DATOS:
Luz = 8.00 m Ancho de carril = 3.80 m A. barre = 0.40 m
A.F.B = 8.40 m Asfalto = 2.0 ” 0.05 m C.V = HL-93
fy = 4200 kg/cm² P. barrera = 600 kg/cm²
f`c losa = 280 kg/cm² h. barrera = 0.70 m
⟫ Sección Longitunidal:
Losa de C. A. t
A B
L = 8.00 m
⟫ Sección Transversal:
E.C
0.40 m 3.80 m 3.80 m 0.40 m
Carril 01 Carril 02
2% 2%
0.70 m
A. F. B. = 8.40 m
A.- PRE-DIMENSIONAMIENTO:
1.2 * (s + 3 ) s = 8.0 m
Tmin =
30
2
MDC = W * L / 8 = 1.08 * 8.00 m / 8 = 8.64 T-m
2
MDW = W * L / 8 = 0.11 * 8.00 m / 8 = 0.91 T-m
3.52 T R = 7.62 T
0.952 T-m
0.952 T-m RA = 3.81 T
RB = 3.81 T
3.70 m
Mm = 7.57 T-m
L = 8.00 m
− M(LL + IM)
E = 2.1 + 0.12 L1 * W1 ≤ W
NL
ESTADOS LIMITES
Carga M(+) T-m
Carga M(+) T-m
Resistencia I Servicio I Fatiga I
DC 8.64 T-m 1.25 1.00 0.00
DW 0.91 T-m 1.50 1.00 0.00
LL+IM 19.22 T-m 1.75 1.00 1.75
Resistencia I = 1.25 * 8.640 T-m + 1.50 * 0.910 T-m + 1.75 * 19.22 T-m
Resistencia I = 45.797 T-m
Servicio I = 1.00 * 8.640 T-m + 1.00 * 0.910 T-m + 1.00 * 19.22 T-m
Servicio I = 28.769 T-m
Fatiga I = 0.00 * 8.640 T-m + 0.00 * 0.910 T-m + 1.75 * 19.22 T-m
Fatiga I = 33.632 T-m
d= 45 cm - 3.770 cm = 41.230 cm
0.45 cm Ø = 1"
z= 2.5 cm + 2.54 / 2 = 3.770 cm
b = 100.00 cm Mu 45.80
d = 41.230 cm As 32.65
f'c = 280 kg/cm² a 5.762
fy = 4200 kg/cm² 1° It. 2° It. 3° It. 4° It.
Mu = 45.797 T-m As 32.65 31.59 31.52 31.51096
a 5.762 5.575 5.562 5.56076
As = 31.51 cm²
5.07 cm²
Utilizando varillas Ø = 1" la separación será: s = = 0.161 m
31.51 cm²
* Acero mínimo :
Mu > Mcr
Mcr = 1.1 * fr * s
Mu > Mcr ES
45.797 T-m > 12.48652 T-m OK ➞ OBLIGATORIO
QUE DE OK.
*As de Distribución:
PARALELO AL TRÁFICO
55 Smáx = 0.45 m
% = ≤ 67 %
√s
55
% = = 19.4 % ≤ 67 % Cumple ➞ 19.4 %
8.0 m
1.98 cm²
Utilizando varillas Ø = 5/8" la separación será: s = = 0.3231 m Ok
6.1274 cm²
*As de Temperatura:
758.4 * 840 cm * 45 cm
As temp = = 3.86 cm²
2 * ( 840 cm + 45 cm ) * 4200 kg/cm²
Condición:
2.33 cm²/m ≤ As temp ≤ 12.70 cm²/m
1.29 cm²
Utilizando varillas Ø = 1/2" la separación será: s = = 0.3345 m Ok
3.86 cm²
* Momento Actuante :
Servicio I = SI
S𝖨 = 28.7685 T-m
0.16 m
fn (-)
y/3
C
y
C
y
Eje Neutro
y
45.0 cm @ 0.16 d = 41.230 cm jd = d-y/3
-
1"
41.23
T
z= 3.770 cm (fs/n) (+)
y = 12.144 cm
y 12.14 cm
Jd = d - = 41.23 cm - = 37.18 cm
3 3
125 000 * Ye Ye = 1
Smax = - 2 * dc
βs * Fss
dc 3.770 cm
βs = 1 + = 1 + = 1.1306
0.7 *( h - dc ) 0.7 *( 45 cm - 3.770 cm )
125000 * Ye
Smax = - 2 * dc
βs * Fss
125000 * 1
Smax = - 2 * 3.770 cm = 37.74 cm
1.131 * 2441.72 kg/cm²
0.5 P 0.5 P
0.40 m 0.30 m 1.80 m E.C 0.40 m
Camion ó tanden
0.45 m
0.77 m
L= 8.4 m
3.00 m
E. Borde = 1.47 m
2
MDC = W * L / 8 = 1.49 * 8.00 ² m / 8 = 11.91 T-m
2
MDW = W * L / 8 = 0.08 * 8.00 ² m / 8 = 0.66 T-m
0.30 m + 0.77 m
0.50 * 38.81 T-m * 1.33 + 7.57 T-m *( )
M(LL+IM) = 3.00 m
1.47 m
ESTADOS LIMITES
Carga M(+) T-m
Resistencia I Servicio I Fatiga I
DC 11.91 T-m 1.25 1.00 0.00
DW 0.66 T-m 1.50 1.00 0.00
LL+IM 19.39 T-m 1.75 1.00 1.75
Resistencia I = 1.25 * 11.905 T-m + 1.50 * 0.663 T-m + 1.75 * 19.39 T-m
Resistencia I = 49.817 T-m
Servicio I = 1.00 * 11.905 T-m + 1.00 * 0.663 T-m + 1.00 * 19.39 T-m
Servicio I = 31.963 T-m
Fatiga I = 0.00 * 11.905 T-m + 0.00 * 0.663 T-m + 1.75 * 19.39 T-m
Fatiga I = 33.941 T-m
d= 45 cm - 3.770 cm = 41.230 cm
0.45 m Ø = 1"
z= 2.5 cm + 2.54 / 2 = 3.770 cm
b = 100.00 cm Mu 49.82
d = 41.230 cm As 35.52
f'c = 280 kg/cm² a 6.268
fy = 4200 kg/cm² 1° It. 2° It. 3° It. 4° It.
Mu = 49.817 T-m As 35.52 34.59 34.52 34.51439
a 6.268 6.105 6.092 6.09078
As = 34.51 cm²
5.07 cm²
Utilizando varillas Ø = 1" la separación será: s = = 0.147 m
34.51 cm²
* Acero mínimo :
Mu > Mcr
Mcr = 1.1 * fr * s
Mu > Mcr ES
49.817 T-m > 12.49 T-m OK ➞ OBLIGATORIO
QUE DE OK.
*As de Distribución:
PARALELO AL TRÁFICO
55 Smáx = 0.45 m
% = ≤ 67 %
√s
55
% = = 19.4 % ≤ 67 % Cumple ➞ 19.4 %
8.0 m
1.98 cm²
Utilizando varillas Ø = 5/8" la separación será: s = = 0.2950 m Ok
6.7115 cm²
* Momento Actuante :
Servicio I = SI
S𝖨 = 31.9628 T-m
0.15 m
fn (-)
y/3
C
y
Eje Neutro
y
1"
41.23
T
z= 3.770 cm (fs/n) (+)
y = 12.471 cm
y 12.47 cm
Jd = d - = 41.23 cm - = 37.07 cm
3 3
r5
Ms * 10 4.79 T-m * 100000
Fss = = = 2550.8 kg/cm² ≤ 0.6 * Fy
jd * As 37.07 cm * 5.07 cm²
125 000 * Ye Ye = 1
Smax = - 2 * dc
βs * Fss
dc 3.770 cm
βs = 1 + = 1 + = 1.1306
0.7 *( h - dc ) 0.7 *( 45 cm - 3.770 cm )
125000 * Ye
Smax = - 2 * dc
βs * Fss
125000 * 1
Smax = - 2 * 3.77 cm = 36.33 cm
1.131 * 2520.00 kg/cm²
D.- FATIGA:
100 * 45 ²
» s = = 33750.00 cm³
6
» Como F fat = 68.49 kg/cm² > 13.39 kg/cm² ➞ Se usara la sección agrietada.
y 12.14 cm
Jd = d - = 41.23 cm - = 37.18 cm
3 3
45 cm
Nota 1 :
El acero de temperatura se colocará, por no contar con ningún tipo de acero, en la parte superior
de la losa, en ambos sentidos, y en las partes laterales ( As de temp Tran y As de temp Long).
Nota 2 :
Por facilidad en el colocado se uniformizará el resultado con el obtenido para la franja interior
As de distrib. F.I. 1∅ 5/8" @ 0.32 m adoptándose As de distrib. F.E. 1∅ 5/8" @ 0.30 m
0.40 m
HL-93
0.70 m
0.45 m
Ok
Fy
Ok
Fy
29.04 T-m
29.04 T-m
33.40 T-m
1151.30 kg/cm²
45 cm