Calendario de Utilizacion de Equipo

Obra : MEJORAMIENTO DEL SERVICIO DE DRENAJE PLUVIAL EN EL PUEBLO TRADICIONAL DE YARABAMBA, DISTRITO DE YARABAMBA, PROVINCIA AREQUIPA, REGION AREQUIPA
Ubicacion : YARABAMBA - AREQUIPA - AREQUIPA
Costo A : Set - 2021 Cliente : MUNICIPALIDAD DISTRITAL DE YARABAMBA
Ejecuta : Consorcio Yarabamba
PLAZO DE EJECUCION
TOTAL
Cod Descripcion Unid Cantidad Precio Parcial 30 Días 30 Días 30 Días 15 Días
105 Dias
EQUIPO
37 05733 WINCHA UND 0.77 50.00 38.50 - 38.50 - - 38.50
48 07058 MEZCLADORA DE CONCRETO 9 - 11 P3 (23 HP) hm 283.56 15.00 4,253.40 - 950.04 2,877.29 426.07 4,253.40
48 06362 TECLE TILFOR-SIMIL. INCL. CABLE-ACCESOR. hm 62.95 20.00 1,259.00 655.18 603.82 - - 1,259.00
48 04628 ZARANDA HM 93.87 5.00 469.35 - 469.35 - - 469.35
49 07068 CAMION CISTERNA 2000 GL hm 92.06 127.11 11,701.75 5,159.93 5,057.62 1,484.20 - 11,701.75
49 07069 CAMION VOLQUETE DE 15 m3 hm 297.04 144.07 42,794.55 1,986.97 31,901.38 8,906.20 - 42,794.55
49 07077 CARGADOR SOBRE LLANTAS DE 160-195 HP 3.5 yd3 hm 83.91 211.86 17,777.17 2,680.76 10,560.58 4,535.83 - 17,777.17
49 06878 COMPACTADORA VIBRATORIA TIPO PLANCHA 7 HP hm 312.46 15.20 4,749.39 - 3,239.83 635.73 873.83 4,749.39
49 07053 COMPRESORA NEUMATICA 240 - 330 PCM hm 48.18 110.00 5,299.80 5,299.80 - - - 5,299.80
49 06896 CORTADORA DE PAVIMENTO C35 -35HP HM 29.06 21.19 615.78 615.78 - - - 615.78
49 06864 ESTACION TOTAL hm 6.18 15.00 92.70 - 92.70 - - 92.70
49 07042 ESTACION TOTAL he 43.00 15.00 645.00 645.00 - - - 645.00
49 07037 GRUA HIDRAULICA AUTOPROPULSADA 127 HP 9 TN hm 3.00 160.00 480.00 480.00 - - - 480.00
49 06843 MAQUINA PARA PINTAR HM 94.51 10.00 945.10 - - - 945.10 945.10
49 07052 MARTILLO NEUMATICO DE 21 - 24 kg hm 96.37 15.00 1,445.55 1,445.55 - - - 1,445.55
49 07035 MINI CARGADOR BOB CAT 953 hm 464.67 84.75 39,380.78 15,985.60 22,515.39 879.79 - 39,380.78
49 07078 MONTACARGA hm 22.00 90.00 1,980.00 269.98 - 855.01 855.01 1,980.00
49 07067 MOTOBOMBA DE 4" (12 HP) hm 89.93 10.00 899.30 385.92 397.87 115.51 - 899.30
49 07044 RETROEXCAVADORA 62 HP 1.0 y3 hm 65.91 110.00 7,250.10 3,929.13 3,320.97 - - 7,250.10
49 07036 RETROEXCAVADORA 90 HP Cucha. 0.70 m3 (cat 215) hm 168.67 190.00 32,047.30 11,762.20 20,285.10 - - 32,047.30
49 07111 RODILLO ZANJAS CG-11 VIB 1.9 TN hm 168.95 60.00 10,137.00 240.00 4,924.27 4,972.73 - 10,137.00
49 07179 TANQUE IMPRIMADOR DE ASFALTO PORTATIL hm 8.64 50.00 432.00 - - 432.00 - 432.00
49 07182 VEHICULO PARA TRANSPORTE DE PASAJEROS (CUSTER) UND 7.00 5,000.00 35,000.00 10,416.67 12,500.00 12,083.33 - 35,000.00
49 07061 VIBRADOR DE CONCRETO 4 HP 2" hm 247.35 15.00 3,710.25 - 833.20 2,450.98 426.07 3,710.25

COSTO DIRECTO 223,403.77 61,958.47 117,690.62 40,228.60 3,526.08 223,403.77


GASTOS GENERALES 10 % 22,340.38 6,195.85 11,769.06 4,022.86 352.61 22,340.38
UTILIDAD 7% 15,638.26 4,337.09 8,238.34 2,816.00 246.83 15,638.26
SUB TOTAL 261,382.41 72,491.41 137,698.03 47,067.46 4,125.51 261,382.41
IGV. 18 % 47,048.83 13,048.45 24,785.64 8,472.14 742.59 47,048.83
PRESUPUESTO TOTAL 308,431.24 85,539.86 162,483.67 55,539.61 4,868.11 308,431.24

PORCENTAJE DE AVANCE 27.73% 52.68% 18.01% 1.58%


PORCENTAJE ACUMULADO 27.73% 80.41% 98.42% 100.00%

Página 1 de 1