MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
02.01 EQUIPAMIENTO DE PROTECCION PERSONAL S/10,744.60 2,148.92 1,826.58 1,826.58 1,826.58 1,826.58 1,289.35
20% 17% 17% 17% 17% 12%
02.02 SEÑALES INFORMATIVAS S/123.00 24.60 20.91 20.91 20.91 20.91 14.76
20% 17% 17% 17% 17% 12%
02.03 SEÑALIZACION TEMPORAL DE SEGURIDAD S/839.73 167.95 142.75 142.75 142.75 142.75 100.77
20% 17% 17% 17% 17% 12%
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DE SEGURIDAD Y SALUD
02.04 S/2,500.00
EN EL TRABAJO 500.00 425.00 425.00 425.00 425.00 300.00
20% 17% 17% 17% 17% 12%
03 OBRAS PRELIMINARES S/3,226.28
MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
60% 40%
04.01.02.02 REFINE Y NIVELACION DE ZANJAS S/996.65 597.99 398.66
60% 40%
04.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE S/7,465.81 4,479.49 2,986.32
60% 40%
04.01.03 CONCRETO ARMADO
MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
100%
04.02.03.03 ENCOFRADO Y DESENCOFRADO DE MUROS RECTOS Y LOSA SUPERIOR S/1,727.62 1,727.62
100%
04.02.03.04 CONCRETO ARMADO f'c=210 kg/cm2 EN MUROS Y LOSA SUPERIOR S/2,702.46 2,702.46
100%
04.02.03.05 REJILLA PARA DREN COLECTOR S/5,677.74 5,677.74
100%
05 VEREDAS DE CONCRETO S/340,004.74
MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
06.01.01 TRAZO, REPLANTEO Y CONTROL TOPOGRÁFICO S/12,543.48 5,017.39 1,881.52 1,881.52 1,881.52 1,881.52
40% 15% 15% 15% 15%
06.02 MOVIMIENTO DE TIERRAS
MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
06.04.01 JUNTAS ASFALTICAS 1" X 4" CONTRACCION S/2,325.43 930.17 930.17 465.09
40% 40% 20%
06.04.02 JUNTAS ASFALTICAS 1" X 8" DILATACION S/1,189.85 475.94 475.94 237.97
40% 40% 20%
06.04.03 DOWELS EN JUNTAS DE DILATACION E=1PULG S/8,379.92 3,351.97 3,351.97 1,675.98
40% 40% 20%
06.04.04 CURADO DE ELEMENTOS DE CONCRETO S/28,500.69 11,400.28 11,400.28 5,700.14
40% 40% 20%
06.05 SEÑALIZACION
MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
08.03.01 CONCRETO CICLOPEO f'c=175 kg/cm2 + 30% P.G. -ESTRIBOS S/3,564.41 3,564.41
100%
08.03.02 TUBERIA DE PVC PARA DRENAJE S/81.44 81.44
100%
08.03.03 ENCOFRADO Y DESENCOFRADO NORMAL S/2,080.96 2,080.96
100%
CRONOGRAMA DE EJECUCION DE OBRA PROGRAMADO (EN FUNCION A LA FECHA DE INICO DE OBRA)
►ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE INDEPENDENCIA MONTO REFERENCIAL : S/ 2,818,259.17
“MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DE
TRANSITABILIDAD VEHICULAR Y PEATONAL DESDE EL CRUCE RÌO
CASCA HASTA LA INTERSECCIÓN ENTRE LOS JIRONES PALMA REAL Y
►OBRA MONTO CONTRATADO : S/ 2,746,370.73
FRANCISCO MAGUIÑA CONDOR EN EL CENTRO POBLADO DE
HUANCHAC, DISTRITO DE INDEPENDENCIA, PROVINCIA DE HUARAZ,
DEPARTAMENTO DE ANCASH”
►CONTRATISTA CONSORCIO VIAL CONCENTRU PLAZO DE EJECUCION (Dìas) : 150
►RESIDENTE ING. JULIÁN LUIS TARAZONA NEGRETE
►SUPERVISOR ING. JESÚS HUMBERTO MEJÍA YAURI FECHA DE INICIO : 12/09/22
►MODALIDA DE EJECUCION PRECIOS UNITARIOS FECHA DE TERMINO : 08/02/23
MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
08.04 CIMIENTOS
08.05.01 CONCRETO EN LOSA DE PUENTE f'c=210 kg/cm2 INC. FROTACHADO S/79,873.48 79,873.48
100%
08.05.02 ENCOFRADO Y DESENCOFRADO NORMAL S/270.22 270.22
100%
08.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/6,361.37 6,361.37
100%
08.05.04 JUNTA DE DILATACION S/3,110.80 3,110.80
100%
08.06 VIGA DE BORDE
09.01.01 LIMPIEZA Y DESINFECCION EN OBRA S/16,094.00 2,735.98 2,735.98 2,735.98 2,735.98 2,735.98 2,414.10
17% 17% 17% 17% 17% 15%
09.01.02 EVALUACION DE LA CONDICION DE SALUD DEL TRABAJADOR S/13,663.00 2,322.71 2,322.71 2,322.71 2,322.71 2,322.71 2,049.45
17% 17% 17% 17% 17% 15%
09.01.03 LAVADO Y DESINFECCION DE MANOS S/1,503.50 255.60 255.60 255.60 255.60 255.60 225.53
17% 17% 17% 17% 17% 15%
CRONOGRAMA DE EJECUCION DE OBRA PROGRAMADO (EN FUNCION A LA FECHA DE INICO DE OBRA)
►ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE INDEPENDENCIA MONTO REFERENCIAL : S/ 2,818,259.17
“MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DE
TRANSITABILIDAD VEHICULAR Y PEATONAL DESDE EL CRUCE RÌO
CASCA HASTA LA INTERSECCIÓN ENTRE LOS JIRONES PALMA REAL Y
►OBRA MONTO CONTRATADO : S/ 2,746,370.73
FRANCISCO MAGUIÑA CONDOR EN EL CENTRO POBLADO DE
HUANCHAC, DISTRITO DE INDEPENDENCIA, PROVINCIA DE HUARAZ,
DEPARTAMENTO DE ANCASH”
►CONTRATISTA CONSORCIO VIAL CONCENTRU PLAZO DE EJECUCION (Dìas) : 150
►RESIDENTE ING. JULIÁN LUIS TARAZONA NEGRETE
►SUPERVISOR ING. JESÚS HUMBERTO MEJÍA YAURI FECHA DE INICIO : 12/09/22
►MODALIDA DE EJECUCION PRECIOS UNITARIOS FECHA DE TERMINO : 08/02/23
MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
09.01.04 MEDIDAS PREVENTIVAS COLECTIVAS S/3,339.05 567.64 567.64 567.64 567.64 567.64 500.86
17% 17% 17% 17% 17% 15%
09.01.05 MEDIDAS PROTECCION PERSONAL S/2,600.00 442.00 442.00 442.00 442.00 442.00 390.00
17% 17% 17% 17% 17% 15%
09.02 EQUIPAMIENTO Y PERSONAL DE SEGURIDAD Y SALUD EN EL TRABAJO
MES DE PROGRAMACION
PARCIAL
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a
CONTRACTUAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
TOTAL COSTO DIRECTO 2,030,746.69 48,044.23 335,758.93 593,962.68 639,522.14 339,294.30 74,164.41
GASTO GENERALES (9.6097%) 195,148.80 4,616.91 32,265.45 57,078.07 61,456.20 32,605.19 7,126.98
UTILIDAD (8%) 162,459.74 3,843.54 26,860.71 47,517.01 51,161.77 27,143.54 5,933.17
SUB TOTAL PRESUPUESTO REFERENCIAL 2,388,355.23 56,504.68 394,885.09 698,557.76 752,140.11 399,043.03 87,224.56
0.974491899
SUB TOTAL PRESUPUESTO CONTRATADO 2,327,432.82 55,063.35 384,812.32 680,738.88 732,954.44 388,864.20 84,999.63
IGV 18% 418,937.91 9,911.40 69,266.22 122,533.00 131,931.80 69,995.56 15,299.93
TOTAL PRESUPUESTO 2,746,370.73 64,974.75 454,078.54 803,271.88 864,886.24 458,859.76 100,299.56
64,974.75 519,053.29 1,322,325.17 2,187,211.42 2,646,071.18 2,746,370.73
AVANCE PORCENTUAL 100.00% 2.37% 16.53% 29.25% 31.49% 16.71% 3.65%
PORCENTAJE ACUMULADO 2.37% 18.90% 48.15% 79.64% 96.35% 100.00%
CRONOGRAMA DE EJECUCION DE OBRA PROGRAMADO (EN FUNCION A LA FECHA DE INICO DE OBRA)
►ENTIDAD EJECUTORA MUNICIPALIDAD DISTRITAL DE INDEPENDENCIA MONTO REFERENCIAL S/ 2,818,259.17
MES DE PROGRAMACION
PARTIDA COMPONENTES Y/O METAS 12/09/2022 a 01/10/2022 a 01/11/2022 a 01/01/2021 a 01/01/2023 a 01/02/2022 a TOTAL
30/09/2022 31/10/2022 30/11/2022 11/01/2021 31/01/2023 08/02/2022
01 OBRAS PROVISIONALES
En Nuevos Soles S/. 5,876.470 300.000 5,421.840 300.000 150.000 150.000 12,198.31
En Porcentaje % 48.17% 2.46% 44.45% 2.46% 1.23% 1.23% 100.00%
02 SEGURIDAD EN OBRA
En Nuevos Soles S/. 2,841.466 2,415.246 2,415.246 2,415.246 2,415.246 1,704.880 14,207.33
En Porcentaje % 20.00% 17.00% 17.00% 17.00% 17.00% 12.00% 100.00%
03 OBRAS PRELIMINARES
En Nuevos Soles S/. 0.000 3,226.280 0.000 0.000 0.000 0.000 3,226.28
En Porcentaje % 0.00% 100.00% 0.00% 0.00% 0.00% 0.00% 100.00%
04 SISTEMA DE ALCANTARILLADO PLUVIAL
En Nuevos Soles S/. 387.105 63,655.145 197,257.081 8,516.520 5,677.740 0.000 275,493.59
0.14% 23.11% 71.60% 3.09% 2.06% 0.00% 100.00%
05 VEREDAS DE CONCRETO
En Nuevos Soles S/. 0.000 0.000 2,095.925 239,694.471 61,531.545 36,682.800 340,004.74
En Porcentaje % 0.00% 0.00% 0.62% 70.50% 18.10% 10.79% 100.00%
06 PAVIMENTO
En Nuevos Soles S/. 5,017.392 245,151.999 363,673.421 329,615.498 165,748.510 23,771.020 1,132,977.84
En Porcentaje % 0.44% 21.64% 32.10% 29.09% 14.63% 2.10% 100.00%
07 CUNETAS
En Nuevos Soles S/. 0.000 0.000 0.000 37,948.720 0.000 0.000 37,948.72
En Porcentaje % 0.00% 0.00% 0.00% 100.00% 0.00% 0.00% 100.00%
08 PONTON
En Nuevos Soles S/. 0.000 0.000 0.000 8,141.430 91,419.890 0.000 99,561.32
En Porcentaje % 0.00% 0.00% 0.00% 8.18% 91.82% 0.00% 100.00%
09 PLAN PARA LA VIGILANCIA, PREVENCION Y CONTROL DEL COVID-19 EN EL TRABAJO
En Nuevos Soles S/. 11,269.186 10,190.259 10,190.259 10,190.259 10,190.259 8,991.405 61,021.63
En Porcentaje % 18.47% 16.70% 16.70% 16.70% 16.70% 14.73% 100.00%
10 OTROS
En Nuevos Soles S/. 1.370 6,300.000 4,050.000 2,700.000 1,350.000 0.000 14,401.37
En Porcentaje % 0.01% 43.75% 28.12% 18.75% 9.37% 0.00% 100.00%
11 MITIGACION AMBIENTAL
En Nuevos Soles S/. 4,079.000 270.000 270.000 0.000 0.000 2,864.300 7,483.30
En Porcentaje % 54.51% 3.61% 3.61% 0.00% 0.00% 38.28% 100.00%
12 GESTION DE RIESGOS EN LA PLANIFICACION DE OBRA
En Nuevos Soles S/. 1,600.000 400.000 0.000 0.000 0.000 0.000 2,000.00
En Porcentaje % 80.00% 20.00% 0.00% 0.00% 0.00% 0.00% 100.00%
13 PLAN DE MONITOREO ARQUELOGICO
En Nuevos Soles S/. 6,300.000 2,100.000 2,100.000 0.000 0.000 0.000 10,500.00
En Porcentaje % 60.00% 20.00% 20.00% 0.00% 0.00% 0.00% 100.00%
14 CAPACITACION
En Nuevos Soles S/. 1,750.000 1,750.000 0.000 0.000 0.000 0.000 3,500.00
En Porcentaje % 50.00% 50.00% 0.00% 0.00% 0.00% 0.00% 100.00%
15 FLETE
En Nuevos Soles S/. 8,922.243 0.000 6,488.904 0.000 811.113 0.000 16,222.26
En Porcentaje % 55.00% 0.00% 40.00% 0.00% 5.00% 0.00% 100.00%
TOTAL COSTO DIRECTO 48,044.23 335,758.93 593,962.68 639,522.14 339,294.30 74,164.41 2,030,746.69
GASTO GENERALES (9.6097%) 4,616.91 32,265.45 57,078.07 61,456.20 32,605.19 7,126.98 195,148.80
UTILIDAD (5%) 3,843.54 26,860.71 47,517.01 51,161.77 27,143.54 5,933.17 162,459.74
SUB TOTAL PRESUPUESTO REFERENCIAL 56,504.68 394,885.09 698,557.76 752,140.11 399,043.03 87,224.56 2,388,355.23
0.974491899
SUB TOTAL PRESUPUESTO CONTRACTUAL 55,063.35 384,812.32 680,738.88 732,954.44 388,864.20 84,999.63 2,327,432.82
IGV 18% 9,911.40 69,266.22 122,533.00 131,931.80 69,995.56 15,299.93 418,937.91
TOTAL PRESUPUESTO CONTRACTUAL 64,974.75 454,078.54 803,271.88 864,886.24 458,859.76 100,299.56 2,746,370.73
AVANCE PORCENTUAL 2.37% 16.53% 29.25% 31.49% 16.71% 3.65% 100.00%
PORCENTAJE ACUMULADO 2.37% 18.90% 48.15% 79.64% 96.35% 100.00%