Examen metrados
ASIGNATURA: Construcciones 2
DOCENTE: Ing. Kildare Ascue Escalante
ESTUDIANTES:
 Ricardo Jhamel Ramos Lopez
 Carlos Gonzalo Sánchez Carmona
CODIGO:019201704f

2021
Partida : MOVIMIENTO DE TIERRA
2.1. Excavaciones
2.1.1 Excavación para zapatas
 Z-1 Eje A-A (1-7) = 3 x 1.5 x 1.5 x 2 = 13.50 m3
 Z-1 Eje B-B(1-7) = 1 x 1.5 x 1.5 x 2 = 4.50 m3
 Z-1 EJE C-C (1-7) = 1 x 1.5 x 1.5 x 2 = 4.50 m3
 Z-2 EJE D-D (1-7)= 7 x 1.3 x 1.3 x 2 = 23.66 m3
 Z-3 EJE A-A(1-7)= 3 x 2.2 x 1.7 x 2 = 22.44m3
 Z.3 EJE C-C(1-7) = 3 x 2.2 x 1.7 x 2 = 22.44 m3
 Z-4 EJE B-B(1-7)= 1 x 1.8 x 1.5 x 2 = 5.40m3
 Z-5 EJE A-A (1-7)= 1 x 1.7 x 1.7 x 2 = 5.78m3
 Z.-5 EJE B-B (1-7)= 3 x 1.7 x 1.7 x 2 = 17.34m3
 Z-5 EJE C-C (1-7)=3 x 1.7 x 1.7 x 2 = 17.34m3
TOTAL = 136.90m3

2.1.2 Excavación para vigas de cimentación


 VC EJE A-A (1-7) = 1 x 8.32x 0.25 x 1.5 = 3.12m3
 VC EJE B-B (1-7) = 1x 3.6 x 0.25 x 1.5 = 1.35m3
 VCEJE C-C(1-7) = 1 x 8.13 x 0.25 x 1.5= 3.05
 VC EJE D-D(1-7)=1 x 11.95 x 0.25 x 1.5 = 4.48m3
 VC EJE 1-1 (A-D)= 1 x 5.45 x 0.25 x 1.5 = 2.04m3
 VC EJE 2-2(A-D) = 1 x 5.15 x 0.25 x 1.5 = 1.93m3
 VC EJE 3-3 (A-D)= 1 x 0.75 x 0.25 x 1.5 = 0.28m3
 VC EJE 4-4 (A-D)=1 x 0.75 x 0.25 x 1.5 = 0.28m3
 VC EJE 5-5 (A-D)= 1 x 4.95 x 0.25 x 1.5 = 1.86m3
 VC EJE 6-6 (A-D)= 1 x 5.05 x 0.25 x 1.5 = 1.89m3
 VC EJE 7-7 (A-D)= 1 x 5.05 x 0.25 x 1.5 = 1.89m3
TOTAL = 22.18 m3

2.1.3 Relleno
 Z-1 EJE A-A (7 Y 6) = 2 ((Area=1.7188) * 1.5) = 5.16m3
 Z-1 EJE 1-1 (A)= 1((Area =1.875)*1.5) = 2.81m3
 Z-1 EJE 1-1 (B Y C)= 2((Area =1.7187)*1.5)=5.16m3
 Z-2 EJE D-D (5,6 Y 7)= 3((Area = 1.2337) *1.5)=5.55m3
 Z-2 EJE D-D (2,3 Y 4)= 3 ((Area =1.2337)*1.5)=5.55m3
 Z-2 EJE D-D (1) = 1((Area =1.365)*1.5) = 2.05m3
 Z-3 EJE A-A(4 Y 3)= 2((Area = 3.115)*1.5)= 9.35m3
 Z-3 EJE A-A(2) = 2((Area =2.9725)*1.5) = 8.92m3
 Z-3 EJE C-C ( 4 Y 5)= 2((Area =2.9338)*1.5)=8.80m3
 Z-3 EJE C-C ( 2)= 1((Area = 2.7892)*1.5) =4.18m3
 Z-4 EJE B-B (2) = 1((Area =2.0625)*1.5)=3.09m3
 Z-5 EJE B-B (7Y6)= 2((Area =1.8125)*1.5)= 5.44m3
 Z-5 EJE B-B (5)= 1((Area =2.465)*1.5)= 3.70m3
 Z-5 EJE C-C (7)= 1((Area =2.1025)*1.5)= 3.15m3
 Z-5 EJE C-C (6)= 1((Area =1.8125)*1.5)= 2.72m3
 Z-5 EJE C-C (5)= 1((Area =2.1026)*1.5)=3.15m3
TOTAL = 78.78m3

Volumen de excavacion = 136.9m3 + 22.18m3 = 159.08m3


Volumen de relleno = 78.78x 1.25(factor de compactación 25%) = 98.47m3
Volumen a excavar = 159.08m3-98.47m3 = 60.61m3
Factor de esponjamiento(30%) = 60.61m3*1.3 = 78.79m3

2.2 Concreto:
2.2.1 Concreto en zapata:
 Z1= 5 x 1.5 x1.5 x 0.5= 5.63m3
 Z2= 7 x 1.3 x 1.3 x 0.5 = 5.92m3
 Z3= 6 x 1.7 x 2.2 x 0.5 = 11.22m3
 Z4= 1 x 1.5 x 1.8 x 0.5 = 1.35m3
 Z5= 7 x 1.7 x 1.7 x 0.5 = 10.12m3
TOTAL = 34.23m3
Con desperdicio del 5% = 35.94m3

2.2.2 Concreto en columna:


 EJE A,C,D CON EJE 1-5= 3 x 16.25 x 0.25 x 0.5 = 6.09m3
 EJE B CON EJE 1-2= 1 x 3.72 x 0.25 x 0.5 = 0.47m3
 EJE 1,5 CON EJE A-C= 2 x 7.35 x 0.25 x 0.5 = 1.84m3
 EJE 2 CON EJE A-C= 1 x 7.35 x 0.3 x 0.5 = 1.10m3
 EJE1,2,3,4,5 CON EJE CD = 5 x 2 x 0.25 x 0.5 = 1.25m3
 EJE 6,7 CON EJE A-D= 2 x 10.1 x 0.25 x 0.5 = 2.53m3
 EJE A,B,C,D CON EJE 6-7 = 4 x 3.75 x 0.25 x 0.5 = 1.88m3
TOTAL = 15.15m3
Con desperdicio del 5% = 15.91m3

2.2.3 Concreto en viga de cimentación:


PRIMER PISO
 C1 = 6 x 0.25 x 0.4 x 4 = 2.40m3
 C2= 1 x 0.3 x 0.4 x 4 = 0.48m3
 C3= 7 x 0.25 x 0.25 x 4 = 1.75m3
 C6= 6 x 0.25 x 1 x 4 =6.00m3
 C8= 6 x 0.1625 x 1 x 4 =3.90m3
TOTAL = 14.53m3
SEGUNDO PISO
 C1= 6 x 0.25 x 0.4 x 2.9 = 1.74m3
 C2= 1 x 0.3 x 0.4 x 4.06 = 0.49m3
 C3= 7 x 0.25 x 0.25 x 2.21 = 0.97m3
 C6= 6 x 0.25 x 1 x 2.90 =4.35m3
 C8= 6 x 0.1625 x 1 x 2.90 = 2.83m3
TOTAL = 10.37m3

TOTAL = 24.90m3
Con desperdicio del 5% = 26.15m3

2.3 Encofrado:
2.3.1 Encofrado en zapatas
 Z-1= ((1.5X2X0.5)+ (1.5X2X0.5))5= 15m2
 Z-2=((1.3X0.5X2)+( 1.3X0.5X2))7=18.2m2
 Z-3=((2.2X0.5X2)+(1.7X0.5X2))6=23.4m2
 Z-4=((1.8X0.5X2)+(1.5X0.5X2))1=3.3m2
 Z-5=((1.7X0.5X2)+(1.7X0.5X2))7=23.8m2
TOTAL= 83.7m2
Total con desperdicio del 10% = 92.07
2.3.2 Encofrado en vigas de conexión.
 EJE 7,6,5,1 CON A-D = 4 x 10.1 x 0.5 = 20.2
 EJE A,D CON 7-6 = 2 x 4.25 x 0.5 = 4.25
 EJE A,D CON 5-1 = 2 x 16.25 x 0.5 = 16.25
 EJE A,B,C,D CON 7-6 = 6 x 3.75 x 0.5 = 11.25
 EJE 7,8 CON A-C = 4 x 3.55 x 0.5 = 7.1
 EJE 7,8 CON C-D = 2 x 2 x 0.5 = 2
 EJE A CON 5.4 = 1 x 3.73 x 0.5 = 1.865
 EJE A CON 4-3 = 1 x 3.7 x 0.5 = 1.85
 EJE A CON 3-2 = 1 x 3.7 x 0.5 = 1.85
 EJE A CON 2-1 = 1 x 3.73 x 0.5 = 1.865
 EJE B CON 2-1 = 2 x 3.73 x 0.5 = 3.73
 EJE C CON 5-4 = 1 x 3.73 x 0.5 = 1.865
 EJE C CON4-3 = 1 x 3.7 x 0.5 = 1.85
 EJE C CON 3-2 = 1 x 3.7 x 0.5 = 1.85
 EJE C CON 2-1 = 1 x 3.73 x 0.5 = 1.865
 EJE C CON 5-1 = 4 x 3.75 x 0.5 = 7.5
 EJE D CON 5-1 = 4 x 3.75 x 0.5 = 7.50
 EJE 5,2 CON A-C = 2 x 7.35 x 0.5 = 7.35
 EJE 1,2 CON AB Y BC = 4 x 3.55 x 0.5 = 7.10
 EJE 5,4,3,2,1 CON CD = 8 x 2 x 0.5 = 8
TOTAL = 117.09
CON DESPERDICIO = 128.80

2.3.3 ENCOFRADO EN COLUMNAS


Primer piso
 C1 = (0.4x4x2+0.25x4x2) x 6 = 31.20
 C2 = (0.4x4x2+0.3x4x2) x1 = 5.60
 C3 = (0.25x4x2+0.25x4x2) x 7 =28
 C6 =6 x 9.925 x 1 = 59.55
 C8 = 6 x 6.4 x 1 = 38.4
TOTAL = 162.75
Segundo piso
 C1 = (0.4x2.9x2+0.25x2.9x2) x 6 = 22.62
 C2 = (0.4x4.06x2+0.3x4.06x2) x1 = 5.68
 C3 = (0.25x2.21x2+0.25x2.21x2) x 7 = 15.47
 C6 = 6 x 6.96 x 1 = 41.76
 C8 = 6 x 4.64 x 1 = 27.84
TOTAL = 113.374

TOTAL, DE ENCOFRADO DE COLUMNAS = 276.124 M2


CON DESPERDICIO = 303.74 M2