CONTRATO DE CONSULTORIA DE OBRA N°014-2018-GM-MPPA-A

MONTO CONTRATADO S/. 3,377,000.00


RESUMEN DE VALORIZACIONES DE SUPERVISIÓN
N° Concepto Monto S/igv Amortización S/igv Total s/igv
0 ADELANTO DIRECTO S/. 858,559.32 S/. 0.00 S/. 858,559.32
1 PAGO POR VAL. Nº 1-AGO18 S/. 81,086.16 S/. 24,325.85 S/. 56,760.31
2 PAGO POR VAL. Nº 2-SET18 S/. 143,093.22 S/. 42,927.97 S/. 100,165.25
3 PAGO POR VAL. Nº 3-OCT18 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
4 PAGO POR VAL. Nº 4-NOV18 S/. 143,093.22 S/. 42,927.97 S/. 100,165.25
5 PAGO POR VAL. Nº 5-DIC18 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
6 PAGO POR VAL. Nº 6-ENE19 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
7 PAGO POR VAL. Nº 7-FEB19 S/. 133,553.67 S/. 40,066.10 S/. 93,487.57
8 PAGO POR VAL. Nº 8-MAR19 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
9 PAGO POR VAL. Nº 9-ABR19 S/. 143,093.22 S/. 42,927.97 S/. 100,165.25
10 PAGO POR VAL. Nº 10-MAY19 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
11 PAGO POR VAL. Nº 11-JUN19 S/. 143,093.22 S/. 42,927.97 S/. 100,165.25
12 PAGO POR VAL. Nº 12-JUL19 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
13 PAGO POR VAL. Nº 13-AGO19 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
14 PAGO POR VAL. Nº 14-SET19 S/. 143,093.22 S/. 42,927.97 S/. 100,165.25
15 PAGO POR VAL. Nº 15-OCT19 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
16 PAGO POR VAL. Nº 16-NOV19 S/. 143,093.22 S/. 42,927.97 S/. 100,165.25
17 PAGO POR VAL. Nº 17-DIC19 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
18 PAGO POR VAL. Nº 18-ENE20 S/. 147,862.99 S/. 44,358.90 S/. 103,504.09
TOTAL PAGADO S/. 3,410,388.37 S/. 765,548.74 S/. 2,644,839.63
19 FALTA PAGO POR VAL. Nº 19-FEB20 S/. 138,323.45 S/. 44,358.90 S/. 93,964.55
20 FALTA PAGO POR VAL. Nº 20-MAR20 S/. 71,546.61 S/. 48,651.68 S/. 22,894.93
TOTAL DEBEN S/. 209,870.06 S/. 93,010.58 S/. 116,859.48
TOTAL S/. 3,620,258.43 S/. 858,559.32 S/. 2,761,699.11

PLA
PROPUESTA N°01 PRO
CONTRATO
Adenda 01 Adenda 01
Plazo Contractual Ampliación 05 Ampliación 02
Fecha de Termino 2/5/2020 4/28/2020 2/7/2020
Plazo 540 83 2
Tárifa S/. 4,769.77 S/. 5,299.75 S/. 5,299.75
Total s/igv S/. 2,575,677.97 S/. 439,879.16 S/. 10,599.50
Total c/igv S/. 3,039,300.00 S/. 519,057.41 S/. 12,507.41
Liquidación S/. 337,700.00 S/. 0.00 S/. 0.00
Total Contratado S/. 3,377,000.00 S/. 3,558,357.41 S/. 3,051,807.41
-S/. 181,357.41
FALTA PRESUPUESTO
UPERVISIÓN Total percibido c/descuento
Total c/igv Acumulado Saldo Total Acumulado
S/. 1,013,100.00 S/. 1,013,100.00 S/. 2,363,900.00 S/. 1,013,100.00 S/. 1,013,100.00
S/. 66,977.17 S/. 1,080,077.17 S/. 2,296,922.83 S/. 66,977.17 S/. 1,080,077.17
S/. 118,195.00 S/. 1,198,272.17 S/. 2,178,727.83 S/. 118,195.00 S/. 1,198,272.17
S/. 122,134.83 S/. 1,320,407.00 S/. 2,056,593.00 S/. 122,134.83 S/. 1,320,407.00
S/. 118,195.00 S/. 1,438,602.00 S/. 1,938,398.00 S/. 118,195.00 S/. 1,438,602.00
S/. 122,134.83 S/. 1,560,736.83 S/. 1,816,263.17 S/. 122,134.83 S/. 1,560,736.83
S/. 122,134.83 S/. 1,682,871.66 S/. 1,694,128.34 S/. 122,134.83 S/. 1,682,871.66
S/. 110,315.33 S/. 1,793,186.99 S/. 1,583,813.01 S/. 110,315.33 S/. 1,793,186.99
S/. 122,134.83 S/. 1,915,321.82 S/. 1,461,678.18 S/. 122,134.83 S/. 1,915,321.82
S/. 118,195.00 S/. 2,033,516.82 S/. 1,343,483.18 S/. 118,195.00 S/. 2,033,516.82
S/. 122,134.83 S/. 2,155,651.65 S/. 1,221,348.35 S/. 122,134.83 S/. 2,155,651.65
S/. 118,195.00 S/. 2,273,846.65 S/. 1,103,153.35 S/. 105,195.00 S/. 2,260,846.65
S/. 122,134.83 S/. 2,395,981.47 S/. 981,018.53 S/. 109,134.83 S/. 2,369,981.47
S/. 122,134.83 S/. 2,518,116.30 S/. 858,883.70 S/. 109,134.83 S/. 2,479,116.30
S/. 118,195.00 S/. 2,636,311.29 S/. 740,688.71 S/. 105,195.00 S/. 2,584,311.29
S/. 122,134.83 S/. 2,758,446.12 S/. 618,553.88 S/. 109,134.83 S/. 2,693,446.12
S/. 118,195.00 S/. 2,876,641.12 S/. 500,358.88 S/. 105,195.00 S/. 2,798,641.12
S/. 122,134.83 S/. 2,998,775.94 S/. 378,224.06 S/. 109,134.83 S/. 2,907,775.94
S/. 122,134.83 S/. 3,120,910.77 S/. 256,089.23 S/. 109,134.83 S/. 3,016,910.77
S/. 3,120,910.77 S/. 3,377,000.00 S/. 3,016,910.77 S/. 104,000.00
S/. 110,878.17 S/. 3,231,788.94 S/. 145,211.06 S/. 97,878.17 S/. 3,114,788.94
S/. 27,016.01 S/. 3,258,804.95 S/. 118,195.05 S/. 14,016.01 S/. 3,128,804.95
S/. 137,894.18 S/. 3,377,000.00 S/. 111,894.18 S/. 26,000.00
S/. 3,258,804.95 S/. 118,195.05 S/. 3,128,804.95 S/. 130,000.00

PLANTEAMIENTO SUPERVISIÓN
PROPUESTA N°02 PROPUESTA N°03PROPUESTA N°04
Adenda 01 Adenda 02 Adenda 01 Adenda 01
Paralización Ampliación 04 Ampliación 05
3/15/2020 4/8/2020 4/28/2020 3/30/2020 4/28/2020
37 24 20 54 83
S/. 5,299.75 S/. 3,448.03 S/. 3,448.03 S/. 5,299.75 S/. 3,448.03
S/. 196,090.71 S/. 82,752.71 S/. 68,960.59 S/. 286,186.44 S/. 286,186.44
S/. 231,387.04 S/. 97,648.19 S/. 81,373.49 S/. 337,700.00 S/. 337,700.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
S/. 3,283,194.45 S/. 3,380,842.64 S/. 3,462,216.13 S/. 3,377,000.00 S/. 3,377,000.00
-S/. 85,216.13 S/. 0.00 S/. 0.00
FALTA PRESUPUESTO OK OK
AÑO EJECUCIÓN SALDO
SEGÚN VALORIZACIONES PAGADAS
2018 S/. 1,438,602.00 S/. 1,938,398.00
2019 S/. 1,319,844.12 S/. 618,553.88
2020 S/. 362,464.65 S/. 256,089.23
SEGÚN INFORME N°027-2020 DE PRESUPUESTO
2018 S/. 1,438,602.00 S/. 1,938,398.00
2019 S/. 1,319,844.14 S/. 618,553.86
2020 S/. 355,147.83 S/. 263,406.03

MONTO CONTRATADO S/ 3,377,000.00


EJECUCIÓN S/ 3,039,300.00 LIQUIDACION
AÑO EJECUCIÓN SALDO EJE
SEGÚN VALORIZACIONES PAGADAS
2018 S/. 1,438,602.00 S/. 1,600,698.00
2019 S/. 1,319,844.12 S/. 280,853.88
2020 S/. 252,712.16 S/. 28,141.72
2020 S/. 137,894.18 S/. 0.00

PLANTEAMIENTO MUNICIPALIDAD
PROPUESTA N°01PROPUESTA N°02
Adenda 01 Adenda 01
Ampliación 05 Ampliación 05
4/28/2020 4/28/2020
83 83
S/. 3,990.57 S/. 3,447.68
S/. 331,217.31 S/. 286,157.53
S/. 390,836.43 S/. 337,665.88
S/. 0.00 S/. 0.00
S/. 3,430,136.43 S/. 3,376,965.88
-S/. 53,136.43 S/. 34.12
FALTA PRESUPUESTO OK
S/ 3,377,000.00
S/ 337,700.00
SALDO LIQUI
S PAGADAS
S/. 337,700.00
S/. 337,700.00
S/. 337,700.00 HASTA ENERO
S/. 227,947.54 HASTA 15 MARZO
PAGO A CUENTA A CANCELAR AL SUPERVISOR
POR EL MES DE MARZO DEL 2020
VALORIZACIÓN 20

ENTIDAD : MUNICIPALIDAD PROVINCIAL DE PADRE ABAD


CONTRATISTA :CONSORCIO AGUAS DE AGUAYTIA
"AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO DE LA
OBRA :
CIUDAD DE AGUAYTIA Y CENTROS POBLADOS ALEDAÑOS - PROVINCIA DE PADRE DE ABAD - UCAYALI”
SUPERVISOR : CONSORCIO BOQUERÓN

PRESUPUESTO CONTRATADO CON IGV S/. 3,377,000.00


PRESUPUESTO CONTRATADO SIN IGV S/. 2,861,864.41
SUPERVISIÓN EJECUCIÓN DE OBRA S/. 2,575,677.97 90.00%
ETAPA DE LIQUIDACIÓN S/. 286,186.44 10.00%
FACTOR RELACIÓN : : 1,0
FECHA DE CONTRATO : 8/10/2018
INICIO DE PLAZO DE EJEC. DE OBRA : 8/15/2018
FECHA DE INICIO DE MES : 3/1/2020
FECHA DE FIN DE MES : 3/15/2020
DÍAS TRABAJADOS (DT) : 15.00 Dias
TARIFA POR DÍA (TD) : S/. 4,769.77
MONTO VALORIZADO (MV) : S/. 71,546.61 MV = DT * TD
PLAZO DE EJECUCIÓN : 540 días calendarios
AMPLIACIÓN DE PLAZO N°02: 2 días calendarios
AMPLIACIÓN DE PLAZO N°03: 26 días calendarios
AMPLIACIÓN DE PLAZO N°04: 35 días calendarios
AMPLIACIÓN DE PLAZO N°05: 20 días calendarios
FECHA DE TERMINO : 4/28/2020
ADELANTO DIRECTO CON IGV: S/. 1,013,100.00
ADELANTO DIRECTO SIN IGV: S/. 858,559.32
ADELANTO DE MATERIALES : S/. -

VALORIZACIÓN VALORIZACIÓN VALORIZACIÓN VALORIZACIÓN


ÍTEM CONCEPTOS ACTUAL ACUMULADA ACUMULADA SALDO
Mar-20 ANTERIOR ACTUAL

1.0 VALORIZACIÓN Y REAJUSTES


1.1 MONTO VALORIZACIÓN 71,546.61 2,690,152.50 ### 100,165.30
1.2 REAJUSTE VALORIZACIÓN
1.3 DEDUCCIÓN DE REAJUSTE DE ADELANTO DIRECTO

A. TOTAL VALORIZACIÓN BRUTA 71,546.61 2,690,152.50 ### 100,165.30

2.0 AMORTIZACIONES
2.1 DEL ADELANTO DIRECTO 48,651.68 809,907.64 858,559.32 -

B. TOTAL DE AMORTIZACIONES 48,651.68 809,907.64 858,559.32 -

C. VALORIZACIÓN NETA = (A-B) 22,894.93 1,880,244.86 ### 100,165.30


D FACTURACIÓN S/. 22,894.93

VALORIZACIÓN NETA S/. 22,894.93


I. G. V. (18.00%) S/. 4,121.09
TOTAL A FACTURAR S/. 27,016.02

E. RESUMEN

EN EFECTIVO A CANCELAR S/. 27,016.02

(*) RETENCIÓN GARANTÍA DE FIEL CUMPLIMIENTO (10%) - -

F. TOTAL A CANCELAR AL SUPERVISOR S/. 27,016.02

G. PORCENTAJE DE AVANCE FÍSICO 2.50% 94.00% 96.50%

SON: CIENTO DIECISIETE MIL SESENTA Y NUEVE CON 35/100 SOLES


VALORIZACION DE SUPERVISION DE OBRA No.20 MES DE MARZO 2020

CUADRO DE AVANCES DE SUPERVISION DE OBRA

ENTIDAD : MUNICIPALIDAD PROVINCIAL DE PADRE ABAD


CONTRATISTA : CONSORCIO AGUAS DE AGUAYTIA
"AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO DE LA CIUDAD DE AGUAYTIA Y CENTROS POBLADOS
OBRA :
ALEDAÑOS - PROVINCIA DE PADRE DE ABAD - UCAYALI”
PRESUPUESTO CONTRATADO CON IGV : S/. 3,377,000.00
PRESUPUESTO CONTRATADO SIN IGV : S/. 2,861,864.41
SUPERVISIÓN EJECUCIÓN DE OBRA : S/. 2,575,677.97
ETAPA DE LIQUIDACIÓN : S/. 286,186.44
SUPERVISOR : CONSORCIO BOQUERÓN

VALORIZACIÓN AVANCE EJECUTADO POR EL CONTRATISTA DE OBRA AVANCE EJECUTADO DE SUPERVISION DE OBRA
N° MES MENSUAL S/IGV % ACUMULADO S/IGV % % MONTO VALORIZACION S/IGV ACUMULADO AMORTIZACION S/IGV FACTURAR RETENCION S/IGV A PAGAR PAGADO SALDO S/IGV

01 Aug-18 S/. 226,475.97 0.29% S/. 226,475.97 0.29% 2.83% S/. 81,086.16 S/. 81,086.16 S/. 24,325.85 S/. 56,760.31 S/. 0.00 S/. 56,760.31 56,760.31 S/. 2,780,778.25
02 Sep-18 S/. 840,958.45 1.09% S/. 1,067,434.42 1.38% 5.00% S/. 143,093.22 S/. 224,179.38 S/. 42,927.97 S/. 100,165.25 S/. 100,165.25 100,165.25 S/. 2,637,685.03
03 Oct-18 S/. 2,559,433.72 3.31% S/. 3,626,868.14 4.69% 5.17% S/. 147,862.99 S/. 372,042.37 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 2,489,822.04
04 Nov-18 S/. 3,421,981.63 4.42% S/. 7,048,849.77 9.11% 5.00% S/. 143,093.22 S/. 515,135.59 S/. 42,927.97 S/. 100,165.25 S/. 100,165.25 100,165.25 S/. 2,346,728.82
05 Dec-18 S/. 3,057,689.37 3.95% S/. 10,106,539.14 13.06% 5.17% S/. 147,862.99 S/. 662,998.58 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 2,198,865.83
06 Jan-19 S/. 4,370,495.31 5.65% S/. 14,477,034.45 18.70% 5.17% S/. 147,862.99 S/. 810,861.57 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 2,051,002.84
07 Feb-19 S/. 3,629,054.48 4.69% S/. 18,106,088.93 23.39% 4.67% S/. 133,553.67 S/. 944,415.24 S/. 40,066.10 S/. 93,487.57 S/. 93,487.57 93,487.57 S/. 1,917,449.17
08 Mar-19 S/. 3,953,294.74 5.11% S/. 22,059,383.67 28.50% 5.17% S/. 147,862.99 S/. 1,092,278.23 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 1,769,586.18
09 Apr-19 S/. 3,631,637.11 4.69% S/. 25,691,020.78 33.19% 5.00% S/. 143,093.22 S/. 1,235,371.45 S/. 42,927.97 S/. 100,165.25 S/. 100,165.25 100,165.25 S/. 1,626,492.96
10 May-19 S/. 5,693,751.52 7.36% S/. 31,384,772.30 40.54% 5.17% S/. 147,862.99 S/. 1,383,234.44 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 1,478,629.97
11 Jun-19 S/. 3,271,620.04 4.23% S/. 34,656,392.34 44.77% 5.00% S/. 143,093.22 S/. 1,526,327.66 S/. 42,927.97 S/. 100,165.25 S/. 100,165.25 100,165.25 S/. 1,335,536.75
12 Jul-19 S/. 5,173,085.52 6.68% S/. 39,829,477.86 51.45% 5.17% S/. 147,862.99 S/. 1,674,190.65 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 1,187,673.76
13 Aug-19 S/. 3,710,140.48 4.79% S/. 43,539,618.33 56.24% 5.17% S/. 147,862.99 S/. 1,822,053.64 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 1,039,810.77
14 Sep-19 S/. 3,147,757.64 4.07% S/. 46,687,375.97 60.31% 5.00% S/. 143,093.22 S/. 1,965,146.86 S/. 42,927.97 S/. 100,165.25 S/. 100,165.25 100,165.25 S/. 896,717.55
15 Oct-19 S/. 3,368,541.16 4.35% S/. 50,055,917.13 64.66% 5.17% S/. 147,862.99 S/. 2,113,009.85 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 748,854.56
16 Nov-19 S/. 5,405,815.20 6.98% S/. 55,461,732.33 71.65% 5.00% S/. 143,093.22 S/. 2,256,103.07 S/. 42,927.97 S/. 100,165.25 S/. 100,165.25 100,165.25 S/. 605,761.34
17 Dec-19 S/. 2,884,043.13 3.73% S/. 58,345,775.46 75.37% 5.17% S/. 147,862.99 S/. 2,403,966.06 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 457,898.35
18 Jan-20 S/. 2,052,063.81 2.65% S/. 60,397,839.27 78.02% 5.17% S/. 147,862.99 S/. 2,551,829.05 S/. 44,358.90 S/. 103,504.09 S/. 103,504.09 103,504.09 S/. 310,035.36
18 Feb-20 S/. 844,310.74 1.09% S/. 61,242,150.01 79.11% 4.83% S/. 138,323.45 S/. 2,690,152.50 S/. 44,358.90 S/. 93,964.55 S/. 93,964.55 93,964.55 S/. 171,711.91
19 Mar-20 S/. 61,242,150.01 79.11% 2.50% S/. 71,546.61 S/. 2,761,699.11 S/. 48,651.68 S/. 22,894.93 S/. 22,894.93 22,894.93 S/. 100,165.30
S/. 61,242,150.01 79.11% 96.50% S/. 2,761,699.11 S/. 858,559.32 S/. 1,903,139.79 S/. 0.00 S/. 1,903,139.79 S/. 1,903,139.79
DESAGREGADO DE COSTOS DE OFERTA ECONOMICA - SUPERVISION DE OBRA
ENTIDAD MUNICIPALIDAD PROVINCIAL DE PADRE ABAD
CONTRATIST CONSORCIO AGUAS DE AGUAYTIA
SUPERVISIÓNCONSORCIO BOQUERÓN
OBRA "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO DE LA CIUDAD
DE AGUAYTIA Y CENTROS POBLADOS ALEDAÑOS - PROVINCIA DE PADRE DE ABAD - UCAYALI”
PLAZO DE EJ 540 d.c.
COEF
CANT . TIEMPO C. UNIT C. PARCIAL SUB TOTAL
ITEM DESCRIPCIÓN DEL GASTO UND
. PART MESES S/. S/. S/.
1.00 PERSONAL PROFESIONAL . 1,420,500.00
GERENTE DE SUPERVISIÓN MES 1.00 0.50 12.00 8,000.00 48,000.00
JEFE DE SUPERVISIÓN DE OBRA MES 1.00 1.00 18.00 12,000.00 216,000.00
ASIST. DE SUPERVISIÓN 1 MES 1.00 1.00 18.00 10,000.00 180,000.00
ASIST. DE SUPERVISIÓN 2 MES 1.00 0.50 18.00 10,000.00 90,000.00
ESP. ELECTROMECANICO MES 1.00 0.50 18.00 5,500.00 49,500.00
ESP. EN PRESUPUESTO, PROGRAMACIÓN Y VALORMES 1.00 0.50 18.00 12,000.00 108,000.00
ESP. EN ESTRUCTURAS MES 1.00 0.50 18.00 12,000.00 108,000.00
ESP. AMBIENTAL MES 1.00 0.50 18.00 8,000.00 72,000.00
ESP. SANITARIO 1 MES 1.00 0.50 18.00 14,000.00 126,000.00
ESP. SANITARIO 2 MES 1.00 0.50 18.00 14,000.00 126,000.00
ESP. EN SEGURIDAD E HIGIENE OCUPACIONAL MES 1.00 0.50 18.00 11,000.00 99,000.00
ESP. EN ARQUEOLOGIA MES 1.00 0.50 18.00 11,000.00 99,000.00
ESP. EN MECANICA DE SUELOS MES 1.00 0.50 18.00 11,000.00 99,000.00

2.00 PERSONAL TECNICO 732,600.00


TOPOGRAFO MES 2.00 1.00 18.00 3,500.00 126,000.00
AYUDANTE DE TOPOGRAFO MES 4.00 1.00 18.00 1,800.00 129,600.00
TECNICO EN METRADOS MES 3.00 1.00 18.00 2,500.00 135,000.00
TECNICO DE CAMPO MES 6.00 1.00 18.00 2,500.00 270,000.00
SECRETARIA MES 2.00 1.00 18.00 2,000.00 72,000.00

3.00 ALQUILERES Y SERVICIOS 474,392.12


OFICINA MES 2.00 1.00 18.00 1,000.00 36,000.00
UTILES DE OFICINA Y DIBUJO MES 2.00 1.00 18.00 1,000.00 36,000.00
COPIAS, REPRODUCCIONES, IMPRESIONES Y OTR MES 2.00 1.00 18.00 477.56 17,192.12
EQUIPO DE TOPOGRAFÍA MES 2.00 1.00 18.00 5,000.00 180,000.00
CAMIONETA (INCLY. CHOFER) MES 2.00 1.00 18.00 5,000.00 180,000.00
COMUNICACIONES MES 2.00 1.00 18.00 700.00 25,200.00

COSTO DIRECTO S/. 2,627,492.12


GASTOS GENERALES 129,272.61
UTILIDAD 105,099.68
SUB TOTAL S/. 2,861,864.41
IGV 515,135.59
TOTAL DE OFERTA ECONOMICA S/. 3,377,000.00
DESAGREGADO DE GASTOS GENERALES - SUPERVISION DE OBRA
ENTIDAD MUNICIPALIDAD PROVINCIAL DE PADRE ABAD
CONTRATIST CONSORCIO AGUAS DE AGUAYTIA
SUPERVISIÓNCONSORCIO BOQUERÓN
OBRA "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO DE LA CIUDAD
DE AGUAYTIA Y CENTROS POBLADOS ALEDAÑOS - PROVINCIA DE PADRE DE ABAD - UCAYALI”
PLAZO DE EJ 540 d.c.

CANT COEF TIEMPO C. UNIT C. PARCIAL SUB TOTAL


ITEM DESCRIPCIÓN DEL GASTO UND
. . MESES S/. S/. S/.
1.00 PERSONAL DE OFICINA 9,000.00
ASISTENTE ADMINISTRATIVO Y LOGISTICO MES 1.00 0.25 18.00 2,000.00 9,000.00
2.00 EQUIPOS Y SERVICIOS DE INGENIERIA 2,700.00
EQUIPO DE LABORATORIO DE CAMPO MES 1.00 0.50 18.00 300.00 2,700.00
3.00 EQUIPOS DE OFICINA 54,180.00
PLOTER MES 2.00 1.00 18.00 300.00 10,800.00
IMPRESORA MES 2.00 1.00 18.00 100.00 3,600.00
FOTOCOPIADORA MES 2.00 1.00 18.00 150.00 5,400.00
CAMARAS DIGITALES MES 3.00 1.00 18.00 50.00 2,700.00
CAMARAS DE VIDEO MES 2.00 1.00 18.00 80.00 2,880.00
EQUIPOS DE COMPUTO MES 8.00 1.00 18.00 200.00 28,800.00
4.00 GASTOS FINANCIEROS 63,392.61
CARTA FIANZA DE FIEL CUMPLIMIENTO MES 1.00 1.00 18.00 1,500.00 27,000.00
CARTA FIANZA DE ADELANTO DIRECTO MES 1.00 1.00 18.00 2,021.81 36,392.61
GASTOS GENERALES 129,272.61
DESAGREGADO DE COSTOS DE OFERTA ECONOMICA - SUPERVISION DE OBRA
ENTIDAD MUNICIPALIDAD PROVINCIAL DE PADRE ABAD
CONTRATIST CONSORCIO AGUAS DE AGUAYTIA
SUPERVISIÓNCONSORCIO BOQUERÓN
OBRA "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO DE LA CIUDAD
DE AGUAYTIA Y CENTROS POBLADOS ALEDAÑOS - PROVINCIA DE PADRE DE ABAD - UCAYALI”
PLAZO DE EJ 540 d.c.
COEF
CANT . TIEMPO C. UNIT C. PARCIAL SUB TOTAL
ITEM DESCRIPCIÓN DEL GASTO UND
. PART MESES S/. S/. S/.
1.00 PERSONAL PROFESIONAL . 107,208.33
JEFE DE SUPERVISIÓN DE OBRA MES 1.00 1.00 2.77 12,000.00 33,200.00
ESP. ELECTROMECANICO MES 1.00 0.50 2.77 5,500.00 7,608.33
ESP. EN PRESUPUESTO, PROGRAMACIÓN Y VALORMES 1.00 0.50 2.77 12,000.00 16,600.00
ESP. SANITARIO 2 MES 1.00 0.50 2.77 14,000.00 19,366.67
ESP. EN MECANICA DE SUELOS MES 1.00 0.50 2.77 11,000.00 15,216.67
ESP. EN SEGURIDAD, SALUD Y MEDIO AMBIENTE MES 1.00 0.50 2.77 11,000.00 15,216.67

2.00 PERSONAL TECNICO 82,723.33


TOPOGRAFO MES 1.00 1.00 2.77 3,500.00 9,683.33
AYUDANTE DE TOPOGRAFO MES 3.00 1.00 2.77 1,800.00 14,940.00
TECNICO EN METRADOS MES 3.00 1.00 2.77 2,500.00 20,750.00
TECNICO DE CAMPO MES 5.00 1.00 2.77 2,500.00 34,583.33
SECRETARIA MES 1.00 0.50 2.77 2,000.00 2,766.67

3.00 ALQUILERES Y SERVICIOS 72,817.55


OFICINA MES 2.00 1.00 2.77 1,000.00 5,533.33
UTILES DE OFICINA Y DIBUJO MES 2.00 1.00 2.77 1,000.00 5,533.33
COPIAS, REPRODUCCIONES, IMPRESIONES Y OTR MES 2.00 1.00 2.77 459.80 2,544.22
EQUIPO DE TOPOGRAFÍA MES 2.00 1.00 2.77 5,000.00 27,666.67
CAMIONETA (INCLY. CHOFER) MES 2.00 1.00 2.77 5,000.00 27,666.67
COMUNICACIONES MES 2.00 1.00 2.77 700.00 3,873.33

COSTO DIRECTO S/. 262,749.21


GASTOS GENERALES 12,927.26
UTILIDAD 10,509.97
SUB TOTAL S/. 286,186.44
IGV 51,513.56
TOTAL DE OFERTA ECONOMICA S/. 337,700.00
DESAGREGADO DE COSTOS DE OFERTA ECONOMICA - SUPERVISION DE OBRA
ENTIDAD MUNICIPALIDAD PROVINCIAL DE PADRE ABAD
CONTRATIST CONSORCIO AGUAS DE AGUAYTIA
SUPERVISIÓNCONSORCIO BOQUERÓN
OBRA "AMPLIACIÓN Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO DE LA CIUDAD
DE AGUAYTIA Y CENTROS POBLADOS ALEDAÑOS - PROVINCIA DE PADRE DE ABAD - UCAYALI”
PLAZO DE EJ 540 d.c.
COEF
CANT . TIEMPO C. UNIT C. PARCIAL SUB TOTAL
ITEM DESCRIPCIÓN DEL GASTO UND
. PART MESES S/. S/. S/.
1.00 PERSONAL PROFESIONAL . 102,591.67
GERENTE DE SUPERVISIÓN MES 1.00 0.50 0.87 8,000.00 3,466.67
JEFE DE SUPERVISIÓN DE OBRA MES 1.00 1.00 1.30 12,000.00 15,600.00
ASIST. DE SUPERVISIÓN 1 MES 1.00 1.00 1.30 10,000.00 13,000.00
ASIST. DE SUPERVISIÓN 2 MES 1.00 0.50 1.30 10,000.00 6,500.00
ESP. ELECTROMECANICO MES 1.00 0.50 1.30 5,500.00 3,575.00
ESP. EN PRESUPUESTO, PROGRAMACIÓN Y VALORMES 1.00 0.50 1.30 12,000.00 7,800.00
ESP. EN ESTRUCTURAS MES 1.00 0.50 1.30 12,000.00 7,800.00
ESP. AMBIENTAL MES 1.00 0.50 1.30 8,000.00 5,200.00
ESP. SANITARIO 1 MES 1.00 0.50 1.30 14,000.00 9,100.00
ESP. SANITARIO 2 MES 1.00 0.50 1.30 14,000.00 9,100.00
ESP. EN SEGURIDAD E HIGIENE OCUPACIONAL MES 1.00 0.50 1.30 11,000.00 7,150.00
ESP. EN ARQUEOLOGIA MES 1.00 0.50 1.30 11,000.00 7,150.00
ESP. EN MECANICA DE SUELOS MES 1.00 0.50 1.30 11,000.00 7,150.00

2.00 PERSONAL TECNICO 52,910.00


TOPOGRAFO MES 2.00 1.00 1.30 3,500.00 9,100.00
AYUDANTE DE TOPOGRAFO MES 4.00 1.00 1.30 1,800.00 9,360.00
TECNICO EN METRADOS MES 3.00 1.00 1.30 2,500.00 9,750.00
TECNICO DE CAMPO MES 6.00 1.00 1.30 2,500.00 19,500.00
SECRETARIA MES 2.00 1.00 1.30 2,000.00 5,200.00

3.00 ALQUILERES Y SERVICIOS 34,261.65


OFICINA MES 2.00 1.00 1.30 1,000.00 2,600.00
UTILES DE OFICINA Y DIBUJO MES 2.00 1.00 1.30 1,000.00 2,600.00
COPIAS, REPRODUCCIONES, IMPRESIONES Y OTR MES 2.00 1.00 1.30 477.56 1,241.65
EQUIPO DE TOPOGRAFÍA MES 2.00 1.00 1.30 5,000.00 13,000.00
CAMIONETA (INCLY. CHOFER) MES 2.00 1.00 1.30 5,000.00 13,000.00
COMUNICACIONES MES 2.00 1.00 1.30 700.00 1,820.00

COSTO DIRECTO S/. 189,763.32


GASTOS GENERALES 9,336.36
UTILIDAD 7,590.53
SUB TOTAL S/. 206,690.21
IGV 37,204.24
TOTAL DE OFERTA ECONOMICA S/. 243,894.45