MCO-EPMAPS-GT02-2014
RUBRO PRECIO
CODIGO DESCRIPCION UNIDAD CANTIDAD
Nº UNITARIO USD
CA01 CONEXIONES
1 01.003 .4.01 EXCAVACION ZANJA A MANO H=0.00-2.75m (EN TIERRA) m3 331.00 6.30 2,085.30
5 01.039 .4.13 ENSAYO DE COMPACTACION CON DENSIMETRO NUCLEAR u 45.00 19.67 885.15
7 03.006 .4.07 SILLA YEE 400 X 160MM (MAT/TRAN/INST) u 10.00 25.38 253.80
9 03.006 .4.31 SILLA YEE 500 X 160MM (MAT/TRAN/INST) u 10.00 28.91 289.10
10 03.006 .4.33 SILLA YEE 600 X 160MM (MAT/TRAN/INST) u 5.00 34.55 172.75
11 03.008 .4.01 CAJA DOMICILIARIA H=0.60-1.50M CON TAPA H.A. u 45.00 88.69 3,991.05
13 01.003 .4.02 EXCAVACION ZANJA A MANO H=2.76-3.99m (EN TIERRA) m3 394.00 9.13 3,597.22
14 01.003 .4.24 EXCAVACION ZANJA A MAQUINA H=0.00-2.75m (EN TIERRA) m3 1,127.00 2.02 2,276.54
15 01.003 .4.25 EXCAVACION ZANJA A MAQUINA H=2.76-3.99m (EN TIERRA) m3 641.00 2.42 1,551.22
16 01.003 .4.26 EXCAVACION ZANJA A MAQUINA H=4.00-6.00m (EN TIERRA) m3 10.00 3.49 34.90
CA03 TUBERIAS
46 01.030 .4.02 DERROCAMIENTO HORMIGON SIMPLE (HERRAMIENTA MENOR) m3 2.00 34.90 69.80
48 01.039 .4.13 ENSAYO DE COMPACTACION CON DENSIMETRO NUCLEAR u 30.00 19.67 590.10
53 06.004 .4.06 REPARACION CONEXION DOMICILIARIA 1/2" AGUA POTABLE u 10.00 9.90 99.00
54 01.011 .4.13 HORMIGON SIMPLE PLINTOS f'c=210 KG/CM2 m3 6.00 129.44 776.64
55 01.037 .4.08 ACERO ESTRUCTURA PUENTE (FABRICACION Y MONTAJE) kg 2,285.00 4.93 11,265.05
56 01.018 .4.66 TANQUE DE TOL DE 55 GLNS (PROVISION Y MONTAJE) u 12.00 15.84 190.08
59 01.024 .4.09 CINTA REFLECTIVA - ROLLO 3" X 200 PIES (CON LEYENDA) u 2.00 20.40 40.80
60 03.016 .4.01 PASOS PEATONALES DE MADERA 1.2m ANCHO m 12.00 10.04 120.48
CERRAMIENTO DE TOOL,ANGULO/TUBO
61 04.020 .4.37 m2 2.00 31.98 63.96
RECT.,PINGO/VIGA(SUMINISTRO, MONTAJE Y PINTURA)
62 07.005 .4.07 VOLANTE INFORMATIVO - HOJA A5 (INCLUYE DISTRIBUCION) u 60.00 0.05 3.00
66 01.036 .4.54 ELABORACION DE PLANO AS BUILT LAMINA, TAMAÑO A0 O A1 u 6.00 53.34 320.04
71 03.010 .4.14 TAPA CON CERCO HF D=600MM (MAT,TRANS,INST) u 2.00 171.26 342.52
PRESUPUESTO ACEPTADO: USD $ 166,518.01 (CIENTO SESENTA Y SEIS MIL QUINIENTOS DIECIOCHO ,01/100 dólares de
Estados Unidos de América) má IVA
Jaime Buitrón V