ID Task Name Duration Start Finish Predecessors

1 CAMARAS DE INSPECCION DE C°A° 14 days Tue 4/01/08 Tue 4/15/08


2 CONCRETO f 'c=140kg/cm2; 1 day Wed 4/02/08 Thu 4/03/08 3
3 ACERO FY=4200kg/cm2, LOS 1 day Tue 4/01/08 Wed 4/02/08
4 CONCRETO f 'c=210 kg/cm2, 1 day Thu 4/10/08 Fri 4/11/08 5
5 ENCOFRADO Y DESENCOFRA 5 days Sat 4/05/08 Thu 4/10/08 6;13;14
6 ACERO FY=4200KG/CM2, CA 1 day Thu 4/03/08 Fri 4/04/08 2
7 CONCRETO f 'c=210 kg/cm2, 1 day Mon 4/14/08 Tue 4/15/08 8
8 ENCOFRADO Y DESENCOFRA 3 days Fri 4/11/08 Mon 4/14/08 9
9 ACERO FY=4200KG/CM2, DA 1 day Thu 4/10/08 Fri 4/11/08 5
10 CONCRETO f 'c=210 kg/cm2, 1 day Sun 4/13/08 Mon 4/14/08 12
11 ENCOFRADO Y DESENCOFRA 1 day Fri 4/11/08 Sat 4/12/08 4
12 ACERO FY=4200kg/cm2, LOS 1 day Sat 4/12/08 Sun 4/13/08 11
13 ESCALERA TIPO GATO DE AC.1 day Fri 4/04/08 Sat 4/05/08 6
14 TUBERIA DE LIMPIEZA PVC, D 1 day Fri 4/04/08 Sat 4/05/08 6
15 VALVULA COMPUERTA, D=6" 1 day Sat 4/05/08 Sun 4/06/08 14
16 TARRAJEO INTERIOR DE CAMA 3 days Fri 4/11/08 Mon 4/14/08 4
17 MARCO Y TAPA DE F°F° 1.00 x 1 day Mon 4/14/08 Tue 4/15/08 10
18 BUZON TIPO CHIMENEA, D= 1.209 days Tue 4/01/08 Thu 4/10/08
19 TUB. PVC PERF. C/REF. AC. 1 day Tue 4/01/08 Wed 4/02/08
20 CONCRETO SIMPLE f'c=140 k 1 day Sat 4/05/08 Sun 4/06/08 21
21 ENCOFRADO Y DESENCOFRA 2 days Thu 4/03/08 Sat 4/05/08 25
22 CONCRETO f 'c=175 kg/cm2, 1 day Tue 4/08/08 Wed 4/09/08 24
23 ENCOFRADO Y DESENCOFRAD 1 day Sun 4/06/08 Mon 4/07/08 20
24 ACERO FY=4200kg/cm2, LOS 1 day Mon 4/07/08 Tue 4/08/08 23
25 ESCALERA DE GATO DE AC.C 1 day Wed 4/02/08 Thu 4/03/08 19
26 MARCO Y TAPA DE F°F° D= 0. 1 day Wed 4/09/08 Thu 4/10/08 22
27 BUZON TIPO CHIMENEA, D= 1.203 days Tue 4/01/08 Fri 4/04/08
28 TUB. PVC PERF. C/REF. AC. 1 day Tue 4/01/08 Wed 4/02/08
29 CONCRETO SIMPLE f'c=140 k 1 day Tue 4/01/08 Wed 4/02/08
30 ENCOFRADO Y DESENCOFRA 3 days Tue 4/01/08 Fri 4/04/08
31 CONCRETO f 'c=175 kg/cm2, 1 day Tue 4/01/08 Wed 4/02/08
32 ENCOFRADO Y DESENCOFRAD 1 day Tue 4/01/08 Wed 4/02/08
33 ACERO FY=4200kg/cm2, LOS 1 day Tue 4/01/08 Wed 4/02/08
34 ESCALERA DE GATO DE AC.C 1 day Tue 4/01/08 Wed 4/02/08
35 MARCO Y TAPA DE F°F° D= 0. 1 day Tue 4/01/08 Wed 4/02/08
36 BUZON TIPO CHIMENEA, D= 1.203 days Tue 4/01/08 Fri 4/04/08
37 TUB. PVC PERF. C/REF. AC. 1 day Tue 4/01/08 Wed 4/02/08
38 CONCRETO SIMPLE f'c=140 k 1 day Tue 4/01/08 Wed 4/02/08
39 ENCOFRADO Y DESENCOFRA 3 days Tue 4/01/08 Fri 4/04/08
40 CONCRETO f 'c=175 kg/cm2, 1 day Tue 4/01/08 Wed 4/02/08
41 ENCOFRADO Y DESENCOFRAD 1 day Tue 4/01/08 Wed 4/02/08
42 ACERO FY=4200kg/cm2, LOS 1 day Tue 4/01/08 Wed 4/02/08
43 ESCALERA DE GATO DE AC.C 1 day Tue 4/01/08 Wed 4/02/08
44 MARCO Y TAPA DE F°F° D= 0. 1 day Tue 4/01/08 Wed 4/02/08
45 BUZON TIPO CHIMENEA, D= 1.204 days Tue 4/01/08 Sat 4/05/08
46 TUB. PVC PERF. C/REF. AC. 1 day Tue 4/01/08 Wed 4/02/08
47 CONCRETO SIMPLE f'c=140 k 2 days Tue 4/01/08 Thu 4/03/08
48 ENCOFRADO Y DESENCOFRA 4 days Tue 4/01/08 Sat 4/05/08
49 CONCRETO f 'c=175 kg/cm2, 1 day Tue 4/01/08 Wed 4/02/08
50 ENCOFRADO Y DESENCOFRAD 1 day Tue 4/01/08 Wed 4/02/08
51 ACERO FY=4200kg/cm2, LOS 1 day Tue 4/01/08 Wed 4/02/08
52 ESCALERA DE GATO DE AC.C 1 day Tue 4/01/08 Wed 4/02/08
53 MARCO Y TAPA DE F°F° D= 0. 1 day Tue 4/01/08 Wed 4/02/08
Resource Names

CEMENTO PORTLAND TIPO I (42.5 kg) [1848%],ACEITE PARA MOTOR GRADO 30[1%],GASOLINA 84 OCTANOS[52%],O
CAPATAZ[2%],OPERARIO[26%],OFICIAL[26%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[13%],ALAMBRE NEG
CEMENTO PORTLAND TIPO I (42.5 kg) [3606%],ACEITE PARA MOTOR GRADO 30[3%],GASOLINA 84 OCTANOS[106%]
CAPATAZ[18%],OPERARIO[92%],OFICIAL[92%],ALAMBRE NEGRO # 8[500%],CLAVOS P/ MADERA C. C. 3"[1126%],MAD
CAPATAZ[5%],OPERARIO[54%],OFICIAL[54%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[27%],ALAMBRE NEG
CEMENTO PORTLAND TIPO I (42.5 kg) [1959%],ACEITE PARA MOTOR GRADO 30[1%],GASOLINA 84 OCTANOS[58%],O
CAPATAZ[15%],OPERARIO[79%],OFICIAL[79%],ALAMBRE NEGRO # 8[258%],CLAVOS P/ MADERA C. C. 3"[582%],MAD
CAPATAZ[5%],OPERARIO[52%],OFICIAL[52%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[26%],ALAMBRE NEG
CEMENTO PORTLAND TIPO I (42.5 kg) [993%],ACEITE PARA MOTOR GRADO 30[0%],GASOLINA 84 OCTANOS[29%],O
CAPATAZ[4%],OPERARIO[46%],OFICIAL[46%],ALAMBRE NEGRO # 8[88%],CLAVOS P/ MADERA C. C. 3",MADERA TOR
CAPATAZ[1%],OPERARIO[11%],OFICIAL[11%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[5%],ALAMBRE NEGR
CAPATAZ[0%],OPERARIO[17%],OFICIAL[17%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[8%],ALAMBRE NEGR
PEGAMENTO PLASTICO PARA PVC CCP[1%],CAPATAZ[0%],OPERARIO[5%],PEON[5%],TUBO PVC DESAGUE SAL 6"X5
CAPATAZ[3%],OPERARIO[33%],CINTA TEFLON,VALVULA COMPUERTA LIVIANA DE 6"
CEMENTO PORTLAND TIPO I (42.5 kg) [415%],CAPATAZ[7%],OPERARIO[154%],PEON[77%],CLAVOS P/ MADERA C. C.
CAPATAZ[0%],OPERARIO[5%],PEON[2%],TAPA DE FIERRO FUNDIDO PARA DESAGUE 0.60m x 1.00m,MARCO Fª Fª P/

TUB. PVC PERF. C/REF. AC. D=1.20m (INC. PERFORACION Y EMPALME)[132%]


CEMENTO PORTLAND TIPO I (42.5 kg) [6363%],ACEITE PARA MOTOR GRADO 30[6%],GASOLINA 84 OCTANOS[181%]
CAPATAZ[17%],OPERARIO[87%],OFICIAL[87%],ALAMBRE NEGRO # 8[188%],CLAVOS P/ MADERA C. C. 3"[424%],MAD
CEMENTO PORTLAND TIPO I (42.5 kg) [714%],ACEITE PARA MOTOR GRADO 30[0%],GASOLINA 84 OCTANOS[12%],O
CAPATAZ[4%],OPERARIO[43%],OFICIAL[58%],PEON[29%],ALAMBRE NEGRO # 8[65%],CLAVOS P/ MADERA C. C. 3"[91
CAPATAZ[0%],OPERARIO[6%],OFICIAL[6%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[3%],ALAMBRE NEGRO
CAPATAZ[0%],OPERARIO[5%],OFICIAL[5%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[2%],ALAMBRE NEGRO
CAPATAZ[0%],OPERARIO[2%],PEON[1%],TAPA DE FIERRO FUNDIDO PARA DESAGUE D=0.60m,MARCO CIRCULAR F

TUB. PVC PERF. C/REF. AC. D=1.20m (INC. PERFORACION Y EMPALME)[165%]


CEMENTO PORTLAND TIPO I (42.5 kg) [8631%],ACEITE PARA MOTOR GRADO 30[8%],GASOLINA 84 OCTANOS[246%]
CAPATAZ[15%],OPERARIO[77%],OFICIAL[77%],ALAMBRE NEGRO # 8[249%],CLAVOS P/ MADERA C. C. 3"[561%],MAD
CEMENTO PORTLAND TIPO I (42.5 kg) [714%],ACEITE PARA MOTOR GRADO 30[0%],GASOLINA 84 OCTANOS[12%],O
CAPATAZ[4%],OPERARIO[43%],OFICIAL[58%],PEON[29%],ALAMBRE NEGRO # 8[65%],CLAVOS P/ MADERA C. C. 3"[91
CAPATAZ[0%],OPERARIO[6%],OFICIAL[6%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[3%],ALAMBRE NEGRO
CAPATAZ[0%],OPERARIO[7%],OFICIAL[7%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[3%],ALAMBRE NEGRO
CAPATAZ[0%],OPERARIO[2%],PEON[1%],TAPA DE FIERRO FUNDIDO PARA DESAGUE D=0.60m,MARCO CIRCULAR F

TUB. PVC PERF. C/REF. AC. D=1.20m (INC. PERFORACION Y EMPALME)[252%]


CEMENTO PORTLAND TIPO I (42.5 kg) [13174%],ACEITE PARA MOTOR GRADO 30[12%],GASOLINA 84 OCTANOS[376
CAPATAZ[19%],OPERARIO[96%],OFICIAL[96%],ALAMBRE NEGRO # 8[311%],CLAVOS P/ MADERA C. C. 3"[700%],MAD
CEMENTO PORTLAND TIPO I (42.5 kg) [714%],ACEITE PARA MOTOR GRADO 30[0%],GASOLINA 84 OCTANOS[12%],O
CAPATAZ[4%],OPERARIO[43%],OFICIAL[58%],PEON[29%],ALAMBRE NEGRO # 8[65%],CLAVOS P/ MADERA C. C. 3"[91
CAPATAZ[0%],OPERARIO[6%],OFICIAL[6%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[3%],ALAMBRE NEGRO
CAPATAZ[0%],OPERARIO[12%],OFICIAL[12%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[6%],ALAMBRE NEGR
CAPATAZ[0%],OPERARIO[2%],PEON[1%],TAPA DE FIERRO FUNDIDO PARA DESAGUE D=0.60m,MARCO CIRCULAR F

TUB. PVC PERF. C/REF. AC. D=1.20m (INC. PERFORACION Y EMPALME)[330%]


CEMENTO PORTLAND TIPO I (42.5 kg) [17157%],ACEITE PARA MOTOR GRADO 30[16%],GASOLINA 84 OCTANOS[490
CAPATAZ[17%],OPERARIO[86%],OFICIAL[86%],ALAMBRE NEGRO # 8[374%],CLAVOS P/ MADERA C. C. 3"[841%],MAD
CEMENTO PORTLAND TIPO I (42.5 kg) [714%],ACEITE PARA MOTOR GRADO 30[0%],GASOLINA 84 OCTANOS[12%],O
CAPATAZ[4%],OPERARIO[43%],OFICIAL[58%],PEON[29%],ALAMBRE NEGRO # 8[65%],CLAVOS P/ MADERA C. C. 3"[91
CAPATAZ[0%],OPERARIO[6%],OFICIAL[6%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[3%],ALAMBRE NEGRO
CAPATAZ[0%],OPERARIO[16%],OFICIAL[16%],CIZALLA FE CONSTRUCCION MANUAL HASTA 1"[8%],ALAMBRE NEGR
CAPATAZ[0%],OPERARIO[2%],PEON[1%],TAPA DE FIERRO FUNDIDO PARA DESAGUE D=0.60m,MARCO CIRCULAR F
1%],GASOLINA 84 OCTANOS[52%],OPERADOR DE EQUIPO LIVIANO[26%],CAPATAZ[1%],OPERARIO[13%],OFICIAL[13%],PEON[105
UAL HASTA 1"[13%],ALAMBRE NEGRO # 16[355%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[7455%]
3%],GASOLINA 84 OCTANOS[106%],OPERADOR DE EQUIPO LIVIANO[62%],CAPATAZ[6%],OPERARIO[62%],OFICIAL[31%],PEON[37
OS P/ MADERA C. C. 3"[1126%],MADERA TORNILLO LARGA[16988%]
UAL HASTA 1"[27%],ALAMBRE NEGRO # 16[728%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[15653%]
1%],GASOLINA 84 OCTANOS[58%],OPERADOR DE EQUIPO LIVIANO[34%],CAPATAZ[3%],OPERARIO[34%],OFICIAL[17%],PEON[204
OS P/ MADERA C. C. 3"[582%],MADERA TORNILLO LARGA[8774%]
UAL HASTA 1"[26%],ALAMBRE NEGRO # 16[692%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[14881%]
%],GASOLINA 84 OCTANOS[29%],OPERADOR DE EQUIPO LIVIANO[10%],CAPATAZ[1%],OPERARIO[10%],OFICIAL[5%],PEON[64%],
S P/ MADERA C. C. 3",MADERA TORNILLO LARGA[2818%]
UAL HASTA 1"[5%],ALAMBRE NEGRO # 16[161%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[3381%]
UAL HASTA 1"[8%],ALAMBRE NEGRO # 8[140%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[4760%]
[5%],TUBO PVC DESAGUE SAL 6"X5M[21%]

ON[77%],CLAVOS P/ MADERA C. C. 3"[69%],ARENA FINA[69%],AGUA[17%],MADERA TORNILLO LARGA[1594%]


GUE 0.60m x 1.00m,MARCO Fª Fª P/ DESAGUE 0.60m x 1.00m E= 2mm

6%],GASOLINA 84 OCTANOS[181%],OPERADOR DE EQUIPO LIVIANO[90%],CAPATAZ[22%],OPERARIO[90%],OFICIAL[45%],PEON[3


OS P/ MADERA C. C. 3"[424%],MADERA TORNILLO LARGA[6393%]
%],GASOLINA 84 OCTANOS[12%],OPERADOR DE EQUIPO LIVIANO[8%],CAPATAZ[0%],OPERARIO[8%],OFICIAL[4%],PEON[51%],ME
5%],CLAVOS P/ MADERA C. C. 3"[91%],MADERA TORNILLO [3872%]
L HASTA 1"[3%],ALAMBRE NEGRO # 16[81%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[1703%]
L HASTA 1"[2%],ALAMBRE NEGRO # 8[65%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[2188%]
GUE D=0.60m,MARCO CIRCULAR Fª Fª P/ DESAGUE 0.60m E= 2mm

8%],GASOLINA 84 OCTANOS[246%],OPERADOR DE EQUIPO LIVIANO[123%],CAPATAZ[30%],OPERARIO[123%],OFICIAL[61%],PEO


OS P/ MADERA C. C. 3"[561%],MADERA TORNILLO LARGA[8461%]
%],GASOLINA 84 OCTANOS[12%],OPERADOR DE EQUIPO LIVIANO[8%],CAPATAZ[0%],OPERARIO[8%],OFICIAL[4%],PEON[51%],ME
5%],CLAVOS P/ MADERA C. C. 3"[91%],MADERA TORNILLO [3872%]
L HASTA 1"[3%],ALAMBRE NEGRO # 16[81%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[1703%]
L HASTA 1"[3%],ALAMBRE NEGRO # 8[91%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[3063%]
GUE D=0.60m,MARCO CIRCULAR Fª Fª P/ DESAGUE 0.60m E= 2mm

0[12%],GASOLINA 84 OCTANOS[376%],OPERADOR DE EQUIPO LIVIANO[188%],CAPATAZ[47%],OPERARIO[188%],OFICIAL[94%],PE


OS P/ MADERA C. C. 3"[700%],MADERA TORNILLO LARGA[10561%]
%],GASOLINA 84 OCTANOS[12%],OPERADOR DE EQUIPO LIVIANO[8%],CAPATAZ[0%],OPERARIO[8%],OFICIAL[4%],PEON[51%],ME
5%],CLAVOS P/ MADERA C. C. 3"[91%],MADERA TORNILLO [3872%]
L HASTA 1"[3%],ALAMBRE NEGRO # 16[81%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[1703%]
UAL HASTA 1"[6%],ALAMBRE NEGRO # 8[143%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[4813%]
GUE D=0.60m,MARCO CIRCULAR Fª Fª P/ DESAGUE 0.60m E= 2mm

0[16%],GASOLINA 84 OCTANOS[490%],OPERADOR DE EQUIPO LIVIANO[122%],CAPATAZ[30%],OPERARIO[122%],OFICIAL[61%],PE


OS P/ MADERA C. C. 3"[841%],MADERA TORNILLO LARGA[12686%]
%],GASOLINA 84 OCTANOS[12%],OPERADOR DE EQUIPO LIVIANO[8%],CAPATAZ[0%],OPERARIO[8%],OFICIAL[4%],PEON[51%],ME
5%],CLAVOS P/ MADERA C. C. 3"[91%],MADERA TORNILLO [3872%]
L HASTA 1"[3%],ALAMBRE NEGRO # 16[81%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[1703%]
UAL HASTA 1"[8%],ALAMBRE NEGRO # 8[188%],ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60[6345%]
GUE D=0.60m,MARCO CIRCULAR Fª Fª P/ DESAGUE 0.60m E= 2mm
RARIO[13%],OFICIAL[13%],PEON[105%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [13%],VIBRADOR DE CONCRETO G
DO 60[7455%]
RARIO[62%],OFICIAL[31%],PEON[376%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [31%],VIBRADOR DE CONCRETO

DO 60[15653%]
RARIO[34%],OFICIAL[17%],PEON[204%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [17%],VIBRADOR DE CONCRETO G

DO 60[14881%]
ARIO[10%],OFICIAL[5%],PEON[64%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [5%],VIBRADOR DE CONCRETO GASO

O 60[3381%]

LARGA[1594%]

ERARIO[90%],OFICIAL[45%],PEON[363%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [45%],VIBRADOR DE CONCRETO

RIO[8%],OFICIAL[4%],PEON[51%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [4%],VIBRADOR DE CONCRETO GASOL

PERARIO[123%],OFICIAL[61%],PEON[493%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [61%],VIBRADOR DE CONCRE

RIO[8%],OFICIAL[4%],PEON[51%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [4%],VIBRADOR DE CONCRETO GASOL

,OPERARIO[188%],OFICIAL[94%],PEON[752%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [94%],VIBRADOR DE CONC

RIO[8%],OFICIAL[4%],PEON[51%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [4%],VIBRADOR DE CONCRETO GASOL

,OPERARIO[122%],OFICIAL[61%],PEON[490%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [61%],VIBRADOR DE CONC

RIO[8%],OFICIAL[4%],PEON[51%],MEZCLADORA DE CONCRETO TAMBOR 20-35 HP 16 p3 [4%],VIBRADOR DE CONCRETO GASOL


3 [13%],VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[13%],PIEDRA CHANCADA DE 1/2"[211%],ARENA GRUESA[198%],AGUA[4

p3 [31%],VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[31%],PIEDRA CHANCADA DE 1/2"[313%],ARENA GRUESA[196%],AGUA[

3 [17%],VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[17%],PIEDRA CHANCADA DE 1/2"[170%],ARENA GRUESA[106%],AGUA[3

%],VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[5%],PIEDRA CHANCADA DE 1/2"[86%],ARENA GRUESA[54%],AGUA[19%],GRA

p3 [45%],VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[45%],PIEDRA CHANCADA DE 1/2"[727%],ARENA GRUESA[681%],AGUA

VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[4%],PIEDRA CHANCADA DE 1/2"[68%],ARENA GRUESA[42%],AGUA[15%],GRAS

16 p3 [61%],VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[61%],PIEDRA CHANCADA DE 1/2"[986%],ARENA GRUESA[924%],AG

VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[4%],PIEDRA CHANCADA DE 1/2"[68%],ARENA GRUESA[42%],AGUA[15%],GRAS

P 16 p3 [94%],VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[94%],PIEDRA CHANCADA DE 1/2"[1505%],ARENA GRUESA[1411%

VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[4%],PIEDRA CHANCADA DE 1/2"[68%],ARENA GRUESA[42%],AGUA[15%],GRAS

P 16 p3 [61%],VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[61%],PIEDRA CHANCADA DE 1/2"[1960%],ARENA GRUESA[1838%

VIBRADOR DE CONCRETO GASOLINA 5 HP 1.50"[4%],PIEDRA CHANCADA DE 1/2"[68%],ARENA GRUESA[42%],AGUA[15%],GRAS


1%],ARENA GRUESA[198%],AGUA[47%],GRASA POTE 200 GR [3%]

13%],ARENA GRUESA[196%],AGUA[72%],GRASA POTE 200 GR [7%]

0%],ARENA GRUESA[106%],AGUA[39%],GRASA POTE 200 GR [3%]

ENA GRUESA[54%],AGUA[19%],GRASA POTE 200 GR [1%]

727%],ARENA GRUESA[681%],AGUA[163%],GRASA POTE 200 GR [12%]

A GRUESA[42%],AGUA[15%],GRASA POTE 200 GR [0%]

2"[986%],ARENA GRUESA[924%],AGUA[221%],GRASA POTE 200 GR [16%]

A GRUESA[42%],AGUA[15%],GRASA POTE 200 GR [0%]

1/2"[1505%],ARENA GRUESA[1411%],AGUA[338%],GRASA POTE 200 GR [25%]

A GRUESA[42%],AGUA[15%],GRASA POTE 200 GR [0%]

1/2"[1960%],ARENA GRUESA[1838%],AGUA[441%],GRASA POTE 200 GR [32%]

A GRUESA[42%],AGUA[15%],GRASA POTE 200 GR [0%]


ID Resource name Type Material label Initials Group Max.Units

1 OPERADOR DE EQUIPO LIVIANOWork O Mano de Ob65%


2 CAPATAZ Work C Mano de Ob47%
3 OPERARIO Work O Mano de Ob281%
4 OFICIAL Work O Mano de Ob212%
5 PEON Work P Mano de Ob312%
6 ACEITE PARA MOTOR GRADO 3 Work A Material 100%
7 ALAMBRE NEGRO # 16 Work A Material 100%
8 ALAMBRE NEGRO # 8 Work A Material 100%
9 CLAVOS P/ MADERA C. C. 3" Work C Material 100%
10 ACERO CORRUGADO fy=4200 kg Work A Material 100%
11 ARENA FINA Work A Material 100%
12 PIEDRA CHANCADA DE 1/2" Work P Material 100%
13 ARENA GRUESA Work A Material 100%
14 CEMENTO PORTLAND TIPO I (42.5Work C Material 100%
15 VALVULA COMPUERTA LIVIANA DWork V Material 100%
16 PEGAMENTO PLASTICO PARA P Work P Material 100%
17 CINTA TEFLON Work C Material 100%
18 GASOLINA 84 OCTANOS Work G Material 100%
19 AGUA Work A Material 100%
20 MADERA TORNILLO Work M Material 100%
21 MADERA TORNILLO LARGA Work M Material 100%
22 TAPA DE FIERRO FUNDIDO PARAWork T Material 100%
23 MARCO Fª Fª P/ DESAGUE 0.60m Work M Material 100%
24 TAPA DE FIERRO FUNDIDO PAR Work T Material 100%
25 MARCO CIRCULAR Fª Fª P/ DESAWork M Material 100%
26 GRASA POTE 200 GR Work G Material 100%
27 TUBO PVC DESAGUE SAL 6"X5M Work T Material 100%
28 HERRAMIENTAS MANUALES Work H Equipo 10000%
29 MEZCLADORA DE CONCRETO TAM Work M Equipo 32%
30 CIZALLA FE CONSTRUCCION MAWork C Equipo 9%
31 VIBRADOR DE CONCRETO GASOLI Work V Equipo 32%
32 TUB. PVC PERF. C/REF. AC. D Work T Subcontrat 8%
Std.Rate Ovt.Rate Cost/Use Accrue At Base Calendar Code

S12.23/hr S0.00/hr S 0.00 Prorated Estándar 0147000022


S15.90/hr S0.00/hr S 0.00 Prorated Estándar 0147010001
S12.23/hr S0.00/hr S 0.00 Prorated Estándar 0147010002
S10.89/hr S0.00/hr S 0.00 Prorated Estándar 0147010003
S9.85/hr S0.00/hr S 0.00 Prorated Estándar 0147010004
S0.00/hr S0.00/hr S 41.17 Prorated Estándar 0201030002
S0.00/hr S0.00/hr S 4.73 Prorated Estándar 0202000010
S0.00/hr S0.00/hr S 4.20 Prorated Estándar 0202000015
S0.00/hr S0.00/hr S 4.20 Prorated Estándar 0202010022
S0.00/hr S0.00/hr S 2.49 Prorated Estándar 0203020003
S0.00/hr S0.00/hr S 18.77 Prorated Estándar 0204000000
S0.00/hr S0.00/hr S 39.50 Prorated Estándar 0205000003
S0.00/hr S0.00/hr S 23.53 Prorated Estándar 0205010004
S0.00/hr S0.00/hr S 14.29 Prorated Estándar 0221000001
S0.00/hr S0.00/hr S 20.00 Prorated Estándar 0230090011
S0.00/hr S0.00/hr S 127.40 Prorated Estándar 0230460019
S0.00/hr S0.00/hr S 1.47 Prorated Estándar 0230480032
S0.00/hr S0.00/hr S 8.40 Prorated Estándar 0234000000
S0.00/hr S0.00/hr S 1.83 Prorated Estándar 0239050000
S0.00/hr S0.00/hr S 3.00 Prorated Estándar 0243040000
S0.00/hr S0.00/hr S 3.00 Prorated Estándar 0243040005
S0.00/hr S0.00/hr S 50.00 Prorated Estándar 0250010013
S0.00/hr S0.00/hr S 60.00 Prorated Estándar 0250010014
S0.00/hr S0.00/hr S 30.00 Prorated Estándar 0250010015
S0.00/hr S0.00/hr S 35.00 Prorated Estándar 0250010016
S0.00/hr S0.00/hr S 3.78 Prorated Estándar 0253010003
S0.00/hr S0.00/hr S 81.60 Prorated Estándar 0274010032
S8.00/hr S0.00/hr S 0.00 Prorated Estándar 0337010001
S31.45/hr S0.00/hr S 0.00 Prorated Estándar 0348010086
S1.55/hr S0.00/hr S 0.00 Prorated Estándar 0348960009
S11.76/hr S0.00/hr S 0.00 Prorated Estándar 0349520055
S0.00/hr S0.00/hr S 690.00 Prorated Estándar 0401080005
Uid Task name Resource name Work Duration
3 CONCRETO f 'c=140kgCEMENTO PORTLAND0TIhrs 1 day
4 CONCRETO f 'c=140kgACEITE PARA MOTOR0 hrs 1 day
5 CONCRETO f 'c=140kgGASOLINA 84 OCTAN 0 hrs 1 day
6 CONCRETO f 'c=140kgOPERADOR DE EQUIP2.11 hrs 1 day
7 CONCRETO f 'c=140kgCAPATAZ 0.1 hrs 1 day
8 CONCRETO f 'c=140kgOPERARIO 1.06 hrs 1 day
9 CONCRETO f 'c=140kgOFICIAL 1.06 hrs 1 day
10 CONCRETO f 'c=140kgPEON 8.45 hrs 1 day
11 CONCRETO f 'c=140kgMEZCLADORA DE CONC 1.06 hrs 1 day
12 CONCRETO f 'c=140kgVIBRADOR DE CONCRE 1.06 hrs 1 day
13 CONCRETO f 'c=140kgPIEDRA CHANCADA DE 0 hrs 1 day
14 CONCRETO f 'c=140kgARENA GRUESA 0 hrs 1 day
15 CONCRETO f 'c=140kgAGUA 0 hrs 1 day
16 CONCRETO f 'c=140kgGRASA POTE 200 GR 0 hrs 1 day
18 ACERO FY=4200kg/cmCAPATAZ 0.21 hrs 1 day
19 ACERO FY=4200kg/cmOPERARIO 2.1 hrs 1 day
20 ACERO FY=4200kg/cmOFICIAL 2.1 hrs 1 day
21 ACERO FY=4200kg/cmCIZALLA FE CONSTRU1.05 hrs 1 day
22 ACERO FY=4200kg/cmALAMBRE NEGRO # 1 28.4 hrs 1 day
23 ACERO FY=4200kg/cmACERO CORRUGADO 596.4
fy hrs 1 day
25 CONCRETO f 'c=210 k CEMENTO PORTLAND0TIhrs 1 day
26 CONCRETO f 'c=210 k ACEITE PARA MOTOR0 hrs 1 day
27 CONCRETO f 'c=210 k GASOLINA 84 OCTAN 0 hrs 1 day
28 CONCRETO f 'c=210 k OPERADOR DE EQUIP5.02 hrs 1 day
29 CONCRETO f 'c=210 k CAPATAZ 0.5 hrs 1 day
30 CONCRETO f 'c=210 k OPERARIO 5.02 hrs 1 day
31 CONCRETO f 'c=210 k OFICIAL 2.51 hrs 1 day
32 CONCRETO f 'c=210 k PEON 30.1 hrs 1 day
33 CONCRETO f 'c=210 k MEZCLADORA DE CONC2.51 hrs 1 day
34 CONCRETO f 'c=210 k VIBRADOR DE CONCRE2.51 hrs 1 day
35 CONCRETO f 'c=210 k PIEDRA CHANCADA DE0 hrs 1 day
36 CONCRETO f 'c=210 k ARENA GRUESA 0 hrs 1 day
37 CONCRETO f 'c=210 k AGUA 0 hrs 1 day
38 CONCRETO f 'c=210 k GRASA POTE 200 GR 0 hrs 1 day
40 ENCOFRADO Y DESE CAPATAZ 7.42 hrs 5 days
41 ENCOFRADO Y DESE OPERARIO 37.1 hrs 5 days
42 ENCOFRADO Y DESE OFICIAL 37.1 hrs 5 days
43 ENCOFRADO Y DESE ALAMBRE NEGRO # 80 hrs 5 days
44 ENCOFRADO Y DESE CLAVOS P/ MADERA C. 0 hrs 5 days
45 ENCOFRADO Y DESE MADERA TORNILLO L 0 hrs 5 days
47 ACERO FY=4200KG/C CAPATAZ 0.44 hrs 1 day
48 ACERO FY=4200KG/C OPERARIO 4.4 hrs 1 day
49 ACERO FY=4200KG/C OFICIAL 4.4 hrs 1 day
50 ACERO FY=4200KG/C CIZALLA FE CONSTRU2.2 hrs 1 day
51 ACERO FY=4200KG/C ALAMBRE NEGRO # 1 58.24 hrs 1 day
52 ACERO FY=4200KG/C ACERO CORRUGADO 1252.24
fy hrs1 day
54 CONCRETO f 'c=210 CEMENTO PORTLAND0TIhrs 1 day
55 CONCRETO f 'c=210 ACEITE PARA MOTOR0 hrs 1 day
56 CONCRETO f 'c=210 GASOLINA 84 OCTAN 0 hrs 1 day
57 CONCRETO f 'c=210 OPERADOR DE EQUIP2.72 hrs 1 day
58 CONCRETO f 'c=210 CAPATAZ 0.27 hrs 1 day
59 CONCRETO f 'c=210 OPERARIO 2.72 hrs 1 day
60 CONCRETO f 'c=210 OFICIAL 1.36 hrs 1 day
61 CONCRETO f 'c=210 PEON 16.36 hrs 1 day
62 CONCRETO f 'c=210 MEZCLADORA DE CONC 1.36 hrs 1 day
63 CONCRETO f 'c=210 VIBRADOR DE CONCRE 1.36 hrs 1 day
64 CONCRETO f 'c=210 PIEDRA CHANCADA DE 0 hrs 1 day
65 CONCRETO f 'c=210 ARENA GRUESA 0 hrs 1 day
66 CONCRETO f 'c=210 AGUA 0 hrs 1 day
67 CONCRETO f 'c=210 GRASA POTE 200 GR 0 hrs 1 day
69 ENCOFRADO Y DESE CAPATAZ 3.83 hrs 3 days
70 ENCOFRADO Y DESE OPERARIO 19.16 hrs 3 days
71 ENCOFRADO Y DESE OFICIAL 19.16 hrs 3 days
72 ENCOFRADO Y DESE ALAMBRE NEGRO # 80 hrs 3 days
73 ENCOFRADO Y DESE CLAVOS P/ MADERA C. 0 hrs 3 days
74 ENCOFRADO Y DESE MADERA TORNILLO L 0 hrs 3 days
76 ACERO FY=4200KG/C CAPATAZ 0.42 hrs 1 day
77 ACERO FY=4200KG/C OPERARIO 4.18 hrs 1 day
78 ACERO FY=4200KG/C OFICIAL 4.18 hrs 1 day
79 ACERO FY=4200KG/C CIZALLA FE CONSTRU2.09 hrs 1 day
80 ACERO FY=4200KG/C ALAMBRE NEGRO # 1 55.37 hrs 1 day
81 ACERO FY=4200KG/C ACERO CORRUGADO 1190.5
fy hrs 1 day
83 CONCRETO f 'c=210 k CEMENTO PORTLAND0TIhrs 1 day
84 CONCRETO f 'c=210 k ACEITE PARA MOTOR0 hrs 1 day
85 CONCRETO f 'c=210 k GASOLINA 84 OCTAN 0 hrs 1 day
86 CONCRETO f 'c=210 k OPERADOR DE EQUIP0.86 hrs 1 day
87 CONCRETO f 'c=210 k CAPATAZ 0.08 hrs 1 day
88 CONCRETO f 'c=210 k OPERARIO 0.86 hrs 1 day
89 CONCRETO f 'c=210 k OFICIAL 0.43 hrs 1 day
90 CONCRETO f 'c=210 k PEON 5.18 hrs 1 day
91 CONCRETO f 'c=210 k MEZCLADORA DE CONC0.43 hrs 1 day
92 CONCRETO f 'c=210 k VIBRADOR DE CONCRE0.43 hrs 1 day
93 CONCRETO f 'c=210 k PIEDRA CHANCADA DE0 hrs 1 day
94 CONCRETO f 'c=210 k ARENA GRUESA 0 hrs 1 day
95 CONCRETO f 'c=210 k AGUA 0 hrs 1 day
96 CONCRETO f 'c=210 k GRASA POTE 200 GR 0 hrs 1 day
98 ENCOFRADO Y DESE CAPATAZ 0.37 hrs 1 day
99 ENCOFRADO Y DESE OPERARIO 3.73 hrs 1 day
100 ENCOFRADO Y DESE OFICIAL 3.73 hrs 1 day
101 ENCOFRADO Y DESE ALAMBRE NEGRO # 87.06 hrs 1 day
102 ENCOFRADO Y DESE CLAVOS P/ MADERA C. 8.06 hrs 1 day
103 ENCOFRADO Y DESE MADERA TORNILLO L 225.46 hrs 1 day
105 ACERO FY=4200kg/cmCAPATAZ 0.1 hrs 1 day
106 ACERO FY=4200kg/cmOPERARIO 0.95 hrs 1 day
107 ACERO FY=4200kg/cmOFICIAL 0.95 hrs 1 day
108 ACERO FY=4200kg/cmCIZALLA FE CONSTRU0.48 hrs 1 day
109 ACERO FY=4200kg/cmALAMBRE NEGRO # 1 12.88 hrs 1 day
110 ACERO FY=4200kg/cmACERO CORRUGADO 270.48
fy hrs 1 day
112 ESCALERA TIPO GATO CAPATAZ 0.07 hrs 1 day
113 ESCALERA TIPO GATO OPERARIO 1.4 hrs 1 day
114 ESCALERA TIPO GATO OFICIAL 1.4 hrs 1 day
115 ESCALERA TIPO GATO CIZALLA FE CONSTRU0.7 hrs 1 day
116 ESCALERA TIPO GATO ALAMBRE NEGRO # 811.2 hrs 1 day
117 ESCALERA TIPO GATO ACERO CORRUGADO 380.8
fy hrs 1 day
119 TUBERIA DE LIMPIEZAPEGAMENTO PLASTIC0 hrs 1 day
120 TUBERIA DE LIMPIEZACAPATAZ 0.02 hrs 1 day
121 TUBERIA DE LIMPIEZAOPERARIO 0.44 hrs 1 day
122 TUBERIA DE LIMPIEZAPEON 0.44 hrs 1 day
123 TUBERIA DE LIMPIEZATUBO PVC DESAGUE 0 hrs 1 day
125 VALVULA COMPUERTA CAPATAZ 0.27 hrs 1 day
126 VALVULA COMPUERTA OPERARIO 2.67 hrs 1 day
127 VALVULA COMPUERTA CINTA TEFLON 0 hrs 1 day
128 VALVULA COMPUERTA VALVULA COMPUERTA 0 hrs 1 day
130 TARRAJEO INTERIOR CEMENTO
D PORTLAND0TIhrs 3 days
131 TARRAJEO INTERIOR CAPATAZ
D 1.85 hrs 3 days
132 TARRAJEO INTERIOR OPERARIO
D 36.97 hrs 3 days
133 TARRAJEO INTERIOR PEON
D 18.48 hrs 3 days
134 TARRAJEO INTERIOR CLAVOS
D P/ MADERA C.0 hrs 3 days
135 TARRAJEO INTERIOR ARENA
D FINA 0 hrs 3 days
136 TARRAJEO INTERIOR AGUA
D 0 hrs 3 days
137 TARRAJEO INTERIOR MADERA
D TORNILLO L 0 hrs 3 days
139 MARCO Y TAPA DE F°F°CAPATAZ 0.02 hrs 1 day
140 MARCO Y TAPA DE F°F°OPERARIO 0.4 hrs 1 day
141 MARCO Y TAPA DE F°F°PEON 0.2 hrs 1 day
142 MARCO Y TAPA DE F°F°TAPA DE FIERRO FUN8 hrs 1 day
143 MARCO Y TAPA DE F°F°MARCO Fª Fª P/ DESA8 hrs 1 day
146 TUB. PVC PERF. C/R TUB. PVC PERF. C/R 10.56 hrs 1 day
148 CONCRETO SIMPLE f' CEMENTO PORTLAND0TIhrs 1 day
149 CONCRETO SIMPLE f' ACEITE PARA MOTOR0 hrs 1 day
150 CONCRETO SIMPLE f' GASOLINA 84 OCTAN 0 hrs 1 day
151 CONCRETO SIMPLE f' OPERADOR DE EQUIP7.27 hrs 1 day
152 CONCRETO SIMPLE f' CAPATAZ 1.82 hrs 1 day
153 CONCRETO SIMPLE f' OPERARIO 7.27 hrs 1 day
154 CONCRETO SIMPLE f' OFICIAL 3.64 hrs 1 day
155 CONCRETO SIMPLE f' PEON 29.09 hrs 1 day
156 CONCRETO SIMPLE f' MEZCLADORA DE CONC 3.64 hrs 1 day
157 CONCRETO SIMPLE f' VIBRADOR DE CONCRE 3.64 hrs 1 day
158 CONCRETO SIMPLE f' PIEDRA CHANCADA DE 0 hrs 1 day
159 CONCRETO SIMPLE f' ARENA GRUESA 0 hrs 1 day
160 CONCRETO SIMPLE f' AGUA 0 hrs 1 day
161 CONCRETO SIMPLE f' GRASA POTE 200 GR 0 hrs 1 day
163 ENCOFRADO Y DESEN CAPATAZ 2.79 hrs 2 days
164 ENCOFRADO Y DESEN OPERARIO 13.96 hrs 2 days
165 ENCOFRADO Y DESEN OFICIAL 13.96 hrs 2 days
166 ENCOFRADO Y DESEN ALAMBRE NEGRO # 80 hrs 2 days
167 ENCOFRADO Y DESEN CLAVOS P/ MADERA C. 0 hrs 2 days
168 ENCOFRADO Y DESEN MADERA TORNILLO L 0 hrs 2 days
170 CONCRETO f 'c=175 k CEMENTO PORTLAND0TIhrs 1 day
171 CONCRETO f 'c=175 k ACEITE PARA MOTOR0 hrs 1 day
172 CONCRETO f 'c=175 k GASOLINA 84 OCTAN 0 hrs 1 day
173 CONCRETO f 'c=175 k OPERADOR DE EQUIP0.68 hrs 1 day
174 CONCRETO f 'c=175 k CAPATAZ 0.07 hrs 1 day
175 CONCRETO f 'c=175 k OPERARIO 0.68 hrs 1 day
176 CONCRETO f 'c=175 k OFICIAL 0.34 hrs 1 day
177 CONCRETO f 'c=175 k PEON 4.08 hrs 1 day
178 CONCRETO f 'c=175 k MEZCLADORA DE CONC0.34 hrs 1 day
179 CONCRETO f 'c=175 k VIBRADOR DE CONCRE0.34 hrs 1 day
180 CONCRETO f 'c=175 k PIEDRA CHANCADA DE0 hrs 1 day
181 CONCRETO f 'c=175 k ARENA GRUESA 0 hrs 1 day
182 CONCRETO f 'c=175 k AGUA 0 hrs 1 day
183 CONCRETO f 'c=175 k GRASA POTE 200 GR 0 hrs 1 day
185 ENCOFRADO Y DESEN CAPATAZ 0.35 hrs 1 day
186 ENCOFRADO Y DESEN OPERARIO 3.48 hrs 1 day
187 ENCOFRADO Y DESEN OFICIAL 4.64 hrs 1 day
188 ENCOFRADO Y DESEN PEON 2.32 hrs 1 day
189 ENCOFRADO Y DESEN ALAMBRE NEGRO # 85.22 hrs 1 day
190 ENCOFRADO Y DESEN CLAVOS P/ MADERA C.
7.31 hrs 1 day
191 ENCOFRADO Y DESEN MADERA TORNILLO 309.78 hrs 1 day
193 ACERO FY=4200kg/cmCAPATAZ 0.05 hrs 1 day
194 ACERO FY=4200kg/cmOPERARIO 0.48 hrs 1 day
195 ACERO FY=4200kg/cmOFICIAL 0.48 hrs 1 day
196 ACERO FY=4200kg/cmCIZALLA FE CONSTRU0.24 hrs 1 day
197 ACERO FY=4200kg/cmALAMBRE NEGRO # 1 6.49 hrs 1 day
198 ACERO FY=4200kg/cmACERO CORRUGADO 136.25
fy hrs 1 day
200 ESCALERA DE GATO D CAPATAZ 0.02 hrs 1 day
201 ESCALERA DE GATO D OPERARIO 0.44 hrs 1 day
202 ESCALERA DE GATO D OFICIAL 0.44 hrs 1 day
203 ESCALERA DE GATO D CIZALLA FE CONSTRU0.22 hrs 1 day
204 ESCALERA DE GATO D ALAMBRE NEGRO # 85.2 hrs 1 day
205 ESCALERA DE GATO D ACERO CORRUGADO 175.04
fy hrs 1 day
207 MARCO Y TAPA DE F°F CAPATAZ 0.01 hrs 1 day
208 MARCO Y TAPA DE F°F OPERARIO 0.23 hrs 1 day
209 MARCO Y TAPA DE F°F PEON 0.11 hrs 1 day
210 MARCO Y TAPA DE F°F TAPA DE FIERRO FU 8 hrs 1 day
211 MARCO Y TAPA DE F°F MARCO CIRCULAR Fª 8 hrs 1 day
214 TUB. PVC PERF. C/R TUB. PVC PERF. C/R 13.2 hrs 1 day
216 CONCRETO SIMPLE f' CEMENTO PORTLAND0TIhrs 1 day
217 CONCRETO SIMPLE f' ACEITE PARA MOTOR0 hrs 1 day
218 CONCRETO SIMPLE f' GASOLINA 84 OCTAN 0 hrs 1 day
219 CONCRETO SIMPLE f' OPERADOR DE EQUIP9.86 hrs 1 day
220 CONCRETO SIMPLE f' CAPATAZ 2.46 hrs 1 day
221 CONCRETO SIMPLE f' OPERARIO 9.86 hrs 1 day
222 CONCRETO SIMPLE f' OFICIAL 4.93 hrs 1 day
223 CONCRETO SIMPLE f' PEON 39.46 hrs 1 day
224 CONCRETO SIMPLE f' MEZCLADORA DE CONC 4.93 hrs 1 day
225 CONCRETO SIMPLE f' VIBRADOR DE CONCRE 4.93 hrs 1 day
226 CONCRETO SIMPLE f' PIEDRA CHANCADA DE 0 hrs 1 day
227 CONCRETO SIMPLE f' ARENA GRUESA 0 hrs 1 day
228 CONCRETO SIMPLE f' AGUA 0 hrs 1 day
229 CONCRETO SIMPLE f' GRASA POTE 200 GR 0 hrs 1 day
231 ENCOFRADO Y DESEN CAPATAZ 3.7 hrs 3 days
232 ENCOFRADO Y DESEN OPERARIO 18.48 hrs 3 days
233 ENCOFRADO Y DESEN OFICIAL 18.48 hrs 3 days
234 ENCOFRADO Y DESEN ALAMBRE NEGRO # 80 hrs 3 days
235 ENCOFRADO Y DESEN CLAVOS P/ MADERA C.
0 hrs 3 days
236 ENCOFRADO Y DESEN MADERA TORNILLO L 0 hrs 3 days
238 CONCRETO f 'c=175 k CEMENTO PORTLAND0TIhrs 1 day
239 CONCRETO f 'c=175 k ACEITE PARA MOTOR0 hrs 1 day
240 CONCRETO f 'c=175 k GASOLINA 84 OCTAN 0 hrs 1 day
241 CONCRETO f 'c=175 k OPERADOR DE EQUIP0.68 hrs 1 day
242 CONCRETO f 'c=175 k CAPATAZ 0.07 hrs 1 day
243 CONCRETO f 'c=175 k OPERARIO 0.68 hrs 1 day
244 CONCRETO f 'c=175 k OFICIAL 0.34 hrs 1 day
245 CONCRETO f 'c=175 k PEON 4.08 hrs 1 day
246 CONCRETO f 'c=175 k MEZCLADORA DE CONC0.34 hrs 1 day
247 CONCRETO f 'c=175 k VIBRADOR DE CONCRE0.34 hrs 1 day
248 CONCRETO f 'c=175 k PIEDRA CHANCADA DE0 hrs 1 day
249 CONCRETO f 'c=175 k ARENA GRUESA 0 hrs 1 day
250 CONCRETO f 'c=175 k AGUA 0 hrs 1 day
251 CONCRETO f 'c=175 k GRASA POTE 200 GR 0 hrs 1 day
253 ENCOFRADO Y DESEN CAPATAZ 0.35 hrs 1 day
254 ENCOFRADO Y DESEN OPERARIO 3.48 hrs 1 day
255 ENCOFRADO Y DESEN OFICIAL 4.64 hrs 1 day
256 ENCOFRADO Y DESEN PEON 2.32 hrs 1 day
257 ENCOFRADO Y DESEN ALAMBRE NEGRO # 85.22 hrs 1 day
258 ENCOFRADO Y DESEN CLAVOS P/ MADERA C.
7.31 hrs 1 day
259 ENCOFRADO Y DESEN MADERA TORNILLO 309.78 hrs 1 day
261 ACERO FY=4200kg/cmCAPATAZ 0.05 hrs 1 day
262 ACERO FY=4200kg/cmOPERARIO 0.48 hrs 1 day
263 ACERO FY=4200kg/cmOFICIAL 0.48 hrs 1 day
264 ACERO FY=4200kg/cmCIZALLA FE CONSTRU0.24 hrs 1 day
265 ACERO FY=4200kg/cmALAMBRE NEGRO # 1 6.49 hrs 1 day
266 ACERO FY=4200kg/cmACERO CORRUGADO 136.25
fy hrs 1 day
268 ESCALERA DE GATO D CAPATAZ 0.03 hrs 1 day
269 ESCALERA DE GATO D OPERARIO 0.62 hrs 1 day
270 ESCALERA DE GATO D OFICIAL 0.62 hrs 1 day
271 ESCALERA DE GATO D CIZALLA FE CONSTRU0.31 hrs 1 day
272 ESCALERA DE GATO D ALAMBRE NEGRO # 87.28 hrs 1 day
273 ESCALERA DE GATO D ACERO CORRUGADO 245.05
fy hrs 1 day
275 MARCO Y TAPA DE F°F CAPATAZ 0.01 hrs 1 day
276 MARCO Y TAPA DE F°F OPERARIO 0.23 hrs 1 day
277 MARCO Y TAPA DE F°F PEON 0.11 hrs 1 day
278 MARCO Y TAPA DE F°F TAPA DE FIERRO FU 8 hrs 1 day
279 MARCO Y TAPA DE F°F MARCO CIRCULAR Fª 8 hrs 1 day
282 TUB. PVC PERF. C/R TUB. PVC PERF. C/R 20.24 hrs 1 day
284 CONCRETO SIMPLE f' CEMENTO PORTLAND0TIhrs 1 day
285 CONCRETO SIMPLE f' ACEITE PARA MOTOR0 hrs 1 day
286 CONCRETO SIMPLE f' GASOLINA 84 OCTAN 0 hrs 1 day
287 CONCRETO SIMPLE f' OPERADOR DE EQUIP15.06 hrs 1 day
288 CONCRETO SIMPLE f' CAPATAZ 3.76 hrs 1 day
289 CONCRETO SIMPLE f' OPERARIO 15.06 hrs 1 day
290 CONCRETO SIMPLE f' OFICIAL 7.53 hrs 1 day
291 CONCRETO SIMPLE f' PEON 60.22 hrs 1 day
292 CONCRETO SIMPLE f' MEZCLADORA DE CONC 7.53 hrs 1 day
293 CONCRETO SIMPLE f' VIBRADOR DE CONCRE 7.53 hrs 1 day
294 CONCRETO SIMPLE f' PIEDRA CHANCADA DE 0 hrs 1 day
295 CONCRETO SIMPLE f' ARENA GRUESA 0 hrs 1 day
296 CONCRETO SIMPLE f' AGUA 0 hrs 1 day
297 CONCRETO SIMPLE f' GRASA POTE 200 GR 0 hrs 1 day
299 ENCOFRADO Y DESEN CAPATAZ 4.61 hrs 3 days
300 ENCOFRADO Y DESEN OPERARIO 23.07 hrs 3 days
301 ENCOFRADO Y DESEN OFICIAL 23.07 hrs 3 days
302 ENCOFRADO Y DESEN ALAMBRE NEGRO # 80 hrs 3 days
303 ENCOFRADO Y DESEN CLAVOS P/ MADERA C.
0 hrs 3 days
304 ENCOFRADO Y DESEN MADERA TORNILLO L 0 hrs 3 days
306 CONCRETO f 'c=175 k CEMENTO PORTLAND0TIhrs 1 day
307 CONCRETO f 'c=175 k ACEITE PARA MOTOR0 hrs 1 day
308 CONCRETO f 'c=175 k GASOLINA 84 OCTAN 0 hrs 1 day
309 CONCRETO f 'c=175 k OPERADOR DE EQUIP0.68 hrs 1 day
310 CONCRETO f 'c=175 k CAPATAZ 0.07 hrs 1 day
311 CONCRETO f 'c=175 k OPERARIO 0.68 hrs 1 day
312 CONCRETO f 'c=175 k OFICIAL 0.34 hrs 1 day
313 CONCRETO f 'c=175 k PEON 4.08 hrs 1 day
314 CONCRETO f 'c=175 k MEZCLADORA DE CONC0.34 hrs 1 day
315 CONCRETO f 'c=175 k VIBRADOR DE CONCRE0.34 hrs 1 day
316 CONCRETO f 'c=175 k PIEDRA CHANCADA DE0 hrs 1 day
317 CONCRETO f 'c=175 k ARENA GRUESA 0 hrs 1 day
318 CONCRETO f 'c=175 k AGUA 0 hrs 1 day
319 CONCRETO f 'c=175 k GRASA POTE 200 GR 0 hrs 1 day
321 ENCOFRADO Y DESEN CAPATAZ 0.35 hrs 1 day
322 ENCOFRADO Y DESEN OPERARIO 3.48 hrs 1 day
323 ENCOFRADO Y DESEN OFICIAL 4.64 hrs 1 day
324 ENCOFRADO Y DESEN PEON 2.32 hrs 1 day
325 ENCOFRADO Y DESEN ALAMBRE NEGRO # 85.22 hrs 1 day
326 ENCOFRADO Y DESEN CLAVOS P/ MADERA C.
7.31 hrs 1 day
327 ENCOFRADO Y DESEN MADERA TORNILLO 309.78 hrs 1 day
329 ACERO FY=4200kg/cmCAPATAZ 0.05 hrs 1 day
330 ACERO FY=4200kg/cmOPERARIO 0.48 hrs 1 day
331 ACERO FY=4200kg/cmOFICIAL 0.48 hrs 1 day
332 ACERO FY=4200kg/cmCIZALLA FE CONSTRU0.24 hrs 1 day
333 ACERO FY=4200kg/cmALAMBRE NEGRO # 1 6.49 hrs 1 day
334 ACERO FY=4200kg/cmACERO CORRUGADO 136.25
fy hrs 1 day
336 ESCALERA DE GATO D CAPATAZ 0.05 hrs 1 day
337 ESCALERA DE GATO D OPERARIO 0.98 hrs 1 day
338 ESCALERA DE GATO D OFICIAL 0.98 hrs 1 day
339 ESCALERA DE GATO D CIZALLA FE CONSTRU0.49 hrs 1 day
340 ESCALERA DE GATO D ALAMBRE NEGRO # 811.44 hrs 1 day
341 ESCALERA DE GATO D ACERO CORRUGADO 385.09
fy hrs 1 day
343 MARCO Y TAPA DE F°F CAPATAZ 0.01 hrs 1 day
344 MARCO Y TAPA DE F°F OPERARIO 0.23 hrs 1 day
345 MARCO Y TAPA DE F°F PEON 0.11 hrs 1 day
346 MARCO Y TAPA DE F°F TAPA DE FIERRO FU 8 hrs 1 day
347 MARCO Y TAPA DE F°F MARCO CIRCULAR Fª 8 hrs 1 day
350 TUB. PVC PERF. C/R TUB. PVC PERF. C/R 26.4 hrs 1 day
352 CONCRETO SIMPLE f' CEMENTO PORTLAND0TIhrs 2 days
353 CONCRETO SIMPLE f' ACEITE PARA MOTOR0 hrs 2 days
354 CONCRETO SIMPLE f' GASOLINA 84 OCTAN 0 hrs 2 days
355 CONCRETO SIMPLE f' OPERADOR DE EQUIP19.61 hrs 2 days
356 CONCRETO SIMPLE f' CAPATAZ 4.9 hrs 2 days
357 CONCRETO SIMPLE f' OPERARIO 19.61 hrs 2 days
358 CONCRETO SIMPLE f' OFICIAL 9.8 hrs 2 days
359 CONCRETO SIMPLE f' PEON 78.43 hrs 2 days
360 CONCRETO SIMPLE f' MEZCLADORA DE CONC 9.8 hrs 2 days
361 CONCRETO SIMPLE f' VIBRADOR DE CONCRE 9.8 hrs 2 days
362 CONCRETO SIMPLE f' PIEDRA CHANCADA DE 0 hrs 2 days
363 CONCRETO SIMPLE f' ARENA GRUESA 0 hrs 2 days
364 CONCRETO SIMPLE f' AGUA 0 hrs 2 days
365 CONCRETO SIMPLE f' GRASA POTE 200 GR 0 hrs 2 days
367 ENCOFRADO Y DESEN CAPATAZ 5.54 hrs 4 days
368 ENCOFRADO Y DESEN OPERARIO 27.71 hrs 4 days
369 ENCOFRADO Y DESEN OFICIAL 27.71 hrs 4 days
370 ENCOFRADO Y DESEN ALAMBRE NEGRO # 80 hrs 4 days
371 ENCOFRADO Y DESEN CLAVOS P/ MADERA C.
0 hrs 4 days
372 ENCOFRADO Y DESEN MADERA TORNILLO L 0 hrs 4 days
374 CONCRETO f 'c=175 k CEMENTO PORTLAND0TIhrs 1 day
375 CONCRETO f 'c=175 k ACEITE PARA MOTOR0 hrs 1 day
376 CONCRETO f 'c=175 k GASOLINA 84 OCTAN 0 hrs 1 day
377 CONCRETO f 'c=175 k OPERADOR DE EQUIP0.68 hrs 1 day
378 CONCRETO f 'c=175 k CAPATAZ 0.07 hrs 1 day
379 CONCRETO f 'c=175 k OPERARIO 0.68 hrs 1 day
380 CONCRETO f 'c=175 k OFICIAL 0.34 hrs 1 day
381 CONCRETO f 'c=175 k PEON 4.08 hrs 1 day
382 CONCRETO f 'c=175 k MEZCLADORA DE CONC0.34 hrs 1 day
383 CONCRETO f 'c=175 k VIBRADOR DE CONCRE0.34 hrs 1 day
384 CONCRETO f 'c=175 k PIEDRA CHANCADA DE0 hrs 1 day
385 CONCRETO f 'c=175 k ARENA GRUESA 0 hrs 1 day
386 CONCRETO f 'c=175 k AGUA 0 hrs 1 day
387 CONCRETO f 'c=175 k GRASA POTE 200 GR 0 hrs 1 day
389 ENCOFRADO Y DESEN CAPATAZ 0.35 hrs 1 day
390 ENCOFRADO Y DESEN OPERARIO 3.48 hrs 1 day
391 ENCOFRADO Y DESEN OFICIAL 4.64 hrs 1 day
392 ENCOFRADO Y DESEN PEON 2.32 hrs 1 day
393 ENCOFRADO Y DESEN ALAMBRE NEGRO # 85.22 hrs 1 day
394 ENCOFRADO Y DESEN CLAVOS P/ MADERA C.
7.31 hrs 1 day
395 ENCOFRADO Y DESEN MADERA TORNILLO 309.78 hrs 1 day
397 ACERO FY=4200kg/cmCAPATAZ 0.05 hrs 1 day
398 ACERO FY=4200kg/cmOPERARIO 0.48 hrs 1 day
399 ACERO FY=4200kg/cmOFICIAL 0.48 hrs 1 day
400 ACERO FY=4200kg/cmCIZALLA FE CONSTRU0.24 hrs 1 day
401 ACERO FY=4200kg/cmALAMBRE NEGRO # 1 6.49 hrs 1 day
402 ACERO FY=4200kg/cmACERO CORRUGADO 136.25
fy hrs 1 day
404 ESCALERA DE GATO DCAPATAZ 0.06 hrs 1 day
405 ESCALERA DE GATO DOPERARIO 1.29 hrs 1 day
406 ESCALERA DE GATO DOFICIAL 1.29 hrs 1 day
407 ESCALERA DE GATO DCIZALLA FE CONSTRU0.64 hrs 1 day
408 ESCALERA DE GATO DALAMBRE NEGRO # 815.08 hrs 1 day
409 ESCALERA DE GATO DACERO CORRUGADO 507.61
fy hrs 1 day
411 MARCO Y TAPA DE F°F
CAPATAZ 0.01 hrs 1 day
412 MARCO Y TAPA DE F°F
OPERARIO 0.23 hrs 1 day
413 MARCO Y TAPA DE F°F
PEON 0.11 hrs 1 day
414 MARCO Y TAPA DE F°F
TAPA DE FIERRO FU 8 hrs 1 day
415 MARCO Y TAPA DE F°F
MARCO CIRCULAR Fª 8 hrs 1 day