TRAMOS TRAMOS
PRESUPUESTO
PRESUPUESTO PRESUPUESTO PRESUPUESTO FACTOR DE PRESUPUESTO VALORIZADO
OFERTADO DEL PLAN VALORIZADO CORRECCIÓN OFERTADO CORREGIDO % AVANCE
92 LECCLESPAMPA-CHANQUIL 38,401.98 37,140.32 3,198.20 1.033970 38,401.98 3,306.84
93 PTA.CARRETERA EMP (RAYANNIYUCC)-HV 830-CHUÑUNAPAMPA-CCOCHCCACCASA 37,864.71 39,649.30 3,414.25 0.954991 37,864.71 3,260.58
94 LECCLESPAMPA-CHANQUIL 67,915.79 75,350.52 6,488.51 0.901331 67,915.79 5,848.30
95 PTA.CARRETERA EMP (RAYANNIYUCC)-HV 830-CHUÑUNAPAMPA-CCOCHCCACCASA 10,250.83 10,392.97 894.95 0.986323 10,250.83 882.71
8.61%
96 EMP.HV-107 (HUAYANAY)-PATACANCHA- RAYANNIYOCC-EMP.HV-827. 13,825.67 19,045.04 1,639.99 0.725946 13,825.67 1,190.54
97 EMP.HV-830 (ANTA)-EMP.HV-831 14,392.35 20,225.98 1,741.69 0.711577 14,392.35 1,239.35
98 TRAMO 1 DE SECTOR ANTA EMP.HV.829-EMP-PTA CARRETERA . 32,370.33 13,217.53 1,138.17 2.449045 32,370.33 2,787.43
TOTAL DE PRESUPUESTO 215,021.66 215,021.66 18,515.76 215,021.66 18,515.75
p
0 30.00
"AÑO DE LA UNIVERSALIZACIÓN DE LA SALUD "
PORCENTA
MONTO TOTAL ACTUAL
ITEM CONCEPTO JE
EJECUTAD
DEL TRAMO (.S/.) MES (S./)
O
01 Tramo 92: LECCLESPAMPA-CHANQUIL
COSTO DIRECTO S/. 27,068.37 S/. 2,330.89
GASTOS GENERALES (9.302326%) S/. 2,517.99 S/. 216.83
UTILIDAD (6.976744%) C.D S/. 1,888.49 S/. 162.62
SUB TOTAL S/. 31,474.85 S/. 2,710.34
8.61%
IMPUESTO IGV (18%) S/. 5,665.47 S/. 487.86
PRESUPUESTO S/. 37,140.32 S/. 3,198.20
FACTOR DE RELACIÓN (F.R) S/. 1.00 1.00
PRESUPUESTO TOTAL DE LA OBRA S/. 37,140.32 S/. 3,198.20
Tramo 93: PTA.CARRETERA EMP (RAYANNIYUCC)-HV 830-
02 CHUÑUNAPAMPA-CCOCHCCACCASA
COSTO DIRECTO S/. 28,896.95 S/. 2,488.35
GASTOS GENERALES (9.302326%) S/. 2,688.09 S/. 231.47
UTILIDAD (6.976744%) C.D S/. 2,016.07 S/. 173.61
SUB TOTAL S/. 33,601.10 S/. 2,893.43
8.61%
IMPUESTO IGV (18%) S/. 6,048.20 S/. 520.82
PRESUPUESTO S/. 39,649.30 S/. 3,414.25
FACTOR DE RELACIÓN (F.R) S/. 1.00 1.00
PRESUPUESTO TOTAL DE LA OBRA S/. 39,649.30 S/. 3,414.25
Tramo 94: EMP.HV-107 (HUAYANAY)-PATACANCHA-
RAYANNIYOCC-EMP.HV-827.
03
COSTO DIRECTO S/. 54,916.48 S/. 4,728.92
GASTOS GENERALES (9.302326%) S/. 5,108.51 S/. 439.90
UTILIDAD (6.976744%) C.D S/. 3,831.38 S/. 329.92
SUB TOTAL S/. 63,856.37 S/. 5,498.74
8.61%
IMPUESTO IGV (18%) S/. 11,494.15 S/. 989.77
PRESUPUESTO S/. 75,350.52 S/. 6,488.51
FACTOR DE RELACIÓN (F.R) S/. 1.00 1.00
PRESUPUESTO TOTAL DE LA OBRA S/. 75,350.52 S/. 6,488.51