PLANEACION PROGRAMACIÓN Y CONTROL DE OBRAS

C.P.M. ALTERNATIVA OPTIMA


EJERCICIO

TABLA UNO: DATOS BASICOS TABLA DOS: RELACION COSTO-TIEMPO

ACTIVIDA INCREMETO
DURACIO RELACION
ACTIVIDA D RELACION RELACION DURACION COSTO DEL
N COSTO MINIMO COSTO/TIEMP
D SIGUIENT COSTO TIEMPO MINIMA MAXIMO COSTO/TIEMP
NORMAL O
E O
A B 1 $ 1,641.60 0 0 1 $ 1,641.60 --------- -------
B C 2 $ 1,740.96 555.78 1 1 $ 2,296.74 555.78/1 555.78
C D 14 $ 10,689.09 4446.24 8 6 $ 15,135.33 4446.24/8 555.78
D E 2 $ 3,929.64 555.78 1 1 $ 4,485.42 555.78/1 555.78
E F, I 2 $ 12,549.60 555.78 1 1 $ 13,105.38 555.78/1 555.78
F G 56 $ 121,290.44 18896.52 34 22 $ 140,186.96 18896.52/34 555.78
G H 5 $ 10,768.55 1667.34 3 2 $ 12,435.89 1667.34/3 555.78
H JK 5 $ 11,776.92 1667.34 3 2 $ 13,444.26 1667.34/3 555.78
I J 2 $ 4,224.89 555.78 1 1 $ 4,780.67 555.78/1 555.78
J N 18 $ 18,967.20 6113.58 11 7 $ 25,080.78 6113.58/11 555.78
K L 1 $ 462.19 555.78 1 1 $ 1,017.97 555.78/1 555.78
L M 2 $ 3,980.16 555.78 1 1 $ 4,535.94 555.78/1 555.78
M N 10 $ 21,643.81 3334.68 6 4 $ 24,978.49 3334.68/6 555.78
N O 32 $ 108,505.80 10559.82 19 13 $ 119,065.62 10559.82/19 555.78
O P, W 20 $ 50,326.72 6669.36 12 8 $ 56,996.08 6669.36/12 555.78
P Q 3 $ 7,420.46 555.78 1 2 $ 7,976.24 555.78/1 555.78
Q R 7 $ 14,280.67 2223.12 4 3 $ 16,503.79 2223.12 555.78
R S 2 $ 3,672.58 555.78 1 1 $ 4,228.36 555.78/1 555.78
S T 2 $ 4,243.39 555.78 1 1 $ 4,799.17 555.78/1 555.78
T U 1 $ 924.38 0 0 1 $ 924.38 ----- ------
U V 9 $ 19,237.44 2778.9 5 4 $ 22,016.34 2778.9/5 555.78
V X 1 $ 2,278.30 555.78 1 1 $ 2,834.08 555.78/1 555.78
W X 19 $ 65,103.48 6113.58 11 8 $ 71,217.06 6113.58/11 555.78
X Z, AB 29 $ 38,348.54 10004.04 18 11 $ 48,352.58 10004.04/18 555.78
Y AA 13 $ 17,073.41 4446.24 8 5 $ 21,519.65 4446.24/8 555.78
Z Y 1 $ 2,505.17 555.78 1 1 $ 3,060.95 555.78/1 555.78
AA _ 25 $ 98,553.00 8336.7 15 10 $ 106,889.70 8336.7/15 555.78
AB AA 7 $ 21,339.99 2223.12 4 3 $ 23,563.11 2223.12/4 555.78
AC AD, AK 10 $ 26,089.10 3334.68 6 4 $ 29,423.78 3334.68/6 555.78
AD AE 4 $ 8,244.96 1111.56 2 2 $ 9,356.52 1111.56/2 555.78
AE AF 7 $ 14,280.67 2223.12 4 3 $ 16,503.79 2223.12/4 555.78
AF AG 1 $ 1,224.19 555.78 1 1 $ 1,779.97 555.78/1 555.78
AG AH 1 $ 2,828.93 555.78 1 1 $ 3,384.71 555.78/1 555.78
AH AI 1 $ 1,386.58 555.78 1 1 $ 1,942.36 555.78/1 555.78
AI AJ 9 $ 19,237.44 2778.9 5 4 $ 22,016.34 2778.9/5 555.78
AJ AL 1 $ 1,518.86 0 0 1 $ 1,518.86 ----- ------
ACTIVIDA INCREMETO
DURACIO RELACION
ACTIVIDA D RELACION RELACION DURACION COSTO DEL
N COSTO MINIMO COSTO/TIEMP
D SIGUIENT COSTO TIEMPO MINIMA MAXIMO COSTO/TIEMP
NORMAL O
E O
AK AL 19 $ 65,103.48 6113.58 11 8 $ 71,217.06 6113.58/11 555.78
AL AN, AP 15 $ 19,879.68 5002.02 9 6 $ 24,881.70 5002.02/9 555.78
AM AO 13 $ 17,073.41 4446.24 8 5 $ 21,519.65 4446.24/8 555.78
AN AM 1 $ 2,505.17 0 0 1 $ 2,505.17 ---- ------
AO _ 15 $ 59,131.80 5002.02 9 6 $ 64,133.82 5002.02/9 555.78
AP AO 4 $ 11,062.54 1111.56 2 2 $ 12,174.10 1111.56/2 555.78

SUMAS $ 927,045.19 $ 233,611.00

NOTAS: LOS COSTOS INDIRECTOS SON DE $555.78 /UT


ACTIVIDADES CON MENOR INCREMENTO DEL COSTO CON RESPECTO AL TIEMPO.
SON LAS ACTIVIDADES QUE SE SUGIERE "COMPACTAR".

RELACION COSTO/TIEMPO
40
35
30
25
20
15
10
5
0
0 10 20 30 40 50
-5