PRESUPUESTO

ITEM DESCRIPCION UND METRADO PRECIO S/. PARCIAL S/.


1 OBRAS PROVISONALES
1.1 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS, HERRAMIENTAS Y MATERIALES GLB 1.00 S/. 2,000.00 S/. 2,000.00

1.2 TOPOGRAFIA M2 1250.00 S/. 1.50 S/. 1,875.00


1.3 EQUIPAMIENTO DE SEGURIDAD Y SEGUROS GLB 1.00 S/. 4,000.00 S/. 4,000.00
1.4 PAZ SOCIAL GLB 1.00 S/. 3,000.00 S/. 3,000.00
1.5 VIGIA MES 2.00 S/. 2,000.00 S/. 4,000.00
1.6 EXAMENES MEDICOS UND 30.00 S/. 200.00 S/. 6,000.00
1.7 ANDAMIOS NORMADOS MES 1.00 S/. 4,000.00 S/. 4,000.00
1.8 OFICINA DE OBRA M2 12.00 S/. 150.00 S/. 1,800.00
1.9 ALMACEN DE OBRA M2 24.00 S/. 150.00 S/. 3,600.00
1.10 VESTUARIO Y COMEDOR M2 60.00 S/. 150.00 S/. 9,000.00
1.11 REPARACION DE INSTALACIONES EXISTENTES GLB 1.00 S/. 2,000.00 S/. 2,000.00
1.12 CERCO DE POSTES Y MALLA Y SEÑALIZACIÓN GLB 1.00 S/. 1,500.00 S/. 1,500.00
2 TRABAJOS PRELIMINARES
2.1 LIMPIEZA DE TERRENO M2 1250.00 S/. 1.10 S/. 1,375.00
2.2 TRAZO Y REPLANTEO M2 1250.00 S/. 1.50 S/. 1,875.00
3 DEMOLICIONES
3.1 DEMOLICION DE ESTRUCTURAS M3 25.00 S/. 80.00 S/. 2,000.00
3.2 ELIMINACION DE MATERIAL EXCEDENTE M3 45.00 S/. 40.00 S/. 1,800.00
4 MOVIEMIENTO DE TIERRAS
4.1 NIVELACION DE TERRENO M2 378.00 S/. 1.70 S/. 642.60
4.2 EXCAVACION DE TERRENO M3 220.00 S/. 25.00 S/. 5,500.00
4.3 RELLENO CON MATERIAL PROPIO M3 85.00 S/. 22.00 S/. 1,870.00
4.4 ELIMINACION DE MATERIAL EXCEDENTE M3 180.00 S/. 40.00 S/. 7,200.00
5 OBRAS DE CONCRETO SIMPLE
5.1 FALSA ZAPATA
5.1.1 CONCRETO FC=100KG/CM2 E=10CM M3 30.00 S/. 30.00 S/. 900.00
5.1.2 ENCOFRADO Y DESENCOFRADO M2 55.20 S/. 20.00 S/. 1,104.00
5.2 SOLADO
5.2.1 CONCRETO FC=100KG/CM2 E=10CM M3 20.00 S/. 50.00 S/. 1,000.00
5.2.2 ENCOFRADO Y DESENCOFRADO M2 35.00 S/. 20.00 S/. 700.00
5.3 FALSO PISO
5.3.1 CONCRETO FC=100KG/CM2 E=10CM M2 105.00 S/. 25.00 S/. 2,625.00
6 OBRAS DE CONCRETO ARMADO
6.1 ZAPATA
6.1.1 CONCRETO FC=210KG/CM2 E=10CM M3 62.40 S/. 70.00 S/. 4,368.00
6.1.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 1,615.19 S/. 2.50 S/. 4,037.98
6.1.3 ENCOFRADO Y DESENCOFRADO M2 105.20 S/. 35.00 S/. 3,682.00
6.2 VIGA DE CIMENTACION
6.1.1 CONCRETO FC=175KG/CM2 E=10CM M3 7.50 S/. 70.00 S/. 525.00
6.1.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 742.80 S/. 2.50 S/. 1,857.00
6.1.3 ENCOFRADO Y DESENCOFRADO M2 53.80 S/. 57.00 S/. 3,066.60
6.3 SOBRECIMIENTO
6.3.1 CONCRETO FC=175KG/CM2 E=10CM M3 11.54 S/. 70.00 S/. 807.80
6.3.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 706.50 S/. 2.50 S/. 1,766.25
6.3.3 ENCOFRADO Y DESENCOFRADO M2 85.00 S/. 55.00 S/. 4,675.00
6.4 COLUMNAS
6.4.1 CONCRETO FC=280KG/CM2 E=10CM M3 70.00 S/. 100.00 S/. 7,000.00
6.4.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 10,000.00 S/. 2.50 S/. 25,000.00
6.4.3 ENCOFRADO Y DESENCOFRADO M2 580.00 S/. 62.00 S/. 35,960.00
6.5 VIGAS
6.5.1 CONCRETO FC=280KG/CM2 E=10CM M3 32.00 S/. 100.00 S/. 3,200.00
6.5.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 3,599.20 S/. 2.50 S/. 8,998.00
6.5.3 ENCOFRADO Y DESENCOFRADO M2 137.00 S/. 60.00 S/. 8,220.00
6.6 LOSA
6.6.1 CONCRETO FC=210KG/CM2 E=10CM M3 25.00 S/. 80.00 S/. 2,000.00
6.6.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 1,205.00 S/. 2.50 S/. 3,012.50
6.6.3 ENCOFRADO Y DESENCOFRADO M2 256.00 S/. 48.00 S/. 12,288.00
6.6.4 LADRILLOS, BLOQUES HUECOS UND 2334.00 S/. 8.00 S/. 18,672.00
6.7 MUROS REFORZADOS
6.7.1 CONCRETO FC=210KG/CM2 E=10CM M3 3.00 S/. 100.00 S/. 300.00
6.7.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 157.30 S/. 2.50 S/. 393.25
6.7.3 ENCOFRADO Y DESENCOFRADO M2 20.00 S/. 55.00 S/. 1,100.00
6.8 PLACAS
6.8.1 CONCRETO FC=280KG/CM2 E=10CM M3 11.20 S/. 100.00 S/. 1,120.00
6.8.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 791.50 S/. 2.50 S/. 1,978.75
6.8.3 ENCOFRADO Y DESENCOFRADO M2 85.00 S/. 55.00 S/. 4,675.00
6.9 ESCALERAS
6.9.1 CONCRETO FC=210KG/CM2 E=10CM M3 9.81 S/. 150.00 S/. 1,471.50
6.9.2 ACERO DE REFUERZO FY=4200KG/CM2 KG 448.00 S/. 2.50 S/. 1,120.00
6.9.3 ENCOFRADO Y DESENCOFRADO M2 55.92 S/. 60.00 S/. 3,355.20
6.9.4 ESCARIFICADO DE ELEMETOS ESTRUCTURALES M2 141.20 S/. 20.00 S/. 2,824.00
6.9.5 ADHERENCIA M2 141.20 S/. 15.00 S/. 2,118.00
7 ARQUITECTURA
7.1 MUROS Y TABIQUES DE ALBAÑILERIA
7.1.1 MURO DE LADRILO KK APAREJO DE SOGA
7.1.1.1 MURO DE LADRILLO KK Y PANDERETA M2 648.00 S/. 35.00 S/. 22,680.00
7.2 REVOQUES Y REVESTIMIENTOS
7.2.1 TARRAJEO PRIMARIO
7.2.1.1 TARRAJEO PRIMARIO M2 230.00 S/. 15.00 S/. 3,450.00
7.2.2 TARRAJEO EN INTERIORES
7.2.2.1 PRIMER Y SEGUNDO PISO M2 706.20 S/. 20.00 S/. 14,124.00
7.2.3 TARRAJEO DE EXTERIORES
7.2.3.1 PRIMER Y SEGUNDO PISO M2 330.00 S/. 25.00 S/. 8,250.00
7.2.4 TARRAJEO DE COLUMNAS
7.2.4.1 PRIMER Y SEGUNDO PISO M2 660.00 S/. 25.00 S/. 16,500.00
7.2.5 TARRAJEO DE VIGAS
7.2.5.1 PRIMER Y SEGUNDO PISO M2 315.00 S/. 40.00 S/. 12,600.00
7.2.6 TARRAJEO DE MUROS DE CONCRETO
7.2.6.1 PRIMER Y SEGUNDO PISO M2 46.00 S/. 25.00 S/. 1,150.00
7.2.7 VESTIDURA DE DERRAMES
7.2.7.1 PRIMER Y SEGUNDO PISO M 430.00 S/. 10.00 S/. 4,300.00
7.2.8 TARRAJEO DE FONDO DE ESCALERA
7.2.8.1 TARRAJEO DE FONDO DE ESCALERA M2 30.00 S/. 25.00 S/. 750.00
7.2.9 TARRAJEO DE GRADAS
7.2.9.1 TARRAJEO DE GRADAS ML 19.80 S/. 20.00 S/. 396.00
7.2.10 TARRAJEO DE DESCANSO
7.2.10.1 TARRAJEO DE DESCANSO M2 11.00 S/. 25.00 S/. 275.00
7.2.11 CIELO RASO
7.2.11.1 PRIMER PISO M2 350.00 S/. 25.00 S/. 8,750.00
7.2.12 JUNTA DE DILATACION
7.2.12.1 JUNTA DE DILATACION 1" ML 300 S/. 5.00 S/. 1,500.00

PERFORACION Y ANCLAJE UND 730 S/. 26.00 S/. 18,980.00


LOSA DE PISO DE CONCRETO M2 80 S/. 30.00 S/. 2,400.00
CURADO M2 1650 S/. 2.50 S/. 4,125.00
VIGA PARA RE-UBICACIÓN DEL MASTIL GLB 1 S/. 380.00 S/. 380.00
APUNTALAMIENTO M2 490 S/. 40.00 S/. 19,600.00

COSTO DIRECTO S/. 381,168.43


GASTOS GENERALES S/. 68,700.00
UTILIDAD S/. 30,493.47
SUB TOTAL S/. 480,361.90
IGV S/. 86,465.14
TOTAL S/. 566,827.04