VALORIZACION
SALDO POR EJECUTAR
PRESUPUESTO ANTERIOR ACTUAL ACUMULADA
IDENTIF. DESCRIPCION UNIDAD METRADO PREC. UNIT. PARCIAL METRADO COSTO METRADO COSTO METRADO COSTO PORC. METRADO COSTO
10.00.00 CIELORASOS
10.01.00 CIELORASOS DE MORTERO
10.01.01 CIELORASO DE CEMENTO, MEZCLA 1:5 M2 82.52 80 6,601.60 22.00 1,760.00 22.00 1,760.00 26.66% 60.52 4,841.60
10.01.02 VESTIDURA DE FONDO DE ESCALERAS, MEZCLA 1:4 M2 18.96 92.47 1,753.23 10.00 924.70 10.00 924.70 52.74% 8.96 828.53
10.01.03 CIELORASO DE YESO M2 35.8 70 2,506.00 30.00 2,100.00 30.00 2,100.00 83.80% 5.80 406.00
- -
10.02.00 CIELORASO SUSPENDIDO - -
10.02.01 CIELORASO SUSPENDIDO CON BALDOSA YESO-CARTON,M2 E=1/2" 42.58 65 2,767.70 - - - 0.00% 42.58 2,767.70
10.02.02 CIELORASO SUSPENDIDO CON BALDOSA YESO-VINILICO,
M2E=7MM 28.47 65 1,850.55 - - - 0.00% 28.47 1,850.55
COSTOS INDIRECTOS
GASTOS GENERALES FIJOS (0.5%) 0.50% 77.40 - 23.92 23.92 53.47
GASTOS GENERALES VARIABLES (8.5%) 9.00% 1,393.12 - 430.62 430.62 962.49
UTILIDAD (10%) 9.00% 1,393.12 - 430.62 430.62 962.49
VALORIZACION
SALDO POR EJECUTAR
PRESUPUESTO ANTERIOR ACTUAL ACUMULADA
IDENTIF. DESCRIPCION UNIDAD METRADO PREC. UNIT. PARCIAL METRADO COSTO METRADO COSTO METRADO COSTO PORC. METRADO COSTO
10.00.00 CIELORASOS
10.01.00 CIELORASOS DE MORTERO
10.01.01 CIELORASO DE CEMENTO, MEZCLA 1:5 M2 82.52 80 6,601.60 22.00 1,760.00 65.00 5,200.00 87.00 6,960.00 105.43% - 4.48 - 358.40
10.01.02 VESTIDURA DE FONDO DE ESCALERAS, MEZCLA 1:4 M2 18.96 92.47 1,753.23 10.00 924.70 10.00 924.70 20.00 1,849.40 105.49% - 1.04 - 96.17
10.01.03 CIELORASO DE YESO M2 35.8 70 2,506.00 30.00 2,100.00 - 30.00 2,100.00 83.80% 5.80 406.00
- -
10.02.00 CIELORASO SUSPENDIDO - -
10.02.01 CIELORASO SUSPENDIDO CON BALDOSA YESO-CARTON,M2 E=1/2" 42.58 65 2,767.70 - - - 0.00% 42.58 2,767.70
10.02.02 CIELORASO SUSPENDIDO CON BALDOSA YESO-VINILICO,
M2E=7MM 28.47 65 1,850.55 - - - 0.00% 28.47 1,850.55
COSTOS INDIRECTOS
GASTOS GENERALES FIJOS (0.5%) 0.50% 77.40 23.92 30.62 54.55 22.85
GASTOS GENERALES VARIABLES (8.5%) 9.00% 1,393.12 430.62 551.22 981.85 411.27
UTILIDAD (10%) 9.00% 1,393.12 430.62 551.22 981.85 411.27
VALORIZACION
SALDO POR EJECUTAR
PRESUPUESTO ANTERIOR ACTUAL ACUMULADA
IDENTIF. DESCRIPCION UNIDAD METRADO PREC. UNIT. PARCIAL METRADO COSTO METRADO COSTO METRADO COSTO PORC. METRADO COSTO
10.00.00 CIELORASOS
10.01.00 CIELORASOS DE MORTERO
10.01.01 CIELORASO DE CEMENTO, MEZCLA 1:5 M2 82.52 80 6,601.60 87.00 6,960.00 - 87.00 6,960.00 105.43% - 4.48 - 358.40
10.01.02 VESTIDURA DE FONDO DE ESCALERAS, MEZCLA 1:4 M2 18.96 92.47 1,753.23 20.00 1,849.40 - 20.00 1,849.40 105.49% - 1.04 - 96.17
10.01.03 CIELORASO DE YESO M2 35.8 70 2,506.00 30.00 2,100.00 - 30.00 2,100.00 83.80% 5.80 406.00
- -
10.02.00 CIELORASO SUSPENDIDO - -
10.02.01 CIELORASO SUSPENDIDO CON BALDOSA YESO-CARTON,M2 E=1/2" 42.58 65 2,767.70 45.00 2,925.00 45.00 2,925.00 105.68% - 2.42 - 157.30
10.02.02 CIELORASO SUSPENDIDO CON BALDOSA YESO-VINILICO,
M2E=7MM 28.47 65 1,850.55 27.00 1,755.00 27.00 1,755.00 94.84% 1.47 95.55
COSTOS INDIRECTOS
GASTOS GENERALES FIJOS (0.5%) 0.50% 77.40 54.55 23.40 77.95 - 0.55
GASTOS GENERALES VARIABLES (8.5%) 9.00% 1,393.12 981.85 421.20 1,403.05 - 9.93
UTILIDAD (10%) 9.00% 1,393.12 981.85 421.20 1,403.05 - 9.93