CRONOGRAMA INSTALACION DE TUBERIAS - GMD CHOTA

ID Task Name Duration Start Finish Thu 08 May Fri 09 May Sat 10 May Sun 11 May Mon 12 May Tue 13 May Wed 14 May Thu 15 May Fri 16 May Sat 17 May Sun 18 May Mon 19 May Tue 20 May Wed 21 May Thu 22 May Fri 23 May Sat 24 May Sun 25 May Mon 26 May Tue 27 May Wed 28 May Thu 29 May Fri 30 May
0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18
1 INSTALACION DE TUBERIAS DE 2 days Thu Sat 10/05/14
REFRIGERACION - SALA 08/05/14
TELECOM1

2 Instalación de soportería 3 hours Thu 08/05/14Thu 08/05/14

3 Trazo de tuberías de Cu 2 hours Thu 08/05/14Fri 09/05/14

4 Instalación de tuberías de Cu 4 hours Fri 09/05/14 Fri 09/05/14

5 Soldeo de tuberías de Cu 4 hours Fri 09/05/14 Sat 10/05/14

6 Instalación de enchaquetado de 3 hours Sat Sat 10/05/14


armaflex 10/05/14

7 INSTALACION DE TUBERIAS DE 2,13 days Sat Tue 13/05/14


REFRIGERACION - SALA 10/05/14
TELECOM2

8 Instalación de soportería 3 hours Sat 10/05/14Mon 12/05/14

9 Trazo de tuberías de Cu 2 hours Mon 12/05/14


Mon 12/05/14

10 Instalación de tuberías de Cu 4 hours Mon 12/05/14


Mon 12/05/14

11 Soldeo de tuberías de Cu 4 hours Tue 13/05/14Tue 13/05/14

12 Instalación de enchaquetado de 4 hours Tue Tue 13/05/14


armaflex 13/05/14

13 INSTALACION DE TUBERIAS DE 2 days Wed Thu 15/05/14


REFRIGERACION - CINTOTECA 14/05/14

14 Instalación de soportería 3 hours Wed 14/05/14


Wed 14/05/14

15 Trazo de tuberías de Cu 2 hours Wed 14/05/14


Wed 14/05/14

16 Instalación de tuberías de Cu 4 hours Wed 14/05/14


Thu 15/05/14

17 Soldeo de tuberías de Cu 4 hours Thu 15/05/14Thu 15/05/14

18 Instalación de enchaquetado de 3 hours Thu Thu 15/05/14


armaflex 15/05/14

19 Sala de UPS habilitada para 0 days Thu Thu 15/05/14 15/05


tendido de tuberías 15/05/14

20 INSTALACION DE TUBERIAS DE 2,88 days Fri Tue 20/05/14


REFRIGERACION - SALA UPS 16/05/14

21 Instalación de soportería 3 hours Fri 16/05/14 Fri 16/05/14

22 Trazo de tuberías de Cu 3 hours Fri 16/05/14 Fri 16/05/14

23 Instalación de tuberías de Cu 6 hours Fri 16/05/14 Sat 17/05/14

24 Soldeo de tuberías de Cu 8 hours Sat 17/05/14Mon 19/05/14

25 Instalación de enchaquetado de 3 hours Mon Tue 20/05/14


armaflex 19/05/14

26 INSTALACION DE TUBOS DATA 4 days Tue Sat 24/05/14


CENTER (VERTICAL) 20/05/14

27 Instalación de soportería 6 hours Tue 20/05/14Tue 20/05/14

28 Trazo de tuberías de Cu 4 hours Wed 21/05/14


Wed 21/05/14

29 Instalación de tuberías de Cu 8 hours Wed 21/05/14


Thu 22/05/14

30 Soldeo de tuberías de Cu 8 hours Thu 22/05/14Fri 23/05/14

31 Instalación de enchaquetado de armaflex


6 hours Fri 23/05/14 Sat 24/05/14

32 Sala de UPS habilitada para 0 days Mon Mon 26/05/14 26/05


tendido de tuberías 26/05/14

33 INSTALACION DE TUBOS DATA 4 days Mon Fri 30/05/14


CENTER (HORIZONTAL) 26/05/14

34 Instalación de soportería 6 hours Mon 26/05/14


Mon 26/05/14

35 Trazo de tuberías de Cu 4 hours Mon 26/05/14


Tue 27/05/14

36 Instalación de tuberías de Cu 8 hours Tue 27/05/14Wed 28/05/14

37 Soldeo de tuberías de Cu 8 hours Wed 28/05/14


Thu 29/05/14

38 Instalación de enchaquetado de armaflex


6 hours Thu 29/05/14Fri 30/05/14

Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Project: Project1 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress