CRONOGRAMA VALORIZADO

MANTENIMIENTO PERIÓDICO Y RUTINARIO DEL CAMINO VECINAL, TRAYECTORIA : EMP. AP-940 (PICHACA) - EMP. AP-942 (CHOQQUECCA), TRAYECTORIA
: EMP. AP-940 - HUAYLLAHUILQUE- PUMAMARCA, TRAYECTORIA : EMP. R30504-06 (HUAYLLAHUILQUE) - ÑUÑUNPATA, TRAYECTORIA : EMP. AP-940 -
HUAYLLAHUILQUE- PUMAMARCA - EMP. A (HUAYLLAHUILQUE), TRAYECTORIA : EMP. AP-940 (ASACASI) - CCASACANCHA, TRAYECTORIA : EMP. R30504-
09 (CCASACANCHA) - PILLCO
PRESUPUESTO SEGÚN EXP. TEC. MODIFICADO Nº 01 VALORIZACION PROGRAMADA
PARTIDA DESCRIPCION PRECIO TOTAL SALDO TOTAL
UND METRADO UNITARIO PRESUPUES. PRESUPUES. NOVIEMBRE DICIEMBRE
S/. S/. S/.
1 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 66,769.94 66,769.94 33,384.97 33,384.97
1.02 TRAZO Y REPLANTEO KM 21.69 625.84 13,576.97 -
2 PAVIMENTOS - -
2.01 CAPA NIVELANTE E=0.05 M m3 4,338.80 17.02 73,846.38 64,482.66 20,634.45 43,848.21
2.02 MATERIAL GRANULAR DE CANTERA E=0.15 M m3 16270.50 20.69 336,636.65 253,891.36 81,245.23 172,646.12
3 TRANSPORTE - - -
3.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3/K 17,493.95 6.71 117,384.40 117,384.40 37,563.01 79,821.40
3.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1 KM M3/K 45,297.30 2.63 119,131.90 119,131.90 38,122.21 81,009.69
3.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3/K 857.04 6.39 5,476.49 5,476.49 1,752.48 3,724.01
3.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM M3/K 9788.25 2.51 24,568.51 24,568.51 7,861.92 16,706.59
4 OBRAS DE ARTE Y DRENAJE - - -
4.01 RECONFORMACION DE CUNETAS ml 21694.00 2.55 55,319.70 44,609.81 23,791.90 20,817.91
5 SEÑALIZACION - - -
5.01 INSTALACION DE POSTES KILOMETRICOS und 30.00 290.15 8,704.50 8,704.50 8,704.50
5.02 SEÑALES PREVENTIVAS und 30.00 320.18 9,605.40 9,605.40 9,605.40
5.03 SEÑALES REGLAMENTARIAS und 12.00 580.76 6,969.12 6,969.12 6,969.12
5.04 SEÑALES INFORMATIVAS und 12.00 1,135.41 13,624.92 13,624.92 13,624.92
6 IMPACTO AMBIENTAL - - -
6.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA 1.75 4,966.49 8,691.36 8,691.36 8,691.36
7 EMERGENCIA SANITARIA - - -
7.01 EMERGENCIA SANITARIA COVID 19 GLB 1.00 18,822.89 18,822.89 17,317.06 5,541.46 11,775.60

COSTO DIRECTO 879,129.12 727,842.44 216,512.65 511,329.79


GASTOS GENERALES ( 10.36%) 10.36% 75,409.57 22,432.23 52,977.34
UTILIDAD ( 8%) 8.00% 58,227.40 17,321.01 40,906.38
SUB TOTAL 861,479.41 256,265.89 605,213.51
IMPUESTOS (IGV) (18%) 18.00% 155,066.29 46,127.86 108,938.43
PRESUPUESTO DE OBRA 1,016,545.70 302,393.75 714,151.95

AVANCE EJECUTADO A COSTO TOTAL 100.000% 29.75% 70.25%

AVANCE ACUMULADOA COSTO TOTAL 100.000% 29.75% 100.00%