inactivo solo duración Resumen manual solo fin Hito externo Tareas críticas Progreso
Página 6