CRONOGRAMA DE ADQUISICION DE MATERIALES

"REPARACIÓN DE SENDERO Y MOBILIARIO DE OTROS ACTIVOS COMPLEMENTARIOS, RENOVACIÓN DE ÁREA VERDE,


PROYECTO : ADQUISICIÓN DE MOBILIARIO URBANO EN EL PARQUE TÚPAC AMARU, DISTRITO DE MAGDALENA DEL MAR,
PROVINCIA DE LIMA, DEPARTAMENTO DE LIMA"
FECHA : Nov-21
PRECIO PRESUPUESTO Nov-21 Dic-21
DESCRIPCION UND.
S/. CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL

OPERADOR DE EQUIPO LIVIANO hh S/ 23.38 0.54 S/ 12.63 S/ 0.00 0.54 S/ 12.63

TOPOGRAFO hh S/ 23.38 1.36 S/ 31.80 0.92 S/ 21.51 0.44 S/ 10.29

CAPATAZ hh S/ 27.12 2.04 S/ 55.32 0.22 S/ 5.97 1.82 S/ 49.36

OPERARIO hh S/ 23.38 8.17 S/ 191.01 1.16 S/ 27.12 7.01 S/ 163.89

OFICIAL hh S/ 18.48 2.16 S/ 39.92 S/ 0.00 2.16 S/ 39.92

PEON hh S/ 16.71 23.73 S/ 396.53 5.40 S/ 90.23 18.33 S/ 306.29


S/ 1,500.00
PERSONAL PARA MANTENIMIENTO DE ESPECIES ARBÓREAS est 0.13 S/ 195.00 S/ 0.00 0.13 S/ 195.00

CONTENEDOR PARA RESIDUOS SOLIDOS pza S/ 90.50 2.00 S/ 181.00 S/ 0.00 2.00 S/ 181.00

GUANTES DE CUERO par S/ 10.93 20.00 S/ 218.60 4.85 S/ 53.01 15.15 S/ 165.59

GUANTES DE JEBE par S/ 10.93 10.00 S/ 109.30 2.42 S/ 26.45 7.58 S/ 82.85

CHALECO REFLECTIVO und S/ 9.24 15.00 S/ 138.60 3.64 S/ 33.63 11.36 S/ 104.97

UNIFORME PARA OBRERO und S/ 53.47 14.00 S/ 748.58 3.39 S/ 181.26 10.61 S/ 567.32

BOTAS DE SEGURIDAD DIFRENTES TALLAS par S/ 40.80 20.00 S/ 816.00 4.85 S/ 197.88 15.15 S/ 618.12

BOTAS DE JEBE par S/ 20.25 10.00 S/ 202.50 2.42 S/ 49.01 7.58 S/ 153.50

LENTES DE POLICARBONATO LUNA CLARA und S/ 5.85 30.00 S/ 175.50 7.27 S/ 42.53 22.73 S/ 132.97

TAPONES DE SILICONA und S/ 2.43 15.00 S/ 36.45 3.64 S/ 8.85 11.36 S/ 27.60

GUANTES QUIRÚRGICOS und S/ 0.43 8.00 S/ 3.44 1.94 S/ 0.83 6.06 S/ 2.61

GUANTES QUIRURGICOS und S/ 0.43 52.00 S/ 22.36 12.61 S/ 5.42 39.39 S/ 16.94

GRASS EN CHAMPA m2 S/ 7.74 395.37 S/ 3,060.16 S/ 0.00 395.37 S/ 3,060.16

ALAMBRE NEGRO RECOCIDO # 16 kg S/ 3.46 1.26 S/ 4.36 S/ 0.00 1.26 S/ 4.36

PERNO DE 5/8" CON TUERCA Y HUACHA 5" und S/ 3.92 20.00 S/ 78.40 20.00 S/ 78.40 S/ 0.00

CLAVOS C/CABEZA P/CONSTRUCCION kg S/ 3.55 31.40 S/ 111.47 1.23 S/ 4.37 30.17 S/ 107.10
ACERO DE REFUERZO FY= 4200 KG/CM2 - PODIOS S/ 4.73
kg 388.89 S/ 1,839.45 152.46 S/ 721.14 236.43 S/ 1,118.31
PARQUE
ACERO DE REFUERZO FY=4200 GRADO 60 kg S/ 2.90 0.05 S/ 0.15 S/ 0.00 0.05 S/ 0.15

ARENA FINA m3 S/ 41.53 0.50 S/ 20.77 S/ 0.00 0.50 S/ 20.77

TIERRA DE CHACRA m3 S/ 33.89 73.26 S/ 2,482.78 S/ 0.00 73.26 S/ 2,482.78

PIEDRA CHANCADA DE 1/2" m3 S/ 50.65 0.30 S/ 15.20 S/ 0.00 0.30 S/ 15.20

ARENA GRUESA m3 S/ 18.70 1.50 S/ 28.05 S/ 0.00 1.50 S/ 28.05

CASCO TIPO JOCKEY DIFERENTES COLORES und S/ 13.48 15.00 S/ 202.20 3.64 S/ 49.07 11.36 S/ 153.13

MATERIAL AFIRMADO m3 S/ 32.59 5.28 S/ 172.08 S/ 0.00 5.28 S/ 172.08

CONOS REFLACTANTES und S/ 25.34 6.00 S/ 152.04 1.45 S/ 36.74 4.55 S/ 115.30

DEMOLICION DE LOSA DE CONCRETO m3 S/ 90.54 1.95 S/ 176.55 0.82 S/ 74.24 1.13 S/ 102.31

RELLENO COMPACTADO DE ZANJAS P/ILUMINACION m3 S/ 44.67 33.96 S/ 1,516.99 11.62 S/ 519.07 22.34 S/ 997.93

EXCAVACION MANUAL DE ZANJAS P/ILUMINACION m3 S/ 39.34 33.96 S/ 1,335.99 11.62 S/ 457.13 22.34 S/ 878.86

INSTALACION DE REFLECTOR SPOT TIPO LED DE 3 W und S/ 109.15 10.00 S/ 1,091.50 3.42 S/ 373.29 6.58 S/ 718.21
INSTALACION DE NTERRUPTOR TERMOMAGNETICO 2X20A, S/ 208.45
und 1.00 S/ 208.45 0.34 S/ 70.87 0.66 S/ 137.58
220V
RELLENO CON MATERIAL PROPIO m3 S/ 14.88 5.17 S/ 76.93 2.16 S/ 32.14 3.01 S/ 44.79

ADOQUIN DE CONCRETO DE 20x10x6 CM m2 S/ 23.96 28.99 S/ 694.60 S/ 0.00 28.99 S/ 694.60

CEMENTO PORTLAND TIPO I (42.5 kg) bls S/ 19.32 1.20 S/ 23.18 1.20 S/ 23.18 S/ 0.00

CEMENTO PORTLAND TIPO I (42.5 kg)) bls S/ 16.64 3.92 S/ 65.23 S/ 0.00 3.92 S/ 65.23

CONCRETO F'C=100 KG/CM2 m3 S/ 274.12 2.70 S/ 740.12 S/ 0.00 2.70 S/ 740.12

CONCRETO FC=210 KG/CM2 m3 S/ 423.43 15.18 S/ 6,427.67 5.93 S/ 2,510.94 9.25 S/ 3,916.73

CURADOR MENBRANIL gal S/ 16.00 0.03 S/ 0.48 S/ 0.00 0.03 S/ 0.48

YESO DE 20 Kg bls S/ 10.28 9.76 S/ 100.33 8.72 S/ 89.64 1.04 S/ 10.69

THINNER gal S/ 23.73 - S/ 0.00 S/ 0.00 0.00 S/ 0.00

ELIMINACION DE MATERIAL EXCEDENTE MANUAL m3 S/ 52.29 0.33 S/ 17.26 0.11 S/ 5.75 0.22 S/ 11.50

DESMOLDADOR PARA ENCOFRADO gal S/ 61.20 0.01 S/ 0.61 S/ 0.00 0.01 S/ 0.61

LETREROS AMBIENTALES und S/ 79.84 10.00 S/ 798.40 S/ 0.00 10.00 S/ 798.40

TERMOMETRO LASER A PILAS und S/ 100.85 0.18 S/ 18.15 0.04 S/ 4.03 0.14 S/ 14.12
PRECIO PRESUPUESTO Nov-21 Dic-21
DESCRIPCION UND.
S/. CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL

PULSIOXIOMETRO DIGITAL und S/ 116.07 0.18 S/ 20.89 0.04 S/ 4.64 0.14 S/ 16.25

PRUEBA RAPIDA COVID-19 und S/ 53.39 19.00 S/ 1,014.41 S/ 0.00 19.00 S/ 1,014.41

PRUEBA MOLECULAR COVID-19 und S/ 228.82 2.00 S/ 457.64 S/ 0.00 2.00 S/ 457.64

PEDILUVIO PARA DESINFECCIÓN DE CALZADO und S/ 99.08 1.00 S/ 99.08 0.24 S/ 23.78 0.76 S/ 75.30

PROTECTOR FACIAL - CARETA und S/ 6.69 8.00 S/ 53.52 1.94 S/ 12.98 6.06 S/ 40.54

MAMELUCO BIOLÓGICO DESCARTABLE und S/ 14.41 8.00 S/ 115.28 1.94 S/ 27.96 6.06 S/ 87.32

MASCARILLA QUIRÚRGICA und S/ 0.48 8.00 S/ 3.84 1.94 S/ 0.93 6.06 S/ 2.91

MASCARILLA QUIRURGICA und S/ 0.39 52.00 S/ 20.28 12.61 S/ 4.92 39.39 S/ 15.36

DISPENSADOR DE PAPEL DESECHABLE pza S/ 54.15 1.50 S/ 81.23 0.25 S/ 13.54 1.25 S/ 67.69

DISPENSADOR PEDESTAL ALCOHOL EN GEL pza S/ 86.26 1.50 S/ 129.39 0.25 S/ 21.57 1.25 S/ 107.83

MOCHILA PULVERIZADORA PARA DESINFECCION pza S/ 169.41 1.00 S/ 169.41 0.17 S/ 28.80 0.83 S/ 140.61
SEÑALIZACIÓN CUMPLIMIENTO DE ADOPCIÓN DE S/ 30.43
und 1.00 S/ 30.43 S/ 0.00 1.00 S/ 30.43
MEDIDAS COVID-19
SEÑAL DE VINIL 0.20X0.30M und S/ 4.20 11.00 S/ 46.20 S/ 0.00 11.00 S/ 46.20

CACHACO DE CONCRETO 1.20M und S/ 12.93 11.00 S/ 142.23 S/ 0.00 11.00 S/ 142.23

WINCHA und S/ 5.00 4.07 S/ 20.35 3.03 S/ 15.15 1.04 S/ 5.20

AGUA m3 S/ 5.04 0.15 S/ 0.76 0.06 S/ 0.30 0.09 S/ 0.45

LIJA PARA MADERA und S/ 1.69 2.00 S/ 3.38 2.00 S/ 3.38 S/ 0.00

BANDEJA ANTI DERRAME und S/ 72.40 1.00 S/ 72.40 S/ 0.00 1.00 S/ 72.40

TRANSPORTE DE EQUIPOS. HERRAMIENTAS Y MATERIALES glb S/ 2,250.00 1.00 S/ 2,250.00 1.00 S/ 2,250.00 S/ 0.00

HORMIGON m3 S/ 46.61 0.40 S/ 18.64 0.40 S/ 18.64 S/ 0.00

EXCAVACION m3 S/ 55.07 0.08 S/ 4.41 0.08 S/ 4.41 S/ 0.00

LIJA AL AGUA # 100 plg S/ 1.00 0.12 S/ 0.12 S/ 0.00 0.12 S/ 0.12

EXCAVACIÓN MANUAL - PARQUES m3 S/ 40.78 20.00 S/ 815.60 7.97 S/ 325.02 12.03 S/ 490.58
INSTALACION DE CAJA DE REGISTRO DE 300 x 300 x 400 S/ 106.76
und 1.00 S/ 106.76 0.34 S/ 36.30 0.66 S/ 70.46
mm CON TAPA DE CONCRETO
ENCOFRADO Y DESENCOFRADO DE LOSA m2 S/ 54.28 11.92 S/ 647.02 4.08 S/ 221.46 7.84 S/ 425.56

ENCOFRADO Y DESENCOFRADO DE PODIOS m2 S/ 54.28 20.16 S/ 1,094.28 8.44 S/ 458.12 11.72 S/ 636.16

AGUA m3 S/ 1.04 306.57 S/ 318.83 S/ 0.00 306.57 S/ 318.83

HUMUS m3 S/ 247.20 20.53 S/ 5,075.02 S/ 0.00 20.53 S/ 5,075.02

FERTILIZANTE UREA kg S/ 11.19 0.45 S/ 5.04 S/ 0.00 0.45 S/ 5.04


DENSIDAD - DURANTA LIMON (INC. MATERIALES S/ 2.60
und 1,501.20 S/ 3,903.12 S/ 0.00 1,501.20 S/ 3,903.12
P/PLANTADO
DENSIDAD - LANTANA BLANCA (INC. MATERIALES S/ 1.65
und 1,725.00 S/ 2,846.25 S/ 0.00 1,725.00 S/ 2,846.25
P/PLANTADO)
DENSIDAD - CROTON (INC. MATERIALES P/PLANTADO) und S/ 31.04 296.00 S/ 9,187.84 S/ 0.00 296.00 S/ 9,187.84

JAZMIN (INCLUIDO MATERIALES P/PLANTADO) und S/ 26.53 120.00 S/ 3,183.60 S/ 0.00 120.00 S/ 3,183.60

CAMILLA RIGIDA DE MADERA und S/ 200.00 2.00 S/ 400.00 0.48 S/ 96.00 1.52 S/ 304.00
S/ 134.08
BOLSAS DE POLIETILENO DE ALTA DENSIDAD (de colores) und 3.00 S/ 402.24 S/ 0.00 3.00 S/ 402.24

BOTIQUIN und S/ 84.66 1.00 S/ 84.66 0.24 S/ 20.32 0.76 S/ 64.34

GIGANTOGRAFIA SEGUN DISEÑO 3.60X7.20M und S/ 182.63 1.00 S/ 182.63 1.00 S/ 182.63 S/ 0.00
CARTEL INFORMATIVO 0.75 m x 1.4 m LOGO S/ 25.00
und 4.00 S/ 100.00 0.97 S/ 24.25 3.03 S/ 75.75
MUNICIPALIDAD
SEÑALIZACION PREVENTIVAS 2.40 X 1.50 m und S/ 136.24 6.00 S/ 817.44 1.45 S/ 197.55 4.55 S/ 619.89

PRUEBAS ELECTRICAS glb S/ 720.72 1.00 S/ 720.72 0.34 S/ 245.04 0.66 S/ 475.68

EMPALME 3M-0 und S/ 62.41 4.00 S/ 249.64 1.37 S/ 85.50 2.63 S/ 164.14

INSTALACION DE CABLE N2XOH 1KV, 2-1x4mm² + 4mm² (T) ml S/ 12.74 71.30 S/ 908.36 24.39 S/ 310.73 46.91 S/ 597.63

CABLE N2XOH 1KV, 2-1x6mm² + 6mm² (T) ml S/ 15.26 41.90 S/ 639.39 14.33 S/ 218.68 27.57 S/ 420.72

MALLA RASCHEL 90% H=4.20ml ml S/ 14.84 100.00 S/ 1,484.00 S/ 0.00 100.00 S/ 1,484.00

MADERA TORNILLO CEPILLADA p2 S/ 2.84 255.00 S/ 724.20 85.00 S/ 241.40 170.00 S/ 482.80

MADERA TORNILLO CEPILLADA. p2 S/ 0.73 1.47 S/ 1.07 S/ 0.00 1.47 S/ 1.07


PLAN DE CONTINGENCIA Y SEGURIDAD DURANTE LA S/ 2,250.00
glb 1.00 S/ 2,250.00 S/ 0.00 1.00 S/ 2,250.00
CONSTRUCCION
TRANQUERA DE MADERA DE 2.40x1.20m und S/ 45.00 3.00 S/ 135.00 0.73 S/ 32.85 2.27 S/ 102.15

ROLLIZO DE EUCALIPTO DE 2.5 mts (altura) pza S/ 16.28 10.00 S/ 162.80 S/ 0.00 10.00 S/ 162.80

CALAM.G°ZINC GA28:1.83 X 0.830 M X 0.4MM pln S/ 9.27 10.00 S/ 92.70 S/ 0.00 10.00 S/ 92.70

ESTACA DE MADERA p2 S/ 2.50 4.88 S/ 12.20 4.36 S/ 10.90 0.52 S/ 1.30


PRECIO PRESUPUESTO Nov-21 Dic-21
DESCRIPCION UND.
S/. CANT. PRESUP. (S/.) CANT. PARCIAL CANT. PARCIAL

PINTURA DE TRAFICO gal S/ 16.67 0.01 S/ 0.17 S/ 0.00 0.01 S/ 0.17

HERRAMIENTAS MANUALES %MO - S/ 0.00 S/ 0.00 S/ 0.00

CAMION CISTERNA 4 X 2 (AGUA) 178-210 HP 3000 gl hm S/ 108.92 0.07 S/ 7.62 S/ 0.00 0.07 S/ 7.62

CAMION VOLQUETE 6 X 4 330 HP 10 m3 hm S/ 163.73 0.91 S/ 148.99 S/ 0.00 0.91 S/ 148.99


MOCHILA PULVERIZADORA PARA APLICACION DE S/ 3.50
he - S/ 0.00 S/ 0.00 - S/ 0.00
ADITIVO
ELIMINACION DE MATERIAL EXCEDENTE MANUAL m3 S/ 52.29 0.78 S/ 40.79 0.27 S/ 14.12 0.51 S/ 26.67

ROTOMARTILLO ELECTRICO hm S/ 18.72 0.16 S/ 3.00 0.16 S/ 3.00 0.00 S/ 0.00

COMPRESORA NEUMATICA 196 HP 600-690 PCM hm S/ 105.82 0.16 S/ 16.93 0.16 S/ 16.93 0.00 S/ 0.00

COMPACTADOR VIBRATORIO TIPO PLANCHA 5.8 HP hm S/ 9.07 0.55 S/ 4.99 S/ 0.00 0.55 S/ 4.99

MINI CARGADOR 70HP hm S/ 63.33 0.12 S/ 7.60 S/ 0.00 0.12 S/ 7.60

VIBRADOR DE CONCRETO 4 HP 1.35" hm S/ 6.08 0.02 S/ 0.12 S/ 0.00 0.02 S/ 0.12

VIBROAPISONADOR - SALTARIN hm S/ 23.40 0.51 S/ 11.93 S/ 0.00 0.51 S/ 11.93

MEZCLADORA DE CONCRETO TAMBOR 18 HP 11 p3 hm S/ 5.17 0.02 S/ 0.10 S/ 0.00 0.02 S/ 0.10

NIVEL TOPOGRAFICO hm S/ 8.00 1.36 S/ 10.88 0.92 S/ 7.36 0.44 S/ 3.52

ESTACION TOTAL hm S/ 14.25 1.36 S/ 19.38 0.92 S/ 13.11 0.44 S/ 6.27


SC MONITOREO DE MATERIAL PARTICULADO (PM10 Y S/ 316.72
und 2.00 S/ 633.44 S/ 0.00 2.00 S/ 633.44
PM2.5)
SC MONITOREO DE RUIDO und S/ 108.59 0.01 S/ 1.09 S/ 0.00 0.01 S/ 1.09

SC MONITOREO DE GASES ATMOSFERICOS und S/ 316.72 2.00 S/ 633.44 S/ 0.00 2.00 S/ 633.44

LOGÍSTICA PARA MONITOREO und S/ 1,357.36 0.01 S/ 13.57 S/ 0.00 0.01 S/ 13.57

SC MONITOREO DE SUELO und S/ 361.96 0.01 S/ 3.62 S/ 0.00 0.01 S/ 3.62

KIT ANTIDERRAME und S/ 99.00 0.01 S/ 0.99 S/ 0.00 0.01 S/ 0.99


SUBCONTRATO DE FABRICACION E INSTALACION DE S/ 3,464.83
und 0.01 S/ 34.65 0.00 S/ 0.00 0.01 S/ 34.65
FIGURA 200 SEGUN DETALLE DE PLANOS
SUBCONTRATO DE FABRICACION E INSTALACION DE S/ 4,594.16
und 0.01 S/ 45.94 0.00 S/ 0.00 0.01 S/ 45.94
LETRAS "LIMA" SEGUN DETALLE DE PLANOS
SUBCONTRATO DE FABRICACION E INSTALACION DE S/ 4,730.67
TÓTEM DE ESTRUCTURA METALICA, BASE C° SEGUN und 0.01 S/ 47.31 0.00 S/ 0.00 0.01 S/ 47.31
DETALLE DE PLANOS
SUBCONTRATO DE FABRICACION E INSTALACION DE S/ 2,864.16
TÓTEM DE INFORMATIIVO , BASE DE C° SEGUN DETALLE DE und 4.00 S/ 11,456.64 S/ 0.00 4.00 S/ 11,456.64
PLANOS
SUBCONTRATO DE FABRICACION E INSTALACION DE S/ 96,263.30
und 0.01 S/ 962.63 0.00 S/ 0.00 0.01 S/ 962.63
PERGOLA SOL Y SOMBRA SEGUN DETALLE DE PLANOS

TOTALES S/ 80,444.20 S/.10,985.97 S/.69,458.24


Gastos Generales 17.04% S/ 13,708.14 S/ 1,872.07 S/ 11,836.07
Utilidad 10.00% S/ 8,044.42 S/ 1,098.60 S/ 6,945.82
Sub-Total S/ 102,196.78 S/ 13,956.64 S/ 88,240.14
Impuesto General a las Ventas 18.00% S/ 18,395.42 S/ 2,512.20 S/ 15,883.23
Total Final S/ 120,592.20 S/ 16,468.84 S/ 104,123.37
AVANCE MENSUAL 13.66% 86.34%
AVANCE MENSUAL ACUMULADO 13.66% 100.00%