DIAGRAMA DE GANTT

CRONOGRAMA DE EJECUCION DE OBRA


OBRA :MEJORAMIENTO Y AMPLIACION DEL SERVICIO DEL CEMENTERIO MUNICIPAL DE TIABAYA- DISTRIT FINAL
SUB PRESUPUESTO :FORMULA ARQUITECTURA
PROPIETARIO :MUNICIPALIDAD DISTRITAL DE TIABAYA
UBICACIÓN :TIABAYA- AREQUIPA- AREQUIPA
Metrad Precio MES 1 MES 2 MES 3 MES 4
Item Descripción Und. Parcial (S/.)
o (S/.) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
01 ALBAÑILERIA 60,757.55 30% 15,952.20 30% 15,952.20 40% 21,269.60
01.01 MURO LADRILLO K.K.DE ARCILLA 18 H.(m2 1,567.63 33.92 53,174.01
100% 7,583.54
01.02 MURO LADRILLO K.K.DE ARCILLA 18 H (m2 86.58 87.59 7,583.54
02 REVOQUES ENLUCIDOS Y MOLDURAS 64,687.98 100% 628.26
02.01 TARRAJEO PRIMARIO m2 27.96 22.47 628.26
100% 27,190.77
02.02 TARRAJEO DE MUROS INTERIORES m2 1,097.73 24.77 27,190.77
50% 3,942.44 50% 3,942.44
02.03 TARRAJEO DE MUROS EXTERIORES m2 247.33 31.88 7,884.88
70% 19,033.25 30% 8,157.11
02.04 DERRAMES A=0.15 m.MORTERO 1:3 m 2,012.61 13.51 27,190.36
100% 1,793.71
02.05 ENCHAPADO CON SILLAR m2 23.38 76.72 1,793.71
03 CIELORRASOS 1,443.27 100% 1,443.27
03.01 TARRAJEO DE CIELORASO m2 44.85 32.18 1,443.27
04 PISOS Y PAVIMENTOS 58,666.86 50% 19,708.67 50% 19,708.67
04.01 VEREDA EXTERIOR f'c= 175 kg/cm2 ,C m2 506.78 77.78 39,417.35
50% 2,003.63 50% 2,003.63
04.02 ENCOFRADO Y DESENCOFRADO DE VE m2 89.07 44.99 4,007.26
100% 938.46
04.03 PISO DE PORCELANATO DE 30 X 30 cm m2 16.47 56.98 938.46
100% 12,314.28
04.04 CONCRETO f'c=175 kg/cm2 EN GRADAS m3 31.35 392.80 12,314.28
100% 1,989.51
04.05 PISO DE CEMENTO ACABADO PULIDO EN
m 14.12 140.90 1,989.51
05 ZOCALOS 2,949.22 100% 2,949.22
05.01 ZOCALO DE PORCELANATO 30X30 cm m2 27.96 105.48 2,949.22
06 CARPINTERIA DE MADERA 10,061.01 100% 5,364.99
06.01 PERGOLA Y BANCAS SEGUN DETALLE und 3.00 1,788.33 5,364.99
50% 2,348.01 50% 2,348.01
06.02 PUERTAS DE MADERA TABLEROS REBAJm2 7.37 637.18 4,696.02
07 VIDRIOS 294.14 100% 294.14
07.01 VENTANA DE CRISTAL TEMPLADO m2 6.40 45.96 294.14
08 CUBIERTAS 3,236.04 100% 2,895.60
08.01 LADRILLO PASTELERO 0.25x0.25x0.03 m2 60.59 47.79 2,895.60
100% 340.44
08.02 CUBIERTA TECHO METALICO LIVIANO m2 4.00 85.11 340.44
09 CERRAJERIA 721.57 100% 172.32
09.01 BISAGRAS CAPUCHINA ALUMINIZADA DE
und3 12.00 14.36 172.32
100% 320.80
09.02 CERRADURA PARA PUERTA DE BAÑOS und 4.00 80.20 320.80
100% 228.45
09.03 CERRADURA PARA PUERTA INTERIORE und 3.00 76.15 228.45
10 CARPINTERIA METALICA 6,035.08 100% 225.00
10.01 PUERTA METALICA SS.HH. m2 1.50 150.00 225.00
100% 2,118.27
10.02 TABIQUERIA CON PERFILES DE ALUMI m2 7.35 288.20 2,118.27
100% 2,564.31
10.03 TABIQUE DE DRYWALL m2 32.09 79.91 2,564.31
100% 1,127.50
10.04 REPARACION DE ESFERA EN CERCO M und 10.00 112.75 1,127.50
11 PINTURA 28,325.15 100% 617.58
11.01 PINTURA LATEX EN CIELO RASO m2 44.85 13.77 617.58
100% 15,005.97
11.02 PINTURA LATEX EN MUROS INTERIOREm2 1,097.73 13.67 15,005.97
100% 7,460.05
11.03 PINTURA LATEX EN MUROS EXTERIOREm2 448.59 16.63 7,460.05
100% 4,893.38
11.04 PINTURA LATEX EN MUROS EXTERIOREm2 294.25 16.63 4,893.38
100% 98.06
11.05 BARNIZ EN PUERTAS DE MADERA m2 4.37 22.44 98.06
100% 250.11
11.06 ESMALTE EN CARPINTERIA METALICA m2 11.99 20.86 250.11
DIAGRAMA DE GANTT
CRONOGRAMA DE EJECUCION DE OBRA
OBRA : MEJORAMIENTO Y AMPLIACION DEL SERVICIO DEL CEMENTERIO MUNICIPAL DE TIABAYA- DISTRIT FINAL
SUB PRESUPUESTO : FORMULA ARQUITECTURA
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE TIABAYA
UBICACIÓN : TIABAYA- AREQUIPA- AREQUIPA
Metrad Precio MES 1 MES 2 MES 3 MES 4
Item Descripción Und. Parcial (S/.)
o (S/.) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
12 APARATOS Y ACCESORIOS SANITARIOS 3,423.56 100% 1,436.05
12.01 LAVATORIO PEDESTAL BLANCO und 5.00 287.21 1,436.05
100% 1,085.24
12.02 INODORO ONE PIECE BLANCO und 4.00 271.31 1,085.24
100% 112.40
12.03 PAPELERA LOSA BLANCO und 4.00 28.10 112.40
100% 680.90
12.04 URINARIO NACIONAL und 2.00 340.45 680.90
100% 108.97
12.05 GRIFO DE RIEGO und 1.00 108.97 108.97
13 OTROS 6,252.08 100% 2,850.00
13.01 IMAGEN RELIGIOSA DE ANGEL H= 2.00 und 1.00 2,850.00 2,850.00
100% 241.04
13.02 MONTAJE DE ESTATUAS RELIGIOSAS und 2.00 120.52 241.04
100% 1,061.04
13.03 DESCARGA DE AGUA DE LLUVIAS NIC und 12.00 88.42 1,061.04
50% 1,050.00 50% 1,050.00
13.04 ARBORIZACION glb 1.00 2,100.00 2,100.00

Costo directo 246,853.51 15,952.20 57,531.75 129,597.37 43,772.20


GASTOS GENERALES 10.00 % 10% 24,685.35 1,595.22 5,753.17 12,959.74 4,377.22
UTILIDAD 10% 10% 24,685.35 1,595.22 5,753.17 12,959.74 4,377.22
DESEMBOLSO MENSUAL 296,224.21 19,142.64 69,038.10 155,516.85 52,526.64
MONTO ACUMULADO 296,224.21 19,142.64 88,180.74 243,697.59 296,224.23
% DE AVANCE 100.00 6.46 23.31 52.50 17.73
% DE AVANCE ACUMULADO 100.00 6.46 29.77 82.27 100.00