PROGRAMA DE INVERSION

MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL TERCIARIA EN PUNTOS CRITICOS Y OBRAS COMPLEMENTARIAS EN EL TRAMO CASCO URBANO DE DONCELLO - SERRANÍA DEL MUNICIPIO DE DONCELLO CAQUETA

MES 1 MES 2 MES 3 MES 4


No. Descripción Unidad Cantidad Valor parcial Total general
Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 MES 1 Semana 5 Semana 6 Semana 7 Semana 8 Semana 9 MES 2 Semana 9 Semana 10 Semana 11 Semana 12 Semana 13 Semana 14 MES 3 Semana 14 Semana 15 Semana 16 Semana 17 Semana 18 MES 4

TRAMO 1 Y 2

ESTRUCTURA PLACA HUELLA

1 EXCAVACIONES

1.1 EXCAVACIONES VARIAS SIN CLASIFICAR m3 880.94 $98,404,767.00 $ 98,404,767.00 $ 98,404,767.00 $ 98,404,767.00
$100,794,951.00
1.2 CONFORMACIÓN DE LA CALZADA EXISTENTE m2 2600.00 $2,390,184.00 $ 2,390,184.00 $ 2,390,184.00 $ 2,390,184.00

2 DESMONTES, DESCAPOTES Y ESTABILIZACION

TRANSPORTE DE MATERIALES PROVENIENTES DE LA


EXCAVACIÓN DE LA EXPLANACIÓN, CANALES Y PRÉSTAMOS
2.1 m3/km 9148.43 $8,316,756.00 $8,316,756.00 $ 8,316,756.00 $ 8,316,756.00 $ 8,316,756.00
PARA DISTANCIAS MAYORES DE MIL METROS (1.000 M)
MEDIDOS A PARTIR DE CIEN METROS (100 M).

3 AFIRMADOS, RELLENOS Y CAPAS GRANULARES

3.1 SUB-BASE GRANULAR CLASE B m3 358.80 $34,445,227.00 $ 34,445,227.00 $ 34,445,227.00 $ 34,445,227.00

CONCRETO RESISTENCIA 21MPA RELACIÓN 60C/40P


3.2 m3 119.08 $38,168,821.00 $ 17,812,116.48 $ 17,812,116.48 $ 2,544,588.02 $ 38,168,821.02 $ 38,168,821.00
(PIEDRA PEGADA)

3.3 CONCRETO RESISTENCIA 21MPA (D) m3 407.31 $184,607,745.00 $345,120,783.00 $ 2,494,699.26 $ 17,462,894.80 $ 17,462,894.80 $ 12,473,496.28 $ 49,893,985.14 $ 4,989,398.51 $ 17,462,894.80 $ 17,462,894.80 $ 17,462,894.80 $ 17,462,894.80 $ 2,494,699.26 $ 77,335,676.97 $ 14,968,195.54 $ 17,462,894.80 $ 17,462,894.80 $ 7,484,097.75 $ 57,378,082.89 $ 184,607,745.00

3.4 CONCRETO RESISTENCIA 14MPA (F) m3 5.25 $1,941,338.00 $ 1,941,338.00 $ 1,941,338.00 $ 1,941,338.00

3.5 ACERO DE REFUERZO FY 4200 MPA. kg 22017.33 $85,957,652.00 $ 4,524,086.95 $ 7,917,152.17 $ 7,917,152.17 $ 5,655,108.70 $ 26,013,499.99 $ 2,262,043.48 $ 7,917,152.17 $ 7,917,152.17 $ 7,917,152.17 $ 7,917,152.17 $ 1,131,021.73 $ 35,061,673.89 $ 6,786,130.43 $ 7,917,152.17 $ 7,917,152.17 $ 2,262,043.35 $ 24,882,478.12 $ 85,957,652.00

4 SEÑALIZACIÓN Y DEMARCACIÓN DE VÍAS

SEÑAL VERTICAL DE TRANSITO TIPO 1 CON LAMINA


4.1 UNIDAD 10.00 $4,230,425.00 $4,230,425.00 $ 4,230,425.00 $ 4,230,425.00 $ 4,230,425.00
RETRORREFLECTIVA TIPO III (60 X 60 ) CM

SUBTOTAL TRAMO

TRAMO 3

ESTRUCTURA PLACA HUELLA

1 EXCAVACIONES

1.1 EXCAVACIONES VARIAS SIN CLASIFICAR m3 511.45 $57,131,017.00 $ 28,565,508.50 $ 28,565,508.50 $ 57,131,017.00 $ 57,131,017.00
$58,530,929.00
1.2 CONFORMACIÓN DE LA CALZADA EXISTENTE m2 1522.80 $1,399,912.00 $ 1,399,912.00 $ 1,399,912.00 $ 1,399,912.00

2 DESMONTES, DESCAPOTES Y ESTABILIZACION

TRANSPORTE DE MATERIALES PROVENIENTES DE LA


EXCAVACIÓN DE LA EXPLANACIÓN, CANALES Y PRÉSTAMOS
2.1 m3/km 6350.10 $5,772,816.00 $5,772,816.00 $ 2,886,408.00 $ 2,886,408.00 $ 5,772,816.00 $ 5,772,816.00
PARA DISTANCIAS MAYORES DE MIL METROS (1.000 M)
MEDIDOS A PARTIR DE CIEN METROS (100 M).

3 AFIRMADOS, RELLENOS Y CAPAS GRANULARES

3.1 SUB-BASE GRANULAR CLASE B m3 212.22 $20,373,373.00 $ 20,373,373.00 $ 20,373,373.00 $ 20,373,373.00

CONCRETO RESISTENCIA 21MPA RELACIÓN 60C/40P


3.2 m3 25.35 $8,124,668.00 $ 6,093,501.00 $ 2,031,167.00 $ 8,124,668.00 $ 8,124,668.00
(PIEDRA PEGADA)

3.3 CONCRETO RESISTENCIA 21MPA (D) m3 278.17 $126,073,669.00 $215,173,205.00 $ 3,654,309.24 $ 12,790,082.35 $ 9,135,773.11 $ 25,580,164.70 $ 3,654,309.24 $ 12,790,082.35 $ 12,790,082.35 $ 12,790,082.35 $ 12,790,082.35 $ 1,827,154.62 $ 56,641,793.26 $ 10,962,927.72 $ 12,790,082.35 $ 12,790,082.35 $ 7,308,618.62 $ 43,851,711.04 $ 126,073,669.00

3.4 CONCRETO RESISTENCIA 14MPA (F) m3 3.28 $1,213,791.00 $ 1,213,791.00 $ 1,213,791.00 $ 1,213,791.00

3.5 ACERO DE REFUERZO FY 4200 MPA. kg 15211.66 $59,387,704.00 $ 2,344,251.46 $ 5,469,920.08 $ 5,469,920.08 $ 3,907,085.78 $ 17,191,177.40 $ 1,562,834.31 $ 5,469,920.08 $ 5,469,920.08 $ 5,469,920.08 $ 5,469,920.08 $ 781,417.16 $ 24,223,931.79 $ 4,688,502.93 $ 5,469,920.08 $ 5,469,920.08 $ 2,344,251.72 $ 17,972,594.81 $ 59,387,704.00

4 SEÑALIZACIÓN Y DEMARCACIÓN DE VÍAS

SEÑAL VERTICAL DE TRANSITO TIPO 1 CON LAMINA


4.1 UNIDAD 8.00 $3,384,340.00 $3,384,340.00 $ 3,384,340.00 $ 3,384,340.00 $ 3,384,340.00
RETRORREFLECTIVA TIPO III (60 X 60 ) CM

SUBTOTAL TRAMO

5 OBRAS DE DRENAJE (03 ALCANTARILLAS )

5.1 EXCAVACIONES VARIAS EN MATERIAL COMÚN BAJO AGUA. m3 43.88 $5,032,174.00 $ 5,032,174.00 $ 5,032,174.00 $ 5,032,174.00

5.2 CONCRETO RESISTENCIA 21MPA (D) m3 55.32 $25,073,475.00 $ 12,536,737.50 $ 12,536,737.50 $ 25,073,475.00 $ 25,073,475.00
$76,080,181.00
5.3 CONCRETO RESISTENCIA 14MPA (F) m3 8.20 $3,032,185.00 $ 3,032,185.00 $ 3,032,185.00 $ 3,032,185.00

5.4 ACERO DE REFUERZO FY 4200 MPA. kg 10999.32 $42,942,347.00 $ 3,903,849.72 $ 6,831,737.00 $ 6,831,737.00 $ 6,831,737.00 $ 2,927,887.30 $ 27,326,948.02 $ 3,903,849.72 $ 6,831,737.00 $ 4,879,812.26 $ 15,615,398.98 $ 42,942,347.00

TOTAL DE COSTOS DIRECTOS $ 817,404,386.00 $ 11,968,208.72 $ 6,831,737.00 $ 6,831,737.00 $ 6,831,737.00 $ 2,927,887.30 $ 35,391,307.02 $ 142,077,289.22 $ 109,410,516.17 $ 51,920,826.05 $ 56,176,786.90 $ 31,171,463.87 $ 390,756,882.21 $ 12,468,585.54 $ 43,640,049.40 $ 43,640,049.40 $ 43,640,049.40 $ 43,640,049.40 $ 6,234,292.77 $ 193,263,075.91 $ 37,405,756.62 $ 43,640,049.40 $ 61,452,165.88 $ 43,304,628.92 $ 12,190,520.02 $ 197,993,120.88 $ 817,404,386.00

27.6% $ 225,603,611.00 $ 3,303,226.00 $ 1,885,559.00 $ 1,885,559.00 $ 1,885,559.00 $ 808,097.00 $ 9,768,001.00 $ 39,213,332.00 $ 30,197,302.00 $ 14,330,148.00 $ 15,504,793.00 $ 8,603,324.00 $ 107,848,899.00 $ 3,441,330.00 $ 12,044,654.00 $ 12,044,654.00 $ 12,044,654.00 $ 12,044,654.00 $ 1,720,665.00 $ 53,340,609.00 $ 10,323,989.00 $ 12,044,654.00 $ 16,960,798.00 $ 11,952,078.00 $ 3,364,584.00 $ 54,646,101.00 $ 225,603,611.00

AIU 2.0% $ 16,348,088.00 $ 239,364.00 $ 136,635.00 $ 136,635.00 $ 136,635.00 $ 58,558.00 $ 707,826.00 $ 2,841,546.00 $ 2,188,210.00 $ 1,038,417.00 $ 1,123,536.00 $ 623,429.00 $ 7,815,138.00 $ 249,372.00 $ 872,801.00 $ 872,801.00 $ 872,801.00 $ 872,801.00 $ 124,686.00 $ 3,865,262.00 $ 748,115.00 $ 872,801.00 $ 1,229,043.00 $ 866,093.00 $ 243,810.00 $ 3,959,862.00 $ 16,348,088.00

5.0% $ 40,870,219.00 $ 598,410.00 $ 341,587.00 $ 341,587.00 $ 341,587.00 $ 146,394.00 $ 1,769,565.00 $ 7,103,864.00 $ 5,470,526.00 $ 2,596,041.00 $ 2,808,839.00 $ 1,558,573.00 $ 19,537,844.00 $ 623,429.00 $ 2,182,002.00 $ 2,182,002.00 $ 2,182,002.00 $ 2,182,002.00 $ 311,715.00 $ 9,663,154.00 $ 1,870,288.00 $ 2,182,002.00 $ 3,072,608.00 $ 2,165,231.00 $ 609,526.00 $ 9,899,656.00 $ 40,870,219.00

COSTOS AMBIENTALES Y DE FORMALIZACIÓN


6
INSTITUCIONAL

6.1 PREVISIÓN PARA EL PLAN DE MANEJO DE TRANSITO (PMT) UND 1.00 $17,282,227.00 $ 864,111.00 $ 1,008,130.00 $ 1,008,130.00 $ 1,008,130.00 $ 432,056.00 $ 4,320,557.00 $ 576,074.00 $ 1,008,130.00 $ 1,008,130.00 $ 1,008,130.00 $ 720,093.00 $ 4,320,557.00 $ 288,037.00 $ 1,008,130.00 $ 1,008,130.00 $ 1,008,130.00 $ 1,008,130.00 $ 144,019.00 $ 4,464,575.00 $ 864,111.00 $ 1,008,130.00 $ 1,008,130.00 $ 1,008,130.00 $ 288,036.50 $ 4,176,537.50 $ 17,282,227.00

6.2 PREVISIÓN OBRAS DE LA GESTIÓN AMBIENTAL UND 1.00 $40,765,178.00 $ 2,038,259.00 $ 2,377,969.00 $ 2,377,969.00 $ 2,377,969.00 $ 1,019,129.00 $ 10,191,295.00 $ 1,358,839.00 $ 2,377,969.00 $ 2,377,969.00 $ 2,377,969.00 $ 1,698,549.00 $ 10,191,295.00 $ 679,420.00 $ 2,377,969.00 $ 2,377,969.00 $ 2,377,969.00 $ 2,377,969.00 $ 339,710.00 $ 10,531,004.00 $ 2,038,259.00 $ 2,377,969.00 $ 2,377,969.00 $ 2,377,969.00 $ 679,417.00 $ 9,851,583.00 $ 40,765,178.00
$61,564,883.00

INVENTARIO VIAL PARA REPORTE DE INFORMACIÓN DE LA


6.3 VÍA SEGÚN RESOLUCIÓN 0000412 DEL 26 DE FEBRERO DE KM 3.90 $3,517,478.00 $ 175,874.00 $ 205,186.00 $ 205,186.00 $ 205,186.00 $ 87,937.00 $ 879,370.00 $ 117,249.00 $ 205,186.00 $ 205,186.00 $ 205,186.00 $ 146,562.00 $ 879,370.00 $ 58,625.00 $ 205,186.00 $ 205,186.00 $ 205,186.00 $ 205,186.00 $ 29,312.00 $ 908,682.00 $ 175,874.00 $ 205,186.00 $ 205,186.00 $ 205,186.00 $ 58,625.50 $ 850,057.50 $ 3,517,478.00
2020 DEL MINISTERIO DE TRANSPORTE

Costo total obra $ 1,161,791,187.00 $ 1,161,791,187.00

Interventoría $ 105,400,907.00 $ 5,270,045.34 $ 6,148,386.23 $ 6,148,386.23 $ 6,148,386.23 $ 2,635,022.67 $ 26,350,226.70 $ 3,513,363.56 $ 6,148,386.23 $ 6,148,386.23 $ 6,148,386.23 $ 4,391,704.45 $ 26,350,226.70 $ 1,756,681.78 $ 6,148,386.23 $ 6,148,386.23 $ 6,148,386.23 $ 6,148,386.23 $ 878,340.89 $ 27,228,567.59 $ 5,270,045.34 $ 6,148,386.23 $ 6,148,386.23 $ 6,148,386.23 $ 1,756,681.98 $ 25,471,886.01 $ 105,400,907.00

Valor total del proyecto $ 1,267,192,094.00 $ 36,425,706.78 $ 25,766,926.23 $ 25,766,926.23 $ 25,766,926.23 $ 11,042,968.27 $ 124,769,454.74 $ 338,878,846.00 $ 266,416,741.57 $ 131,545,929.33 $ 141,530,413.03 $ 80,085,162.19 $ 958,457,094.12 $ 32,034,065.86 $ 112,119,227.03 $ 112,119,227.03 $ 112,119,227.03 $ 112,119,227.03 $ 16,017,033.43 $ 496,528,005.41 $ 96,102,194.58 $ 112,119,227.03 $ 153,906,451.99 $ 111,332,331.07 $ 31,381,721.02 $ 504,841,924.77 $ 1,267,192,094.00