TRAZO Y REPLANTEO
ZAPATA Z-1
1.00 1.00 8 8.00
MOVIMIENTO DE TIERRAS
AREA ALTO
COLUMNA
C-1 m3 0.13 1.70 8
1.71 1.71
ENCOFRADO Y DESENCOFRADO
COLUMNA
C-1 m2 1.26 1.70 8 17.09
17.09
Tarrajeo
COLUMNA
C-1 m2 1.26 1.70 8 17.08
17.08
PINTADO
COLUMNA
C-1 m2 1.26 1.70 8 17.08
17.08
ACERO DE REFUERZO F´c= 4500 kg/cm2
C-1 ZAPATA VECES LONGITUDVALOR SUBTOTAL
BASE LONGITU. 6.00 0.90 1.55 8.00 66.96
BASE TRANS. 6.00 0.90 1.55 8.00 66.96
SUPÈRIOR CIRCULAR LONG. 6.00 1.26 1.55 8.00 93.45
SUPÈRIOR CIRCULAR TRANS. 5.00 1.26 1.55 8.00 77.87
KG 305.24
COLUMNA
VECES LONGITUDVALOR SUBTOTAL
C-1 COLUMNA
TRANSVERSAL 13 1.38 1.55 8.00 222.46
LONGITUDINAL 6.00 1.70 1.55 8.00 126.48
348.94
0.16 31.89
5.1024
NOTA:
LAMINA:
HOJA DE METRADOS
PARQUE ULRICH NEISSER
LATERAL IZ . M2 81.80
LATERAL DERE. M2 63.96
PLANTA M2 735.83
881.59
881.59
HOJA DE METRADOS
TRAZO Y REPLANTEO
ZAPATA Z-3
0.50 0.50 0.50
MOVIMIENTO DE TIERRAS
COLUMNA
CIMIENTO C-3 m3 0.30 0.20 2.68 2.00 0.16
0.69
ENCOFRADO Y DESENCOFRADO
COLUMNA
C-3 m2 1.00 2.68 2.68
5.36
TARRAJEO
COLUMNA
C-3 m2 1.00 2.68 2.68
5.36
PINTADO
COLUMNA
C-3 m2 1.00 2.68 2.68
5.36
ACERO DE REFUERZO F´c= 4500 kg/cm2
C-3
ZAPATA
TRANSVERSAL 1/2" @ 0.20 m2 3.50 0.46 0.99 1 1.60
LONGITUDINAL 1/2" @ 0.20 m2 3.50 0.46 0.99 1 1.60
6.39
COLUMNA
MOVIMIENTO DE TIERRAS
CONCRETO
CONCRETO
SOLADO
CIMIENTO m3 ? 0.40 0.10 #VALUE!
CONCRETO CICLOPEO #VALUE!
CIMIENTO m3 ? 0.40 0.30 #VALUE!
ENCOFRADO Y DESENCOFRADO
CIMIENTO
CERCO m2 ? ? #VALUE!
SOBRECIMIENTO
CERCO m2 ? 0.40 #VALUE!
#VALUE!
ACERO DE REFUERZO F´c= 4500 kg/cm2
ZAPATA
TRANSVERSAL 3/4" @ 0.20 m2
LONGITUDINAL 3/4" @ 0.20 m2
-
COLUMNA
TRANSVERSAL 3/4" TIPO 1 ML
TRANSVERSAL 3/4" TIPO 2 ML
LONGITUDINAL 3/4" ML -
TUBERIA DE CONDUCCION
CORTE A-A TUBO COADRADO 15*15 cm ML 8.00 1 8.00 8.00