CRONOGRAMA

PROYECTO : RECUPERACION DEL SERVICIO DEL PUENTE CARROZABLE SOBRE EL RIO RAMIS DEL DISTRITO DE SAN ANTON-PROVINCIA DE AZANGARO-DEPARTAMENTO DE PUNO
ETAPA 1.0 : PUENTE SAN ANTON
PROPIETARIO : NINGUNO
UBICACION : DPTO:PUNO PROV:AZANGARO DIST:SAN ANTON
FECHA PROYECTO : 01/06/2022
15/06/2022 19/06/2022 26/06/2022 03/07/2022 10/07/2022 17/07/2022 24/07/2022 31/07/2022 07/08/2022 14/08/2022 21/08/2022 28/08/2022 04/09/2022 11/09/2022 18/09/2022 25/09/2022 02/10/2022 09/10/2022 16/10/2022 23/10/2022 30/10/2022 06/11/2022 13/11/2022 20/11/2022 27/11/2022 04/12/2022 11/12/2022 18/12/2022 25/12/2022 01/01/2023 08/01/2023 15/01/2023 22/01/2023 29/01/2023 05/02/2023 12/02/20…
Item Descripción Duracion Inicio Fin
M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M

1.0 PUENTE SAN ANTON 245 días 15/06/2022 14/02/2023

1.1 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 59 días 15/06/2022 12/08/2022

1.1.1 OBRAS PROVISIONALES 35 días 16/06/2022 20/07/2022

1 día
1.1.1.1 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60M X 2.40M 1 días 16/06/2022 16/06/2022

1 día
1.1.1.2 CAMPAMENTO P/OFICINA GUARDIANIA Y/O DEPOSITO 1 días 08/07/2022 08/07/2022

3 días
1.1.1.3 CERCO PERIMETRICO 3 días 09/07/2022 11/07/2022

9 días
1.1.1.4 ENCAUSAMIENTO DE CURSOS DE AGUA R=300 M3/DIA(A.D) 9 días 12/07/2022 20/07/2022

1.1.2 ZONAS DE PREVENCION 3 días 01/08/2022 03/08/2022

1 día
1.1.2.1 ZONA DE CONTROL PREVIO 1 días 01/08/2022 01/08/2022

1 día
1.1.2.2 ZONA DE CONTROL DE DESINFECCION 1 días 02/08/2022 02/08/2022

1 día
1.1.2.3 ZONA DE VESTUARIO 1 días 03/08/2022 03/08/2022

1.1.3 INSTALACIONES PROVISIONALES 2 días 04/08/2022 05/08/2022

1 día
1.1.3.1 SERVICIO PROVISIONAL DE AGUA 1 días 04/08/2022 04/08/2022

1 día
1.1.3.2 SERVICIO PROVISIONAL DE ENERGIA ELECTRICA 1 días 05/08/2022 05/08/2022

MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y


1.1.4 3 días 06/08/2022 08/08/2022
HERRAMIENTAS
1 día
1.1.4.1 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA 1 días 06/08/2022 06/08/2022

1 día
1.1.4.2 TRANSPORTE DE MATERIAL A OBRA 1 días 08/08/2022 08/08/2022

1.1.5 DEMOLICIONES 35 días 09/07/2022 12/08/2022

15 días
1.1.5.1 DEMOLICION PUENTE EXISTENTE SUB ESTRUCTURA 15 días 09/07/2022 23/07/2022

15 días
1.1.5.2 DEMOLICION PUENTE EXISTENTE SUPERESTRUCTURA 15 días 24/07/2022 07/08/2022

5 días
1.1.5.3 ELIMINACION DE MATERIAL DE REMOCION Y/O DEMOLICION 5 días 08/08/2022 12/08/2022

1.1.6 TRABAJOS PRELIMINARES 41 días 15/06/2022 25/07/2022

2 días
1.1.6.1 TRAZO, NIVELACION Y REPLANTEO 2 días 15/06/2022 16/06/2022

3 días
1.1.6.2 TRAZO Y REPLANTEO DURANTE LA OBRA 3 días 04/07/2022 06/07/2022

1 día
1.1.6.3 LIMPIEZA Y DESFORESTACION R=1.0 HA/DIA 1 días 25/07/2022 25/07/2022

1.2 SEGURIDAD Y SALUD 66 días 28/07/2022 01/10/2022

ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN


1.2.1 57 días 28/07/2022 22/09/2022
DE SEGURIDAD Y SALUD EN EL TRABAJO
1 día
1.2.1.1 EQUIPOS DE PROTECCION INDIVIDUAL 1 días 28/07/2022 28/07/2022

1 día
1.2.1.2 SEÑALIZACION TEMPORAL EN SEGURIDAD 1 días 22/09/2022 22/09/2022

1.2.2 MEDIDAD PREVENTIVAS 7 días 25/09/2022 01/10/2022

1 día
1.2.2.1 PROTECCION PERSONAL COVID-19 1 días 25/09/2022 25/09/2022

1 día
1.2.2.2 MATERIAL Y/O EQUIPO PARA PREVENCION COVID-19 1 días 28/09/2022 28/09/2022

1 día
1.2.2.3 SEÑALIZACION PARA PREVENCION 1 días 01/10/2022 01/10/2022

1.3 MOVIMIENTO DE TIERRAS 66 días 13/08/2022 17/10/2022

1.3.1 MOVIMIENTO DE TIERRAS 56 días 13/08/2022 07/10/2022

4 días
1.3.1.1 CORTE DE MATERIAL SUELTO 4 días 13/08/2022 16/08/2022

2 días
1.3.1.2 EXCAVACION PARA ZAPATAS EN MATERIAL SECO 2 días 17/08/2022 18/08/2022

8 días
1.3.1.3 EXCAVACION PARA ZAPATAS BAJO AGUA 8 días 21/08/2022 28/08/2022

4 días
1.3.1.4 RELLENO CON MATERIAL PROPIO 4 días 29/08/2022 01/09/2022

6 días
1.3.1.5 CARGUIO Y TRANSPORTE DE MATERIAL DE PRESTAMO 6 días 03/09/2022 08/09/2022

15 días
1.3.1.6 RELLENO CON MATERIAL DE PRESTAMO CON EQUIPO LIVIANO 15 días 12/09/2022 26/09/2022

8 días
1.3.1.7 ELIMINACION DE MATERIAL EXCEDENTE 8 días 30/09/2022 07/10/2022

1.3.2 CONFORMACION DE BASE PARA FALSO PUENTE 8 días 10/10/2022 17/10/2022

8 días
1.3.2.1 RELLENO COMPACTADO C/MATERIAL PROPIO 8 días 10/10/2022 17/10/2022

1.4 OBRAS DE CONCRETO SIMPLE 78 días 19/08/2022 04/11/2022

1.4.1 OBRAS DE CONCRETO SIMPLE 78 días 19/08/2022 04/11/2022

16 días
1.4.1.1 SUB ZAPATA Cº CICLOPEO F'C=140 KG/CM2 +30% PG 16 días 19/08/2022 03/09/2022

4 días
1.4.1.2 FALSO PISO PARA APOYO DE FALSO PUENTE 4 días 29/10/2022 01/11/2022

3 días
1.4.1.3 CONCRETO F'C=140 KG/CM2 PARA ANCLAJES Y/O DADOS 3 días 02/11/2022 04/11/2022

4 días
1.4.1.4 SOLADOS CONCRETO F'C=100 KG/CM2, E=4" 4 días 25/10/2022 28/10/2022

1.5 OBRAS DE CONCRETO ARMADO 115 días 03/09/2022 26/12/2022

1.5.1 SUB ESTRUCTURAS 94 días 03/09/2022 05/12/2022

1.5.1.1 ZAPATAS EN ESTRIBOS Y PILAR 52 días 03/09/2022 24/10/2022

20 días
1.5.1.1.1 CONCRETO PARA ZAPATAS F'C=210 KG/CM2 20 días 05/10/2022 24/10/2022

12 días
1.5.1.1.2 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS 12 días 23/09/2022 04/10/2022

20 días
1.5.1.1.3 ZAPATAS- ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 20 días 03/09/2022 22/09/2022

1.5.1.2 ESTRIBO 27 días 25/10/2022 20/11/2022

3 días
1.5.1.2.1 CONCRETO F'C=280 KG/CM2 EN ESTRIBOS 3 días 18/11/2022 20/11/2022

14 días
1.5.1.2.2 ENCOFRADO Y DESENCOFRADO PARA ESTRIBOS 14 días 04/11/2022 17/11/2022

10 días
1.5.1.2.3 ACERO CORRUGADO FY=4200 KG/CM2 P/ ESTRIBOS 10 días 25/10/2022 03/11/2022

1.5.1.3 PILARES 30 días 08/10/2022 06/11/2022

3 días
1.5.1.3.1 CONCRETO F'C=280 KG/CM2 EN PILAR 3 días 08/10/2022 10/10/2022

6 días
1.5.1.3.2 ENCOFRADO Y DESENCOFRADO EN PILAR 6 días 16/10/2022 21/10/2022

17 días
1.5.1.3.3 ACERO CORRUGADO FY=4200 KG/CM2 P/PILAR 17 días 21/10/2022 06/11/2022

1.5.1.4 ALEROS 16 días 20/11/2022 05/12/2022

7 días
1.5.1.4.1 CONCRETO F'C=210 KG/CM2 P/ALEROS 7 días 29/11/2022 05/12/2022

4 días
1.5.1.4.2 ENCOFRADO Y DESENCOFRADO P/ALEROS 4 días 25/11/2022 28/11/2022

5 días
1.5.1.4.3 ACERO CORRUGADO FY=4200 KG/CM2 P/ALEROS 5 días 20/11/2022 24/11/2022

1.5.2 SUPERESTRUCTURA 21 días 06/12/2022 26/12/2022

1.5.2.1 VIGAS PRINCIPALES Y DIAFRAGMAS 20 días 06/12/2022 25/12/2022

CONCRETO F'C=280 KG/CM2 EN VIGAS PRINCIPALES Y 2 días


1.5.2.1.1 2 días 24/12/2022 25/12/2022
DIAFRAGMAS
10 días
1.5.2.1.2 ENCOFRADO Y DESENCOFRADO P/VIGA P. Y DIAFRAGMA 10 días 14/12/2022 23/12/2022

10 días
1.5.2.1.3 ACERO CORRUGADO FY=4200 KG/CM2 P/VIGA P. Y DIAFRAGMAS 10 días 06/12/2022 15/12/2022

1.5.2.2 LOSA MACISA 11 días 16/12/2022 26/12/2022

2 días
1.5.2.2.1 CONCRETO F'C=280 KG/CM2 EN LOSA MACISA 2 días 25/12/2022 26/12/2022

5 días
1.5.2.2.2 ENCOFRADO Y DESENCOFRADO P/LOSAS MACISAS 5 días 20/12/2022 24/12/2022

4 días
1.5.2.2.3 ACERO CORRUGADO FY=4200 KG/CM2 P/LOSAS MACIZAS 4 días 16/12/2022 19/12/2022

1.6 ELEMENTOS COMPLEMENTARIOS 138 días 31/08/2022 15/01/2023

1.6.1 VEREDAS DE CONCRETO 19 días 20/12/2022 07/01/2023

1 día
1.6.1.1 CONCRETO F'C=280 KG/CM2 PARA VEREDAS 1 días 07/01/2023 07/01/2023

5 días
1.6.1.2 ENCOFRADO Y DESENCOFRADO PARA VEREDAS 5 días 25/12/2022 29/12/2022

5 días
1.6.1.3 ACERO CORRUGADO FY=4200 KG/CM2 P/VEREDAS 5 días 20/12/2022 24/12/2022

1.6.2 BARANDAS 2 días 14/01/2023 15/01/2023

2 días
1.6.2.1 BARANDAS PARA PUENTES SEGUN DISEÑO 2 días 14/01/2023 15/01/2023

1.6.3 LOSA DE APROXIMACION 14 días 05/10/2022 18/10/2022

2 días
1.6.3.1 CONCRETO F'C=210 KG/CM2 PARA LOSA 2 días 05/10/2022 06/10/2022

2 días

Pág. 1 de 3
15/06/2022 19/06/2022 26/06/2022 03/07/2022 10/07/2022 17/07/2022 24/07/2022 31/07/2022 07/08/2022 14/08/2022 21/08/2022 28/08/2022 04/09/2022 11/09/2022 18/09/2022 25/09/2022 02/10/2022 09/10/2022 16/10/2022 23/10/2022 30/10/2022 06/11/2022 13/11/2022 20/11/2022 27/11/2022 04/12/2022 11/12/2022 18/12/2022 25/12/2022 01/01/2023 08/01/2023 15/01/2023 22/01/2023 29/01/2023 05/02/2023 12/02/20…
Item Descripción Duracion Inicio Fin
M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M
1.6.3.2 ENCOFRADO Y DESENCOFRADO PARA LOSA 2 días 10/10/2022 11/10/2022

6 días
1.6.3.3 ACERO CORRUGADO FY=4200 KG/CM2 P/LOSA 6 días 13/10/2022 18/10/2022

1.6.4 FALSO PUENTE 30 días 31/08/2022 29/09/2022

30 días
1.6.4.1 CONSTRUCCION DE FALSO PUENTE 30 días 31/08/2022 29/09/2022

1.7 VARIOS 127 días 03/10/2022 06/02/2023

1.7.1 VARIOS 98 días 01/11/2022 06/02/2023

1 día
1.7.1.1 TUBERIA PVC SAL 2" 1 días 01/11/2022 01/11/2022

4 días
1.7.1.2 JUNTAS DE DILATACION METALICAS 4 días 07/12/2022 10/12/2022

8 días
1.7.1.3 APOYO DE NEOPRENE 0.50 X 0.50 X 0.05 8 días 02/11/2022 09/11/2022

ACABADO PULIDO DE VEREDAS CON MORTERO 1:2 X 1.5 CM DE 5 días


1.7.1.4 5 días 11/11/2022 15/11/2022
ESPESOR
3 días
1.7.1.5 PLACA RECORDATORIA DE BRONCE 3 días 04/02/2023 06/02/2023

3 días
1.7.1.6 GUARDAVIAS DE FIERRO GALVANIZADO R=10 MOD/DIA 3 días 18/11/2022 20/11/2022

1 día
1.7.1.7 TERMINALES DE GUARDAVIAS R=5 UND/DIA 1 días 22/11/2022 22/11/2022

1.7.2 SEÑALES INFORMATIVAS 11 días 31/12/2022 10/01/2023

1 día
1.7.2.1 PÌNTURA DE FILO DE VEREDAS 1 días 31/12/2022 31/12/2022

FABRICACION DE SEÑALES INFORMATIVAS PANELES 3 días


1.7.2.2 3 días 03/01/2023 05/01/2023
INFORMATIVOS
1 día
1.7.2.3 COLOCACION DE SEÑALES INFORMATIVAS 1 días 06/01/2023 06/01/2023

4 días
1.7.2.4 PORTICO DE FIJACION DE SEÑALES INFORMATIVAS 4 días 07/01/2023 10/01/2023

1.7.3 SISTEMA DE ILUMINACION SOLAR 1 días 20/01/2023 20/01/2023

1 día
1.7.3.1 SISTEMA FOTOVOLTAICO DE ILUMINACION SOLAR 1 días 20/01/2023 20/01/2023

1.7.4 PRUEBAS DE LABORATORIO 24 días 03/10/2022 26/10/2022

3 días
1.7.4.1 PRUEBA DE CALIDAD DE CONCRETO (PRUEBA A LA COMPRESION) 3 días 03/10/2022 05/10/2022

1 día
1.7.4.2 DISEÑO DE MEZCLAS 1 días 26/10/2022 26/10/2022

1.8 TRABAJOS PRELIMINARES 48 días 16/06/2022 02/08/2022

1.8.1 TRAZO Y REPLANTEO 48 días 16/06/2022 02/08/2022

3 días
1.8.1.1 TRAZO Y REPLANTEO 3 días 16/06/2022 18/06/2022

4 días
1.8.1.2 TRAZO Y REPLANTEO DURANTE LA OBRA 4 días 30/07/2022 02/08/2022

1.9 MOVIMIENTO DE TIERRAS 156 días 04/08/2022 06/01/2023

1.9.1 CORTES 14 días 04/08/2022 17/08/2022

1.9.1.1 CORTES 14 días 04/08/2022 17/08/2022

3 días
1.9.1.1.1 CORTE DE TERRENO CON MAQUINARIA D 1KM 3 días 04/08/2022 06/08/2022

3 días
1.9.1.1.2 ELIMINACION DE MATERIAL EXCEDENTE 3 días 10/08/2022 12/08/2022

2 días
1.9.1.1.3 PERFILADO Y COMPACTADO DE SUBRASANTE 2 días 16/08/2022 17/08/2022

1.9.2 ENROCADO 11 días 27/12/2022 06/01/2023

1.9.2.1 ENROCADO 4 días 27/12/2022 30/12/2022

4 días
1.9.2.1.1 MEJORAMIENTO DE SUB RASANTE CON ENROCADO 4 días 27/12/2022 30/12/2022

1.9.2.2 CAPA NIVELANTE 7 días 31/12/2022 06/01/2023

1 día
1.9.2.2.1 EXTRACCION DE APILAMIENTO DE MATERIAL DE PRESTAMO 1 días 31/12/2022 31/12/2022

2 días
1.9.2.2.2 CARGUIO Y TRANSPORTE DE MATERIAL PARA CAPA NIVELANTE 2 días 01/01/2023 02/01/2023

CONFORMACION DE CAPA NIVELANTE CON MATERIAL DE 4 días


1.9.2.2.3 4 días 03/01/2023 06/01/2023
PRESTAMO

1.10 SUB BASE 13 días 07/01/2023 19/01/2023

1.10.1 MATERIAL DE PRESTAMO 1 días 07/01/2023 07/01/2023

1 día
1.10.1.1 SUMINISTRO DE HORMIGON PARA SUB BASE (MEZCLA 60%) 1 días 07/01/2023 07/01/2023

1.10.2 MATERIAL SELECCIONADO 7 días 08/01/2023 14/01/2023

EXTRACCION Y APILAMIENTO DE MATERIAL SELECCIONADO 2 días


1.10.2.1 2 días 08/01/2023 09/01/2023
(MEZCLA 40%)
4 días
1.10.2.2 ZARANDEADO DE MATERIAL SELECCIONADO 4 días 10/01/2023 13/01/2023

1 día
1.10.2.3 CARGUIO Y TRANSPORTE DE MATERIAL SELECCIONADO 1 días 14/01/2023 14/01/2023

1.10.3 CONFORMACION DE SUB BASE 5 días 15/01/2023 19/01/2023

MEZCLADO DE MATERIAL DE PRESTAMO 60% Y SELECCIONADO 1 día


1.10.3.1 1 días 15/01/2023 15/01/2023
40%
1 día
1.10.3.2 CARGUIO Y TRANSPORTE DE MATERIAL MEZCLADO 1 días 16/01/2023 16/01/2023

3 días
1.10.3.3 CONFORMACION DE SUB BASE E=0.20M 3 días 17/01/2023 19/01/2023

1.11 PAVIMENTO RIGIDO 20 días 20/01/2023 08/02/2023

1.11.1 PAVIMENTO RIGIDO 20 días 20/01/2023 08/02/2023

4 días
1.11.1.1 PAVIMENTO RIGIDO: CONCRETO F'C=210 KG/CM2 4 días 30/01/2023 02/02/2023

4 días
1.11.1.2 PAVIMENTO RIGIDO: ENCOFRADO Y DESENCOFRADO 4 días 20/01/2023 23/01/2023

5 días
1.11.1.3 PAVIMENTO RIGIDO: CURADO DE LOSA 5 días 04/02/2023 08/02/2023

6 días
1.11.1.4 PAVIMENTO RIGIDO: JUNTAS ASFALTICA 6 días 24/01/2023 29/01/2023

1.12 VEREDAS 13 días 30/01/2023 11/02/2023

1.12.1 VEREDAS 13 días 30/01/2023 11/02/2023

2 días
1.12.1.1 VEREDAS: (AFIRMADO + BOLONERIA) E=0.20M 2 días 30/01/2023 31/01/2023

VEREDAS: CONCRETO F'C =175 KG/CM2 E=10 CM, ACABADO 4 días


1.12.1.2 4 días 01/02/2023 04/02/2023
COLOREADO, FROTACHADO Y BRUÑADO C:A 1:2
4 días
1.12.1.3 VEREDAS: ENCOFRADO Y DESENCOFRADO 4 días 05/02/2023 08/02/2023

1 día
1.12.1.4 VEREDA: CURADO DE LOSA 1 días 09/02/2023 09/02/2023

2 días
1.12.1.5 VEREDA: JUNTA ASFALTICA 2 días 10/02/2023 11/02/2023

1.13 SARDINELES 7 días 29/01/2023 04/02/2023

1.13.1 SARDINELES 7 días 29/01/2023 04/02/2023

1 día
1.13.1.1 SARDINEL: CONCRETO F'C=175 KG/CM2 1 días 29/01/2023 29/01/2023

4 días
1.13.1.2 SARDINEL: ENCOFRADO Y DESENCOFRADO 4 días 30/01/2023 02/02/2023

2 días
1.13.1.3 SARDINEL: JUNTA ASFALTICA 2 días 03/02/2023 04/02/2023

1.14 RAMPAS 2 días 05/02/2023 06/02/2023

1.14.1 RAMPAS 2 días 05/02/2023 06/02/2023

RAMPAS: CONCRETO F'C=175 KG/CM2 E=10 CM, ACABADO, 1 día


1.14.1.1 1 días 06/02/2023 06/02/2023
COLOREADO,FROTACHADO Y BRUÑADO C:A 1:2
1 día
1.14.1.2 RAMPAS: ENCOFRADO Y DESENCOFRADO 1 días 05/02/2023 05/02/2023

1.15 VARIOS 167 días 01/09/2022 14/02/2023

1.15.1 VARIOS 167 días 01/09/2022 14/02/2023

2 días
1.15.1.1 LIMPIEZA FINAL DE OBRA 2 días 13/02/2023 14/02/2023

1 día
1.15.1.2 DISEÑO DE MEZCLA DE CANTERA 1 días 01/09/2022 01/09/2022

1 día
1.15.1.3 DISEÑO DE MEZCLA DE CONCRETO 1 días 02/09/2022 02/09/2022

1 día
1.15.1.4 SOMBRILLA 1 días 12/02/2023 12/02/2023

1 día
1.15.1.5 ROTURA DE BRIQUETAS 1 días 05/09/2022 05/09/2022

1.16 OBRAS DE ENCAUSAMIENTO DE AGUA 212 días 15/06/2022 12/01/2023

1.16.1 TRABAJOS PRELIMINARES 107 días 15/06/2022 29/09/2022

2 días
1.16.1.1 TRAZO Y REPLANTEO 2 días 15/06/2022 16/06/2022

2 días
1.16.1.2 TRAZO Y REPLANTEO DURANTE LA OBRA 2 días 05/09/2022 06/09/2022

8 días
1.16.1.3 DEMOLICION DE INFRAESTRUCTURA EXISTENTE 8 días 07/09/2022 14/09/2022

5 días
1.16.1.4 ELIMINACION DE MATERIAL CON MAQUINARIA 5 días 25/09/2022 29/09/2022

1.16.2 ENCAUSAMIENTO DE CURSO DE AGUA 102 días 03/10/2022 12/01/2023

5 días
1.16.2.1 ENCAUSAMIENTO DE CURSOS DE AGUA R=350 M3/DIA 5 días 03/10/2022 07/10/2022

1 día
1.16.2.2 GAVIONES-SUMINISTRO E INSTALACION 5 X1.0 X 1.5M 1 días 12/10/2022 12/10/2022

12 días
1.16.2.3 GAVIONES-SUMINISTRO E INSTALACION 5 X1.0 X 1.0M 12 días 02/11/2022 13/11/2022

Pág. 2 de 3
15/06/2022 19/06/2022 26/06/2022 03/07/2022 10/07/2022 17/07/2022 24/07/2022 31/07/2022 07/08/2022 14/08/2022 21/08/2022 28/08/2022 04/09/2022 11/09/2022 18/09/2022 25/09/2022 02/10/2022 09/10/2022 16/10/2022 23/10/2022 30/10/2022 06/11/2022 13/11/2022 20/11/2022 27/11/2022 04/12/2022 11/12/2022 18/12/2022 25/12/2022 01/01/2023 08/01/2023 15/01/2023 22/01/2023 29/01/2023 05/02/2023 12/02/20…
Item Descripción Duracion Inicio Fin
M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M
1 día
1.16.2.4 GAVIONES-SUMINISTRO E INSTALACION 5 X1.0 X 0.5M 1 días 17/11/2022 17/11/2022

5 días
1.16.2.5 GAVIONES-SUMINISTRO E INSTALACION 5 X0.3 X 2.75M 5 días 08/01/2023 12/01/2023

1.17 OBRAS DE MITIGACION DE IMPACTO AMBIENTAL 14 días 30/01/2023 12/02/2023

1.17.1 OBRAS DE MITIGACION DE IMPACTO AMBIENTAL 14 días 30/01/2023 12/02/2023

4 días
1.17.1.1 REACONDICIONAMIENTO AREA OCUPADA POR CAMPAMENTO 4 días 30/01/2023 02/02/2023

4 días
1.17.1.2 REACONDICIONAMIENTO AREA OCUPADA POR MAQUINARIA 4 días 05/02/2023 08/02/2023

1 día
1.17.1.3 REFORESTACION 1 días 12/02/2023 12/02/2023