"MEJORAMIENTO DEL SERVICIO EDUCATIVO DEL NIVEL INICIAL Y PRIMARIA EN LA
PROYECTO INSTITUCIÓN EDUCATIVA Nro .81909 - CASERÍO DE TAYAHUAL, DISTRITO Y PROVINCIA DE OTUZCO-LA LIBERTAD" - I ETAPA PRESUPUESTO BASE S/. 453,939.99 Nuevos Soles UBICACIÓN LA LIBERTAD - OTUZCO - OTUZCO INICIO DE OBRA DE ACUERDO A CONTRATO 15-Feb-16 PLAZO DE EJECUCION DE OBRA 70 D.C
PRESUPUESTO S/. / MESES
ITEM PARTIDAS Und S/. MES 1 MES 2 MES 3 OE.01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 24,261.91 S/. 24,261.91 (100%) 0.00 0.00 0 0 0 0.00 #N/A #N/A #N/A OE.02 ESTRUCTURAS 194,382.85 S/. 19,001.50 (9.78%) S/. 175,000.96 (90.03%) S/. 380.39 (0.2%) 0 0 0 0.00 #N/A #N/A #N/A OE.03 ARQUITECTURA 88,768.84 0.00 0.00 S/. 88,768.84 (100%) 0 0 0 0.00 #N/A #N/A #N/A OE.04 INSTALACIONES SANITARIAS 12,738.96 0.00 0.00 S/. 12,738.96 (100%) 0 0 0 0.00 #N/A #N/A #N/A OE.05 INSTALACIONES ELECTRICAS 14,364.75 0.00 0.00 S/. 14,364.75 (100%) 0 0 0 0.00 #N/A #N/A #N/A 0 0 0 0.00 #N/A #N/A #N/A COSTO DIRECTO 334,517.31 43,263.41 175,000.96 116,252.94 GASTOS GENERALES (10 %CD) 33,451.73 4,326.34 17,500.10 11,625.29 UTILIDAD (5 %CD) 16,725.87 2,163.17 8,750.05 5,812.65 SUB TOTAL 384,694.91 49,752.92 201,251.11 133,690.88 IGV (18% ST) 69,245.08 8,955.53 36,225.20 24,064.36 COSTO DE OBRA 453,939.99 58,708.45 237,476.30 157,755.24 AVANCE MENSUAL (%) 100.00% 12.93% 52.31% 34.75% AVANCE ACUMULADO (%) 100.00% 12.93% 65.25% 100.00% CRONOGRAMA DE DESEMBOLSOS "MEJORAMIENTO DEL SERVICIO EDUCATIVO DEL NIVEL INICIAL Y PRIMARIA EN LA PROYECTO : INSTITUCIÓN EDUCATIVA Nro .81909 - CASERÍO DE TAYAHUAL, DISTRITO Y PROVINCIA DE OTUZCO-LA LIBERTAD" - I ETAPA PRESUPUESTO BASE :S/. 453,939.99 Nuevos Soles UBICACIÓN : LA LIBERTAD - OTUZCO - OTUZCO INICIO DE OBRA DE ACUERDO A CONTRATO 15-Feb-16 PLAZO DE EJECUCION DE OBRA :70 D.C