Documentos de Académico
Documentos de Profesional
Documentos de Cultura
ADELANTOS:
ADELANTO DIRECTO S/. 333,845.47 (Sin I.G.V.)
( 10% M.C.)
ADELANTOS DE MATERIALES
ACERO S/. 33,195.00 (Sin I.G.V.)
CEMENTO S/. 110,169.00 (Sin I.G.V.)
DEPARTAMENTO AYACUCHO
VALORIZACION DE AVANCE DE OBRA Nº 01
(DEL 08/04/2019 AL 30/04/2019)
PRESUPUESTO
ITEM DESCRIPCIÓN
UNIDAD METRADO
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA 2.40 X 4.80 M UND 1.00
01.02 CAMPAMENTO PROVISIONAL DE OBRA M2 570.00
01.03 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO GLB 1.00
01.04 TRAZO, NIV.Y REPLANTEO DURANTE EJECUCIÓN DE OBRA KM 18.00
02 MOVIMIENTO DE TIERRAS
02.01 CORTE EN MATERIAL SUELTO M3 126,996.34
02.02 CORTE EN ROCA SUELTA M3 7,335.29
02.03 CORTE EN ROCA FIJA M3 32,459.53
02.04 RELLENO CON MATERIAL PROPIO M3 5,547.35
02.05 REMOCION DE DERRUMBES M3 7,766.49
02.06 DESBROCE Y LIMPIEZA HA 1.80
03 PAVIMENTOS
03.01 PERFILADO Y COMPACTACIÓN DE SUBRASANTE M2 53,850.00
03.02 AFIRMADO M3 8,073.00
04 OBRAS DE ARTE Y DRENAJE
04.01 CUNETAS
04.01.01 CONFORMACIÓN Y PERFILADO DE CUNETAS M 15,970.00
04.02 TAJEAS (PASES DE AGUA)
04.02.01 EXCAVACIÓN NO CLASIFICADA PARA ESTRUCTURAS M3 582.37
04.02.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 246.87
04.02.03 CONCRETO F'C= 175 KG/CM2 M3 47.21
04.02.04 ENCOFRADO Y DESENCOFRADO M2 393.45
04.02.05 ACERO DE REFUERZO KG 4,040.96
04.02.06 MAMPOSTERÍA DE PIEDRA M3 148.36
04.02.07 ELIMINACIÓN DE MATERIAL EXCEDENTE Dprom=30 m M3 352.44
04.03 ALCANTARILLAS
04.03.01 ALCANTARILLAS TMC
04.03.01.01 EXCAVACIÓN NO CLASIFICADA PARA ESTRUCTURAS M3 104.89
04.03.01.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 61.42
04.03.01.03 CONCRETO F'C= 140 KG/CM2 M3 3.12
04.03.01.04 CONCRETO CICLOPEO F'C= 175 KG/CM2 M3 13.50
04.03.01.05 ENCOFRADO Y DESENCOFRADO M2 98.21
04.03.01.06 MAMPOSTERÍA DE PIEDRA M3 3.48
04.03.01.07 ALCANTARILLA TMC 0= 24" M 21.00
04.03.01.08 ELIMINACIÓN DE MATERIAL EXCEDENTE Dprom=30 m M3 62.94
04.04 BADENES
04.04.01 EXCAVACIÓN NO CLASIFICADA PARA ESTRUCTURAS M3 669.96
04.04.02 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO M3 326.60
04.04.03 ENCOFRADO Y DESENCOFRADO M2 458.90
04.04.04 MAMPOSTERÍA DE PIEDRA M3 357.25
04.04.05 ELIMINACIÓN DE MATERIAL EXCEDENTE Dprom=30 m M3 392.54
05 SEÑALIZACIÓN
05.01 SEÑAL PREVENTIVA UND 76.00
05.02 SEÑAL REGLAMENTARIA UND 4.00
05.03 SEÑAL INFORMATIVA UND 2.00
05.04 POSTES KILOMÉTRICOS UND 19.00
06 TRANSPORTES
06.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3K 7,272.00
06.02 TRANSPORTE DE MATERIAL GRANULAR > 1 KM M3K 29,823.95
06.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3K 110,134.19
06.04 TRANSPORTE DE MATERIAL EXCEDENTE >1 KM M3K 51,229.22
07 IMPACTO AMBIENTAL
07.01 RESTAURACIÓN DE CANTERA M2 2,124.33
07.02 RESTAURACIÓN DE PATIO DE MÁQUINA Y CAMPAMENTO M2 570.00
07.03 ACONDICIONAMIENTO DE DEPÓSITO DE MATERIAL EXCEDENTE M2 15,150.00
07.04 REVEGETACIÓN HA 1.85
COSTO DIRECTO
GASTOS GENERALES FIJOS 0.80%
GASTOS GENERALES VARIABLES 4.00%
UTILIDAD 3.00%
SUB TOTAL
IMPUESTO IGV 18%
TOTAL DEL PRESUPUESTO
DEDUCTIVO DE OBRA
(DEL 01/08/2019 AL 20/08/2019)
VECINAL XXXXXXXXXXXXXXXXXXXXXXX
X; PROVINCIA: XXXXXXXXXXXXXX; DPTO. xxxxxxx
INICIO DE OBRA 4/8/2019 FIN DE OBRA
PRESUPUESTO ANTERIOR
P. UNIT. SUB TOTAL METRADO VALORIZADO %
100,439.69
1,783.98 1,783.98
33.33 18,998.10
48,999.83 48,999.83
1,703.21 30,657.78
1,659,771.90
4.07 516,875.10
14.76 108,268.88
28.83 935,808.25
5.25 29,123.59
8.76 68,034.45
923.13 1,661.63
200,892.24
1.20 64,620.00
16.88 136,272.24
271,843.05
23,635.60
1.48 23,635.60
106,992.73
5.12 2,981.73
29.20 7,208.60
387.05 18,272.63
45.03 17,717.05
4.56 18,426.78
206.78 30,677.88
33.22 11,708.06
20,671.19
20,671.19
5.12 537.04
29.20 1,793.46
332.24 1,036.59
282.54 3,814.29
45.03 4,422.40
206.78 719.59
297.95 6,256.95
33.22 2,090.87
120,543.53
5.12 3,430.20
29.20 9,536.72
45.03 20,664.27
206.78 73,872.16
33.22 13,040.18
73,893.10
825.06 62,704.56
725.44 2,901.76
2,603.44 5,206.88
162.10 3,079.90
737,546.88
6.06 44,068.32
2.04 60,840.86
5.00 550,670.95
1.60 81,966.75
52,509.89
0.75 1,593.25
0.56 319.20
2.31 34,996.50
8,432.94 15,600.94
3,096,896.75 -
24,775.17 -
123,875.87 -
92,906.90 -
3,338,454.69 -
600,921.84 -
S/. 3,939,376.53 S/. -
-
RA
2019)
IN DE OBRA 8/20/2019
ACTUAL ACUMULADO
METRADO VALORIZADO % METRADO VALORIZADO %
- -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- -
- - - 0.00 - -
- - - 0.00 - -
- 0.00 -
- - 0.00 -
- - 0.00 -
- -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - -
- - - - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
- - - 0.00 - -
9,301.40 9,301.40
717.34 4,347.07 717.34 4,347.07 9.86
2,428.59 4,954.33 2,428.59 4,954.33 8.14
- - - 0.00 - -
- - - 0.00 - -
5,920.21 5,920.21
1,062.1650 796.62 1,062.17 796.62 50.00
114.00 63.84 114.00 63.84 20.00
1,515.00 3,499.65 1,515.00 3,499.65 10.00
0.19 1,560.09 0.19 1,560.09 10.00
15,221.61 15,221.61
121.77 121.77
608.86 608.86
456.65 456.65
16,408.90 16,408.90
2,953.60 2,953.60
S/. 19,362.50 S/. 19,362.50
0.49 0.49
SALDO
METRADO VALORIZADO %
100,439.69
1.00 1,783.98 100.00
570.00 18,998.10 100.00
1.00 48,999.83 100.00
18.00 30,657.78 100.00
1,659,771.91
126,996.34 516,875.10 100.00
7,335.29 108,268.88 100.00
32,459.53 935,808.25 100.00
5,547.35 29,123.59 100.00
7,766.49 68,034.45 100.00
1.80 1,661.63 100.00
200,892.24
53,850.00 64,620.00 100.00
8,073.00 136,272.24 100.00
292,514.23
23,635.60
15,970.00 23,635.60 100.00
106,992.74
582.37 2,981.73 100.00
246.87 7,208.60 100.00
47.21 18,272.63 100.00
393.45 17,717.05 100.00
4,040.96 18,426.78 100.00
148.36 30,677.88 100.00
352.44 11,708.06 100.00
41,342.37
20,671.19
104.89 537.04 100.00
61.42 1,793.46 100.00
3.12 1,036.59 100.00
13.50 3,814.29 100.00
98.21 4,422.40 100.00
3.48 719.59 100.00
21.00 6,256.95 100.00
62.94 2,090.87 100.00
120,543.52
669.96 3,430.20 100.00
326.60 9,536.72 100.00
458.90 20,664.27 100.00
357.25 73,872.16 100.00
392.54 13,040.18 100.00
- - -
76.00 62,704.56 100.00
4.00 2,901.76 100.00
2.00 5,206.88 100.00
19.00 3,079.90 100.00
728,245.48
6,554.66 39,721.25 90.14
27,395.36 55,886.53 91.86
110,134.19 550,670.95 100.00
51,229.22 81,966.75 100.00
46,589.68
1,062.17 796.62 50.00
456.00 255.36 80.00
13,635.00 31,496.85 90.00
1.67 14,040.85 90.00
3,081,675.14
24,653.40
123,267.01
92,450.25
3,322,045.79
597,968.24
3,920,014.03
99.51
CÁLCULO DEL COEFICIENTE DE REAJUSTE (K)
FÓRMULA POLINÓMICA
K = 0.154 * (Mr / Mo) + 0.077 * (DCAr /DCAo) + 0.080* (DFr /DFo) +0.383*(Mr/Mo)+0.176*(Mr/Mo)+0.130 * (Ir / Io)
Ir
I0 Ir Ir Ir Ir
I.
COEF. % BASE REAJUSTE REAJUSTE REAJUSTE REAJUSTE
SIMBOLO IU DESCRIPCIÓN INCIDE INCIDENCI REAJUSTE
FEB 2019 MAYO 2019 JUNIO 2019 AGOSTO 2019 SETIEMBRE 2019
NCIA A JULIO 2019
INDICE INDICE K INDICE K INDICE K INDICE K K
INDICE
M 47 MANO DE OBRA INCL. LEYES SOCIALES 0.154 100.0% 600.40 600.40 0.154 619.76 0.159 619.76 0.159 619.76 0.159 619.76 0.159
DCA 02 ACERO DE CONSTRUCCIÓN LISO 12.987% 553.53 555.05 0.010 553.89 0.010 548.06 0.010 562.55 0.010 559.22 0.010
21 CEMENTO PORTLAND TIPO I 0.077 42.857% 449.56 449.56 0.033 449.56 0.033 449.56 0.033 449.56 0.033 449.56 0.033
28 DINAMITA 44.156% 585.33 587.27 0.034 586.03 0.034 579.87 0.034 595.19 0.035 591.66 0.034
DF 30 DÓLAR 0.080 66.250% 487.29 496.36 0.054 496.36 0.054 491.24 0.053 505.07 0.055 502.06 0.055
32 FLETE TERRESTRE 33.750% 469.40 471.42 0.027 472.50 0.027 472.50 0.027 472.50 0.027 474.11 0.027
M 49 MAQUINARIA Y EQUIPO IMPORTADO 0.383 100.0% 309.14 312.35 0.387 311.91 0.386 308.84 0.383 317.45 0.393 315.57 0.391
M 48 MAQUINARIA Y EQUIPO NACIONAL 0.176 100.0% 370.25 371.16 0.176 370.90 0.176 369.59 0.176 374.19 0.178 373.24 0.177
I 39 INDICE GENERAL DE PRECIOS AL CONS. 0.130 100.0% 452.87 457.75 0.131 457.36 0.131 458.29 0.132 458.56 0.132 458.59 0.132
Resumen
K1 1.006
K2 1.010
K3 1.007
K4 1.022
K5 1.018
Ka 1.001
CÁLCULO DEL COEFICIENTE DE REAJUSTE (Ka)
FÓRMULA POLINÓMICA
K = 0.154 * (Mr / Mo) + 0.077 * (DCAr /DCAo) + 0.080* (DFr /DFo) +0.383*(Mr/Mo)+0.176*(Mr/Mo)+0.130 * (Ir / Io)
I0 Ir
COEF. % I.
SIMBOLO IU DESCRIPCIÓN INCIDE INCIDENCI BASE REAJUSTE
NCIA A FEB 2019 ABRIL 2019
INDICE INDICE Ka
M 47 MANO DE OBRA INCL. LEYES SOCIALES 0.154 100.0% 600.40 600.40 0.154
Valoriz. N° 01 976,015.97 328,173.70 976,015.97 328,173.70 Apr-19 1.006 5,856.10 1,969.04 5,856.10 487.52 82.17 5,286.41
Valoriz. N° 02 645,594.24 1,253,050.11 1,621,610.21 1,581,223.81 May-19 1.010 6,455.94 12,530.50 6,455.94 580.45 40.82 5,834.67
Valoriz. N° 03 1,091,703.27 1,215,671.34 2,713,313.48 2,796,895.15 Jun-19 1.007 7,641.92 8,509.70 7,641.92 654.37 -45.95 7,033.50
Valoriz. N° 04 201,778.80 375,713.57 2,915,092.28 3,172,608.72 Jul-19 1.022 4,439.13 8,265.70 423.31 44.33 -467.64
Valoriz. N° 05 406,953.52 165,845.97 3,322,045.79 3,338,454.69 Aug-19 1.018 7,325.16 691.13 67.53 -758.66
TOTAL 3,322,045.79 3,338,454.69 3,322,045.79 3,338,454.69 31,718.25 31,274.94 19,953.96 2836.78 188.90 16,928.28
PROPIETARIO INSPECCIÓN
FECHA DE INICIO
AMORTIZACION
VAL.MES ADELANTO OTORGADO
DESCRIPCION AMORTIZACION
Sin Reaj.
SIN I.G.V. CON I.G.V. Amort=VB * 10.00%
AMORTIZACION
SALDO POR AMORTIZ.
(SIN I.G.V)
236,243.87
171,684.45
62,514.12
42,336.24
-
0.00
DEDUCCIÓN DEL REAJUSTE QUE NO CORRESPONDE POR ADELANTO DIRECTO
ADELANTO OTORGADO
N° DESCRIPCION FECHA MONTO SIN IGV % Ka-abr-2019
ADELANTO
1 01 Abril del 2019 S/. 333,845.47 10.00 1.001
DIRECTO
PROPIETARIO CONTRATISTA
PLAZO EJECUCIÓN
- CEMENTO
mo de Adelanto de Materiales
cidencia del material
r Valorizar
erial al mes del adelanto
erial al mes del P.B.
Monto
Monto Otorgado
Solicitado
50,000.00 33,195.00
120,000.00 110,169.00
SUMATORIA: S/. 143,364.00
Consumo de Materiales
Agosto
Acero de Refuerzo S/. 2,500.00
Cemento Portland S/. 15,000.00
FORMULA UNICA
Material : ACERO DE CONSTRUCCION liso
S/. ABR.2019
No. Mes
a b
FORMULA UNICA
Material : CEMENTO PORTLAND TIPO I
S/. ABR.2019
No. Mes
a b
IU = 02
FEB.2019
c d=axb/c
IU = 21
FEB.2019
c d=axb/c
d e f g=cxf/e
SUMATORIA: S/.
d e f g=cxf/e
82.17
40.82
-45.95
44.33
67.53
188.90
DELANTO DE MATERIALES
Monto utilizado
Mu = c.i. x V para la Deducción
deducción
h=axb j k = j x (d - e)/f
Monto utilizado
Mu = c.i. x V para la Deducción
deducción
h=axb j k = j x (d - e)/f
PROPIETARIO CONTRATISTA
1 - -
2 - -
3 - -
4 - -
5 - -
TOTAL - - - - - -
Adelantos
N°
1
2
ALORIZACIONES RECALCULADAS
XXXXXXXX
ERVISOR EXTERNO XXXXXXXX
ZO EJECUCIÓN 135 D.C.
HA DE INICIO 8-abr-19
HA DE TÉRMINO 20-ago-19
- - - 359033 5/21/2019
- - - 359045 6/27/2019
- - - 359055 7/25/2019
- - - 359062 8/24/2019
- - - 359068 9/12/2019
- - - -
Total = S/. - -
"CONSORCIO CAD"
AVANCES MENSUALES
120.00%
AVANCE
MES AVANCE
MENSUAL
MENSUAL
PROGRAMAD
EJECUTADO
O
100.00% 100.00%
Aug-12 328,173.70 - 95.03%
Sep-12 1,253,050.11 #REF!
Oct-12 1,215,671.34 #REF! 83.78%
80.00%
Nov-12 375,713.57 #REF!
Dec-12 165,845.97 #REF!
Monto Valorizado
programado
60.00%
9.83%