Está en la página 1de 20

REF F O R M U L A R I O No.

10 : A N A L I S I S DE COSTOS UNITARIOS

Dólar/Sol
FECHA : 16/04/21 #REF!
OBRA #REF! COSTO POR : Cjto LUGAR #REF!
PARTIDA : Reinstalacion de Artefactos de iluminación, que comprende : Instalación Artefacto 70 W TABLA DE RENDIMIENTOS (En 8 horas) en
Lampara, portafusible y conexionado a la red.incluye suministro de REN.CUADRILLA 20.0 Cjto/dia 0.0
manta termocontraible y soldar luminaria al pastoral. FACTOR REND. 1.0 0.0
ESPECIFICACION CANTID. HORAS REN.EQUIPOS 20.0 Cjto/dia 0.0 0.0
Camioneta 1000 Kg. 0.10 0.8
Camión Grúa 5 Tn. 0.60 4.8 PERSONAL BASE : Principal C. # B
Escalera dielectrica embonable 7.5m (3 Cuerpos) 1.00 8.0 CAPATAZ : 0.1 = 0.8 0.0
0.00 0.0 OPERARIO : 1.0 = 8.0 0.0 0.0
OFICIAL : 1.0 = 8.0 0.0 0.0
PEON : 1.0 = 8.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
9007 Manta termocontraible UNID. 0.24 81.2 19.49 0 0.00%
2001 Material Menudo (soldadura,Pintura) Glob 6.00 5.1 30.60 50.09 21 #REF!
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0 0.00%
0.00 0.00 54 #REF!
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 50.09 0.00%
MANO DE OBRA :
Capataz H.H. 0.04 #REF! #REF!
Operario H.H. 0.40 #REF! #REF!
Oficial H.H. 0.40 #REF! #REF!
Peon H.H. 0.40 #REF! #REF!
0.00
0.00 #REF! 47 #REF!
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% #REF! #REF! 0
Equipos Seguridad EST. 5% #REF! #REF!
Camioneta 1000 Kg. H.M 0.04 #REF! #REF!
Camión Grúa 5 Tn. H.M 0.24 #REF! #REF!
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.40 #REF! #REF!

0 0.00 #REF! 37 #REF!


COSTO DIRECTO S/. #REF!
G.G., D.T. Y UTILIDADES S/. #REF! 39 #REF!
TOTAL S/. #REF! #REF!
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

370.0001 FECHA : 16/04/21

OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMIC

COSTO POR : Cjto LUGAR Cajamarca


PARTIDA : INSTALACIÓN DE ACOMETIDA DOMICILIARIA AÉREA SIMPLE DE LA RED CON TABLA DE RENDIMIENTOS (En 8 horas) en
EMPALME DE DERIVACIÓN EN CAJA GEL; CORTE DE ACOMETIDA EXISTENTE EN REN.CUADRILLA 18.0 Cjto/dia 0.0

PUNTO DE FIJACIÓN DE INGRESO AL SITEMA DE MEDICIÓN Y EMPALME CON FACTOR REND. 1.0 0.0

NUEVA ACOMETIDA; INCLUYE ACCESORIOS DE FIJACIÓN, SUMINISTRO DE CINTA


AUTOFUNDENTE EPR, CINTA AISLANTE Y CORREA PLÁSTICA DE NYLON.
ESPECIFICACION CANTID. HORAS REN.EQUIPOS 18.0 Cjto/dia 0.0
Camioneta 1000 Kg. 0.10 0.8
Escalera dielectrica embonable 7.5m (3 Cuerpos) 1.00 8.0 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
MEZCLA 0.00 0.0 OPERARIO : = 0.0 0.0
OFICIAL : 1.0 = 8.0 0.0
HECHO POR : PEON : 1.0 = 8.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
2001 Material Menudo(cinta EPR, vinilica y cintillo) Glb 1.00 4.23 4.23 0 0.00%
0.00 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 4.23 0.00%
MANO DE OBRA :
Capataz H.H. 0.04 26.18 1.16
Operario H.H. 0.00 23.80 0.00
Oficial H.H. 0.44 18.84 8.37
Peon H.H. 0.44 17.01 7.56
0.00
0.00 17.10 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 17.10 0.85
Equipos Seguridad EST. 5% 17.10 0.85
Camioneta 1000 Kg. H.M 0.04 48.34 2.15
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.44 1.67 0.74
Equipos de Protección Personal - COVID-19 EQ. 0.93 0.74 0.69

H.M 0 0.00 5.29 0.00%


COSTO DIRECTO S/. 26.62
G.G., D.T. Y UTILIDADES S/. 5.32 0.00%
TOTAL S/. 31.94 0.00%
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

370.0002 FECHA : 16/04/21


OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMICCOSTO POR : Cjto LUGAR Cajamarca
PARTIDA : INSTALACIÓN DE ACOMETIDA DOMICILIARIA AÉREA SIMPLE DE LA RED CON TABLA DE RENDIMIENTOS (En 8 horas) en

EMPALME DE DERIVACIÓN EN CAJA GEL CON CRUCE DE CALLE; CORTE DE REN.CUADRILLA 12.0 Cjto/dia 0.0

ACOMETIDA EXISTENTE EN PUNTO DE FIJACIÓN DE INGRESO AL SITEMA DE FACTOR REND. 1.0 0.0

MEDICIÓN Y EMPALME CON NUEVA ACOMETIDA; INCLUYE ACCESORIOS DE


FIJACIÓN, SUMINISTRO DE CINTA AUTOFUNDENTE EPR, CINTA AISLANTE Y
CORREA PLÁSTICA DE NYLON.
ESPECIFICACION CANTID. HORAS REN.EQUIPOS 12.0 Cjto/dia 0.0
Camioneta 1000 Kg. 0.10 0.8
Escalera dielectrica embonable 7.5m (3 Cuerpos) 1.00 8.0 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
MEZCLA 0.00 0.0 OPERARIO : 0.0
OFICIAL : 1.0 = 8.0 0.0
HECHO POR : PEON : 2.0 = 16.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
2001 Material Menudo(cinta EPR, vinilica y cintillo, alambre) Glb 1.00 6.48 6.48 0 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00 0.00%
0.00 6.48 0.00%
MANO DE OBRA :
Capataz H.H. 0.07 26.18 1.75
Operario H.H. 0.00 23.80 0.00
Oficial H.H. 0.67 18.84 12.56
Peon H.H. 1.33 17.01 22.68
0.00
0.00 36.99 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 36.99 1.85
Equipos Seguridad EST. 5% 36.99 1.85
Camioneta 1000 Kg. H.M 0.07 48.34 3.22
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.67 1.67 1.11
Equipos de Protección Personal - COVID-19 EQ. 2.07 0.74 1.53

0 0.00 9.56 0.00%


COSTO DIRECTO S/. 53.03
G.G., D.T. Y UTILIDADES S/. 10.61 0.00%
TOTAL S/. 63.64 0.00%
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

370.0003 FECHA : 16/04/21


OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMICCOSTO POR : Cjto LUGAR Cajamarca
PARTIDA : INSTALACIÓN DE ACOMETIDA DOMICILIARIA AEREA SIMPLE DE LA CAJA DE TABLA DE RENDIMIENTOS (En 8 horas) en

DERIVACION; CORTE DE ACOMETIDA EXISTENTE EN PUNTO DE FIJACIÓN DE REN.CUADRILLA 24.0 Cjto/dia 0.0

INGRESO AL SITEMA DE MEDICIÓN Y EMPALME CON NUEVA ACOMETIDA; FACTOR REND. 1.0 0.0

INCLUYE ACCESORIOS DE FIJACIÓN, SUMINISTRO DE CINTA AUTOFUNDENTE


EPR, CINTA AISLANTE Y CORREA PLÁSTICA DE NYLON.
ESPECIFICACION CANTID. HORAS REN.EQUIPOS 24.0 Cjto/dia 0.0
Camioneta 1000 Kg. 0.10 0.8
Escalera dielectrica embonable 7.5m (3 Cuerpos) 1.00 8.0 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
MEZCLA 0.00 0.0 OPERARIO : = 0.0 0.0
OFICIAL : 1.0 = 8.0 0.0
HECHO POR : PEON : 1.0 = 8.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0.00%
2001 Material Menudo(cinta EPR, vinilica y cintillo) Glb 1.00 4.23 4.23 0.00%
0.00 0 0.00%
0.00 0.00%
0.00 0.00%
0.00 0 0.00%
0.00 0.00 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00%
0.00 0.00 0.00%
0.00 4.23 0.00%
MANO DE OBRA :
Capataz H.H. 0.03 26.18 0.87
Operario H.H. 0.00 23.80 0.00
Oficial H.H. 0.33 18.84 6.28
Peon H.H. 0.33 17.01 5.67
0.00
0.00 12.82 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 12.82 0.64
Equipos Seguridad EST. 5% 12.82 0.64
Camioneta 1000 Kg. H.M 0.03 48.34 1.61
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.33 1.67 0.56
Equipos de Protección Personal - COVID-19 EQ. 0.70 0.74 0.52

0 0.00 3.97 0.00%


COSTO DIRECTO S/. 21.02
G.G., D.T. Y UTILIDADES S/. 4.20 0.00%
TOTAL S/. 25.23 0.00%
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

370.0004 FECHA : 16/04/21


OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMICCOSTO POR : Cjto LUGAR Cajamarca
PARTIDA : INSTALACIÓN DE ACOMETIDA DOMICILIARIA AEREA SIMPLE DE LA CAJA DE TABLA DE RENDIMIENTOS (En 8 horas) en
DERIVACION CON CRUCE DE CALLE, CORTE DE ACOMETIDA EXISTENTE EN REN.CUADRILLA 18.0 Cjto/dia 0.0
PUNTO DE FIJACIÓN DE INGRESO AL SITEMA DE MEDICIÓN Y EMPALME CON FACTOR REND. 1.0 0.0
NUEVA ACOMETIDA; INCLUYE ACCESORIOS DE FIJACIÓN, SUMINISTRO DE CINTA
AUTOFUNDENTE EPR, CINTA AISLANTE Y CORREA PLÁSTICA DE NYLON.

ESPECIFICACION CANTID. HORAS REN.EQUIPOS 18.0 Cjto/dia 0.0


Camioneta 1000 Kg. 0.10 0.8
Escalera dielectrica embonable 7.5m (3 Cuerpos) 1.00 8.0 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
MEZCLA 0.00 0.0 OPERARIO : = 0.0 0.0
OFICIAL : 1.0 = 8.0 0.0
HECHO POR : PEON : 2.0 = 16.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
2001 Material Menudo(cinta EPR, vinilica y cintillo, alambre) Glb 1.00 6.48 6.48 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 6.48 0.00%
MANO DE OBRA :
Capataz H.H. 0.04 26.18 1.16
Operario H.H. 0.00 23.80 0.00
Oficial H.H. 0.44 18.84 8.37
Peon H.H. 0.89 17.01 15.12
0.00
0.00 24.66 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 24.66 1.23
Equipos Seguridad EST. 5% 24.66 1.23
Camioneta 1000 Kg. H.M 0.04 48.34 2.17
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.44 1.67 0.74
Equipos de Protección Personal - COVID-19 EQ. 1.38 0.74 1.02

0 0.00 6.40 0.00%


COSTO DIRECTO S/. 37.53
G.G., D.T. Y UTILIDADES S/. 7.51 0.00%
TOTAL S/. 45.04 0.00%
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

370.0005 FECHA : 16/04/21


OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMICCOSTO POR : Cjto LUGAR Cajamarca
PARTIDA : INSTALACIÓN DE MASTIL DE MADERA TORNILLO DE 2.5" X 2.5" X 4 M. PARA SUJECIÓN DE TABLA DE RENDIMIENTOS (En 8 horas) en
ACOMETIDA REN.CUADRILLA 28.0 Cjto/dia 0.0
FACTOR REND. 1.0 0.0

ESPECIFICACION CANTID. HORAS REN.EQUIPOS 28.0 Cjto/dia 0.0


Camioneta 1000 Kg. 0.10 0.8
Escalera dielectrica embonable 7.5m (3 Cuerpos) 1.00 8.0 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
MEZCLA 0.00 0.0 OPERARIO : = 0.0 0.0
OFICIAL : 1.0 = 8.0 0.0
HECHO POR : PEON : 2.0 = 16.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
2001 Material Menudo(grapas de sujeción, alambre) Glb 1.00 6.48 6.48 0 0.00%
1002 Liston de Madera Tornillo 2.5"x2.5" por 4m. Pza 1.00 31.84 31.84
1001 Cemento Bls 0.03 20.68 0.52 0 0.00%
1004 Agregados m3 0.01 16.15 0.16 0 0.00%
0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 39.00 0.00%
MANO DE OBRA :
Capataz H.H. 0.03 26.18 0.75
Operario H.H. 0.00 23.80 0.00
Oficial H.H. 0.29 18.84 5.38
Peon H.H. 0.57 17.01 9.72
0.00
0.00 15.85 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 15.85 0.79
Equipos Seguridad EST. 5% 15.85 0.79
Camioneta 1000 Kg. H.M 0.03 48.34 1.39
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.29 1.67 0.48
Equipos de Protección Personal - COVID-19 EQ. 0.89 0.74 0.66

0 0.00 4.11 0.00%


COSTO DIRECTO S/. 58.96
G.G., D.T. Y UTILIDADES S/. 11.79 0.00%
TOTAL S/. 70.75 0.00%
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

370.0006 FECHA : 16/04/21


OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMICCOSTO POR : Cjto LUGAR Cajamarca
PARTIDA : INSTALACIÓN DE MASTIL DE MADERA TORNILLO DE 2.5" X 2.5" X2 M. PARA SUJECIÓN DE TABLA DE RENDIMIENTOS (En 8 horas) en
ACOMETIDA REN.CUADRILLA 33.0 Cjto/dia 0.0
FACTOR REND. 1.0 0.0

ESPECIFICACION CANTID. HORAS REN.EQUIPOS 33.0 Cjto/dia 0.0


Camioneta 1000 Kg. 0.10 0.8
Escalera dielectrica embonable 7.5m (3 Cuerpos) 1.00 8.0 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
MEZCLA 0.00 0.0 OPERARIO : = 0.0 0.0
OFICIAL : 1.0 = 8.0 0.0
HECHO POR : PEON : 2.0 = 16.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
2001 Material Menudo(grapas de sujeción, alambre) Glb 1.00 6.48 6.48 0 0.00%
1002 Liston de Madera Tornillo 2.5"x2.5" por 2m. Pza 1.00 15.92 15.92
1001 Cemento Bls 0.03 20.68 0.52
1004 Agregados m3 0.01 16.15 0.16 0 0.00%
0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 23.08 0.00%
MANO DE OBRA :
Capataz H.H. 0.02 26.18 0.63
Operario H.H. 0.00 23.80 0.00
Oficial H.H. 0.24 18.84 4.57
Peon H.H. 0.48 17.01 8.25
0.00
0.00 13.45 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 13.45 0.67
Equipos Seguridad EST. 5% 13.45 0.67
Camioneta 1000 Kg. H.M 0.02 48.34 1.18
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.24 1.67 0.40
Equipos de Protección Personal - COVID-19 EQ. 0.75 0.74 0.56

0 0.00 3.49 0.00%


COSTO DIRECTO S/. 40.02
G.G., D.T. Y UTILIDADES S/. 8.00 0.00%
TOTAL S/. 48.02 0.00%
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

370.0010 FECHA : 16/04/21


OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMICCOSTO POR : Cjto LUGAR Cajamarca
PARTIDA INSTALACION DE ACOMETIDA TRIFASICA, DE LA RED CON EMPALME DE TABLA DE RENDIMIENTOS (En 8 horas) en

DERIVACIÓN EN CAJA GEL; CORTE DE ACOMETIDA EXISTENTE EN PUNTO REN.CUADRILLA 16.0 Cjto/dia 0.0

DE FIJACIÓN DE INGRESO AL SITEMA DE MEDICIÓN Y EMPALME CON NUEVA


ACOMETIDA; INCLUYE ACCESORIOS DE FIJACIÓN, SUMINISTRO DE CINTA
AUTOFUNDENTE EPR, CINTA AISLANTE Y CORREA PLÁSTICA DE NYLON.
FACTOR REND. 1.0 0.0
ESPECIFICACION CANTID. HORAS REN.EQUIPOS 16.0 Cjto/dia 0.0
Camioneta 1000 Kg. 0.10 0.8
Escalera dielectrica embonable 7.5m (3 Cuerpos) 0.70 5.6 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
0.00 0.0 OPERARIO : 0.5 = 4.0 0.0
OFICIAL : 1.0 = 8.0 0.0
HECHO POR : PEON : 1.0 = 8.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
2001 Material Menudo(cinta EPR, vinilica y cintillo) Glb 1.00 6.48 6.48 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 6.48 0.00%
MANO DE OBRA :
Capataz H.H. 0.05 26.18 1.31
Operario H.H. 0.25 23.80 5.95
Oficial H.H. 0.50 18.84 9.42
Peon H.H. 0.50 17.01 8.51
0.00
0.00 25.18 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 25.18 1.26
Equipos Seguridad EST. 5% 25.18 1.26
Camioneta 1000 Kg. H.M 0.05 48.34 2.42
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.35 1.67 0.58
Equipos de Protección Personal - COVID-19 EQ. 1.30 0.74 0.96

0 0.00
0 0.00 6.48 0.00%
COSTO DIRECTO S/. 38.15
G.G., D.T. Y UTILIDADES S/. 7.63 0.00%
TOTAL S/. 45.78 0.00%
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

370.0011 FECHA : 16/04/21


OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMICCOSTO POR : Cjto LUGAR Cajamarca
PARTIDA INSTALACION DE ACOMETIDA TRIFASICA, DE LA RED CON EMPALME DE TABLA DE RENDIMIENTOS (En 8 horas) en

DERIVACIÓN EN CAJA GEL CON CRUCE DE CALLE; CORTE DE ACOMETIDA REN.CUADRILLA 8.0 Cjto/dia 0.0

EXISTENTE EN PUNTO DE FIJACIÓN DE INGRESO AL SITEMA DE MEDICIÓN


Y EMPALME CON NUEVA ACOMETIDA; INCLUYE ACCESORIOS DE FIJACIÓN,
SUMINISTRO DE CINTA AUTOFUNDENTE EPR, CINTA AISLANTE Y CORREA
PLÁSTICA DE NYLON. FACTOR REND. 1.0 0.0
ESPECIFICACION CANTID. HORAS REN.EQUIPOS 8.0 Cjto/dia 0.0
Camioneta 1000 Kg. 0.10 0.8
Escalera dielectrica embonable 7.5m (3 Cuerpos) 0.70 5.6 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
0.00 0.0 OPERARIO : 0.5 = 4.0 0.0
OFICIAL : 1.0 = 8.0 0.0
HECHO POR : PEON : 1.0 = 8.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
2001 Material Menudo(cinta EPR, vinilica y cintillo) Glb 1.00 6.48 6.48 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 6.48 0.00%
MANO DE OBRA :
Capataz H.H. 0.10 26.18 2.62
Operario H.H. 0.50 23.80 11.90
Oficial H.H. 1.00 18.84 18.84
Peon H.H. 1.00 17.01 17.01
0.00
0.00 50.37 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 50.37 2.52
Equipos Seguridad EST. 5% 50.37 2.52
Camioneta 1000 Kg. H.M 0.10 48.34 4.83
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.70 1.67 1.17
Equipos de Protección Personal - COVID-19 EQ. 2.60 0.74 1.92

0 0.00
0 0.00 12.96 0.00%
COSTO DIRECTO S/. 69.81
G.G., D.T. Y UTILIDADES S/. 13.96 0.00%
TOTAL S/. 83.77 0.00%
REF F O R M U L A R I O No. 10 : A N A L I S I S DE COSTOS UNITARIOS

510.0102 FECHA : 16/04/21


OBRA MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA, SECUNDARIA Y CONEXIONES DOMICCOSTO POR : Cjto LUGAR Cajamarca
PARTIDA : Desmontaje de acometidas simple o doble, incluye separador PVC, desconexión TABLA DE RENDIMIENTOS (En 8 horas) en
de cajas y otros. REN.CUADRILLA 27.0 Cjto/dia 0.0
FACTOR REND. 1.0 0.0
ESPECIFICACION CANTID. HORAS REN.EQUIPOS 27.0 Cjto/dia 0.0
Camioneta 1000 Kg. 0.15 1.2
Escalera dielectrica embonable 7.5m (3 Cuerpos) 1.00 8.0 PERSONAL BASE : Principal C. # B
0.00 0.0 CAPATAZ : 0.1 = 0.8
0.00 0.0 OPERARIO : = 0.0 0.0
OFICIAL : = 0.0 0.0
HECHO POR : PEON : 2.0 = 16.0
METRADO C O S T O S INDICE CREPCO
COD D E S C R I P C I O N UNID. CANTID. UNITARIO PARCIAL SUB-TOTAL Nro %
MATERIALES : 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0 0.00%
0.00 0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0 0.00%
0.00 0.00 0 0.00%
0.00 0.00 0.00%
MANO DE OBRA :
Capataz H.H. 0.03 26.18 0.78
Operario H.H. - 23.80 0.00
Oficial H.H. - 18.84 0.00
Peon H.H. 0.59 17.01 10.08
0.00
0.00 10.86 0.00%
HERRAMIENTAS Y EQUIPOS :
Herramientas varias EST. 5% 10.86 0.54
Equipos Seguridad EST. 5% 10.86 0.54
Camioneta 1000 Kg. H.M 0.04 48.34 2.15
Escalera dielectrica embonable 7.5m (3 Cuerpos) H.M 0.30 1.67 0.49
Equipos de Protección Personal - COVID-19 EQ. 0.62 0.74 0.46

0
0 4.19 0.00%
COSTO DIRECTO S/. 15.04
G.G., D.T. Y UTILIDADES S/. 3.01 0.00%
TOTAL S/. 18.05 0.00%
Dólar/Sol
3.60

0.0

0.0
0.0
0.0
Dólar/Sol
3.60

0.0

0.0
0.0
0.0
Dólar/Sol
3.60

0.0

0.0
0.0
0.0
Dólar/Sol
3.60

0.0

0.0
0.0
0.0
Dólar/Sol
3.60

0.0

0.0
0.0
0.0
Dólar/Sol
3.60

0.0

0.0
0.0
0.0
Dólar/Sol
3.30

0.0

0.0
0.0
0.0
Dólar/Sol
3.30

0.0

0.0
0.0
0.0
Dólar/Sol
3.30

0.0

0.0
0.0
0.0
datos generales
1 Obra: MEJORAMIENTO DE REDES DE DISTRIBUCIÓN PRIMARIA,
2 Lugar: Cajamarca
3 T.C. 3.6

Costo/unitario
Capataz 26.18
Operario 23.80
Oficial 18.84
Peon 17.01

HERRAMIENTAS Y EQUIPOS
Camión Grúa 5 Tn. 126.66
Camioneta 1000 kg. 48.34
Escalera dielectrica embonable 10.0m (3 cuerpos) 1.67
Camión volquete 4x2 m3 205.67
Compactadora 20.72
Cortadora de concreto 31.25
Mezcladora 29.8
Vibradora 7.5
Planta de asfalto en frio 130
Amasadora de asfalto 150
Pavimentadoras 124.67
Equipo de medicion y pruebas 50
MATERIALES
Cemento 20.68
Agua 5
Hormigon 25.42
Arena 25.42
Tubo de PVC 1
Ladrillo 0.3
Material Menudo(cinta EPR, vinilica y cintillo) 4.23
Material Menudo(cinta EPR, vinilica y cintillo, alambre) 6.48
Liston de Madera Tornillo 2.5"x2.5" por 2m. 15.92
Agregados 16.15