DATOS GENERALES

INFORME MENSUAL N°03 - FASE 2 – MARZO 2021


CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y
RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-SOCOS-
Nombre del Servicio CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA, PROVINCIA
DE CONCEPCION, DEPARTAMENTO DE JUNIN

Nº de contrato CONTRATO DE SERVICIO Nº 028-2020-A/MPC

Entidad contratante MUNICIPALIDAD PROVINCIAL DE CONCEPCCION

Domicilio legal AV. MCAL CACERES NRO. 329 CONCEPCCION CERCADO (PLAZA PRINCIPAL)

Contratista GEOZU S.A.C.


Domicilio legal JUNIN – HUANCAYO – JR. PROGRESO NRO. 520 (ENTRE HUMBOLT Y PROGRE

Residente de Servicio ING. HUAYRA HUAMAN TIMOTEO

Ing de Seguridad del Servicio ING ORELLANA DE LA CRUZ BETTY DIANA

Inspector de servicio ING. CLAUDIA L.B. RAEZ SAAVEDRA

Plazo de Ejecucion - Contractual 445 dias calendario

Plazo de Ejecucion -FASE 1 20 Días Calendario


Plazo de Ejecucion - FASE 2 60 Días Calendario
Plazo de Ejecucion - FASE 3 360 Días Calendario
Plazo de Ejecucion - INVENTARIO VIAL 05 Días Calendario
Modalidad de Contrata SUMA ALZADA

( UN MILLON VEINTIDOS MIL OCHOCIENTOS


Monto Contratado (Incl. IGV) S/ 1,022,856.00 CINCUENTA SEIS CON 00/100 Soles).

Presupuesto de plan de trabajo S/ 10,228.56


Presupuesto de Mantenimiento Periodico S/ 848,970.48
Presupuesto de Mantenimiento Rutinario S/ 153,428.40
Presupuesto de inventario vial S/ 10,228.56

Aprobacion de Resolucion de Gerencia Municipal


N° 132-2020-GM/MPC Thursday 03/12/2020

Fecha de inicio FASE II Friday 04/12/2020


Fin de FASE II Monday 01/02/2021
SUSPENSIÓN DE SERVICIO FASE II Monday 18/01/2021
REINICIO DEL SERVICIO SUSPENDIDO Tuesday 16/03/2021 Carta N° 007-2021-CLBRS/IS
DIAS SUSPENDIDOS FASE II 14 DIAS
FECHA DE FIN DE FASE II Tuesday 30/03/2021
DESCRIPCION DE LAS ACTIVIDADES EJECUTADAS Y EL PORCENTAJE DE AVANCE
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 S/. 58,237.59

PARTIDA UND METRADO

01.01MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00

AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO

01.01MOVILIZACION Y DESMOVILIZACION DE EQUIPOS 0.50 1.00 0.00

AVANCE PORCENTUAL 50.00% 100.00% 0.00%


AVANCE VALORIZADO S/. 29,118.80 S/. 58,237.59 S/. -

Esta actividad se refiere al traslado del equipo de maquinaria


DESCRPICION DE LOS METRADOS EJECUTADOS hacia la obra

01.02 TRAZO Y REPLANTEO km 15.000 S/. 492.99

PARTIDA UND METRADO


01.02TRAZO Y REPLANTEO km 15.00
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
01.02TRAZO Y REPLANTEO 0.00 15.000 0.00
AVANCE PORCENTUAL 0.00% 100.00% 0.00%
AVANCE VALORIZADO 0.00 7,394.85 S/. -

DESCRICION DE LOS METRADOS EJECUTADOS Esta actividad se refiere al trazo y replanteo del Proyecto, con sus
respectivas referencias y BMs, basandose en el plano

02.01 CAPA NIVELANTE E=0.05M m3 900.00 S/. 26.07

PARTIDA UND METRADO


02.01 CAPA NIVELANTE E=0.05M m3 900.00
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
02.01 CAPA NIVELANTE E=0.05M 417.08 900.00 0.00
AVANCE PORCENTUAL 46.34% 100.00% 0.00%
AVANCE VALORIZADO 10,873.15 23,463.00 S/. -

consiste en trabajos de estabilización de material donde se


DESCRICION DE LOS METRADOS EJECUTADOS buscará mejorar la capacidad del suelo que obtengamos una
respuesta elástica similar al que presenta la plataforma existente.

MATERIAL GRANULAR DE CANTERA PARA


02.02 m3 9,000.00 S/. 26.27
ESTABILIZADO E=0.15M

PARTIDA UND METRADO


02.02 MATERIAL GRANULAR DE CANTERA PARA
ESTABILIZADO E=0.15M m3 9,000.00

AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO


02.02 MATERIAL GRANULAR DE CANTERA PARA 4,020.90 9,000.00 0.00
ESTABILIZADO E=0.15M
AVANCE PORCENTUAL 44.68% 100.00% 0.00%
AVANCE VALORIZADO 105,629.04 236,430.00 S/. -
Esta actividad consiste en el suministro, colocación y compactación de
material granular de cantera para afirmado, conforme con las
DESCRICION DE LOS METRADOS EJECUTADOS dimensiones, alineamientos y pendientes señalados en los planos del
proyecto
03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM m3k 12,029.10 S/. 6.47

PARTIDA UND METRADO


03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA
1KM m3k 12,029.10

AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO


03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 12,029.10 12,029.10 0.00
1KM
AVANCE PORCENTUAL 100.00% 100.00% 0.00%
AVANCE VALORIZADO 77,828.28 77,828.28 S/. -

DESCRICION DE LOS METRADOS EJECUTADOS

03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM m3k 53,317.32 S/. 1.80

PARTIDA UND METRADO


03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR m3k 53,317.32
A 1KM
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR
A 1KM 29,146.80 53,317.32 0.00

AVANCE PORCENTUAL 54.67% 100.00% 0.00%


AVANCE VALORIZADO 52,464.24 95,971.18
Contempla el transporte de material granular de cantera. implica
DESCRICION DE LOS METRADOS EJECUTADOS solamente el transporte de los materiales a los sitios de utilización,
mayores a 1km

03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 km m3k 748.07 S/. 6.75

PARTIDA UND METRADO


03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1
km m3k 748.07

AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO


03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 250.69 748.07 0.00
km
AVANCE PORCENTUAL 33.51% 100.00% 0.00%
AVANCE VALORIZADO 1,692.13 5,049.47 S/. -
Contempla el transporte de material granular de cantera. implica
DESCRICION DE LOS METRADOS EJECUTADOS solamente el transporte de los materiales excedentes a los sitios
de depositos, menores a 1km
TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1
03.04 m3k 8,392.68 S/. 1.89
km

PARTIDA UND METRADO


03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR
A 1 km m3k 8,392.68

AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO


03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR 3,763.20 8,392.68 0.00
A 1 km
AVANCE PORCENTUAL 44.84% 100.00% 0.00%
AVANCE VALORIZADO 7,112.45 15,862.17 S/. -
Contempla el transporte de material granular de cantera. implica
DESCRICION DE LOS METRADOS EJECUTADOS solamente el transporte de los materiales excedentes a los sitios
de depositos, mayores a 1km
04.01 RECONFORMACION DE CUNETAS m 15,000.000 S/. 2.73

PARTIDA UND METRADO


04.01 RECONFORMACION DE CUNETAS m 15,000.00
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
04.01 RECONFORMACION DE CUNETAS 8,200.00 15,000.00 0.00
AVANCE PORCENTUAL 54.67% 100.00% 0.00%
AVANCE VALORIZADO 22,386.02 40,950.00 S/. -

DESCRICION DE LOS METRADOS EJECUTADOS Consiste en escarificar, conformar, nivelar y compactar las cunetas
existentes, con ó sin adición de nuevo material de afirmado.

05.01 INSTALACION DE POSTES KILOMETRICOS und 16.00 S/. 159.37

PARTIDA UND METRADO


05.01 INSTALACION DE POSTES KILOMETRICOS und 16.00
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
05.01 INSTALACION DE POSTES KILOMETRICOS 16.00 16.00 0.00
AVANCE PORCENTUAL 100.00% 100.00% 0.00%
AVANCE VALORIZADO 2,549.92 2,549.92 S/. -

DESCRICION DE LOS METRADOS EJECUTADOS

05.02 SEÑALES PREVENTIVAS und 5.00 S/. 703.78

PARTIDA UND METRADO


05.02 SEÑALES PREVENTIVAS und 5.00
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
05.02 SEÑALES PREVENTIVAS 5.00 5.00 0.00
AVANCE PORCENTUAL 100.00% 100.00% 0.00%
AVANCE VALORIZADO 3,518.90 3,518.90 S/. -

DESCRICION DE LOS METRADOS EJECUTADOS


05.03 SEÑALES REGLAMENTARIAS und 2.00 S/. 642.86

PARTIDA UND METRADO


05.03 SEÑALES REGLAMENTARIAS und 2.00
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
05.03 SEÑALES REGLAMENTARIAS 2.00 2.00 0.00
AVANCE PORCENTUAL 100.00% 100.00% 0.00%
AVANCE VALORIZADO 1,285.71 1,285.71 S/. -
DESCRICION DE LOS METRADOS EJECUTADOS

05.04 SEÑALES INFORMATIVAS und 1.00 S/. 4,499.30

PARTIDA UND METRADO


05.04 SEÑALES INFORMATIVAS und 1.00
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
05.04 SEÑALES INFORMATIVAS 1.00 1.00 0.00
AVANCE PORCENTUAL 100.00% 100.00% 0.00%
AVANCE VALORIZADO 4,499.30 4,499.30 S/. -
DESCRICION DE LOS METRADOS EJECUTADOS

06.01. RECUPERACION AMBIENTAL DE AREAS OCUPADAS Ha 1.21 S/. 7,619.84

PARTIDA UND METRADO

6.01RECUPERACION AMBIENTAL DE AREAS OCUPADAS Ha 1.21

AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO

6.01RECUPERACION AMBIENTAL DE AREAS OCUPADAS 1.21 1.21 0.00

AVANCE PORCENTUAL 100.00% 100.00% 0.00%


AVANCE VALORIZADO 9,220.01 9,220.01 S/. -

DESCRICION DE LOS METRADOS EJECUTADOS Se valoriza la recuperacion ambiental de areas ocupadas

07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00 S/. 17,295.05

PARTIDA UND METRADO


07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00
AVANCE DE PARTIDA MES ACTUAL ACUMULADO SALDO
07.01 EMERGENCIA SANITARIA COVID 19 0.20 1.00 0.00
AVANCE PORCENTUAL 20.00% 100.00% 0.00%
AVANCE VALORIZADO 3,459.03 17,295.05 S/. -
Se valoriza la implementación de Plan protocolo de seguridad en
obras anticontagio COVID-19
DESCRICION DE LOS METRADOS EJECUTADOS
ACTIVIDADES EJECUTADAS VS PROGRAMADAS
SERVICIO CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRIT
ENTIDAD CONTRATO DE SERVICIO Nº 028-2020-A/MPC
CONTRATISTAGEOZU S.A.C.
CONTRATO
CONTRATO DE SERVICIO Nº 028-2020-A/MPC
DE OBRA
INSPECTOR ING. CLAUDIA L.B. RAEZ SAAVEDRA
martes, 30 de marzo de 2021
P.U.
ITEM DESCRIPCIÓN UND METRADO PPTO BASE TOTAL
S/. TOTAL PROGRAMADO
METRADO
% PROGRAMADO TOTAL TOTAL
EJECUTADO METRADO % EJECUTADO
01.00 OBRAS PRELIMINARES S/. 65,632.44 S/ 29,118.80 0.0 0.00% S/. 29,118.79 44.37%
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 S/. 58,237.59 S/. 58,237.59 S/ 29,118.80 0.5 50.00% S/. 29,118.79 0.50 50.00%
01.02 TRAZO Y REPLANTEO km 15.000 S/. 492.99 S/. 7,394.85 S/ 0.00 0.0 0.00% S/. - 0.00%
02.00 PAVIMENTOS S/. 259,893.00 S/ 0.00 0.0 0.00% S/. 116,502.19 44.83%
02.01 CAPA NIVELANTE E=0.05M m3 900.00 S/. 26.07 S/. 23,463.00 S/ 0.00 0.0 0.00% S/. 10,873.15 417.08 46.34%
02.02 MATERIAL GRANULAR DE CANTERA PARA ESTABILIZADO E=0.15M m3 9,000.00 S/. 26.27 S/. 236,430.00 S/ 0.00 0.0 0.00% S/. 105,629.04 4020.90 44.68%
03.00 TRANSPORTE S/. 194,711.10 S/ 0.00 0.0 0.00% S/. 61,268.82 31.47%
03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM m3k 12,029.10 S/. 6.47 S/. 77,828.28 S/ 0.00 0.0 0.00% S/. - 0.00%
03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM m3k 53,317.32 S/. 1.80 S/. 95,971.18 S/ 0.00 0.0 0.00% S/. 52,464.24 29146.80 54.67%
03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 km m3k 748.07 S/. 6.75 S/. 5,049.47 S/ 0.00 0.0 0.00% S/. 1,692.13 250.69 33.51%
03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1 km m3k 8,392.68 S/. 1.89 S/. 15,862.17 S/ 0.00 0.0 0.00% S/. 7,112.45 3763.20 44.84%
04.00 OBRAS DE ARTE Y DRENAJE S/. 40,950.00 S/ 0.00 0.0 0.00% S/. 22,386.02 54.67%
04.01 RECONFORMACION DE CUNETAS m 15,000.00 S/. 2.73 S/. 40,950.00 S/ 0.00 0.0 0.00% S/. 22,386.02 8200.00 54.67%
05.00 SEÑALIZACION S/. 11,853.83 S/ 0.00 0.0 0.00% S/. 11,853.83 100.00%
05.01 INSTALACION DE POSTES KILOMETRICOS und 16.00 S/. 159.37 S/. 2,549.92 S/ 0.00 0.0 0.00% S/. 2,549.92 16.00 100.00%
05.02 SEÑALES PREVENTIVAS und 5.00 S/. 703.78 S/. 3,518.90 S/ 0.00 0.0 0.00% S/. 3,518.90 5.00 100.00%
05.03 SEÑALES REGLAMENTARIAS und 2.00 S/. 642.86 S/. 1,285.71 S/ 0.00 0.0 0.00% S/. 1,285.71 2.00 100.00%
05.04 SEÑALES INFORMATIVAS und 1.00 S/. 4,499.30 S/. 4,499.30 S/ 0.00 0.0 0.00% S/. 4,499.30 1.00 100.00%
06.00 IMPACTO AMBIENTAL S/. 9,220.01 S/ 9,220.01 0.0 0.00% S/. 9,220.01 100.00%
07.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS Ha 1.21 S/. 7,619.84 S/. 9,220.01 S/ 9,220.01 1.2 100.00% S/. 9,220.01 1.21 100.00%
07.00 EMERGENCIA SANITARIA S/. 17,295.05 S/ 172.95 0.0 0.00% S/. 3,459.03 20.00%
07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00 S/. 17,295.05 S/. 17,295.05 S/ 172.95 0.0 1.00% S/. 3,459.03 0.20 20.00%
Costo Directo S/. 599,555.43 S/ 38,511.76 253808.69
Gastos Generales (12%) 12.00% 0.3448 S/. 71,946.65 S/ 4,621.41 30457.04
Utilidad (8%) 8.00% 0.05 S/. 47,964.43 S/ 3,080.94 20304.69
6.423386% 42.332815%
SUBTOTAL S/. 719,466.51 S/ 46,214.11 304570.42
IGV (18.00%) 0.00% 0.18 S/. 129,503.97 S/ 8,318.54 54822.68
PRESUPUESTO TOTAL S/. 848,970.48 S/ 54,532.65 359393.1
CRONOGRAMA PROGRAMADO
CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA, PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN
ENTIDAD CONTRATO DE SERVICIO Nº 028-2020-A/MPC
INSPECTOR ING. CLAUDIA L.B. RAEZ SAAVEDRA
AL 31/12/2020 AL 31/01/2021 AL 28/02/2021 AL 30/03/2021
P.U.
ITEM DESCRIPCIÓN UND METRADO PPTO BASE TOTAL TOTAL
S/. TOTAL PROGRAMADO TOTAL METRADO % PROGRAMADO TOTAL PROGRAMADO TOTAL METRADO % PROGRAMADO TOTAL PROGRAMADO TOTAL METRADO % PROGRAMADO
PROGRAMADO METRADO
% PROGRAMADO

01.00 OBRAS PRELIMINARES S/. 65,632.44 S/. 36,513.65 S/. - S/. 29,118.80
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 S/. 58,237.59 S/. 58,237.59 S/. 29,118.80 0.50 50.00% S/. - 0.00 0.00% S/. 29,118.80 0.50 50.00%
01.02 TRAZO Y REPLANTEO km 15.000 S/. 492.99 S/. 7,394.85 S/. 7,394.85 15.00 100.00% S/. - 0.00 0.00% S/. - 0.00 0.00%
02.00 PAVIMENTOS S/. 259,893.00 S/. 113,378.40 S/. 146,514.60 S/. -
02.01 CAPA NIVELANTE E=0.05M m3 900.00 S/. 26.07 S/. 23,463.00 S/. 14,077.80 540.00 60.00% S/. 9,385.20 360.00 40.00% S/. - 0.00 0.00%
02.02 MATERIAL GRANULAR DE CANTERA PARA ESTABILIZADO E=0.15M m3 9,000.00 S/. 26.27 S/. 236,430.00 S/. 99,300.60 3780.00 42.00% S/. 137,129.40 5220.00 58.00% S/. - 0.00 0.00%
03.00 TRANSPORTE S/. 194,711.10 S/. 88,561.43 S/. 106,149.67 S/. -
03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM m3k 12,029.10 S/. 6.47 S/. 77,828.28 S/. 48,253.53 7458.04 62.00% S/. 29,574.75 4571.06 38.00% S/. - 0.00 0.00%
03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM m3k 53,317.32 S/. 1.80 S/. 95,971.18 S/. 40,307.90 22393.28 42.00% S/. 55,663.28 30924.05 58.00% S/. - 0.00 0.00%
03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 km m3k 748.07 S/. 6.75 S/. 5,049.47 S/. - 0.00 0.00% S/. 5,049.47 748.07 100.00% S/. - 0.00 0.00%
03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1 km m3k 8,392.68 S/. 1.89 S/. 15,862.17 S/. - 0.00 0.00% S/. 15,862.17 8392.68 100.00% S/. - 0.00 0.00%
04.00 OBRAS DE ARTE Y DRENAJE S/. 40,950.00 S/. 18,427.50 S/. 22,522.50 S/. -
04.01 RECONFORMACION DE CUNETAS m 15,000.00 S/. 2.73 S/. 40,950.00 S/. 18,427.50 6750.00 45.00% S/. 22,522.50 8250.00 55.00% S/. - 0.00 0.00%
05.00 SEÑALIZACION S/. 11,853.83 S/. - S/. 11,853.83 S/. -
05.01 INSTALACION DE POSTES KILOMETRICOS und 16.00 S/. 159.37 S/. 2,549.92 S/. - 0.00 0.00% S/. 2,549.92 16.00 100.00% S/. - 0.00 0.00%
05.02 SEÑALES PREVENTIVAS und 5.00 S/. 703.78 S/. 3,518.90 S/. - 0.00 0.00% S/. 3,518.90 5.00 100.00% S/. - 0.00 0.00%
05.03 SEÑALES REGLAMENTARIAS und 2.00 S/. 642.86 S/. 1,285.71 S/. - 0.00 0.00% S/. 1,285.71 2.00 100.00% S/. - 0.00 0.00%
05.04 SEÑALES INFORMATIVAS und 1.00 S/. 4,499.30 S/. 4,499.30 S/. - 0.00 0.00% S/. 4,499.30 1.00 100.00% S/. - 0.00 0.00%
06.00 IMPACTO AMBIENTAL S/. 9,220.01 S/. - S/. - S/. 9,220.01
07.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS Ha 1.21 S/. 7,619.84 S/. 9,220.01 S/. - 0.00 0.00% S/. - 0.00 0.00% S/. 9,220.01 1.21 100.00%
07.00 EMERGENCIA SANITARIA S/. 17,295.05 S/. 8,128.67 S/. 8,993.43 S/. 172.95
07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00 S/. 17,295.05 S/. 17,295.05 S/. 8,128.67 0.47 47.00% S/. 8,993.43 0.52 52.00% S/. 172.9505 0.01 1.00%

Costo Directo S/. 599,555.43 S/. 265,009.64 S/. 296,034.03 S/. - S/. 38,511.76
Gastos Generales (12%) 12.00% 0.3448 S/. 71,946.65 S/. 31,801.16 S/. 35,524.08 S/. - S/. 4,621.41
Utilidad (8%) 8.00% 0.05 S/. 47,964.43 S/. 21,200.77 S/. 23,682.72 S/. - S/. 3,080.94
44.20% 49.38% 0.00% 6.42%
SUBTOTAL S/. 719,466.51 S/. 318,011.57 S/. 355,240.83 S/. - S/. 46,214.11
IGV (18.00%) 0.00% 0.18 S/. 129,503.97 S/. 57,242.08 S/. 63,943.35 S/. - S/. 8,318.54
PRESUPUESTO TOTAL S/. 848,970.48 S/. 375,253.65 S/. 419,184.18 S/. - S/. 54,532.65
VALORIZACION DE OBRA
SERVICIO CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA, PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN
ENTIDAD CONTRATO DE SERVICIO Nº 028-2020-A/MPC
CONTRATISTA GEOZU S.A.C.
CONTRATO DE
OBRA CONTRATO DE SERVICIO Nº 028-2020-A/MPC
INSPECTOR ING. CLAUDIA L.B. RAEZ SAAVEDRA

VALORIZACION DICIEMBRE SALDO


P.U.
ITEM DESCRIPCIÓN UND METRADO PPTO BASE ACUMULADO ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR EJECUTAR
S/.
METRADO MONTO % AVANCE METRADO MONTO % AVANCE METRADO MONTO % AVANCE METRADO MONTO % AVANCE
CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL
SERVICIO TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA, PROVINCIA DE CONCEPCION, S/. 848,970.48
DEPARTAMENTO DE JUNIN
01 OBRAS PRELIMINARES S/. 65,632.44 S/. 140,041.55 213.37% S/. 36,513.65 55.63% S/. 73,027.29 111.27% -S/. 7,394.85 -11.27%
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 S/. 58,237.59 S/. 58,237.59 0.50 S/. 29,118.80 50.00% 0.500 S/. 29,118.80 50.00% 1.00 S/. 58,237.59 100.00% 0.000 S/. - 0.00%
01.02 TRAZO Y REPLANTEO km 15.00 S/. 492.99 S/. 7,394.85 15.00 S/. 110,922.75 1500.00% 15.000 S/. 7,394.85 100.00% 30.000 S/. 14,789.70 200.00% 0.000 -S/. 7,394.85 -100.00%
02 PAVIMENTOS S/. 259,893.00 ### 457318.77% S/. 25,598.25 9.85% S/. 25,598.25 9.85% S/. 234,294.75 90.15%
02.01 CAPA NIVELANTE E=0.05M m3 900.00 S/. 26.07 S/. 23,463.00 482.93 S/. 11,330,869.28 48292.50% 75.00 S/. 1,955.25 8.33% 75.00 S/. 1,955.25 8.33% 825.000 S/. 21,507.75 91.67%
02.02 MATERIAL GRANULAR DE CANTERA PARA ESTABILIZADO E=0.15M m3 9,000.00 S/. 26.27 S/. 236,430.00 4979.10 ### 497910.00% 900.000 S/. 23,643.00 10.00% 900.000 S/. 23,643.00 10.00% 8,100.000 S/. 212,787.00 90.00%
03 TRANSPORTE S/. 194,711.10 S/. - 0.00% S/. 7,997.60 4.11% S/. 7,997.60 4.11% S/. 186,713.50 95.89%
03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM m3k 12,029.10 S/. 6.47 S/. 77,828.28 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.00 S/. - 0.00% 12,029.100 S/. 77,828.28 100.00%
03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM m3k 53,317.32 S/. 1.80 S/. 95,971.18 S/. - 0.00% 4,443.110 S/. 7,997.60 8.33% 4,443.110 S/. 7,997.60 8.33% 48,874.210 S/. 87,973.58 91.67%
03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 km m3k 748.07 S/. 6.75 S/. 5,049.47 S/. - 0.00% 0.000 S/. - 0.00% 0.000 S/. - 0.00% 748.070 S/. 5,049.47 100.00%
03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1 km m3k 8,392.68 S/. 1.89 S/. 15,862.17 S/. - 0.00% 0.000 S/. - 0.00% 0.000 S/. - 0.00% 8,392.680 S/. 15,862.17 100.00%
04 OBRAS DE ARTE Y DRENAJE S/. 40,950.00 ### 680000.00% S/. 3,412.49 8.33% S/. 3,412.49 8.333% S/. 37,537.51 91.67%
04.01 RECONFORMACION DE CUNETAS m 15,000.00 S/. 2.73 S/. 40,950.00 6800.00 ### 680000.00% 1,250.00 S/. 3,412.49 8.33% 1,250.00 S/. 3,412.49 8.33% 13,750.000 S/. 37,537.51 91.67%
05 SEÑALIZACION S/. 11,853.83 S/. - 0.00% S/. - 0.00% S/. - 0.000% S/. 11,853.83 100.00%
05.01 INSTALACION DE POSTES KILOMETRICOS und 16.00 S/. 159.37 S/. 2,549.92 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.000 S/. - 0.00% 16.000 S/. 2,549.92 100.00%
05.02 SEÑALES PREVENTIVAS und 5.00 S/. 703.78 S/. 3,518.90 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.000 S/. - 0.00% 5.000 S/. 3,518.90 100.00%
05.03 SEÑALES REGLAMENTARIAS und 2.00 S/. 642.86 S/. 1,285.71 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.000 S/. - 0.00% 2.000 S/. 1,285.71 100.00%
05.04 SEÑALES INFORMATIVAS und 1.00 S/. 4,499.30 S/. 4,499.30 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.000 S/. - 0.00% 1.000 S/. 4,499.30 100.00%
06.00 IMPACTO AMBIENTAL S/. 9,220.01 S/. - 0.00% S/. - 0.00% S/. - 0.000% S/. 9,220.01 100.00%
06.01. RECUPERACION AMBIENTAL DE AREAS OCUPADAS Ha 1.21 S/. 7,619.84 S/. 9,220.01 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.00 S/. - 0.00% 1.210 S/. 9,220.01 100.00%
07 EMERGENCIA SANITARIA S/. 17,295.05 S/. 13,836.04 80.00% S/. 6,918.01 40.00% S/. 6,918.01 40.000% S/. 10,377.04 60.00%
07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00 S/. 17,295.05 S/. 17,295.05 0.80 S/. 13,836.04 80.00% 0.40 S/. 6,918.01 40.00% 1.20 S/. 6,918.01 40.00% -0.200 S/. 10,377.04 60.00%

Costo Directo S/. 599,555.43 S/. 1,467,153,359.87 S/. 80,440.00 S/. 116,953.64 S/. 482,601.79
Gastos Generales (12%) 12.00% 0.3448 S/. 71,946.65 S/. 176,058,403.18 S/. 9,652.80 S/. 14,034.44 S/. 57,912.21
Utilidad (8%) 8.00% 0.05 S/. 47,964.43 S/. 117,372,268.79 S/. 6,435.20 S/. 9,356.29 S/. 38,608.14
SUBTOTAL S/. 719,466.51 S/. 1,760,584,031.84 S/. 96,528.00 S/. 140,344.37 S/. 579,122.14
IGV (18.00%) 0.00% 0.18 S/. 129,503.97 S/. - S/. 17,375.03 S/. 17,375.03 S/. 104,242.00
PRESUPUESTO TOTAL S/. 848,970.48 S/. 1,760,584,031.84 S/. 113,903.03 S/. 157,719.40 S/. 683,364.14
207378.71% 13.416607% 18.577725% 80.493275%
VALORIZACION DE OBRA MARZO 2021
CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA,
SERVICIO
PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN
ENTIDAD CONTRATO DE SERVICIO Nº 028-2020-A/MPC
CONTRATISTA GEOZU S.A.C.
CONTRATO DE OBRA CONTRATO DE SERVICIO Nº 028-2020-A/MPC
INSPECTOR ING. CLAUDIA L.B. RAEZ SAAVEDRA

VALORIZACION ENERO SALDO


P.U.
ITEM DESCRIPCIÓN UND METRADO PPTO BASE ACUMULADO ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR EJECUTAR
S/.
METRADO MONTO % AVANCE METRADO MONTO % AVANCE METRADO MONTO % AVANCE METRADO MONTO % AVANCE
CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL
SERVICIO TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA, PROVINCIA DE S/. 848,970.48
CONCEPCION, DEPARTAMENTO DE JUNIN
01 OBRAS PRELIMINARES S/. 65,632.44 S/. 36,513.65 55.63% S/. - 0.00% S/. 36,513.65 55.63% S/. 29,118.79 44.37%
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 S/. 58,237.59 S/. 58,237.59 0.50 S/. 29,118.80 50.00% 0.000 S/. - 0.00% 0.50 S/. 29,118.80 50.00% 0.50 S/. 29,118.79 50.00%
01.02 TRAZO Y REPLANTEO km 15.00 S/. 492.99 S/. 7,394.85 15.00 S/. 7,394.85 100.00% 0.000 S/. - 0.00% 15.000 S/. 7,394.85 100.00% 0.00 S/. - 0.00%
02 PAVIMENTOS S/. 259,893.00 S/. 25,598.25 9.85% S/. 117,792.56 45.32% S/. 143,390.81 55.17% S/. 116,502.19 44.83%
02.01 CAPA NIVELANTE E=0.05M m3 900.00 S/. 26.07 S/. 23,463.00 75.00 S/. 1,955.25 8.33% 407.93 S/. 10,634.60 45.32% 482.93 S/. 12,589.85 53.66% 417.08 S/. 10,873.15 46.34%
02.02 MATERIAL GRANULAR DE CANTERA PARA ESTABILIZADO E=0.15M m3 9,000.00 S/. 26.27 S/. 236,430.00 900.00 S/. 23,643.00 10.00% 4,079.10 S/. 107,157.96 45.32% 4,979.10 S/. 130,800.96 55.32% 4,020.90 S/. 105,629.04 44.68%
03 TRANSPORTE S/. 194,711.10 S/. 7,997.60 4.11% S/. 125,444.68 64.43% S/. 133,442.28 68.53% S/. 61,268.82 31.47%
03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM m3k 12,029.10 S/. 6.47 S/. 77,828.28 0.00 S/. - 0.00% 12,029.10 S/. 77,828.28 100.00% 12,029.100 S/. 77,828.28 100.00% 0.00 S/. - 0.00%
03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM m3k 53,317.32 S/. 1.80 S/. 95,971.18 4443.11 S/. 7,997.60 8.33% 19,727.41 S/. 35,509.34 37.00% 24,170.52 S/. 43,506.94 45.33% 29,146.80 S/. 52,464.24 54.67%
03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 km m3k 748.07 S/. 6.75 S/. 5,049.47 0.00 S/. - 0.00% 497.38 S/. 3,357.34 66.49% 497.38 S/. 3,357.34 66.49% 250.69 S/. 1,692.13 33.51%
03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1 km m3k 8,392.68 S/. 1.89 S/. 15,862.17 0.00 S/. - 0.00% 4,629.48 S/. 8,749.72 55.16% 4,629.48 S/. 8,749.72 55.16% 3,763.20 S/. 7,112.45 44.84%
04 OBRAS DE ARTE Y DRENAJE S/. 40,950.00 S/. 3,412.49 8.33% S/. 15,151.49 37.00% S/. 18,563.98 45.333% S/. 22,386.02 54.67%
04.01 RECONFORMACION DE CUNETAS m 15,000.00 S/. 2.73 S/. 40,950.00 1250.00 S/. 3,412.49 8.33% 5,550.00 S/. 15,151.49 37.00% 6,800.00 S/. 18,563.98 45.33% 8,200.00 S/. 22,386.02 54.67%
05 SEÑALIZACION S/. 11,853.83 S/. - 0.00% S/. - 0.00% S/. - 0.000% S/. 11,853.83 100.00%
05.01 INSTALACION DE POSTES KILOMETRICOS und 16.00 S/. 159.37 S/. 2,549.92 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.000 S/. - 0.00% 16.00 S/. 2,549.92 100.00%
05.02 SEÑALES PREVENTIVAS und 5.00 S/. 703.78 S/. 3,518.90 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.000 S/. - 0.00% 5.00 S/. 3,518.90 100.00%
05.03 SEÑALES REGLAMENTARIAS und 2.00 S/. 642.86 S/. 1,285.71 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.000 S/. - 0.00% 2.00 S/. 1,285.71 100.00%
05.04 SEÑALES INFORMATIVAS und 1.00 S/. 4,499.30 S/. 4,499.30 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.000 S/. - 0.00% 1.00 S/. 4,499.30 100.00%
06.00 IMPACTO AMBIENTAL S/. 9,220.01 S/. - 0.00% S/. - 0.00% S/. - 0.000% S/. 9,220.01 100.00%
06.01. RECUPERACION AMBIENTAL DE AREAS OCUPADAS Ha 1.21 S/. 7,619.84 S/. 9,220.01 0.00 S/. - 0.00% 0.00 S/. - 0.00% 0.00 S/. - 0.00% 1.21 S/. 9,220.01 100.00%
07 EMERGENCIA SANITARIA S/. 17,295.05 S/. 6,918.01 40.00% S/. 6,918.01 40.00% S/. 13,836.02 80.000% S/. 3,459.03 20.00%
07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00 S/. 17,295.05 S/. 17,295.05 0.40 S/. 6,918.01 40.00% 0.40 S/. 6,918.01 40.00% 0.80 S/. 13,836.02 80.00% 0.20 S/. 3,459.03 20.00%

Costo Directo S/. 599,555.43 S/. 80,440.00 S/. 265,306.74 S/. 345,746.74 S/. 253,808.69
Gastos Generales (12%) 12.00% 0.3448 S/. 71,946.65 S/. 9,652.80 S/. 31,836.81 S/. 41,489.61 S/. 30,457.04
Utilidad (8%) 8.00% 0.05 S/. 47,964.43 S/. 6,435.20 S/. 21,224.54 S/. 27,659.74 S/. 20,304.69
SUBTOTAL S/. 719,466.51 S/. 96,528.00 S/. 318,368.09 S/. 414,896.09 S/. 304,570.42
IGV (18.00%) 0.00% 18% 0.18 S/. 129,503.97 S/. 17,375.03 S/. 57,306.26 S/. 74,681.29 S/. 54,822.68
PRESUPUESTO TOTAL S/. 848,970.48 S/. 113,903.03 S/. 375,674.35 S/. 489,577.38 S/. 359,393.10
13.416607% 44.2505787% 57.6671851% 42.332815%
VALORIZACION DE OBRA MARZO 2021
SERVICIO CONTRATO DE SERVICIO Nº 028-2020-A/MPC
ENTIDAD MUNICIPALIDAD PROVINCIAL DE CONCEPCCION
CONTRATISTA JUNIN – HUANCAYO – JR. PROGRESO NRO. 520 (ENTRE HUMBOLT Y PROGRESO)
CONTRATO DE OBRA MUNICIPALIDAD PROVINCIAL DE CONCEPCCION
INSPECTOR ING. CLAUDIA L.B. RAEZ SAAVEDRA

VALORIZACION MARZO SALDO


P.U.
ITEM DESCRIPCIÓN UND METRADO PPTO BASE ACUMULADO ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR EJECUTAR
S/.
METRADO MONTO % AVANCE METRADO MONTO % AVANCE METRADO MONTO % AVANCE METRADO MONTO % AVANCE
SERVICIO CONTRATO DE SERVICIO Nº 028-2020-A/MPC S/. 848,970.48
01 OBRAS PRELIMINARES S/. 65,632.44 S/. 36,513.65 55.63% S/. 29,118.79 44.37% S/. 65,632.44 100.00% S/. - 0.00%
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 S/. 58,237.59 S/. 58,237.59 0.50 S/. 29,118.80 50.00% 0.50 S/. 29,118.79 50.00% 1.00 S/. 58,237.59 100.00% 0.00 S/. - 0.00%
01.02 TRAZO Y REPLANTEO km 15.00 S/. 492.99 S/. 7,394.85 15.00 S/. 7,394.85 100.00% 0.00 S/. - 0.00% 15.000 S/. 7,394.85 100.00% 0.00 S/. - 0.00%
02 PAVIMENTOS S/. 259,893.00 S/. 143,390.81 55.17% S/. 116,502.19 44.83% S/. 259,893.00 100.00% S/. - 0.00%
02.01 CAPA NIVELANTE E=0.05M m3 900.00 S/. 26.07 S/. 23,463.00 482.93 S/. 12,589.85 53.66% 417.08 S/. 10,873.15 46.34% 900.00 S/. 23,463.00 100.00% 0.00 S/. - 0.00%
02.02 MATERIAL GRANULAR DE CANTERA PARA ESTABILIZADO E=0.15M m3 9,000.00 S/. 26.27 S/. 236,430.00 4,979.10 S/. 130,800.96 55.32% 4,020.90 S/. 105,629.04 44.68% 9,000.00 S/. 236,430.00 100.00% 0.00 S/. - 0.00%
03 TRANSPORTE S/. 194,711.10 S/. 133,442.28 68.53% S/. 61,268.82 31.47% S/. 194,711.10 100.00% S/. - 0.00%
03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM m3k 12,029.10 S/. 6.47 S/. 77,828.28 12,029.10 S/. 77,828.28 100.00% 0.00 S/. - 0.00% 12,029.100 S/. 77,828.28 100.00% 0.00 S/. - 0.00%
03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM m3k 53,317.32 S/. 1.80 S/. 95,971.18 24,170.52 S/. 43,506.94 45.33% 29,146.80 S/. 52,464.24 54.67% 53,317.32 S/. 95,971.18 100.00% 0.00 S/. - 0.00%
03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 km m3k 748.07 S/. 6.75 S/. 5,049.47 497.38 S/. 3,357.34 66.49% 250.69 S/. 1,692.13 33.51% 748.07 S/. 5,049.47 100.00% 0.00 S/. - 0.00%
03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1 km m3k 8,392.68 S/. 1.89 S/. 15,862.17 4,629.48 S/. 8,749.72 55.16% 3,763.20 S/. 7,112.45 44.84% 8,392.68 S/. 15,862.17 100.00% 0.00 S/. - 0.00%
04 OBRAS DE ARTE Y DRENAJE S/. 40,950.00 S/. 18,563.98 45.33% S/. 22,386.02 54.67% S/. 40,950.00 100.000% S/. - 0.00%
04.01 RECONFORMACION DE CUNETAS m 15,000.00 S/. 2.73 S/. 40,950.00 6,800.00 S/. 18,563.98 45.33% 8,200.00 S/. 22,386.02 54.67% 15,000.00 S/. 40,950.00 100.00% 0.00 S/. - 0.00%
05 SEÑALIZACION S/. 11,853.83 S/. - 0.00% S/. 11,853.83 100.00% S/. 11,853.83 100.000% S/. - 0.00%
05.01 INSTALACION DE POSTES KILOMETRICOS und 16.00 S/. 159.37 S/. 2,549.92 0.00 S/. - 0.00% 16.00 S/. 2,549.92 100.00% 16.000 S/. 2,549.92 100.00% 0.00 S/. - 0.00%
05.02 SEÑALES PREVENTIVAS und 5.00 S/. 703.78 S/. 3,518.90 0.00 S/. - 0.00% 5.00 S/. 3,518.90 100.00% 5.000 S/. 3,518.90 100.00% 0.00 S/. - 0.00%
05.03 SEÑALES REGLAMENTARIAS und 2.00 S/. 642.86 S/. 1,285.71 0.00 S/. - 0.00% 2.00 S/. 1,285.71 100.00% 2.000 S/. 1,285.71 100.00% 0.00 S/. - 0.00%
05.04 SEÑALES INFORMATIVAS und 1.00 S/. 4,499.30 S/. 4,499.30 0.00 S/. - 0.00% 1.00 S/. 4,499.30 100.00% 1.000 S/. 4,499.30 100.00% 0.00 S/. - 0.00%
06.00 IMPACTO AMBIENTAL S/. 9,220.01 S/. - 0.00% S/. 9,220.01 100.00% S/. 9,220.01 100.000% S/. - 0.00%
06.01. RECUPERACION AMBIENTAL DE AREAS OCUPADAS Ha 1.21 S/. 7,619.84 S/. 9,220.01 0.00 S/. - 0.00% 1.21 S/. 9,220.01 100.00% 1.21 S/. 9,220.01 100.00% 0.00 S/. - 0.00%
07 EMERGENCIA SANITARIA S/. 17,295.05 S/. 13,836.02 80.00% S/. 3,459.03 20.00% S/. 17,295.05 100.000% S/. - 0.00%
07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00 S/. 17,295.05 S/. 17,295.05 0.80 S/. 13,836.02 80.00% 0.20 S/. 3,459.03 20.00% 1.00 S/. 17,295.05 100.00% 0.00 S/. - 0.00%

Costo Directo S/. 599,555.43 S/. 345,746.74 S/. 253,808.69 S/. 599,555.43 S/. -
Gastos Generales (12%) 12.00% 0.3448 S/. 71,946.65 S/. 41,489.61 S/. 30,457.04 S/. 71,946.65 S/. -
Utilidad (8%) 8.00% 0.05 S/. 47,964.43 S/. 27,659.74 S/. 20,304.69 S/. 47,964.43 S/. -
SUBTOTAL S/. 719,466.51 S/. 414,896.09 S/. 304,570.42 S/. 719,466.51 S/. -
IGV (18.00%) 0.00% 18% 0.18 S/. 129,503.97 S/. 74,681.29 S/. 54,822.68 S/. 129,503.97 S/. -
PRESUPUESTO TOTAL S/. 848,970.48 S/. 489,577.38 S/. 359,393.10 S/. 848,970.48 S/. -
57.667185% 42.332815% 100.0000000% 0.000000%
CALCULO DE VALORIZACION MENSUAL MARZO
CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-SOCOS-
CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA, PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN

MONTO A PAGAR

CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-
SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA, PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN

FASES DESCRIPCION % VALORIZACION MONTO TOTAL


FASE II
EJECUCION DEL MANTENIMIENTO
PERIODICO 42.332815% S/. 359,393.10 S/. 359,393.10

RETENCION DE GARANTIAS (10% DEL MONTO CONTRACTUAL) YA SE DIO EN LAS DOS


VALORIZACIONES ANTERIORES S/. 102,285.60

RETENCION EN DICIEMBRE (5% DE TOTAL) S/. 51,142.80


RETENCION EN ENERO (5% DE TOTAL) S/. 51,142.80

TOTAL A PAGAR S/. 359,393.10


TRECIENTOS CINCUENTA Y NUEVE MIL TRECIENTOS NOVENTA Y TRES CON 10/100 SOLES

MONTO A FACTURAR

CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-
SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE ANDAMARCA, PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN

FASES DESCRIPCION % VALORIZACION MONTO TOTAL


FASE II EJECUCION DEL MANTENIMIENTO
42.332815% S/. 359,393.10 S/. 359,393.10
PERIODICO
TOTAL A FACTURAR S/. 359,393.10
TRECIENTOS CINCUENTA Y NUEVE MIL TRECIENTOS NOVENTA Y TRES CON 10/100 SOLES
RESUMEN DE METRADOS EJECUTADOS EN EL MES DE MARZO
CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE
SERVICIO
ANDAMARCA, PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN
ENTIDAD MUNICIPALIDAD PROVINCIAL DE CONCEPCCION
CONTRATISTA GEOZU S.A.C.
CONTRATO DE OBRA CONTRATO DE SERVICIO Nº 028-2020-A/MPC
INSPECTOR ING. CLAUDIA L.B. RAEZ SAAVEDRA

METRADO DE ACTIVIDADES EJECUTADAS


ITEM DESCRIPCIÓN UND METRADO PU PARCIAL SALDO % AVANCE % SALDO % AVANCE MENSUAL
ACUMULADO ACUMULADO ACUMULADO POR PARTIDA
ANTERIOR ACTUAL ACTUAL
01 OBRAS PRELIMINARES S/. 65,632.44 100.00% 0.00% 44.37%

01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 S/. 58,237.59 S/. 58,237.59 0.50 0.50 1.00 - 100.00% 0.00% 50.00%

01.02 TRAZO Y REPLANTEO km 15.000 S/. 492.99 S/. 7,394.85 15.00 0.00 15.00 - 100.00% 0.00% 0.00%
02 PAVIMENTOS S/. 259,893.00 0.00 0.00 0.00 - 100.00% 0.00% 44.83%

02.01 CAPA NIVELANTE E=0.05M m3 900.00 S/. 26.07 S/. 23,463.00 482.93 417.08 900.00 - 100.00% 0.00% 46.34%

02.02 MATERIAL GRANULAR DE CANTERA PARA ESTABILIZADO E=0.15 m3 9,000.00 S/. 26.27 S/. 236,430.00 4979.10 4020.90 9,000.00 - 100.00% 0.00% 44.68%
03 TRANSPORTE S/. 194,711.10 0.00 0.00 0.00 - 100.00% 0.00% 31.47%

03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM m3k 12,029.10 S/. 6.47 S/. 77,828.28 12029.10 0.00 12,029.10 - 100.00% 0.00% 0.00%

03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM m3k 53,317.32 S/. 1.80 S/. 95,971.18 24170.52 29146.80 53,317.32 - 100.00% 0.00% 54.67%

03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 km m3k 748.07 S/. 6.75 S/. 5,049.47 497.38 250.69 748.07 - 100.00% 0.00% 33.51%

03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1 km m3k 8,392.68 S/. 1.89 S/. 15,862.17 4629.48 3763.20 8,392.68 - 100.00% 0.00% 44.84%
04 OBRAS DE ARTE Y DRENAJE S/. 40,950.00 0.00 0.00 0.00 - 100.00% 0.00% 54.67%

04.01 RECONFORMACION DE CUNETAS m 15,000.00 S/. 2.73 S/. 40,950.00 6800.00 8200.00 15,000.00 - 100.00% 0.00% 54.67%

05 SEÑALIZACION S/. 11,853.84 0.00 0.00 0.00 - 100.00% 0.00% 100.00%

05.01 INSTALACION DE POSTES KILOMETRICOS und 16.00 S/. 159.37 S/. 2,549.92 0.00 16.00 16.00 - 100.00% 0.00% 100.00%

05.02 SEÑALES PREVENTIVAS und 5.00 S/. 703.78 S/. 3,518.90 0.00 5.00 5.00 - 100.00% 0.00% 100.00%

05.03 SEÑALES REGLAMENTARIAS und 2.00 S/. 642.86 S/. 1,285.72 0.00 2.00 2.00 - 100.00% 0.00% 100.00%

05.04 SEÑALES INFORMATIVAS und 1.00 S/. 4,499.30 S/. 4,499.30 0.00 1.00 1.00 - 100.00% 0.00% 100.00%

06.00 IMPACTO AMBIENTAL S/. 9,220.01 0.00 0.00 0.00 - 100.00% 0.00% 100.00%

06.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS glb 1.21 S/. 7,619.84 S/. 9,220.01 0.00 1.21 1.21 - 100.00% 0.00% 100.00%

07 EMERGENCIA SANITARIA S/. 17,295.05 0.00 0.00 0.00 - 100.00% 0.00% 20.00%

07.01 EMERGENCIA SANITARIA COVID 19 glb 1.00 S/. 17,295.05 S/. 17,295.05 0.80 0.20 1.00 - 100.00% 0.00% 20.00%
CURVA S
PAGOS REAL VS PAGO PROGRAMADO
CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO
OBRA VECINALES DEL TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE
ANDAMARCA, PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN
CONTRATO CONTRATO DE SERVICIO Nº 028-2020-A/MPC
CONTRATISTA GEOZU S.A.C.
SUPERVISOR ING. CLAUDIA L.B. RAEZ SAAVEDRA

GRAFICO DE PAGOS PROGRAMADOS VS PAGOS EFECTUADOS


100.000000%
100.00%
100.00% 93.58% 93.58%
90.00%
80.00%
70.00%
60.00% 57.667185% 57.667185%

50.00% 44.20%
40.00%
30.00%
20.00% 13.416607%
10.00%
0.000000%
0.00%
0.00% AVANCE REAL EJECUTADO ACUMULADO
04 DIC-INICIO 31- DICIEMBRE 31- ENERO 28- FEBRERO 30-MARZO
CRONOGRA PROGRAMADO ACELERADO
AVANCE PROGRAMADO ACUMULADO

AVANCE PROGRAMADO ACUMULADO


MONTOS (Inc/IGV)
MES
PARCIAL S/. ACUMULADO S/. PARCIAL % ACUMULADO %
04 DIC-INICIO S/. - S/. - 0.00% 0.00%
31- DICIEMBRE S/. 375,253.65 S/. 375,253.65 44.20% 44.20%
31- ENERO S/ 419,184.18 S/. 794,437.83 49.38% 93.58%
CRONOGRA PROGRAMADO ACELERADO
28- FEBRERO S/ 419,184.18 S/ 794,437.83 49.38% 93.58%
30-MARZO S/ 54,532.65 S/. 848,970.48 6.42% 100.00%
TOTAL S/. 848,970.48

AVANCE REAL EJECUTADO ACUMULADO


MONTOS (Inc/IGV)
MES
PARCIAL S/. ACUMULADO S/. PARCIAL % ACUMULADO %
04 DIC-INICIO S/. - S/. - 0.00% 0.00%
31- DICIEMBRE S/. 113,903.03 S/. 113,903.03 13.416607% 13.416607%
31- ENERO S/. 375,674.35 489,577.38 44.2505787% 57.6671851%
28- FEBRERO S/. 375,674.35 S/. 489,577.38 44.2505787% 57.6671851%
30-MARZO S/. 359,393.10 S/. 848,970.48 42.3328147% 100.0000%
TOTAL S/. 848,970.48
MES DEL INFORME

265009.638 296034.027
31801.157 35524.08
21200.77 23682.72
318011.57 355240.83
57242.08 63943.35
375253.65 419184.18
0 0
38511.756
4621.41
3080.94
46214.11
8318.54
54532.65
0
Cliente: Contratista:

MUNICIPALIDAD PROVINCIAL DE HUANCAYO

RESUMEN DE BOLETÍN MENSUAL DE VALORIZACIONES


N° de Contrato : 59-2020 MPH/GA Adicional: --
Fecha de Inicio: 1-Feb-21 Valorización: 1 Fecha: November-2020
Fecha de Fin: Err:509 Periodo de Valorización: NOVIEMBRE
Nombre del Servicio: MANTENIMIENTO Moneda: SI NO
PERIÓDICO Y RUTINARIO DEL CAMINO Valorización
VECINAL JU – 1116, TRAMO: EMP. JU-1115 SOLES Parcial X
SECTOR INGENIO – C.P SIUSA L=13.793 KM.

TOTAL CONTRATADO

SUBTOTAL (CI+CD) S/. 719,466.51


IGV S/. 129,503.97
TOTAL S/. 848,970.49

VALORIZACION ACTUAL
VALORIZACION ACTUAL (SIN IGV) S/. 96,528.00
IGV S/. 17,375.03
TOTAL S/. 113,903.03

DESCUENTOS
VALORIZACION ACTUAL S/. 113,903.03
AMORTIZACION ADELANTO DIRECTO Err:509
RETENCION DE GARANTIAS S/. -
TOTAL Err:509

TOTAL A VALORIZAR Err:509

_________________________________________ _________________________________________
CONTRATISTA INSPECTOR DEL SERVICIO
NOMBRE: NOMBRE:
FECHA: FECHA:
RESUMEN DE VALORIZACION MENSUAL CORRESPONDIENTE A LA FASE II MANTENIMIENTO PERIODICO -MARZO 2021
CONTRATACION DEL SERVICIO DE MANTENIMIENTO PERIODICO Y RUTINARIO DE CAMINO VECINALES DEL TRAMO:MATALAQUI-SOCOS-CODIGO R-120203116 (15.000 KM) DISTRITO DE
SERVICIO
ANDAMARCA, PROVINCIA DE CONCEPCION, DEPARTAMENTO DE JUNIN
ENTIDAD CONTRATANTE MUNICIPALIDAD PROVINCIAL DE CONCEPCCION
CONTRATISTA GEOZU S.A.C.
CONTRATO DE OBRA CONTRATO DE SERVICIO Nº 028-2020-A/MPC 0
INSPECTOR ING. CLAUDIA L.B. RAEZ SAAVEDRA

MONTO VALORIZACION ACUMULADO SALDO


DESCRIPCIÓN CONTRATADO ACTUAL
ANTERIOR ACTUAL % MONTO %

VALORIZACIÓN CONTRACTURAL (V)


VALORIZACION MENSUAL N°01 - FASE 2 - MARZO 2021 (CON IGV) S/. 848,970.48 S/. 359,393.10 S/. 489,577.38 S/. 848,970.48 100.00000% S/. - 0.0000000%

VALORIZACION MENSUAL N°01 - FASE 2 - MARZO 2021 (SIN IGV) S/. 719,466.51 S/. 304,570.42 S/. 414,896.09 S/. 719,466.51 100.00000% S/. - 0.0000000%

REAJUSTE ( R ) S/. -
VALORIZACIÓN BRUTA (VB=V+R) S/. 359,393.10 CON IGV

ADELANTOS ( A )
AMORTIZACIÓN DE ADELANTO DIRECTO CON IGV S/. - S/. - S/. - S/. - 0.00% S/. - 0.00%
AMORTIZACIÓN DE ADELANTO DE MATERIALES SIN IGV S/. - S/. - S/. - S/. - 0.00% S/. - 0.00%

TOTAL AMORTIZACIONES SIN IGV S/. - S/. - S/. - S/. - 0.00% S/. - 0.00%

TOTAL AMORTIZACIONES CON IGV S/. - S/. - S/. - 0.00% S/. - 0.00%
DEDUCCIONES QUE NO CORRESPONDEN (D)
DEL ADELANTO DIRECTO NO SE SOLICITO ADELANTO DIRECTO

DEL ADELANTO DE MATERIALES NO SE SOLICITO ADELANTO POR MATERIALES

TOTAL DE DEDUCIONES

RETENCIONES (F)
RETENCION DE FIEL CUMPLIMIENTO 10% HUBO RETENCION EN LAS VALORIZACIONES ANTERIORES

VALORIZACION NETA (VN=VB-A-F) S/. 359,393.10

TOTAL MONTO A FAVOR DEL CONTRATISTA S/. 359,393.10

MONTO A PAGAR AL CONTRATISTA: S/. 359,393.10


SON: TRES CIENTOS CINCUENTA Y NUEVE MIL TRES CIENTOS NOVENTA Y TRES CON 10/100 SOLES