Está en la página 1de 4

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.

50 M EJE 19
DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 21.86 0.25 5.465 50.552 2.863 3.937 1,435.042

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.50 M EJE 1'


DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 12.46 0.25 3.115 28.81 1.63 2.24 817.96

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.50 M EJE 2


DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 20.12 0.25 5.03 46.53 2.64 3.62 1,320.82

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.50 M EJE 3


DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 13.25 0.25 3.3125 30.64 1.74 2.39 869.82

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.50 M EJE 17 - 18


DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 3.48 0.25 0.87 8.05 0.46 0.63 228.45

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.50 M EJE B-M


DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 7.22 0.25 1.805 16.70 0.95 1.30 473.97

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.50 M EJE C - L


DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 76.42 0.25 19.105 176.72 10.01 13.76 5,016.74

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.50 M EJE E - J


DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 8.78 0.25 2.195 20.30 1.15 1.58 576.38

CANTIDAD DE MATERIAL A USAR PARA VIGAS DE 0.50 X 0.50 M EJE G - H


DESCRIPCION ALTO ANCHO LARGO AREA M² VOLUMEN M³ CEMENTO BOLSAS GRAVA M³ ARENA M³ AGUA Litros
VIGA VP-1 0.5 0.5 3.18 0.25 0.795 7.35 0.42 0.57 208.76

TOTAL M³ 41.69 385.66 21.84 30.03 10,947.94


I. INFORMACIÓN SOBRE EL DISEÑO DE MEZCLA Y PROPIEDADES DE LOS AGREGADOS

Resistencia a 28 días Cemento Agua


(psi)
Kilos/m3 Dos. Volumen UM Kilos/m3
1500 234 1 Saco 215
4000 467.5 1 Saco 280

II. CANTIDADES DE MATERIALES EN FUNCIÓN DE VOLUMENES DE CONCRETO A PRODUCIR

Resistencia requerida
II.a. 4000
(psi)
Volumen de concreto a
II.b. 1
colar

II.c. RESUMEN

Material
requerido UM

Cemento 11.00 Bolsas


Agua 280.20 Litros
Grava 3/4" 0.52 m3
Arena 0.48 m3
Agua Grava 3/4" Arena

Dos. Volumen UM Kilos/m3 Dos. Volumen UM Kilos/m3 Dos. Volumen


10.33 gal 1010.2 4.3 ft 3
952.3 4.1
6.73 gal 780 1.676 ft3 680 1.535

PROPORCIÓN POR VOLUMEN USADA

Resistencia Cemento Agua (Gal) Grava 3/4" (ft3) Arena (ft3)

1500 1 10.33 4.3 4.1


4000 1 6.73 1.676 1.535
Arena

UM
ft3
ft3