Está en la página 1de 25

SISTEMA INGLES

Espesor o
Actividad constructiva Largo (m) Ancho (m) Operaciones
altura (m)

Limpieza y descapote (m2)


6.1 10.4 6.10m x 10.40m x 1

Excavación vigas de
m3
cimentación

A (1-6), C(1-6), D(1-6) 6.10 0.4 0.85 6,10m x 0,40m x 0,85m x 3


C' (2-5) 2.20 0.4 0.85 2,20m x 0,40m x 0,85m x 1
1 (A-D) 6.00 0.4 0.85 6,00m x 0,40m x 0,85m x 1
2 (C-C') 0.90 0.4 0.85 0,90m x 0,40m x 0,85m x 1
3 (C'-D) 1.87 0.4 0.85
5 (C-D) 2.77 0.4 0.85
6 (A-C) 3.23 0.4 0.85

Solado de limpieza e= 0,05m m2


f'c= 15 Mpa

A (1-6), C(1-6), D(1-6) 6.10 0.4 0.05 6,10m x 0,40m x 3


C' (2-5) 2.20 0.4 0.05 2,20m x 0,40m x 1
1 (A-D) 6.00 0.4 0.05 6,00m x 0,40m x 1
2 (C-C') 0.90 0.4 0.05 0,90m x 0,40m x 1
3 (C'-D) 1.87 0.4 0.05
5 (C-D) 2.77 0.4 0.05
6 (A-C) 3.23 0.4 0.05

Viga de cimentación 21 MPa


m
(210 kg/cm2) 0,40mx0,30m

A (1-6), C(1-6), D(1-6) 6.10 0.4 0.3 6,10m x 3


C' (2-5) 2.20 0.4 0.3 2,20m x 1
1 (A-D) 6.00 0.4 0.3 6,00m x 1
2 (C-C') 0.90 0.4 0.3 0,90m x 1
3 (C'-D) 1.87 0.4 0.3
5 (C-D) 2.77 0.4 0.3
6 (A-C) 3.23 0.4 0.3

Sobrecimiento en bloque h= m
0,60m impermeabilizado.

A (1-6), D(1-6) 5.75 0.1 0.66 6,10m x 2


C (1-2) 2.67 0.1 0.66 2,20m x 1
C (5-6) 0.93 0.1 0.66 2,20m x 1
C' (2-5) 1.80 0.1 0.66 2,20m x 1
1 (A-D) 4.75 0.1 0.66 6,00m x 1
2 (C-C') 0.80 0.1 0.66 0,90m x 1
3 (C'-D) 1.67 0.1 0.66
5 (C-D) 2.37 0.1 0.66
6 (A-C) 2.93 0.1 0.66

Mamposteria en bloque de m2
concreto de 0,10 x 0,20 x 0,30

A (1-6), D(1-6) 5.70 0.1 2.1 5,70m x 2,10 m X 2


C (1-2), C(5-6) 3.40 0.1 2.1 3,40m x 2,10m x 1
2.20 0.1 2.1 2,20m x 1
C' (2-5) 1.20 0.1 2.1 1,20m x 2,10m x 1
1 (A-D) 5.80 0.1 2.1 5,80m x 2,10m x 1
3 (C'-D) 1.67 0.1 2.1 1,67m x 2,10m x 1
5 (C-D) 2.37 0.1 2.1 2,37m x 2,10m x 1
6 (A-C) 2.93 0.1 2.1 2,93m x 2,10m x 1

Mamposteria en bloque de
concreto de 0,10 x 0,20 x 0,30 m2
muros de culatas (Altura
mayor a 2,10m)

A (1-6), D(1-6) 0.57 0.1 2.75 0,57m x 2,75 m x 2


2.62 0.1 0.51 (2,62m x 0,51m) / 2 x2
C' (2-5) 1.20 0.1 0.565 1,20m x 0,565m x 1
0.70 0.1 0.79 0,70m x 0,79m x 1
2 (C'-D) 0.80 0.1 0.43 0,80m x 0,43m x 1
3 (C'-D) 1.67 0.1 0.54 1,67m x 0,54m x 1
5 (C-D) 2.37 0.1 0.86 2,37m x 0,86m x 1
6 (A-C) 2.93 0.1 0.54 2,93m x 2,10m x 1

Columnas de confinamiento
0,10 x 0,20 - 21 Mpa m
(210kg/cm2)

A(1), C(1) y B(1) 2.65 0.2 0.1


C2 y C'2 3.1 0.2 0.1
A(3), C'(3) y D(3) 3.19 0.2 0.1
C'4 3.35 0.2 0.1
C'(5) y D(5) 3.52 0.2 0.1
6(A-C) 3.73 0.2 0.1

Vigas de confinamiento 0,10


m
x 0,20 - 21 Mpa (210kg/cm2)

A (1-6), D(1-6) 6.10 0.1 0.66 6,10m x 2


C (1-2) 2.77 0.1 0.66 2,20m x 1
C (5-6) 1.13 0.1 0.66 2,20m x 1
C' (2-5) 2.25 0.1 0.66 2,20m x 1
1 (A-D) 6.00 0.1 0.66 6,00m x 1
2 (C-C') 0.90 0.1 0.66 0,90m x 1
3 (C'-D) 1.87 0.1 0.66
5 (C-D) 2.77 0.1 0.66
6 (A-C) 3.23 0.1 0.66

Revoque muros con mortero m2


1:4

A (1-6), D(1-6) 5.70 0.1 2.1 5,70m x 2,10 m X 2


C (1-2), C(5-6) 3.40 0.1 2.1 3,40m x 2,10m x 1
2.20 0.1 2.1 2,20m x 1
C' (2-5) 1.20 0.1 2.1 1,20m x 2,10m x 1
1 (A-D) 5.80 0.1 2.1 5,80m x 2,10m x 1
3 (C'-D) 1.67 0.1 2.1 1,67m x 2,10m x 1
5 (C-D) 2.37 0.1 2.1 2,37m x 2,10m x 1
6 (A-C) 2.93 0.1 2.1 2,93m x 2,10m x 1
Resultado
Frecuencia Descuentos Resultado final Observaciones
parcial

1 63.44 63.44

3 6.22 11.99
1 0.75
1 2.04
1 0.31
1 0.64
1 0.94
1 1.10

3 7.32 14.11 m2
1 0.88
1 2.40
1 0.36
1 0.75
1 1.11
1 1.29

3 18.30 35.27
1 2.20
1 6.00
1 0.90
1 1.87
1 2.77
1 3.23

2 11.50 28.05
1 2.67
1 0.93
1 1.80
1 4.75
1 0.80
1 1.10
1 1.56
1 2.93

57.57
2 23.94
1 7.14 0.40
1 4.62
1 2.52
1 12.18 5.225
1 3.51
1 4.98 1.84
1 6.15

11.89
2 3.12
2 2.67
1 0.68
1 0.55
1 0.34
1 0.90
1 2.04
1 1.58

41.57
3 7.95
2 6.2
3 9.57
1 3.35
2 7.04
2 7.46

31.54
2 12.20
1 2.77
1 1.13
1 2.25
1 6.00
1 0.90
1 1.23
1 1.83
1 3.23

65.04
2 23.94
1 7.14 0.40
1 4.62
1 2.52
1 12.18 5.225
1 3.51
1 4.98 1.84
1 6.15
Trapecio
SERVICIO NACIONAL DE APRENDIZAJE "SENA"
Centro para el desarrollo tecnológico dela Construcción y la industria
Curso de COSTOS Y PRESUPUESTOS PARA EDIFICACIONES II

APRENDIZ: Andrea Sanchez Acevedo


NUMERO DE FICHA: 2422756
CIUDAD Y FECHA DE REALIZACION: Tunja, 18 de Octubre de 2021

1 PRELIMINARES
1.1 Localización y replanteo ACTIVIDAD
MATERIALES
Descripción Unidad Cantidad
PUNTILLA DE 2" CON CABEZA kg 20.00
LISTON DE REVOLTURA 3MT UN 9.00
SUBTOTAL
MANO DE OBRA
Trabajador Unidad Rendimiento
CUADRILLA A ALBAÑILERÍA 1:2 H/C 0.02
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR pala, martillo GL 5%
SUBTOTAL
TOTAL
EXCAVACIONES
2 Limpieza y descapote manual ACTIVIDAD
2.1 MATERIALES
Descripción Unidad Cantidad
excavacion redes de servicio 1m m2 60
excavacion para caja de inspeccion 0.8x08x01 m3 0.064
SUBTOTAL
MANO DE OBRA
Trabajador Unidad Rendimiento
CUADRILLA AA ALBAÑILERÍA 1:3 H/C 0.12
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 5%
SUBTOTAL
TOTAL

3 ESTRUCTURAS DE CONCRETO
3.1 CONCRETO CICLOPEDO ACTIVIDAD
MATERIALES
Descripción Unidad Cantidad
cocreto ciclopeo 0.40 x 0.30X1M 14 Mpa m3 60
SUBTOTAL
MANO DE OBRA
Trabajador Unidad Rendimiento
CUADRILLA AA ALBAÑILERÍA 1:2 H/C 0.06
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 6%
SUBTOTAL
TOTAL

3.2 Solado de limpieza 0.20x0.10.1x040 14MPa ACTIVIDAD


MATERIALES
Descripción Unidad Cantidad
CONCRETO 1:3:6 M3 20.1

SUBTOTAL
MANO DE OBRA
CUADRILLA AA ALBAÑILERIA Colocación H/C 0.25
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 5%

SUBTOTAL
TOTAL

Vigas de cimentación 0,20 m x 0,25 m f'c 21MPa (210


3.3 kg/cm2) 1:2:3
ACTIVIDAD
MATERIALES
Descripción Unidad Cantidad
AGUA LTR 200.00
ARENA GRUESA M3 0.002955
TRITURADO 1/2" M3 0.0041
CEMENTO GRIS * KILOS Argos KG 1.54
SUBTOTAL
MANO DE OBRA

Trabajador Unidad Rendimiento

CUADRILLA 1:3 ALBAÑILERIA preparación H/C 0.050


CUADRILLA 1:3 ALBAÑILERIA Colocación H/C 0.06
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 0.02
Cuadrilla 1:3 DÍA 0.09
mezcladora DIA 0.09
SUBTOTAL
TOTAL

Sobrecimiento en bloque de concreto de 0.20x0.10.1x040


3.4 ACTIVIDAD
14MPa incluye mortero impemeabilizado.
MATERIALES
Descripción Unidad Cantidad
LAD. BLOQUE CCTO # 10 (0,10MX0,20MX0,40M) UN 477.00
MORTERO 1:3 M3 19.00
MORTERO 1:4 de revoque M3 39.00
SIKA 1 2 KG KG 2.000
SUBTOTAL
MANO DE OBRA
Trabajador Unidad Rendimiento
CUADRILLA 1:3 ALBAÑILERIA Muro H/C 0.050
CUADRILLA 1:3 ALBAÑILERIA revoque impermeabilizado H/C 0.050
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 2%
CORTADORA DE LADRILLO (SIN DISCO) DIA 5%
DISCO T 27 9*1/8 ABRASIVO CORTE REFRAC 1/8 x 9T27" UND 5%
SUBTOTAL
TOTAL

3.5 Columna confinamiento 0.10mx0,20m. Concreto 21MPa ACTIVIDAD


MATERIALES
Descripción Unidad Cantidad
AGUA LTR 220.00
ARENA GRUESA M3 55.00
TRITURADO 1/2" M3 77.00
CEMENTO GRIS * KILOS argos KG 50.00
SEPAROL PREMIUM Kg 3.00
PUNTILLA DE 2 1/2" PUMA LBR 1.00
TABLA FORMALETA 1" x 10" 3,0 MTS UN 76.00
TRABILLAS 4*2CM x 3 ML UN 152.00
SUBTOTAL
MANO DE OBRA
Trabajador Unidad Rendimiento
CUADRILLA 1:3 ALBAÑILERIA preparación H/C 6.00
CUADRILLA 1:3 ALBAÑILERIA Colocación H/C 5.00
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 5.00
CONCRETADORA DE 1.5 SACO DIESEL DÍA 6.00
SUBTOTAL
TOTAL

3.6 Viga de confinamiento 0,10mx 0,20m ACTIVIDAD


MATERIALES
Descripción Unidad Cantidad
SEPAROL 3 KG UN 3.00
PUNTILLA DE 2 1/2" PUMA LBR 1.00
TABLA PARA FORMALETA UN 64.00
TRABILLAS 4*2CM UN 140.00
CONCRETO 21 Mpa (1:2:3) M3 360.000
SUBTOTAL
MANO DE OBRA
Trabajador Unidad Rendimiento
CUADRILLA 1:3 ALBAÑILERIA Colocación H/C 6.00
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 5.00
ANDAMIO TUBULAR DE 1.5 M.(SECCIÓN) DIA 6.00
SUBTOTAL
TOTAL

4 MAMPOSTERIA Y PAÑETES
4.1 Muro en bloque de concreto (0.20x0.10x0.40) ACTIVIDAD
MATERIALES
Descripción Unidad Cantidad
LAD. BLOQUE CCTO # 10 UN 477.00
MORTERO 1:3 M3 39.00
SUBTOTAL
MANO DE OBRA
Trabajador Unidad Rendimiento
CUADRILLA 1:2 ALBAÑILERIA H/C 2.00
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 4.00
ANDAMIO TUBULAR DE 1.5 M.(SECCIÓN) DIA 6.00
SUBTOTAL
TOTAL

4.2 Revoque de muros en mortero 1:4 ACTIVIDAD


MATERIALES
Descripción Unidad Cantidad
MORTERO 1:4 M3 39.00
AGUA L 982.00
SUBTOTAL
MANO DE OBRA
Trabajador Unidad Rendimiento
CUADRILLA 1:2 ALBAÑILERIA H/C 2.00
SUBTOTAL
EQUIPOS Y/O MAQUINARIAS
Equipo y/o Maquinaria Unidad Rendimiento
HERRAMIENTA MENOR % H/C 5.00
CONCRETADORA DE 1.5 SACO DIESEL DÍA 6.00

SUBTOTAL
TOTAL

VALOR TOTAL CANTIDADES


UND
ACTIVIDAD m²

Valor Unitario Valor Parcial


$ 2,900.00 $ 58,000.00
$ 8,000.00 $ 72,000.00
SUBTOTAL $ 130,000.00

Tarifa/(hora o dia) Valor Parcial


22,204.00 $ 444.08
SUBTOTAL $ 444.08

Tarifa/(hora o dia) Valor Parcial


$ 444.08 $ 22.20
SUBTOTAL $ 22.20
TOTAL $ 130,466.28

ACTIVIDAD m²/m3

Valor Unitario Valor Parcial

$ 19,106.00 $ 1,146,360.00

$ 19,106.00 $ 1,222.78
SUBTOTAL $ 1,147,583

Tarifa/(hora o dia) Valor Parcial


22,204.00 $ 2,664.48
SUBTOTAL $ 2,664.48

Tarifa/(hora o dia) Valor Parcial


$ 2,664.48 $ 133.22
SUBTOTAL $ 133.22
TOTAL $ 1,150,380.49

UND
ACTIVIDAD m3

Valor Unitario Valor Parcial


$ 130,458.00 $ 7,827,480.00
SUBTOTAL

Tarifa/(hora o dia) Valor Parcial


22,204.00 $ 1,332.24
SUBTOTAL $ 7,828,812.24
Tarifa/(hora o dia) Valor Parcial
$ 2,664.00 $ 159.84
SUBTOTAL $ 159.84
TOTAL $ 7,828,972.08

ACTIVIDAD m²

Valor Unitario Valor Parcial


$ 130,458.00 $ 2,622,205.00

SUBTOTAL $ 2,622,205.00

$ 6,436.00 $ 1,609.00
SUBTOTAL $ 1,609.00

Tarifa/(hora o dia) Valor Parcial


$ 1,609.00 $ 80.45
$ 0.19
SUBTOTAL $ 80.64
TOTAL $ 2,623,894.64

ACTIVIDAD m

Valor Unitario Valor Parcial


$ -
$ 7,000.00 $ 20,685.00
$ 19,900.00 $ 8,159.00
$ 24,600.00 $ 37,884.00
SUBTOTAL $ 66,728.00

Tarifa/(hora o dia) Valor Parcial

$ 28,640.00 $ 1,432.00
$ 31,504.00 $ 1,890.24
$ 3,322.24

Tarifa/(hora o dia) Valor Parcial


$ 3,322.00 $ 6,644.00
$ 28,640.00 $ 2,577.60
$ 1,256.00 $ 113.04
$ 9,334.64
TOTAL $ 79,384.88

ACTIVIDAD m

Valor Unitario Valor Parcial


$ 750.00 $ 357,750.00
$ 130,458.00 $ 2,478,702.00
$ 35,076.00 $ 1,367,964.00
$ 38,900.00 $ 77,800.00
$ 4,282,216.00

Tarifa/(hora o dia) Valor Parcial


$ 31,504.00 $ 1,575.20
$ 31,504.00 $ 1,575.20
$ 3,150.40

Tarifa/(hora o dia) Valor Parcial


$ 14,748.00 $ 294.96
$ 42,900.00 $ 2,145.00
$ 13,900.00 $ 695.00
$ 3,135
TOTAL $ 4,288,501.36

ACTIVIDAD m

Valor Unitario Valor Parcial


$ 110.00 $ 24,200.00
$ 7,000.00 $ 385,000.00
$ 7,500.00 $ 577,500.00
$ 24,900.00 $ 1,245,000.00
$ 192,800.00 $ 578,400.00
$ 6,600.00 $ 6,600.00
$ 520.00 $ 39,520.00
$ 600.00 $ 91,200.00
SUBTOTAL $ 2,947,420.00

Tarifa/(hora o dia) Valor Parcial


$ 22,204.00 $ 133,224.00
$ 22,204.00 $ 111,020.00
SUBTOTAL $ 244,244.00

Tarifa/(hora o dia) Valor Parcial


$ 20,293.00 $ 101,465.00
$ 3,384.00 $ 20,304.00
SUBTOTAL $ 121,769.00
TOTAL $ 3,313,433.00

ACTIVIDAD m

Valor Unitario Valor Parcial


$ 192,800.00 $ 578,400.00
$ 6,600.00 $ 6,600.00
$ 520.00 $ 33,280.00
$ 600.00 $ 84,000.00
$ 39,400.00 $ 14,184,000.00
SUBTOTAL $ 14,886,280.00

Tarifa/(hora o dia) Valor Parcial


$ 28,640.00 $ 171,840.00
SUBTOTAL $ 171,840.00

Tarifa/(hora o dia) Valor Parcial


$ 20,293.00 $ 101,465.00
$ 1,290.00 $ 7,740.00
SUBTOTAL $ 109,205.00
TOTAL $ 15,167,325.00

UND
ACTIVIDAD m²

Valor Unitario Valor Parcial


$ 750.00 $ 357,750.00
$ 130,458.00 $ 5,087,862.00
SUBTOTAL $ 5,445,612.00

Tarifa/(hora o dia) Valor Parcial


$ 22,204.00 $ 44,408.00
SUBTOTAL $ 44,408.00

Tarifa/(hora o dia) Valor Parcial


$ 14,848.00 $ 59,392.00
$ 1,290.00 $ 7,740.00
SUBTOTAL $ 67,132
TOTAL $ 5,557,152.00

ACTIVIDAD m²

Valor Unitario Valor Parcial


$ 130,458.00 $ 5,087,862.00
$ 110.00 $ 108,020.00
SUBTOTAL $ 5,195,882.00

Tarifa/(hora o dia) Valor Parcial


$ 22,204.00 $ 44,408.00
SUBTOTAL $ 44,408.00

Tarifa/(hora o dia) Valor Parcial


$ 20,293.00 $ 101,465.00
$ 3,384.00 $ 20,304.00

SUBTOTAL $ 121,769
TOTAL $ 5,362,059.00

$ 45,501,568.73
APRENDIZ: Andrea Sanchez Acevedo
NUMERO DE FICHA: 2422756
CIUDAD Y FECHA DE REALIZACION: Tunja, 18 de Octubre de 2021

ITEM ACTIVIDAD UNIDAD


1. PRELIMINARES
1.1 localizacion y replanteo m2
1.2 cerramiento en polisombra m
2. EXCAVACIONES
2.1 excavacion redes de servicio H=0.1 m m2
2.3 excavacion para caja de inspeccion 0.8 x 0.8 x 0.1 m3
3. ESTRUCTURAS
3. 1 estructuras de concreto
3. 2 cocreto ciclopeo 0.40 x 0.30X1M m3
3. 3 concreto viga de cimentacion con refuerzo 0.20 x 0.25 m2
3. 4 concreto columna de confinamiento 0.10 x 0.20 m3
3. 5 concreto viga de fundacion 0.40 x 0.40 m2
3. 6 concreto viga futura de fundacion 0.40 x 0.30 m2
3. 7 concreto viga de confinamiento 0.10 x 0.20 m2
3. 8 sobrecimiento en bloque de concreto 0.20 x 0.10 x 0.40 m3
4. MAMPOSTERIA
4.1 ladrillo de arcilla cocido de 0.10 m para muros en un total de 52.46 m un
pañete 1:5 e= 2cm Consume 7.5 bolsas de cemento y 1.05 m3 de arena gruesa
para 0.19476 m3/m2. precio basico de mano de obra aplicación de pañete m2
4.2
CANTIDAD VALOR UNITARIO VALOR TOTAL

60 $ 2,525 $ 151,500
8 $ 6,345 $ 50,760

60 $ 19,106 $ 1,146,360
0.064 $ 19,106 $ 1,222,784

60 $ 130,458 $ 7,827,480
37.57 $ 130,458 $ 4,901,307
20 $ 130,458 $ 2,609,160
37.57 $ 130,458 $ 4,901,307
14.13 $ 130,458 $ 1,843,371
29.95 $ 130,458 $ 3,907,217
20.1 $ 130,458 $ 2,622,206

477 $ 750 $ 357,750

194.76 $ 9,391 $ 1,828,991


VALOR REAL SALARIO 2021

1 MINIMO
SALARIO VALOR

Mensual $ 908,526.00
Subsidio de transporte $ 106,454.00
Total Mensual $ 1,014,980.00
Anual (A/30x365) $ 11,053,733.00
Anual con subsidio de transporte $ 12,331,181.00
Subsidio de transporte Anual (incluido en E) $ 1,167,445.53

CONCEPTO BASE FACTOR Valor Anual


SALARIO
Salario anual (365 dias) $ 11,053,733.00
Subsidio Transporte $ 1,167,445.53
PRESTACIONES
Cesantia anual E 36/365 $ 1,216,226.00
Interes cesantia Cesantia 12.00% $ 145,947.12
Vacaciones - 15 dias A 50.00% $ 454,263.00
Prima 30 dias C 100.00% $ 1,014,980.00
OTROS COSTOS
Botas y overol $ 95,000.00 3 $ 285,000.00
Seguro colectivo D 0.50% $ 55,269.00
SEGURIDAD SOCIAL
Pensiones D 12.00% $ 1,326,448.00
Salud D 8.50% $ 939,567.00
Riesgos Profesionales D 6.96% $ 769,340.00
APORTES SENA
Aporte ordinario D 2.00% $ 221,075.00
Fondo Industria Construccion $ 272,557.80
OTROS APORTES
I.C.B.F. D 3.00% $ 331,612.00
Subsidio Familiar D 4.00% $ 442,149.00
VALOR REAL SALARIO ANUAL $ 19,695,612.45
$ 15,596,802.53
VALOR REAL SALARIO MENSUAL $ 1,641,301.00
$ 1,299,733.54
VALOR REAL SALARIO DIARIO $ 54,710.00
$ 43,324.45

VALOR REAL SALARIO HORA (8,5h/dia) 8.5 $ 6,436.00


TIPO DE CUADRILLA UND VALOR HORA
CUADRILLA AA ALBAÑILERÍA 0:1 H/C $ 6,436.00
CUADRILLA AA ALBAÑILERÍA 0:2 H/C $ 12,872.00
CUADRILLA AA ALBAÑILERÍA 1:0 H/C $ 9,332.00
CUADRILLA AA ALBAÑILERÍA 1:1 H/C $ 15,768.00
CUADRILLA AA ALBAÑILERÍA 1:2 H/C $ 22,204.00
CUADRILLA AA ALBAÑILERÍA 1:3 H/C $ 28,640.00
CUADRILLA AA ALBAÑILERÍA 1:4 H/C $ 35,076.00
CUADRILLA AA ALBAÑILERÍA 1:5 H/C $ 41,512.00
CUADRILLA BB INSTALACIONES 0:1 H/C $ 7,080.00
CUADRILLA BB INSTALACIONES 0:2 H/C $ 14,159.00
CUADRILLA BB INSTALACIONES 1:0 H/C $ 10,265.00
CUADRILLA BB INSTALACIONES 1:1 H/C $ 17,345.00
CUADRILLA BB INSTALACIONES 1:2 H/C $ 24,424.00
CUADRILLA BB INSTALACIONES 1:3 H/C $ 31,504.00
CUADRILLA BB INSTALACIONES 1:4 H/C $ 38,584.00
CUADRILLA BB INSTALACIONES 1:5 H/C $ 45,663.00
CUADRILLA CC PINTURA 0:1 H/C $ 7,401.00
CUADRILLA CC PINTURA 0:2 H/C $ 14,803.00
CUADRILLA CC PINTURA 1:0 H/C $ 10,732.00
CUADRILLA CC PINTURA 1:1 H/C $ 18,133.00
CUADRILLA CC PINTURA 1:2 H/C $ 25,535.00
CUADRILLA CC PINTURA 1:3 H/C $ 32,936.00
CUADRILLA CC PINTURA 1:4 H/C $ 40,337.00
CUADRILLA CC PINTURA 1:5 H/C $ 47,739.00
CUADRILLA DD CARPINTERÍA 0:1 H/C $ 7,723.00
CUADRILLA DD CARPINTERÍA 0:2 H/C $ 15,446.00
CUADRILLA DD CARPINTERÍA 1:0 H/C $ 11,198.00
CUADRILLA DD CARPINTERÍA 1:1 H/C $ 18,922.00
CUADRILLA DD CARPINTERÍA 1:2 H/C $ 26,645.00
CUADRILLA DD CARPINTERÍA 1:3 H/C $ 34,368.00
CUADRILLA DD CARPINTERÍA 1:4 H/C $ 42,091.00
CUADRILLA DD CARPINTERÍA 1:5 H/C $ 49,814.00
REAL SALARIO 2021

AYUDANTE OFICIAL
1 MINIMO 1.0 MINIMOS 1,5. MINIMOS
REFERENCIA VALOR REFERENCIA VALOR REFERENCIA

A $ 908,526.00 A $ 1,362,789.00 A
B $ 106,454.00 B $ 106,454.00 B
C $ 1,014,980.00 C $ 1,469,243.00 C
D $ 11,053,733.00 D $ 16,580,600.00 D
E $ 12,331,181.00 E $ 17,858,048.00 E
$ 1,167,445.53 $ 1,167,445.53

% Valor Anual % Valor Anual %

100% $ 11,053,733.00 100% $ 16,580,600.00 100%


10.56% $ 1,167,445.53 10.56% $ 1,167,445.53 7.04%

11.00% $ 1,216,226.00 11.00% $ 1,761,342.00 10.62%


1.32% $ 145,947.00 1.32% $ 211,361.00 1.27%
4.11% $ 454,263.00 4.11% $ 681,394.50 4.11%
9.18% $ 1,014,980.00 9.18% $ 1,469,243.00 8.86%

2.58% $ 285,000.00 2.58% $ 285,000.00 1.72%


0.50% $ 55,269.00 0.50% $ 82,903.00 0.50%

12.00% $ 1,326,448.00 12.00% $ 1,989,672.00 12.00%


8.50% $ 939,567.00 8.50% $ 1,409,351.00 8.50%
6.96% $ 769,340.00 6.96% $ 1,154,010.00 6.96%

2.00% $ 221,075.00 2.00% $ 331,612.00 2.00%


2.47% $ 272,557.80 2.47% $ 272,557.80 1.64%

3.00% $ 331,612.00 3.00% $ 497,418.00 3.00%


4.00% $ 442,149.00 4.00% $ 663,224.00 4.00%
178.18% $ 19,695,612.33 178.18% $ 28,557,133.83 172.23%

$ 1,641,301.00 $ 2,379,761.00

$ 54,710.00 $ 79,325.00

$ 6,436.00 $ 9,332.00

CUADRILLAS

CUADRILLA 0:1
CUADRILLA 0:2
CUADRILLA 1:0
CUADRILLA 1:1
CUADRILLA 1:2
CUADRILLA 1:3
CUADRILLA 1:4
CUADRILLA 1:5
VALOR HORA VALOR HORA VALOR HORA VALOR HORA
OFICIAL AYUDANTE CUADRILLA CUADRILLA CUADRILLA CUADRILLA
ALBAÑILERIA INSTALACIONES PINTURA CARPINTERIA
0 1 $ 6,436.00 $ 7,080.00 $ 7,401.00 $ 7,723.00
0 2 $ 12,872.00 $ 14,159.00 $ 14,803.00 $ 15,446.00
1 0 $ 9,332.00 $ 10,265.00 $ 10,732.00 $ 11,198.00
1 1 $ 15,768.00 $ 17,345.00 $ 18,133.00 $ 18,922.00
1 2 $ 22,204.00 $ 24,424.00 $ 25,535.00 $ 26,645.00
1 3 $ 28,640.00 $ 31,504.00 $ 32,936.00 $ 34,368.00
1 4 $ 35,076.00 $ 38,584.00 $ 40,337.00 $ 42,091.00
1 5 $ 41,512.00 $ 45,663.00 $ 47,739.00 $ 49,814.00

$ 22,204.00 42.03%
57.97%