Documentos de Académico
Documentos de Profesional
Documentos de Cultura
OBRA: PACCHIPATA, SINHUAPATA, EDEN, TENERIA, MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA, RAYAMPAMPA, MAYABAMBA, ONGOYPATA, JR. LOS
BOSQUES Y CHUQUIBAMBA DEL DISTRITO DE OCOBAMBA – CHINCHEROS – APURIMAC"
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO : APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
FECHA DE TÉRMINO REAL : 03/10/2020
CONTROL DE VALORIZACIONES Nº 02
ENERO 2020
MONTO DEL AVANCE
DESCRIPCION CONTRATO VALORIZACIÓN ACTUAL
ANTERIOR % ACTUAL % SALDO %
SIN/IGV
AMORTIZACIONES (A)
AMORTIZACION ADELANTO DIRECTO 0.00 0.00
VAL Nº 01 DICIEMBRE-19 0.00
VAL Nº 02 ENERO-20 0.00
VAL Nº 03 FEBRERO-20 0.00
VAL Nº 04 MARZO-20 0.00
VAL Nº 05 ABRIL-20 0.00
VAL Nº 06 MAYO-20 0.00
VAL Nº 07 JUNIO-20 0.00
VAL Nº 08 JULIO-20 0.00
VAL Nº 09 AGOSTO-20 0.00
VAL Nº 10 SEPTIEMBRE-20
AMORTIZACION ADELANTO DE MATERIALES 0.00 0.00
VAL Nº 01 DICIEMBRE-19 0.00
VAL Nº 02 ENERO-20 0.00
VAL Nº 03 FEBRERO-20 0.00
VAL Nº 04 MARZO-20 0.00
VAL Nº 05 ABRIL-20 0.00
VAL Nº 06 MAYO-20
VAL Nº 07 JUNIO-20
VAL Nº 08 JULIO-20
VAL Nº 09 AGOSTO-20
VAL Nº 10 SEPTIEMBRE-20
VAL Nº 11 OCTUBRE-20
TOTAL AMORTIZACIONES 0.00 0.00
COSTO DIRECTO 9,490,370.18 287,738.66 647,641.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 935,380.48 8,554,989.70
GASTOS GENERALES (8.75%) 830,407.39 25,177.13 56,668.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 81,845.79 748,561.60
UTILIDAD (7.00%) 664,325.91 20,141.71 45,334.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 65,476.63 598,849.28
COSTO TOTAL (SIN IVG) 10,985,103.48 333,057.50 749,645.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,082,702.91 9,902,400.57
IGV (18%) 1,977,318.63 59,950.35 134,936.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 194,886.52 1,782,432.10
COSTO TOTAL 12,962,422.11 393,007.85 884,581.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,277,589.43 11,684,832.68
% AVANCE MENSUAL 3.03% 6.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9.86% 90.14%
12,962,422.11 393,007.85 884,581.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,277,589.43 11,684,832.68
% AVANCE ACUMULADO 3.03% 9.86% 9.86% 9.86% 9.86% 9.86% 9.86% 9.86% 9.86% 9.86% 9.86% 90.14%
"MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE TRATAMIENTO DE AGUAS SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA, SINHUAPATA, EDEN, TENERIA,
OBRA:
MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA, RAYAMPAMPA, MAYABAMBA, ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL DISTRITO DE OCOBAMBA – CHINCHEROS – APURIMAC"
90.00%
80.00%
OBRA
70.00%
ATRASADA
60.00%
-3.14%
50.00%
40.00%
LEYENDA
LEYENDA 30.00%
CURVA
CURVA PROG
PROG 20.00%
CURVA
CURVA REAL
REAL 10.00%
0.00%
Inicio 09/12/19 dic-19 ene-20 feb-20 mar-20 abr-20 may-20 jun-20 jul-20 ago-20 sep-20 oct-20
MESES
0 1 2 3 4 5 6 7 8 9 10 11
MESES Inicio 09/12/19 dic-19 ene-20 feb-20 mar-20 abr-20 may-20 jun-20 jul-20 ago-20 sep-20 oct-20
PROG 0.00% 1.19% 13.00% 28.87% 37.21% 50.94% 64.51% 83.75% 88.80% 96.18% 99.51% 100.00%
PORCENTAJE ACUMULADO
REAL 0.00% 3.03% 9.86%
VAL ACUMULADO
PROG 13.00% ATRASADA -3.14%
REAL 9.86%
01 Dec-19 130,578.05 1.19% 130,578.05 1.19% 333,057.50 3.03% 333,057.50 3.03% ADELANTADA 1.84%
02 Jan-20 1,297,125.71 11.81% 1,427,703.76 13.00% 749,645.41 6.82% 1,082,702.91 9.86% ATRASADA -3.14%
03 Feb-20 1,743,579.53 15.87% 3,171,283.29 28.87%
04 Mar-20 916,746.52 8.35% 4,088,029.80 37.21%
05 Apr-20 1,507,363.06 13.72% 5,595,392.86 50.94%
06 May-20 1,490,906.45 13.57% 7,086,299.31 64.51%
07 Jun-20 2,113,708.41 19.24% 9,200,007.72 83.75%
08 Jul-20 554,612.46 5.05% 9,754,620.18 88.80%
09 Aug-20 810,450.98 7.38% 10,565,071.15 96.18%
10 Sep-20 366,504.49 3.34% 10,931,575.64 99.51%
11 Oct-20 53,527.84 0.49% 10,985,103.48 100.00%
10,985,103.48
"MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE TRATAMIENTO DE AGUAS SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA, SINHUAPATA, EDEN,
OBRA: TENERIA, MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA, RAYAMPAMPA, MAYABAMBA, ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL DISTRITO DE OCOBAMBA –
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA CHINCHEROS – APURIMAC" CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO: APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
FECHA DE TÉRMINO : 03/10/2020
VALORIZACION 02
ENERO 2020
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
AVANCE
SALDO
Ítem Descripción Und. Metrado Precio Unitario Costo Total ANTERIOR ACTUAL ACUMULADA
COSTO DIRECTO S/. 9,490,370.18 287,738.66 3.03% 647,641.82 6.82% 935,380.52 9.86% 8,554,989.67 90.14%
SUBTOTAL S/. 9,490,370.18 287,738.66 647,641.82 935,380.52 8,554,989.67
PORCENTAJE DE AVANCE MENSUAL 3.03% 6.82% 9.86% 90.14%
OBRA: "MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE
TRATAMIENTO DE AGUAS SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA, SINHUAPATA, EDEN, TENERIA,
MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA, RAYAMPAMPA, MAYABAMBA,
ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL DISTRITO DE OCOBAMBA – CHINCHEROS – APURIMAC"
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO : APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
SUPERVISOR : Ing. Henrry Santa Cruz Castro FECHA DE TÉRMINO REAL : 03/10/2020
RESIDENTE : Ing. Jose Roberto Calderon Catacora
CONCEPTO S/.
Amortizaciones : -
. Del Adelanto Directo en la Valorización (sin IGV) -
. Del Adelanto en Directo en la Valorización (con IGV) -
. Del Adelanto de Materiales en la Valorización (sin IGV) -
. Del Adelanto de Materiales en la Valorización (con IGV) -
Otros :
. Retencion por Retraso en la Obra 0.00
. Multas 0.00
134,936.17
IV.- I.G.V. (18% DE I )
RESUMEN AMORTIZACIONES
PROGRAMADO EJECUTADO
VALORIZACION AMORTIZACION ADELANTO VALORIZACION AMORTIZACION ADELANTO
VAL Nº MES PROGRAMADA DEL DIRECTO DEDUCCION EJECUTADA DEL DIRECTO DEDUCCION
ADELANTO POR FORMULA K Ka PROGRAMADA ADELANTO POR FORMULA K Ka EFECTIVA
(V) (A) (C) (V) (A) (C)
01-02 feb-17 #REF! #REF! S/. 0.00 1.014 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.014 1.056 #REF!
03 mar-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.000 1.056 #REF!
04 abr-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.000 1.056 #REF!
05 may-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.000 1.056 #REF!
06 jun-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.000 1.056 #REF!
07 jul-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.000 1.056 #REF!
08 ago-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.000 1.056 #REF!
09 sep-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.000 1.056 #REF!
10 oct-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.000 1.056 #REF!
11 nov-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! Err:509 Err:509 S/. 0.00 0.000 1.056 Err:509
12 dic-17 #REF! #REF! S/. 0.00 0.000 1.056 #REF! Err:509 Err:509 S/. 0.00 0.000 1.056 Err:509
13 jul-18 #REF! #REF! S/. 0.00 0.000 1.056 #REF! Err:509 Err:509 S/. 0.00 0.000 1.056 Err:509
14 ago-18 #REF! #REF! S/. 0.00 0.000 1.056 #REF! Err:509 Err:509 S/. 0.00 0.000 1.056 Err:509
TOTALES #REF! #REF! #REF! Err:509 Err:509 #REF!
PROGRAMADO EJECUTADO
VALORIZACION AMORTIZACION ADELANTO VALORIZACION AMORTIZACION ADELANTO
VAL Nº MES PROGRAMADA DEL DIRECTO DEDUCCION EJECUTADA DEL DIRECTO DEDUCCION
ADELANTO POR FORMULA K Ka PROGRAMADA ADELANTO POR FORMULA K Ka EFECTIVA
(V) (A) (C) (V) (A) (C)
01-02 feb-17 #REF! #REF! S/. 0.00 1.020 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.020 1.020 #REF!
03 mar-17 #REF! #REF! S/. 0.00 1.018 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.018 1.020 #REF!
04 abr-17 #REF! #REF! S/. 0.00 1.020 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.020 1.020 #REF!
05 may-17 #REF! #REF! S/. 0.00 1.020 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.020 1.020 #REF!
06 jun-17 #REF! #REF! S/. 0.00 1.022 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.022 1.020 #REF!
07 jul-17 #REF! #REF! S/. 0.00 1.021 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.021 1.020 #REF!
08 ago-17 #REF! #REF! S/. 0.00 1.020 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.020 1.020 #REF!
09 sep-17 #REF! #REF! S/. 0.00 0.162 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.162 1.020 #REF!
10 oct-17 #REF! #REF! S/. 0.00 0.162 1.020 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.162 1.020 #REF!
11 nov-17 #REF! #REF! S/. 0.00 0.162 1.020 #REF! Err:509 Err:509 S/. 0.00 0.162 1.020 Err:509
12 dic-17 #REF! #REF! S/. 0.00 0.162 1.020 #REF! Err:509 Err:509 S/. 0.00 0.162 1.020 Err:509
13 jul-18 #REF! #REF! S/. 0.00 0.163 1.020 #REF! Err:509 Err:509 S/. 0.00 0.163 1.020 Err:509
14 ago-18 #REF! #REF! S/. 0.00 0.164 1.020 #REF! Err:509 Err:509 S/. 0.00 0.164 1.020 Err:509
TOTALES #REF! #REF! #REF! Err:509 Err:509 #REF!
CUADRO DE LA DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR EL ADELANTO DIRECTO
FEBRERO 2019
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO : APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
FECHA DE TÉRMINO REAL : 03/10/2020
PROGRAMADO EJECUTADO
VALORIZACION AMORTIZACION ADELANTO VALORIZACION AMORTIZACION ADELANTO
VAL Nº MES PROGRAMADA DEL DIRECTO DEDUCCION EJECUTADA DEL DIRECTO DEDUCCION
ADELANTO POR FORMULA K Ka PROGRAMADA ADELANTO POR FORMULA K Ka EFECTIVA
(V) (A) (C) (V) (A) (C)
01-02 feb-17 #REF! #REF! S/. 0.00 1.042 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 1.042 1.042 #REF!
03 mar-17 #REF! #REF! S/. 0.00 0.858 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.858 1.042 #REF!
04 abr-17 #REF! #REF! S/. 0.00 0.861 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.861 1.042 #REF!
05 may-17 #REF! #REF! S/. 0.00 0.861 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.861 1.042 #REF!
06 jun-17 #REF! #REF! S/. 0.00 0.861 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.861 1.042 #REF!
07 jul-17 #REF! #REF! S/. 0.00 0.861 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.861 1.042 #REF!
08 ago-17 #REF! #REF! S/. 0.00 0.860 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.860 1.042 #REF!
09 sep-17 #REF! #REF! S/. 0.00 0.278 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.278 1.042 #REF!
10 oct-17 #REF! #REF! S/. 0.00 0.186 1.042 #REF! S/. 0.00 S/. 0.00 S/. 0.00 0.186 1.042 #REF!
11 nov-17 #REF! #REF! S/. 0.00 0.186 1.042 #REF! Err:509 Err:509 S/. 0.00 0.186 1.042 Err:509
12 dic-17 #REF! #REF! S/. 0.00 0.186 1.042 #REF! Err:509 Err:509 S/. 0.00 0.186 1.042 Err:509
13 jul-18 #REF! #REF! S/. 0.00 0.186 1.042 #REF! Err:509 Err:509 S/. 0.00 0.186 1.042 Err:509
14 ago-18 S/. 0.00 S/. 0.00 S/. 0.00 0.186 1.042 #REF! Err:509 Err:509 S/. 0.00 0.186 1.042 Err:509
TOTALES #REF! #REF! #REF! Err:509 Err:509 #REF!
ADELANTO OTORGADO
AMORTIZACION
AMORTIZACION SALDO POR AMORTIZ.
VALORIZACION VAL.MES Sin Reaj.
Amort=VB (Cronograma de mat) (SIN I.G.V)
SIN I.G.V. CON I.G.V.
(SIN I.G.V.) : S/.4,605,326.56 1212023.53 Nº Monto sin IGV Monto con IGV
(CON I.G.V.) : S/.5,434,285.34 1430187.77 Nº 01 S/. 921,065.31 S/. 1,086,857.06
ADELANTO OTORGADO
AMORTIZACION
VALORIZACION VAL.MES Sin Reaj. AMORTIZACION SALDO POR AMORTIZ.
SIN I.G.V. CON I.G.V. Amort=VB * 20.00% (SIN I.G.V)
(SIN I.G.V.) : S/.4,605,326.56 1212023.53 Nº Monto sin IGV Monto con IGV
(CON I.G.V.) : S/.5,434,285.34 1430187.77 Nº 01 S/. 921,065.31 S/. 1,086,857.06
03 Mar-17 Acero Corrugado (IU 03) Kg 374.58 S/. 3.22 S/. 1,206.15 464.67 460.32 S/. 1,217.55 S/. 1,217.55 S/. 1,217.55 S/. 0.00
Cemento Portland Tipo I (IU 21) Bol 310.00 S/. 19.49 S/. 6,041.90 410.69 410.96 S/. 6,037.93 S/. 6,037.93 S/. 6,037.93 S/. 0.00
Agregado Grueso (IU 05) M3 70.00 S/. 63.56 S/. 4,449.20 659.15 644.65 S/. 4,549.28 S/. 4,549.28 S/. 4,549.28 S/. 0.00
Madera Nacional para Encofrado (IU 43) P2 500.00 S/. 4.03 S/. 2,015.00 888.64 895.11 S/. 2,000.44 S/. 2,000.44 S/. 2,000.44 S/. 0.00
Tuberia pvc para Agua 110 mm (IU 72) ml 716.16 S/. 21.52 S/. 15,411.76 413.21 411.73 S/. 15,467.16 S/. 15,467.16 S/. 15,467.16 S/. 0.00
Tuberia pvc para Agua 90 mm (IU 72) ml 165.24 S/. 14.25 S/. 2,354.67 413.21 411.73 S/. 2,363.13 S/. 2,363.13 S/. 2,363.13 S/. 0.00
Tuberia pvc para Agua 63 mm (IU 72) ml 3,253.60 S/. 7.15 S/. 23,263.24 413.21 411.73 S/. 23,346.86 S/. 23,346.86 S/. 23,346.86 S/. 0.00
04 Apr-17 Acero Corrugado (IU 03) Kg 1,991.27 S/. 3.22 S/. 6,411.89 464.67 460.32 S/. 6,472.48 S/. 6,472.48 S/. 6,472.48 S/. 0.00
Cemento Portland Tipo I (IU 21) Bol 610.00 S/. 19.49 S/. 11,888.90 410.69 410.96 S/. 11,881.09 S/. 11,881.09 S/. 11,881.09 S/. 0.00
Agregado Grueso (IU 05) M3 80.00 S/. 63.56 S/. 5,084.80 659.15 644.65 S/. 5,199.17 S/. 5,199.17 S/. 5,199.17 S/. 0.00
Madera Nacional para Encofrado (IU 43) P2 250.00 S/. 4.03 S/. 1,007.50 888.64 895.11 S/. 1,000.22 S/. 1,000.22 S/. 1,000.22 S/. 0.00
Tuberia pvc para Agua 90 mm (IU 72) ml 175.82 S/. 14.25 S/. 2,505.44 413.21 411.73 S/. 2,514.44 S/. 2,514.44 S/. 2,514.44 S/. 0.00
Tuberia pvc para Agua 63 mm (IU 72) ml 1,500.00 S/. 7.15 S/. 10,725.00 413.21 411.73 S/. 10,763.55 S/. 10,763.55 S/. 10,763.55 S/. 0.00
Tuberia para agua potable y alcantarillado (IU 72) ml 1,800.00 S/. 29.32 S/. 52,776.00 413.21 411.73 S/. 52,965.71 S/. 52,965.71 S/. 52,965.71 S/. 0.00
05 May-17 Acero Corrugado (IU 03) Kg 2,266.42 S/. 3.22 S/. 7,297.88 464.67 460.32 S/. 7,366.85 S/. 7,366.85 S/. 7,366.85 S/. 0.00
Cemento Portland Tipo I (IU 21) Bol 3,520.00 S/. 19.49 S/. 68,604.80 410.69 410.96 S/. 68,559.73 S/. 68,559.73 S/. 68,559.73 S/. 0.00
Agregado Grueso (IU 05) M3 270.00 S/. 63.56 S/. 17,161.20 659.15 644.65 S/. 17,547.20 S/. 17,547.20 S/. 17,547.20 S/. 0.00
Madera Nacional para Encofrado (IU 43) P2 360.00 S/. 4.03 S/. 1,450.80 888.64 895.11 S/. 1,440.31 S/. 1,440.31 S/. 1,440.31 S/. 0.00
Tuberia pvc para Agua 63 mm (IU 72) ml 216.00 S/. 7.15 S/. 1,544.40 413.21 411.73 S/. 1,549.95 S/. 1,549.95 S/. 1,549.95 S/. 0.00
Tuberia para agua potable y alcantarillado (IU 72) ml 2,000.00 S/. 29.32 S/. 58,640.00 413.21 411.73 S/. 58,850.79 S/. 58,850.79 S/. 58,850.79 S/. 0.00
06 Jun-17 Acero Corrugado (IU 03) Kg 1,964.13 S/. 3.22 S/. 6,324.51 464.67 460.32 S/. 6,384.28 S/. 6,384.28 S/. 6,384.28 S/. 0.00
Cemento Portland Tipo I (IU 21) Bol 3,550.00 S/. 19.49 S/. 69,189.50 410.69 410.96 S/. 69,144.04 S/. 69,144.04 S/. 69,144.04 S/. 0.00
Agregado Grueso (IU 05) M3 270.00 S/. 63.56 S/. 17,161.20 659.15 644.65 S/. 17,547.20 S/. 17,547.20 S/. 17,547.20 S/. 0.00
Madera Nacional para Encofrado (IU 43) P2 240.00 S/. 4.03 S/. 967.20 888.64 895.11 S/. 960.21 S/. 960.21 S/. 960.21 S/. 0.00
Tuberia pvc para Agua 110 mm (IU 72) ml 100.00 S/. 21.52 S/. 2,152.00 413.21 411.73 S/. 2,159.74 S/. 2,159.74 S/. 2,159.74 S/. 0.00
Tuberia pvc para Agua 63 mm (IU 72) ml 1,114.37 S/. 7.15 S/. 7,967.75 413.21 411.73 S/. 7,996.39 S/. 7,996.39 S/. 7,996.39 S/. 0.00
Tuberia para agua potable y alcantarillado (IU 72) ml 1,924.20 S/. 29.32 S/. 56,417.54 413.21 411.73 S/. 56,620.34 S/. 56,620.34 S/. 56,620.34 S/. 0.00
07 Jul-17 Acero Corrugado (IU 03) Kg 261.07 S/. 3.22 S/. 840.66 464.67 460.32 S/. 848.60 S/. 848.60 S/. 848.60 S/. 0.00
Cemento Portland Tipo I (IU 21) Bol 3,000.00 S/. 19.49 S/. 58,470.00 410.69 410.96 S/. 58,431.59 S/. 58,431.59 S/. 58,431.59 S/. 0.00
Agregado Grueso (IU 05) M3 270.00 S/. 63.56 S/. 17,161.20 659.15 644.65 S/. 17,547.20 S/. 17,547.20 S/. 17,547.20 S/. 0.00
Madera Nacional para Encofrado (IU 43) P2 140.00 S/. 4.03 S/. 564.20 888.64 895.11 S/. 560.12 S/. 560.12 S/. 560.12 S/. 0.00
Tuberia pvc para Agua 110 mm (IU 72) ml 100.00 S/. 21.52 S/. 2,152.00 413.21 411.73 S/. 2,159.74 S/. 2,159.74 S/. 2,159.74 S/. 0.00
Tuberia pvc para Agua 63 mm (IU 72) ml 565.63 S/. 7.15 S/. 4,044.25 413.21 411.73 S/. 4,058.79 S/. 4,058.79 S/. 4,058.79 S/. 0.00
Tuberia para agua potable y alcantarillado (IU 72) ml 1,800.00 S/. 29.32 S/. 52,776.00 413.21 411.73 S/. 52,965.71 S/. 52,965.71 S/. 52,965.71 S/. 0.00
08 Aug-17 Acero Corrugado (IU 03) Kg 1,694.45 S/. 3.22 S/. 5,456.13 464.67 460.32 S/. 5,507.69 S/. 5,507.69 S/. 5,507.69 S/. 0.00
Cemento Portland Tipo I (IU 21) Bol 5,150.00 S/. 19.49 S/. 100,373.50 410.69 410.96 S/. 100,307.55 S/. 100,307.55 S/. 100,307.55 S/. 0.00
Agregado Grueso (IU 05) M3 450.00 S/. 63.56 S/. 28,602.00 659.15 644.65 S/. 29,245.34 S/. 29,245.34 S/. 29,245.34 S/. 0.00
Madera Nacional para Encofrado (IU 43) P2 1,500.00 S/. 4.03 S/. 6,045.00 888.64 895.11 S/. 6,001.31 S/. 6,001.31 S/. 6,001.31 S/. 0.00
CÁLCULO DE REAJUSTE
FÓRMULA POLINÓMICA
K = 0.228*(Mr / Mo) + 0.109*(AAMr / AAMo) + 0.127*(CTr / CTo) + 0.187*(Mr / Mo) + 0.349*(Ir / Io)
Monto Mensual Monto Acumulado Reajuste
Mes
Val K
Reajuste
Real Programado Real Programado Real Programado Reconocido
dic-19 287,738.66 130,578.05 287,738.66 130,578.05 Dec-19 1.014 4,028.34 1,828.09 1,828.09
ene-20 647,641.82 1,297,125.71 935,380.48 1,427,703.76 Jan-20 0.000
Reajuste
DESCRIPCION
Real Programado Reconocido
FORMULA GENERAL :
( Imr-Ima )
Dm = Am *
Imo
Donde; Dm = Deducción del Reajuste, que no corresponde por Adelanto Especifico para Materiales
Am = Monto del Material utilizado en la Valorización que se reajusta
Imr = Indice del elemento representativo al mes respectivo de reajuste Indice mes de DICIEMBRE-2019
Ima = Indice del elemento representativo al mes de cancelación del Adelanto (JUNIO 2019)
Imo = Indice del elemento representativo al mes del Presupuesto Base (JULIO 2018)
FÓRMULA POLINÓMICA Nº 01
ADEL. 01 0.00 0.00 Jun-19 VAL. Nº 01 (DIC-19) 333,057.50 0.228 100.000% 0.00 0.00 0.00 #DIV/0!
VAL. Nº 02 (ENE-20) 749,645.41 0.00 0.00 0.00 #DIV/0!
MANO DE OBRA INC. LEYES
SOCIALES VAL. Nº 03 (FEB-20) 0.00 0.00 0.00 0.00 #DIV/0!
47 VAL. Nº 04 (MAR-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 05 (ABR-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 06 (MAY-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 07 (JUN-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 08 (JUL-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 09 (AGO-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 10 (SET-20) 0.00
ADEL. 01 0.00 0.00 Jun-19 VAL. Nº 01 (DIC-19) 333,057.50 0.109 7.339% 0.00 0.00 0.00
MADERA NACIONAL PARA VAL. Nº 02 (ENE-20) 749,645.41 0.00 0.00 0.00
ENCOF. Y CARPINT. VAL. Nº 03 (FEB-20) 0.00 0.00 0.00 0.00
43 VAL. Nº 04 (MAR-20) 0.00 0.00 0.00 0.00
VAL. Nº 05 (ABR-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 06 (MAY-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 07 (JUN-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 08 (JUL-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 09 (AGO-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 10 (SET-20) 0.00 0.00
ADEL. 01 0.00 0.00 Jun-19 VAL. Nº 01 (DIC-19) 333,057.50 0.109 9.174% 0.00 0.00
VAL. Nº 02 (ENE-20) 749,645.41 0.00 0.00
ACERO DE CONSTRUCCION
CORRUGADO VAL. Nº 03 (FEB-20) 0.00 0.00 0.00
03 VAL. Nº 04 (MAR-20) 0.00 0.00 0.00
VAL. Nº 05 (ABR-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 06 (MAY-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 07 (JUN-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 08 (JUL-20) 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 09 (AGO-20) 0.00 0.00 0.00
VAL. Nº 10 (SET-20) 0.00 0.00
ADEL. 01 0.00 0.00 Jun-19 VAL. Nº 01 (DIC-19) 333,057.50 0.109 83.486% 0.00
VAL. Nº 02 (ENE-20) 749,645.41 0.00
AGREGADO GRUESO
VAL. Nº 03 (FEB-20) 0.00 0.00
05 VAL. Nº 04 (MAR-20) 0.00 0.00
VAL. Nº 05 (ABR-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 06 (MAY-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 07 (JUN-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 08 (JUL-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 09 (AGO-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
0.00
ADEL. 01 0.00 0.00 Jun-19 VAL. Nº 01 (DIC-19) 333,057.50 0.127 61.417% 0.00
VAL. Nº 02 (ENE-20) 749,645.41 0.00
CEMENTO PORTLAND TIPO I
VAL. Nº 03 (FEB-20) 0.00 0.00
21 VAL. Nº 04 (MAR-20) 0.00 0.00
VAL. Nº 05 (ABR-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 06 (MAY-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 07 (JUN-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 08 (JUL-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 09 (AGO-20) 0.00 0.00 0.00 7,354.01 -7,354.01 #DIV/0!
OBRA "MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE TRATAMIENTO DE AGUAS SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA,
SINHUAPATA, EDEN, TENERIA, MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA, RAYAMPAMPA, MAYABAMBA, ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA DISTRITO DE OCOBAMBA – CHINCHEROS – APURIMAC" CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO : APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
FECHA DE TÉRMINO : 03/10/2020
FORMULA GENERAL :
( Imr-Ima )
Dm = Am *
Imo
Donde; Dm = Deducción del Reajuste, que no corresponde por Adelanto Especifico para Materiales
Am = Monto del Material utilizado en la Valorización que se reajusta
Imr = Indice del elemento representativo al mes respectivo de reajuste Indice mes de DICIEMBRE-2019
Ima = Indice del elemento representativo al mes de cancelación del Adelanto (JUNIO 2019)
Imo = Indice del elemento representativo al mes del Presupuesto Base (JULIO 2018)
FÓRMULA POLINÓMICA Nº 01
ADEL. 01 0.00 0.00 Jun-19 VAL. Nº 01 (DIC-19) 333,057.50 0.127 38.583% 0.00
VAL. Nº 02 (ENE-20) 749,645.41 0.00
TUBERIA DE PVC PARA AGUA
VAL. Nº 03 (FEB-20) 0.00 0.00
72 VAL. Nº 04 (MAR-20) 0.00 0.00
VAL. Nº 05 (ABR-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 06 (MAY-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 07 (JUN-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 08 (JUL-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 09 (AGO-20) 0.00 0.00 0.00 7,354.01 -7,354.01 #DIV/0!
0.00
OBRA "MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE TRATAMIENTO DE AGUAS SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA,
SINHUAPATA, EDEN, TENERIA, MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA, RAYAMPAMPA, MAYABAMBA, ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA DISTRITO DE OCOBAMBA – CHINCHEROS – APURIMAC" CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO : APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
FECHA DE TÉRMINO : 03/10/2020
FORMULA GENERAL :
( Imr-Ima )
Dm = Am *
Imo
Donde; Dm = Deducción del Reajuste, que no corresponde por Adelanto Especifico para Materiales
Am = Monto del Material utilizado en la Valorización que se reajusta
Imr = Indice del elemento representativo al mes respectivo de reajuste Indice mes de DICIEMBRE-2019
Ima = Indice del elemento representativo al mes de cancelación del Adelanto (JUNIO 2019)
Imo = Indice del elemento representativo al mes del Presupuesto Base (JULIO 2018)
FÓRMULA POLINÓMICA Nº 01
ADEL. 01 0.00 0.00 Jun-19 VAL. Nº 01 (DIC-19) 333,057.50 0.187 100.000% 0.00
MAQUINARIA Y EQUIPO VAL. Nº 02 (ENE-20) 749,645.41 0.00
IMPORTADO VAL. Nº 03 (FEB-20) 0.00 0.00
49 VAL. Nº 04 (MAR-20) 0.00 0.00
VAL. Nº 05 (ABR-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 06 (MAY-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 07 (JUN-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 08 (JUL-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 09 (AGO-20) 0.00 0.00 0.00 7,354.01 -7,354.01 #DIV/0!
0.00
ADEL. 01 0.00 0.00 Jun-19 VAL. Nº 01 (DIC-19) 333,057.50 0.349 100.000% 0.00
INDICE GENERAL DE PRECIOS VAL. Nº 02 (ENE-20) 749,645.41 0.00
AL CONSUMIDOR VAL. Nº 03 (FEB-20) 0.00 0.00
39 VAL. Nº 04 (MAR-20) 0.00 0.00
VAL. Nº 05 (ABR-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 06 (MAY-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 07 (JUN-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 08 (JUL-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
VAL. Nº 09 (AGO-20) 0.00 0.00 0.00 0.00 0.00 #DIV/0!
0.00
0.00 0.00
TOTAL 0.00
ACUMULADO ACTUAL 0.04 #DIV/0!
ACUMULADO ANTERIOR 0.00 #DIV/0!
RESUMEN GENERAL
ACUMULADO ACTUAL 0.00 0.00 0.00
ACUMULADO ANTERIOR 0.00 0.00
COSTO DIRECTO C_D 9,490,370.18 112,810.41 1,120,626.96 1,506,332.21 792,005.63 1,302,257.50 1,288,040.13 1,826,097.98 479,146.83 700,173.63 316,634.55 46,244.36
GASTOS GENERALES (11.35%) GG 8.75% 830,407.39 9,870.91 98,054.86 131,804.07 69,300.49 113,947.53 112,703.51 159,783.57 41,925.35 61,265.19 27,705.52 4,046.38
UTILIDAD UTI 7.00% 664,325.91 7,896.73 78,443.89 105,443.25 55,440.39 91,158.02 90,162.81 127,826.86 33,540.28 49,012.15 22,164.42 3,237.11
============
COSTO PARCIAL C_P 10,985,103.48 130,578.05 1,297,125.71 1,743,579.53 916,746.52 1,507,363.06 1,490,906.45 2,113,708.41 554,612.46 810,450.98 366,504.49 53,527.85
IMPUESTO GENERAL A LAS VENTAS (I.G.V.) I.G.V. 18.00% 1,977,318.63 23,504.05 233,482.63 313,844.32 165,014.37 271,325.35 268,363.16 380,467.51 99,830.24 145,881.18 65,970.81 9,635.01
============
COSTO DE EJECUCION DE OBRA CO 12,962,422.11 154,082.10 1,530,608.34 2,057,423.85 1,081,760.89 1,778,688.41 1,759,269.61 2,494,175.92 654,442.70 956,332.16 432,475.30 63,162.86
AVANCE MENSUAL (%) 1.19% 11.81% 15.87% 8.35% 13.72% 13.57% 19.24% 5.05% 7.38% 3.34% 0.49%
AVANCE ACUMULADO (%) 1.19% 13.00% 28.87% 37.21% 50.94% 64.51% 83.75% 88.80% 96.18% 99.51% 100.00%
ADELANTO ESPECIFICADO PARA MATERIALES E INSUMOS
CALCULO DE MONTOS MAXIMOS A SOLICITAR
FORMULA POLINOMICA
1.00 ESTRUCTURA
K = 0.263*(Mr / Mo) + 0.465*(ACr / ACo) + 0.168*(AMr / AMo) + 0.104*(PMr / PMo)
2.00 ARQUITECTURA
K = 0.347*(Mr / Mo) + 0.334*(ACMHr / ACMHo) + 0.263*(BPLr / BPLo) + 0.056*(IMr / IMo)
Donde:
C.I. : Coeficiente de incidencia del elemento respectivo
% Incidencia : Porcentaje de incidencia del elemento representativo en el Monomio
F.R. : Factor de Relacion
Ima : Indice del elemento representativo a la fecha del adelanto Nov-15
Imo : Indice del elemento representativo a la fecha base Sep-15
1.00 ESTRUCTURAS
A FORMULA POLINOMICA 01
ADELANTO MONTO SALDO POR
COEFICIENTE DE SALDO BRUTO POR OTORGADO AMORTIZADO AMORTIZAR
IU DESCRIPCION % DE INCIDENCIA F.R.
INCIDENCIA VALORIZAR
(SIN IGV) (SIN IGV) (SIN IGV)
47 MANO DE OBRA INC. LEYES SOCIALES 0.263 100.00% #NAME? 1.00 0.00 0.00 0.00
03 ACERO DE CONSTRUCCION CORRUGADO 0.465 60.86% #NAME? 1.00 125,542.09 #NAME? #NAME?
21 CEMENTO PORTLAND TIPO I 0.465 39.14% #NAME? 1.00 64,649.69 #NAME? #NAME?
43 MADERA NACIONAL PARA ENCOF. Y CARPINT. 0.168 33.93% #NAME? 1.00 21,972.48 #NAME? #NAME?
05 AGREGADO GRUESO 0.168 66.07% #NAME? 1.00 48,954.96 #NAME? #NAME?
48 MAQUINARIA Y EQUIPO NACIONAL 0.104 47.12% #NAME? 1.00 0.00 0.00 0.00
54 PINTURA LATEX 0.104 52.88% #NAME? 1.00 22,338.79 #NAME? #NAME?
MONTO
Adelanto Material Imo Ima
IU Descripción Unidad Parcial S/. % Incidencia SOLICITADO
Otorgado Utilizado S/.
Sep-15 Jan-16 (SIN IVG)
03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 94,877.82 97,264.47 #NAME? #NAME? 457.96 469.48 #NAME?
03 ANGULO DE ACERO LIVIANO DE 100 X 50 X 2mm X 6 m pza 5,631.34 5,773.00 0.00 457.96 469.48 0.00
03 ANGULO DE ACERO LIVIANO DE 80 X 40 X 2mm X 6 m pza 2,797.11 2,867.47 0.00 457.96 469.48 0.00
03 ANGULO DE ACERO LIVIANO DE 60 X 40 X 1.8mm X 6 m pza 12,566.18 12,882.28 0.00 457.96 469.48 0.00
03 TIRAFON DE 1/4"X3" und 2,929.33 3,003.02 0.00 457.96 469.48 0.00
03 ALAMBRE NEGRO RECOCIDO N° 8 kg 1,545.29 907.20 #NAME? #NAME? 457.96 469.48 #NAME?
03 ALAMBRE NEGRO RECOCIDO N° 16 kg 2,774.84 2,844.64 #NAME? #NAME? 457.96 469.48 #NAME?
21 CEMENTO PORTLAND TIPO IP (42.50 Kg) Bol 64,649.69 64,649.69 #NAME? #NAME? 410.96 410.96 #NAME?
05 PIEDRA CHANCADA DE 3/4" m3 12,524.33 12,569.19 #NAME? #NAME? 656.07 658.42 #NAME?
05 PIEDRA GRANDE DE RUMICCOLCA DE 8" m3 1,471.09 1,476.36 #NAME? #NAME? 656.07 658.42 #NAME?
05 ARENA GRUESA m3 7,219.91 7,245.77 #NAME? #NAME? 656.07 658.42 #NAME?
05 HORMIGON (PUESTO EN OBRA) m3 5,847.22 5,868.16 #NAME? #NAME? 656.07 658.42 #NAME?
05 TEJA ANDINA ETERNIT 1.14m. x 0.72m. x 5mm. pza 21,717.68 21,795.48 #NAME? #NAME? 656.07 658.42 #NAME?
54 PINTURA ESMALTE SINTETICO gln 22,338.79 22,338.79 #NAME? #NAME? 376.53 376.53 #NAME?
2.00 ARQUITECTURA
B FORMULA POLINOMICA 02
MONTO
COEFICIENTE DE SALDO BRUTO POR Imo Ima MONTO MAXIMO
IU DESCRIPCION % DE INCIDENCIA F.R. SOLICITADO
INCIDENCIA VALORIZAR
Sep-15 Nov-15 (SIN IGV) (SIN IGV)
47 MANO DE OBRA INC. LEYES SOCIALES 0.347 100.00% #NAME? 1.00 544.59 544.59 #NAME?
43 MADERA NACIONAL PARA ENCOF. Y CARPINT. 0.334 4.49% #NAME? 1.00 860.85 866.74 #NAME? 3,088.32
04 AGREGADO FINO 0.334 47.31% #NAME? 1.00 770.16 770.13 #NAME? 51,129.93
21 CEMENTO PORTLAND TIPO I 0.334 44.61% #NAME? 1.00 410.96 410.96 #NAME? 37,828.55
38 HORMIGON 0.334 3.59% #NAME? 1.00 683.10 686.73 #NAME? 4,143.37
14 BALDOSA ACUSTICA 0.263 43.35% #NAME? 1.00 269.90 287.38 #NAME? 35,527.08
40 LOSETA 0.263 27.00% #NAME? 1.00 331.41 331.41 #NAME? 23,727.06
51 PERFIL DE ACERO LIVIANO 0.263 29.66% #NAME? 1.00 284.31 269.92 #NAME? 1,311.06
49 MAQUINARIA Y EQUIPO IMPORTADO 0.056 39.29% #NAME? 1.00 288.48 298.83 #NAME?
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.056 60.71% #NAME? 1.00 418.76 420.80 #NAME?
MONTO
Adelanto Material Imo Ima
IU Descripción Unidad Parcial S/. % Incidencia SOLICITADO
Otorgado Utilizado S/.
Sep-15 Nov-15 (SIN IVG)
43 MADERA CORRIENTE p2 3,067.34 3,088.32 3,067.34 860.85 866.74 3,088.32
21 CEMENTO PORTLAND TIPO IP (42.50 Kg) bol 37,828.55 37,828.55 37,828.55 410.96 410.96 37,828.55
14 BALDOSA WHITER STAR SEGUN DISEÑO m2 33,366.14 35,527.08 33,366.14 269.90 287.38 35,527.08
51 ANGULO DE ACERO LIVIANO DE 1 1/2" X 1 1/2" X 1/8" X 6 m 1,380.96 1,311.06 1,380.96 284.31 269.92 1,311.06
C FORMULA POLINOMICA 03
MONTO
COEFICIENTE DE SALDO BRUTO POR Imo Ima MONTO MAXIMO
IU DESCRIPCION % DE INCIDENCIA F.R. SOLICITADO
INCIDENCIA VALORIZAR
Sep-15 Nov-15 (SIN IGV) (SIN IGV)
47 MANO DE OBRA INC. LEYES SOCIALES 0.246 100.00% #NAME? 1.00 544.59 544.59 #NAME?
72 TUBERIA DE PVC PARA AGUA 0.176 96.59% #NAME? 1.00 405.28 416.95 #NAME?
05 AGREGADO GRUESO 0.176 3.41% #NAME? 1.00 656.07 658.42 #NAME?
12 ARTEFACTO DE ALUMBRADO INTERIOR 0.517 100.00% #NAME? 1.00 332.20 338.23 #NAME? 11,342.11
30 DOLAR (GENERAL PONDERADO) 0.061 14.75% #NAME? 1.00 447.20 462.65 #NAME?
37 HERRAMIENTA MANUAL 0.061 9.84% #NAME? 1.00 296.62 299.42 #NAME?
07 ALAMBRE Y CABLE TIPO TW Y THW 0.061 60.66% #NAME? 1.00 593.43 614.05 #NAME? 1,407.61
65 TUBERIA DE ACERO NEGRO Y/O GALVANIZADO 0.061 14.75% #NAME? 1.00 235.60 242.89 #NAME?
MONTO
Adelanto Imo Ima
IU Descripción Unidad Parcial S/. Parcial SOLICITADO
Otorgado
Sep-15 Nov-15 (SIN IVG)
12 FLUORESCENTE RECTO ISPE 1x40W C/EQUP+PANT. und 1,589.25 1,618.10 1,589.25 332.20 338.23 1,618.10
12 ARTEFACTO EMPOTRABLE REJILLA LUXALON 2/20 und 2,313.36 2,355.35 2,313.36 332.20 338.23 2,355.35
12 PARARRAYOS TIPO IONIZANTE (80m Cobertura) und 7,237.29 7,368.66 7,237.29 332.20 338.23 7,368.66
07 CABLE TW #14 AWG 2.5 mm2. m 876.56 907.02 876.56 593.43 614.05 907.02
07 CABLE TW 4mm2. m 483.78 500.59 483.78 593.43 614.05 500.59
D FORMULA POLINOMICA 04
MONTO
COEFICIENTE DE SALDO BRUTO POR Imo Ima MONTO MAXIMO
IU DESCRIPCION % DE INCIDENCIA F.R. SOLICITADO
INCIDENCIA VALORIZAR
Sep-15 Nov-15 (SIN IGV) (SIN IGV)
47 MANO DE OBRA INC. LEYES SOCIALES 0.066 100.00% #NAME? 1.00 544.59 544.59 #NAME?
72 TUBERIA DE PVC PARA AGUA 0.055 78.18% #NAME? 1.00 405.28 416.95 #NAME? 4,423.27
02 ACERO DE CONSTRUCCION LISO 0.055 20.00% #NAME? 1.00 464.09 477.60 #NAME?
05 AGREGADO GRUESO 0.055 1.82% #NAME? 1.00 656.07 658.42 #NAME?
10 APARATO SANITARIO CON GRIFERIA 0.099 15.15% #NAME? 1.00 399.18 400.32 #NAME?
77 VALVULA DE BRONCE NACIONAL 0.099 5.05% #NAME? 1.00 299.51 306.00 #NAME?
51 PERFIL DE ACERO LIVIANO 0.099 79.80% #NAME? 1.00 284.31 269.92 #NAME? 9,562.19
30 DOLAR (GENERAL PONDERADO) 0.780 99.49% #NAME? 1.00 447.20 462.65 #NAME? 40,276.86
37 HERRAMIENTA MANUAL 0.780 0.51% #NAME? 1.00 296.62 299.42 #NAME?
MONTO
Adelanto Imo Ima
IU Descripción Unidad Parcial S/. Parcial SOLICITADO
Otorgado
Sep-15 Nov-15 (SIN IVG)
72 TUBO PVC SAL P/DESAGUE DE 6"x5m.. und 4,299.46 4,423.27 4,299.46 405.28 416.95 4,423.27
63 RESERVORIO APOYADO Nº 04, ( V= 2.00 M3 ) - LOC. RAYAMPAMPA SECTOR BAJO 7,742.05 - - - 359 7,383 - - - - - -
64 CERCO PERIMETRICO 5,805.36 - - - 307 5,498 - - - - - -
65 RED DE ALCANTARILLADO - LOC. PACCHIPATA Y LOC. SINHUAPATA ( L = 3,693.40 m. ) 734,023.74 1,267 207,642 206,305 112,952 16,210 51,153 83,411 34,494 20,590 - -
66 CONEXIONES DOMICILIARIAS ( 60 UND. ) 54,909.21 - - 4,097 16,916 9,322 23,090 1,485 - - - -
67 UNIDAD BASICA DE SANEAMIENTO ( 01 UND. ) 9,442.84 - - 989 8,453 - - - - - - -
68 RED DE ALCANTARILLADO - LOC. EDEN ( L = 838.35 m. ) 171,973.57 - 12,288 89,009 24,839 38,967 6,871 - - - - -
69 CONEXIONES DOMICILIARIAS ( 10 UND. ) 10,519.73 - - 4,386 6,134 - - - - - - -
70 RED DE ALCANTARILLADO - LOC. TENERIA Y LOC. ANANSAYOCC ( L = 2,097.80 m. ) 422,303.78 - - - 4,112 127,396 133,836 43,620 75,813 25,967 11,560 -
71 CONEXIONES DOMICILIARIAS ( 32 UND. ) 29,284.92 - - - - - 4,206 10,734 14,345 - - -
72 RED DE ALCANTARILLADO - LOC. ESCORNO Y LOC. MISCAPUCRO ( L = 2,843.60 m. ) 555,857.90 - 35,183 220,902 140,852 31,168 78,997 31,378 17,378 - - -
73 CONEXIONES DOMICILIARIAS ( 53 UND. ) 50,423.37 - - - - - 3,939 15,099 19,409 11,976 - -
74 UNIDAD BASICA DE SANEAMIENTO ( 01 UND. ) 9,442.84 - - - - - 807 8,636 - - - -
75 RED DE ALCANTARILLADO - LOC. RAUCACUCHO, RAYAMPAMPA, MAYABAMBA, ONGOYPATA , ORNOPOTA Y JR. LOS BOSQUES ( L = 4,842.80 m. ) 976,009.52 - 200,940 112,531 86,892 111,711 142,332 278,604 43,000 - - -
76 CONEXIONES DOMICILIARIAS ( 99 UND. ) 95,827.33 - - - - - 5,983 35,073 20,276 29,736 4,759 -
77 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES ( PTAR ) 3,956,469.01 16,966 222,691 540,839 143,436 387,686 608,140 1,165,329 114,197 466,065 291,120 -
78 COMPONENTE DE EDUCACION SANITARIA, CAPACITACION A LA JASS, SEGURIDAD Y SALUD 16,269.46 2,817 - 4,451 - 1,709 - - - - 4,376 2,917
79 MITIGACION AMBIENTAL 62,650.07 - - - - 35,317 1,024 1,041 7,478 12,970 4,819 -
80 FLETE 179,682.96 22,461 22,461 22,461 22,461 22,461 22,461 22,461 22,457 - - -
COSTO DIRECTO 9,490,370.18 112,810.41 1,120,626.96 1,506,332.21 792,005.63 1,302,257.50 1,288,040.13 1,826,097.98 479,146.83 700,173.63 316,634.55 46,244.36
GASTOS GENERALES (11.35%) 830,407.39 9,870.91 98,054.86 131,804.07 69,300.49 113,947.53 112,703.51 159,783.57 41,925.35 61,265.19 27,705.52 4,046.38
UTILIDAD 664,325.91 7,896.73 78,443.89 105,443.25 55,440.39 91,158.02 90,162.81 127,826.86 33,540.28 49,012.15 22,164.42 3,237.11
============
COSTO PARCIAL 10,985,103.48 130,578.05 1,297,125.71 1,743,579.53 916,746.52 1,507,363.06 1,490,906.45 2,113,708.41 554,612.46 810,450.98 366,504.49 53,527.85
IMPUESTO GENERAL A LAS VENTAS (I.G.V.) 1,977,318.63 23,504.05 233,482.63 313,844.32 165,014.37 271,325.35 268,363.16 380,467.51 99,830.24 145,881.18 65,970.81 9,635.01
============
COSTO DE EJECUCION DE OBRA 12,962,422.11 154,082.10 1,530,608.34 2,057,423.85 1,081,760.89 1,778,688.41 1,759,269.61 2,494,175.92 654,442.70 956,332.16 432,475.30 63,162.86
AVANCE MENSUAL (%) 1.19% 11.81% 15.87% 8.35% 13.72% 13.57% 19.24% 5.05% 7.38% 3.34% 0.49%
AVANCE ACUMULADO (%) 1.19% 13.00% 28.87% 37.21% 50.94% 64.51% 83.75% 88.80% 96.18% 99.51% 100.00%
OBRA: "MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE
TRATAMIENTO DE AGUAS SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA, SINHUAPATA, EDEN,
TENERIA, MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA, RAYAMPAMPA,
MAYABAMBA, ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL DISTRITO DE OCOBAMBA –
CHINCHEROS – APURIMAC"
CONTROL AMORTIZACION DE ADELANTOS
DICIEMBRE 2019
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO: APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
FECHA DE TÉRMINO REAL : 03/10/2020
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 1.00 31.50 10.20 321.30 321.30
#NAME? #NAME? ### #NAME? #NAME? 1.00 31.50 10.20 321.30 321.30
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 33.00 2.30 2.30 2.15 #NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 1.00 #NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 1.00 #NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 1.00 #NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 1.00 29.00 10.15 294.35 294.35
#NAME? #NAME? ### #NAME? #NAME? 1.00 29.00 10.15 294.35 294.35
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 33.00 2.50 2.50 2.08 #NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 31.00 2.20 2.20 1.43 214.17 214.17
#NAME? #NAME? ### #NAME? #NAME? 1.00 #NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 1.00 #NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME? m2 #NAME? #NAME? 1.00 #NAME? #NAME?
#NAME? #NAME? m2 #NAME? #NAME? 1.00 #NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 0.17 0.17 0.17
#NAME? #NAME?
#NAME? #NAME? ### #NAME? #NAME? 0.10 0.10 0.10
OBRA: "MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE TRATAMIENTO DE AGUAS
SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA, SINHUAPATA, EDEN, TENERIA, MISCAPUCRO, ESCORNO, RAUCACUCHO,
ANANSAYOCC, ORNOPATA, RAYAMPAMPA, MAYABAMBA, ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL DISTRITO DE
CALCULO DE Ka
OCOBAMBA – CHINCHEROS – APURIMAC"
1 M 03 MANO DE OBRA INC. LEYES SOCIALES 0.054 0.054 100.00% 600.40 0.054 619.76 0.056
2 0 05 MADERA NACIIONAL PARA ENCOF. Y CARPINT. 0.109 0.109 100.00% 904.49 0.109 917.51 0.111
3 0 30 ACERO DE CONSTRUCCION CORRUGADO 0.109 0.109 100.00% 527.67 0.109 540.81 0.112
4 AAM 39 AGREGADO GRUESO 0.109 0.109 100.00% 624.93 0.109 629.70 0.110
5 CT 47 CEMENTO PORTLAND TIPO I 0.127 0.127 100.00% 418.57 0.127 412.86 0.125
6 M 48 MAQUINARIA Y EQUIPO IMPORTADO 0.187 0.187 100.00% 308.84 0.187 315.38 0.191
7 I 72 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.349 0.349 100.00% 458.29 0.349 460.59 0.351
2 C 21 CEMENTO PORTLAND TIPO I 0.082 0.082 100.00% 410.96 0.082 410.96 0.082
3 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.077 0.077 100.00% 429.07 0.077 437.38 0.078
4 MO 47 MANO DE OBRA INC. LEYES SOCIALES 0.435 0.435 100.00% 544.12 0.435 563.25 0.450
5 MQ 49 MAQUINARIA Y EQUIPO IMPORTADO 0.081 0.081 100.00% 297.17 0.081 299.32 0.082
6 T 72 TUBERIA DE PVC PARA AGUA 0.257 0.257 100.00% 411.73 0.257 413.21 0.258
1 M 03 MANO DE OBRA INC. LEYES SOCIALES 0.095 0.095 100.00% 600.40 0.095 619.76 0.098
3 C 21 CEMENTO PORTLAND TIPO I 0.186 0.186 100.00% 410.96 0.186 410.96 0.186
4 I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.176 0.176 100.00% 429.07 0.176 437.38 0.179
5 MO 47 MANO DE OBRA INC. LEYES SOCIALES 0.287 0.287 100.00% 544.12 0.287 563.25 0.297
6 MQ 49 MAQUINARIA Y EQUIPO IMPORTADO 0.094 0.094 100.00% 297.17 0.094 299.32 0.095
7 T 72 TUBERIA DE PVC PARA AGUA 0.102 0.102 100.00% 411.73 0.102 413.21 0.102
COEFICIENTE DE REAJUSTE Ka 1.000 1.042
"MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE TRATAMIENTO DE AGUAS SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA, SINHUAPATA, EDEN, TENERIA, MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA,
OBRA:
RAYAMPAMPA, MAYABAMBA, ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL DISTRITO DE OCOBAMBA – CHINCHEROS – APURIMAC"
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO : APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
FECHA DE TÉRMINO REAL : 03/10/2020
INDICE BASE Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20
COEF. COEF. DEL INCIDENCIA
SIMBOLO IU DESCRIPCIÓN
MATERIAL MONOMIO ESPECÍFICA Indice Indice Indice Indice Indice Indice Indice Indice Indice Indice Indice
Incidencia Incidencia Incidencia Incidencia Incidencia Incidencia Incidencia Incidencia Incidencia Incidencia Incidencia
jul19 dic19* ene20 feb20 marz20 abr20 may20 jun20 jul20 ago20 set20
M 47 MANO DE OBRA INC. LEYES SOCIALES 0.228 0.228 100.000% 600.400 0.228 619.760 0.235 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
43 MADERA NACIIONAL PARA ENCOF. Y CARPINT. 0.109 0.109 7.339% 904.490 0.008 917.510 0.008 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
03 ACERO DE CONSTRUCCION CORRUGADO 0.109 0.109 9.174% 527.670 0.010 540.810 0.010 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
AAM 05 AGREGADO GRUESO 0.109 0.109 83.486% 624.930 0.091 629.700 0.092 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
CT 21 CEMENTO PORTLAND TIPO I 0.127 0.127 61.417% 418.570 0.078 412.860 0.077 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
72 TUBERIA DE PVC PARA AGUA 0.127 0.127 38.583% 434.080 0.049 442.390 0.050 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
M 49 MAQUINARIA Y EQUIPO IMPORTADO 0.187 0.187 100.000% 308.840 0.187 315.380 0.191 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 0.349 0.349 100.000% 458.290 0.349 460.590 0.351 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
COEFICIENTE DE REAJUSTE K1 1.000 1.014 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
OBRA: "MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE, ALCANTARILLADO E INSTALACION DE PLANTA DE TRATAMIENTO DE AGUAS SERVIDAS DE LAS LOCALIDADES DE PACCHIPATA, SINHUAPATA, EDEN,
TENERIA, MISCAPUCRO, ESCORNO, RAUCACUCHO, ANANSAYOCC, ORNOPATA, RAYAMPAMPA, MAYABAMBA, ONGOYPATA, JR. LOS BOSQUES Y CHUQUIBAMBA DEL DISTRITO DE OCOBAMBA –
CHINCHEROS – APURIMAC"
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE OCOBAMBA CONTRATISTA : CONSORCIO OCOBAMBA
DEPARTAMENTO : APURIMAC SUPERVISION : CONSORCIO OCOBAMBA
VALOR REF. : S/. 13'438,906.56 inc. IGV PLAZO EJECUCIÓN : 300 DIAS CALENDARIO
VALOR CONTR. : S/. 12'962,422.11 inc. IGV FECHA DE INICIO : 09/02/2019
FECHA DE TÉRMINO REAL : 03/10/2020
12,000,000.00
MONTO PARCIAL
10,931,575.64
10,565,071.15
9,754,620.18
10,000,000.00
9,200,007.72
8,000,000.00
6,000,000.00 5,595,392.86
4,088,029.80
4,000,000.00
3,171,283.29
SITUACIÓN DE LA OBRA
MONTO ACUMULADO
ATRASADA 2,000,000.00 1,427,703.76
S/. 345,000.85 1,082,702.91
333,057.50
130,578.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00
dic-19 ene-20 feb-20 mar-20 abr-20 may-20 jun-20 jul-20 ago-20 sep-20
1 2 3 4 5 6 7 8 9 10
MESES Inicio 09/12/19 dic-19 ene-20 feb-20 mar-20 abr-20 may-20 jun-20 jul-20 ago-20 sep-20
MONTO PROG 0.00 130,578.05 1,427,703.76 3,171,283.29 4,088,029.80 5,595,392.86 7,086,299.31 9,200,007.72 9,754,620.18 10,565,071.15 10,931,575.64
PARCIALES (S/.)
REAL 0.00 333,057.50 1,082,702.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00
VALORIZACIONES:
A) Contrato Principal
DICIEMBRE 2019 Valoriz. 01 333,057.50 333,057.50 - - 333,057.50 59,950.35 393,007.85 393,007.85
ENERO 2020 Valoriz. 02 749,645.41 749,645.41 - - 749,645.41 134,936.17 884,581.58 884,581.58
FEBRERO 2020 Valoriz. 03 - - - - - - - -
MARZO 2020 Valoriz. 04 - - - - - - - -
ABRIL 2020 Valoriz. 05 - - - - - - - -
MAYO 2020 Valoriz. 06 - - - - - - - - -
JUNIO 2020 Valoriz. 07 - - - - - - - - -
JULIO 2020 Valoriz. 08 - - - - - - - - -
AGOSTO 2020 Valoriz. 09
SETIEMBRE 2020 Valoriz. 10
Total Val. Cont. Principal 1,082,702.91 - - 1,082,702.91 - - - 1,082,702.91 194,886.52 1,277,589.43 1,277,589.43
MES VALORIZADO ADELANTO DIRECTO VAL 01 - FEB VAL 02 - MAR VAL 04 - ABR VAL 04 - MAY
Io IND. REAJ. IND. REAJ. IND. REAJ. IND. REAJ. IND. REAJ.
SIMBOLO DESCRIPCION INDICE %INCID FACTOR K K K K K
Jul-18 Jan-19 Jan-19 Feb-19 Mar-19 Apr-19
AT ACERO DE CONSTRUCCION CORRUGADO 3 98.958% 0.096 512.37 537.43 0.101 537.43 0.101 536.72 0.101 530.00 0.099 529.91 0.099
TUBERIA DE PVC PARA AGUA 72 1.042% 434.41 431.72 431.72 433.33 432.33 432.33
CM MADERA NACIONAL ENCOF Y CARPINTER 43 40.187% 0.107 894.58 892.60 0.108 892.60 0.108 893.78 0.108 893.85 0.108 897.58 0.109
CEMENTO PORTLAND TIPO I 21 59.813% 410.96 418.38 418.38 418.57 418.57 420.47
AG AGREGADO FINO 4 100.000% 0.096 751.32 777.43 0.099 777.43 0.099 777.21 0.099 765.98 0.098 760.14 0.097
DM DÓLAR (GENERAL PONDERADO) 30 81.757% 0.148 481.37 489.58 0.150 489.58 0.150 487.29 0.150 486.86 0.149 489.59 0.150
MAQUINARIA Y EQUIPO NACIONAL 48 18.243% 369.08 369.95 369.95 370.25 368.51 369.76
GGU INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 100.000% 0.225 448.81 452.29 0.227 452.29 0.227 452.87 0.227 456.16 0.229 457.08 0.229
J MANO DE OBRA INC. LEYES SOCIALES 47 100.000% 0.328 602.11 600.40 0.327 600.40 0.327 600.40 0.327 600.40 0.327 600.40 0.327
1 February-2019 1.012 January-2019 130,578.05 130,578.05 1,566.94 1,566.94 333,057.50 333,057.50 3,996.69 3,996.69 1,566.94 0.00 0.00 1,566.94
2 March-2019 1.012 February-2019 1,297,125.71 1,427,703.76 15,565.51 17,132.45 749,645.41 1,082,702.91 8,995.74 12,992.43 8,995.74 0.00 0.00 8,995.74
3 April-2019 1.010 March-2019 1,743,579.53 3,171,283.29 17,435.80 34,568.25 0.00 1,082,702.91 0.00 12,992.43 0.00 0.00 0.00 0.00
4 May-2019 1.011 April-2019 916,746.52 4,088,029.80 10,084.21 44,652.46 0.00 1,082,702.91 0.00 12,992.43 0.00 0.00 0.00 0.00
5 June-2019 0.000 May-2019 1,507,363.06 5,595,392.86 0.00 1,082,702.91 0.00 12,992.43
6 July-2019 0.000 June-2019 1,490,906.45 7,086,299.31 0.00 1,082,702.91 0.00 12,992.43
7 August-2019 0.000 July-2019 2,113,708.41 9,200,007.72 0.00 1,082,702.91 0.00 12,992.43
8 September-2019 0.000 August-2019 554,612.46 9,754,620.18 0.00 1,082,702.91 0.00 12,992.43
9 October-2019 0.000 September-2019 810,450.98 10,565,071.15 0.00 1,082,702.91 0.00 12,992.43
10 November-2019 0.000 October-2019 366,504.49 10,931,575.64 0.00 1,082,702.91 0.00 12,992.43
11 December-2019 0.000 November-2019 Err:509 Err:509 0.00 1,082,702.91 0.00 12,992.43
12 January-2020 0.000 December-2019 Err:509 Err:509
Reintegro Total Acumulado Err:509 44,652.46 1,082,702.91 12,992.43 0.00 0.00 0.00 0.00
CRONOGRAMA VALORIZADO
OBRA: "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA Y SANEAMIENTO INTEGRAL DEL CENTRO POBLADO DE HUASAO, DISTRITO DE OROPESA, QUISPICANCHI - CUSCO"
VAL 01 VAL 02 VAL 03 VAL 04 VAL 05 VAL 06 VAL 07 VAL 08 VAL 09 VAL 10 VAL 11 VAL 12
15 DE FEB 15 DE MAR 15 DE ABR 15 DE MAY 15 DE JUN 15 DE JUL 15 DE AGOST 15 DE SET 15 DE OCT 15 DE NOV 15 DE DIC 15 DE ENE
Items ACTIVIDAD PRESUPUESTO INICIO 16 FINAL 15
2º M E S 3º M E S 4º M E S 5º M E S 6º M E S 7º M E S 8º M E S 9º M E S 10º M E S 11º M E S
ENERO ENERO
01 SISTEMA DE AGUA POTABLE 1,228,267.08
OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 71,096.44
OBRAS PROVISIONALES 30,028.00 30,028.00
OBRAS PRELIMINARES 10,035.44 10,035.44
SEGURIDAD Y SALUD 31,033.00 31,033.00
OBRAS GENERALES - AGUA POTABLE 424,713.90
CAPTACIONES 40,369.43 16,147.77 12,110.83 12,110.83
LINEA DE CONDUCCION 211,623.34 52,905.84 52,905.84 52,905.84 52,905.84
RESERVORIO 109,866.37 54,933.19 54,933.19
MANTENIMIENTO DE ESTRUCTURAS EXISTENTES 11,192.21 11,192.21
LINEAS DE ADUCCION 51,662.55 51,662.55
OBRAS SECUNDARIAS - AGUA POTABLE 662,651.57
REDES DE DISTRIBUCION DE AGUA POTABLE 393,417.41 65,569.57 65,569.57 65,569.57 65,569.57 65,569.57 65,569.57
CRUCE DE TUBERÍA (PASE AEREO 02 UND) 13,501.52 4,050.46 4,725.53 4,725.53
CONEXIONES DOMICILIARIAS - AGUA POTABLE 255,732.64 42,622.11 42,622.11 42,622.11 42,622.11 42,622.11 42,622.11
ROTURA Y REPOSICIÓN DE PÁVIMENTOS 52,293.60 5,229.36 18,302.76 18,302.76 10,458.72
FLETE TERRESTRE - SISTEMA AGUA 17,511.57 1,945.73 1,945.73 1,945.73 1,945.73 1,945.73 1,945.73 1,945.73 1,945.73 1,945.73
02 SISTEMA DE DESAGUE Y ALCANTARILLADO 1,634,871.93
OBRAS GENERALES - ALCANTARILLADO 1,314,743.79
TRABAJOS PRELIMINARES 29,349.72 5,869.94 5,869.94 2,934.97 2,934.97 2,934.97 2,934.97 2,934.97 2,934.97
MOVIMIENTO DE TIERRAS 426,403.15 85,280.63 85,280.63 42,640.32 42,640.32 42,640.32 42,640.32 42,640.32 42,640.32
SUMINISTRO E INSTALACION DE TUBERIA PVC UF ISO 4435 471,220.20 94,244.04 94,244.04 47,122.02 47,122.02 47,122.02 47,122.02 47,122.02 47,122.02
CONSTRUCCION DE BUZONES TIPO I 361,158.54 72,231.71 72,231.71 36,115.85 36,115.85 36,115.85 36,115.85 36,115.85 36,115.85
PRUEBAS DE CONTROL DE CALIDAD 26,612.18 8,870.73 8,870.73 8,870.73
CONEXIONES DOMICILIARIAS - ALCANTARILLADO 126,136.00 21,022.67 21,022.67 21,022.67 21,022.67 21,022.67 21,022.67
ROTURA Y REPOSICIÓN DE PÁVIMENTO RIGIDO 126,435.72 25,287.14 25,287.14 25,287.14 25,287.14 25,287.14
ROTURA Y REPOSICIÓN DE PÁVIMENTO FLEXIBLE 67,556.42 13,511.28 13,511.28 13,511.28 13,511.28 13,511.28
03 PLANTA DE TRATAMIENTO 1,217,619.62
PLANTA DE TRATAMIENTO HUASAO 1,217,619.62 121,761.96 401,814.47 328,757.30 365,285.89
COSTOS DIRECTO 4,080,758.63 399,722.10 324,588.72 254,759.20 429,429.69 321,799.95 317,074.42 318,101.11 318,834.60 300,591.19 401,814.47 328,757.30 365,285.89
GASTOS GENERALES FIJOS (0.20%) 8,000.00 783.62 636.33 499.43 841.86 630.86 621.60 623.61 625.05 589.28 787.73 644.50 716.11
0.20% 9.80% 7.95% 6.24% 10.52% 7.89% 7.77% 7.80% 7.81% 7.37% 9.85% 8.06% 8.95%
GASTOS GENERALES VIABLES (3.66%) 149,299.65 14,624.33 11,875.48 9,320.68 15,711.22 11,773.45 11,600.56 11,638.13 11,664.96 10,997.50 14,700.88 12,028.00 13,364.44
3.66% 9.80% 7.95% 6.24% 10.52% 7.89% 7.77% 7.80% 7.81% 7.37% 9.85% 8.06% 8.95%
UTILIDAD (9.00%) 367,268.28 35,974.99 29,212.98 22,928.33 38,648.67 28,962.00 28,536.70 28,629.10 28,695.11 27,053.21 36,163.30 29,588.16 32,875.73
9.00% 9.80% 7.95% 6.24% 10.52% 7.89% 7.77% 7.80% 7.81% 7.37% 9.85% 8.06% 8.95%
SUB TOTAL 4,605,326.56 451,105.04 366,313.51 287,507.64 484,631.45 363,166.26 357,833.28 358,991.94 359,819.72 339,231.18 453,466.39 371,017.95 412,242.17
9.80% 7.95% 6.24% 10.52% 7.89% 7.77% 7.80% 7.81% 7.37% 9.85% 8.06% 8.95%
IGV (18.00%) 828,958.78 81,198.91 65,936.43 51,751.38 87,233.66 65,369.93 64,409.99 64,618.55 64,767.55 61,061.61 81,623.95 66,783.23 74,203.59
18.00% 9.80% 7.95% 6.24% 10.52% 7.89% 7.77% 7.80% 7.81% 7.37% 9.85% 8.06% 8.95%
COSTO REFERENCIAL 5,434,285.34 532,303.95 432,249.95 339,259.02 571,865.11 428,536.19 422,243.27 423,610.50 424,587.27 400,292.80 535,090.34 437,801.18 486,445.76
% ACUMULADO 9.80% 17.75% 23.99% 34.52% 42.40% 50.17% 57.97% 65.78% 73.15% 82.99% 91.05% 100.00%
8.87%
12.85% 2829.00% -2794.48%
130293241.96%
1,537,460.26 1,589,745.47 285932.556265208 96.71%
.
AGUA 142,095.78 66,962.39 125,946.04 279,593.87 133,165.70 128,440.17 120,596.13 121,329.62 110,137.41 0.00 0.00 0.00
278.57 131.27 246.91 548.12 261.06 251.80 236.42 237.86 215.92 0.00 0.00 0.00
5,198.75 2,449.90 4,607.89 10,229.29 4,872.03 4,699.14 4,412.16 4,439.00 4,029.51 0.00 0.00 0.00
12,788.62 6,026.62 11,335.14 25,163.45 11,984.91 11,559.61 10,853.65 10,919.67 9,912.37 0.00 0.00 0.00
160,361.72 75,570.19 142,135.98 315,534.73 150,283.70 144,950.72 136,098.36 136,926.13 124,295.20 0.00 0.00 0.00
DESAGUE 257,626.32 257,626.32 128,813.16 149,835.83 188,634.26 188,634.26 197,504.98 197,504.98 68,691.82 0.00 0.00 0.00
505.06 505.06 252.53 293.74 369.80 369.80 387.19 387.19 134.66 0.00 0.00 0.00
9,425.58 9,425.58 4,712.79 5,481.93 6,901.42 6,901.42 7,225.97 7,225.97 2,513.18 0.00 0.00 0.00
23,186.37 23,186.37 11,593.18 13,485.22 16,977.08 16,977.08 17,775.45 17,775.45 6,182.26 0.00 0.00 0.00
290,743.33 290,743.33 145,371.66 169,096.72 212,882.56 212,882.56 222,893.59 222,893.59 77,521.93 0.00 0.00 0.00
PTAR 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 121,761.96 401,814.47 328,757.30 365,285.89
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 238.70 787.73 644.50 716.11
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,454.81 14,700.88 12,028.00 13,364.44
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,958.58 36,163.30 29,588.16 32,875.73
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 137,414.06 453,466.39 371,017.95 412,242.17
TOTAL 451,105.04 366,313.51 287,507.64 484,631.45 363,166.26 357,833.28 358,991.94 359,819.72 339,231.18 453,466.39 371,017.95 412,242.17
OBRA: : "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA Y SANEAMIENTO INTEGRAL DEL CENTRO POBLADO DE HUASAO, DISTRITO DE OROPESA, QUISPICANCHI - CUSCO"
100.00%
88.87
PORCENTAJE
90.00%
80.00%
70.00%
SITUACIÓN ACTUAL DE LA
OBRA 60.00%
ATRASADA
50.00%
-14.14%
40.00%
30.00%
20.00%
LEYENDA
LEYENDA
10.00%
CURVA
CURVA PROG
PROG
CURVA
CURVA REAL
REAL
0.00%
Inicio 16/01/17 feb-17 mar-17 abr-17 may-17 jun-17 jul-17 ago-17 sep-17 oct-17 nov-17 dic-17 Termino
15/01/18
MESES
0 1 2 3 4 5 6 7 8 9 10 11 12
Inicio Termino
MESES 16/01/17
feb-17 mar-17 abr-17 may-17 jun-17 jul-17 ago-17 sep-17 oct-17 nov-17 dic-17
15/01/18
PROG 0.00% 9.80% 17.75% 23.99% 34.52% 42.40% 50.17% 57.97% 65.78% 73.15% 82.99% 91.05% 100.00%
PORCENTAJE
ACUMULADO
REAL 0.00% 3.03% 9.86% 9.86%
VAL ACUMULADO
PROG 23.99% ATRASADA -14.14%
REAL 9.86%
OBRA: : "MEJORAMIENTO Y AMPLIACIÓN DEL SISTEMA DE AGUA Y SANEAMIENTO INTEGRAL DEL CENTRO POBLADO DE HUASAO, DISTRITO DE OROPESA, QUISPICANCHI - CUSCO"
634,261.80 183156.757047044 1 Feb-17 451,105.04 9.80% 451,105.04 9.80% 333,057.50 3.03% 333,057.50 3.03% ADELANTADA -6.76%
2 Mar-17 366,313.51 7.95% 817,418.56 17.75% 749,645.41 6.82% 1,082,702.91 9.86% ATRASADA -7.89%
3 Apr-17 287,507.64 6.24% 1,104,926.20 23.99% 0.00 0.00% 1,082,702.91 9.86% ATRASADA -14.14%
4 May-17 484,631.45 10.52% 1,589,557.65 34.52%
5 Jun-17 363,166.26 7.89% 1,952,723.92 42.40%
6 Jul-17 357,833.28 7.77% 2,310,557.20 50.17%
7 Aug-17 358,991.94 7.80% 2,669,549.14 57.97%
8 Sep-17 359,819.72 7.81% 3,029,368.86 65.78%
9 Oct-17 339,231.18 7.37% 3,368,600.05 73.15%
10 Nov-17 453,466.39 9.85% 3,822,066.43 82.99%
11 Dec-17 371,017.95 8.06% 4,193,084.39 91.05%
12 Jan-18 412,242.17 8.95% 4,605,326.56 100.00%
4,605,326.56