1.00 PILOTES PP1 Cant. Unid. prec. Unit Total


1.01 Volumen de Excavacion 7.92 m3 Q 35.00 Q 277.36
1.02 Volumen de extraccion 11.09 m3 Q 35.00 Q 388.31
1.03 Volumen de concreto 7.92 m3 Q -
1.04 Cemento 71.32 cemento Q 80.00 Q 5,705.77
1.05 Arena 7.92 Arena Q 115.00 Q 911.34
1.06 Piedrin 7.92 Piedrin Q 200.00 Q 1,584.94
1.07 Varilla no.4 40.38 Var Q 68.00 Q 2,746.15
1.08 Varilla no.6 21.54 Var Q 158.00 Q 3,403.08
1.09 Alambre de amarre 15.00 lbs Q 7.50 Q 112.50
1.10 Mano de obra 7.00 ML Q 750.00 Q 5,250.00
TOTAL MATERIALES Q 20,379.45

TOTAL DE 12 PILOTES REQUERIDOS PARA PARQUEO Q 244,553.45

2.00 PILOTES PP2


2.01 Volumen de Excavacion 5.56 m3 Q 35.00 Q 194.62
2.02 Volumen de extraccion 7.78 m3 Q 35.00 Q 272.47
2.03 Volumen de concreto 5.56 m3 Q -
2.04 Cemento 50.05 cemento Q 80.00 Q 4,003.66
2.05 Arena 5.56 Arena Q 115.00 Q 639.47
2.06 Piedrin 5.56 Piedrin Q 200.00 Q 1,112.13
2.07 Varilla no.4 40.38 Var Q 68.00 Q 2,746.15
2.08 Varilla no.6 21.54 Var Q 158.00 Q 3,403.08
2.09 Alambre de amarre 15.00 lbs Q 7.50 Q 112.50
2.10 Mano de obra 7.00 ML Q 750.00 Q 5,250.00
TOTAL MATERIALES Q 17,734.08

TOTAL DE 20 PILOTES REQUERIDOS PARA PARQUEO Q 354,681.56

3.00 CAPITELES
3.01 Volumen de Excavacion 1.88 m3 Q 35.00 Q 65.63
3.02 Volumen de extraccion 2.63 m3 Q 35.00 Q 91.88
3.03 Volumen de concreto 0.94 m3 Q -
3.04 Cemento 8.44 cemento Q 80.00 Q 675.00
3.05 Arena 0.94 Arena Q 115.00 Q 107.81
3.06 Piedrin 0.94 Piedrin Q 200.00 Q 187.50
3.07 Varilla no.4 14.35 Var Q 68.00 Q 975.54
3.08 Varilla no.6 10.00 Var Q 158.00 Q 1,580.00
3.09 Alambre de amarre 15.00 lbs Q 7.50 Q 112.50
3.10 Mano de obra 1.00 Capiteles Q 2,500.00 Q 2,500.00
TOTAL MATERIALES Q 6,295.85

TOTAL DE 32 PILOTES REQUERIDOS PARA PARQUEO Q 201,467.23

4.00 SOLERA DE AMARRE


4.01 Volumen de Excavacion 37.52 m3 Q 35.00 Q 1,313.20
4.02 Volumen de extraccion 52.53 m3 Q 35.00 Q 1,838.48
4.03 Volumen de concreto 37.52 m3
4.04 Cemento 337.68 cemento Q 80.00 Q 27,014.40
4.05 Arena 37.52 Arena Q 115.00 Q 4,314.80
4.06 Piedrin 37.52 Piedrin Q 200.00 Q 7,504.00
4.07 Varilla no.5 309.23 Var Q 100.00 Q 30,923.08
4.08 Varilla no.3 687.18 Var Q 36.00 Q 24,738.46
4.09 Alambre de amarre 100.00 lbs Q 7.50 Q 750.00
4.10 Mano de obra 268.00 ml Q 115.00 Q 30,820.00
4.11 formaleta 30.00 tabla Q 225.00 Q 6,750.00
TOTAL MATERIALES Q 135,966.42
TOTAL DE SOLERA DE AMARRE SA-1 Q 135,966.42

5.00 COLUMNA C1
5.01 Volumen de concreto 1.03 m3
5.02 Cemento 9.23 cemento Q 80.00 Q 738.72
5.03 Arena 1.03 Arena Q 115.00 Q 117.99
5.04 Piedrin 1.03 Piedrin Q 200.00 Q 205.20
5.05 Varilla no.6 X 9 mts 6.00 Var Q 240.00 Q 1,440.00
5.06 Varilla no.4 36.54 Var Q 36.00 Q 1,315.38
5.07 Alambre de amarre 25.00 lbs Q 7.50 Q 187.50
5.08 Mano de obra 3.80 ml Q 450.00 Q 1,710.00
5.09 formaleta 4.00 tabla Q 225.00 Q 900.00
TOTAL MATERIALES Q 6,614.79

TOTAL DE 32 COLUMNAS DE 0.45X0.60 Q 211,673.43

TOTAL DE PILOTES+CAPITEL+SOLERA DE AMARRE + COLUMNA Q 924,168.09