RESUMEN DE METRADOS - MEJORAMIENTO CON OVER

PROYECTO: "CONSTRUCCION DE LA CARRETERA LA JALCA - NUEVA ESPERANZA, DISTRITO DE LA


JALCA, CHACHAPOYAS, AMAZONAS"

PARTIDA DESCRIPCIÓN UND METRADO

I PRECIOS DEL CONTRATO

01 MOVIMIENTO DE TIERRAS

01.01 MEJORAMIENTO DE SUELOS

01.01.01 EXCAVACIÓN EN MATERIAL SUELTO (A NIVEL DE SUBRASANTE) m3 21,233.92

II PRECIOS PACTADOS

01 MOVIMIENTO DE TIERRAS

01.01 MEJORAMIENTO DE SUELOS

01.01.01 EXTRACCION Y APILAMIENTO DE MATERIAL DE CANTERA PARA MEJORAMIENTO m3 25,480.71

01.01.02 CARGUIO DE MATERIAL OVER PARA MEJORAMIENTO m3 25,480.71

01.01.03 EXTENDIDO Y COMPACTADO DE OVER m3 47,630.07

01.01.04 TRANSPORTE

01.01.04.01 TRANSPORTE DE OVER PARA MEJORAMIENTO DE SUBRASANTE DM=6.68 M3K 9,760.69

01.01.04.02 TRANSPORTE DE OVER PARA MEJORAMIENTO DE SUBRASANTE DM=2.48 M3K 15,720.01


ADICIONAL DE OBRA N° 01
MEJORAMIENTO DE SUELOS CON OVER

OBRA: "CONSTRUCCIÓN DE LA CARRETERA LA JALCA - NUEVA ESPERANZA, DISTRITO DE LA JALCA, CHACHAPOYAS,


AMAZONAS"

01 MOVIMIENTO DE TIERRAS

01.01 MEJORAMIENTO DE SUELOS

01.01.01 EXCAVACION EN MATERIAL SUELTO PARA MEJORAMIENTO SUB RASANTE

PROGRESIVA AREA
LONGITUD ANCHO AREA AREA SA AREA TOTAL ESPESOR VOLUMEN
PLAZOLET
(m) (m) (m2) (m2) (m2) (m) (m3)
DEL AL A (m2)

1+740 5+340 3,600.00 5.30 19,080.00 817.72 437.06 20,334.78 0.40 8,133.91
44+500 44+540 40.00 5.30 212.00 15.81 62.44 290.25 0.40 116.10
44+700 45+190 490.00 5.30 2,597.00 123.05 62.44 2,782.49 0.40 1,112.99
45+840 46+140 300.00 5.30 1,590.00 19.77 0.00 1,609.77 0.40 643.91
46+900 47+110 210.00 5.30 1,113.00 80.43 0.00 1,193.43 0.40 477.37
47+230 47+380 150.00 5.30 795.00 13.39 0.00 808.39 0.40 323.36
47+600 47+980 380.00 5.30 2,014.00 47.71 62.44 2,124.14 1.00 2,124.14
48+880 49+120 240.00 5.30 1,272.00 78.88 0.00 1,350.88 0.40 540.35
49+700 50+460 760.00 5.30 4,028.00 83.72 124.88 4,236.60 0.40 1,694.64
50+780 51+040 260.00 5.30 1,378.00 71.91 62.44 1,512.34 1.00 1,512.34
54+500 54+700 200.00 5.30 1,060.00 32.65 62.44 1,155.09 0.40 462.04
55+500 56+000 500.00 5.30 2,650.00 74.58 62.44 2,787.02 0.40 1,114.81
56+500 57+000 500.00 5.30 2,650.00 80.40 62.44 2,792.84 0.40 1,117.13
57+000 57+845 845.00 5.30 4,478.50 48.68 124.88 4,652.06 0.40 1,860.82
8,475.00 44,917.50 1,588.70 1,123.88 47,630.07 21,233.92 M3

01.01.02 EXTRACCIÓN Y APILAMIENTO DE MATERIAL DE CANTERA PARA MEJORAMIENTO

PROGRESIVA AREA
LONGITUD ANCHO AREA AREA SA VOL.MEJ.SR VOLUMEN
PLAZOLET ESPESOR (m) FAC. ESPONJ.
(m) (m) (m2) (m2) (m3) TOTAL (m3.)
DEL AL A (m2)

1+740 5+340 3,600.00 5.30 19,080.00 817.72 437.06 0.40 8,133.91 1.20 9,760.69
44+500 44+540 40.00 5.30 212.00 15.81 62.44 0.40 116.10 1.20 139.32
44+700 45+190 490.00 5.30 2,597.00 123.05 62.44 0.40 1,112.99 1.20 1,335.59
45+840 46+140 300.00 5.30 1,590.00 19.77 0.00 0.40 643.91 1.20 772.69
46+900 47+110 210.00 5.30 1,113.00 80.43 0.00 0.40 477.37 1.20 572.84
47+230 47+380 150.00 5.30 795.00 13.39 0.00 0.40 323.36 1.20 388.03
47+600 47+980 380.00 5.30 2,014.00 47.71 62.44 1.00 2,124.14 1.20 2,548.97
48+880 49+120 240.00 5.30 1,272.00 78.88 0.00 0.40 540.35 1.20 648.42
49+700 50+460 760.00 5.30 4,028.00 83.72 124.88 0.40 1,694.64 1.20 2,033.57
50+780 51+040 260.00 5.30 1,378.00 71.91 62.44 1.00 1,512.34 1.20 1,814.81
54+500 54+700 200.00 5.30 1,060.00 32.65 62.44 0.40 462.04 1.20 554.44
55+500 56+000 500.00 5.30 2,650.00 74.58 62.44 0.40 1,114.81 1.20 1,337.77
56+500 57+000 500.00 5.30 2,650.00 80.40 62.44 0.40 1,117.13 1.20 1,340.56
57+000 57+845 845.00 5.30 4,478.50 48.68 124.88 0.40 1,860.82 1.20 2,232.99
8,475.00 1,588.70 1,123.88 25,480.71 M3

01.01.03 CARGUIO DE MATERIAL OVER PARA MEJORAMIENTO

PROGRESIVA AREA
LONGITUD ANCHO AREA AREA SA VOL.MEJ.SR VOLUMEN
PLAZOLET ESPESOR (m) FAC. ESPONJ.
(m) (m) (m2) (m2) (m3) TOTAL (m3.)
DEL AL A (m2)

1+740 5+340 3,600.00 5.30 19,080.00 817.72 437.06 0.40 8,133.91 1.20 9,760.69
44+500 44+540 40.00 5.30 212.00 15.81 62.44 0.40 116.10 1.20 139.32
44+700 45+190 490.00 5.30 2,597.00 123.05 62.44 0.40 1,112.99 1.20 1,335.59
45+840 46+140 300.00 5.30 1,590.00 19.77 0.00 0.40 643.91 1.20 772.69
46+900 47+110 210.00 5.30 1,113.00 80.43 0.00 0.40 477.37 1.20 572.84
47+230 47+380 150.00 5.30 795.00 13.39 0.00 0.40 323.36 1.20 388.03
47+600 47+980 380.00 5.30 2,014.00 47.71 62.44 1.00 2,124.14 1.20 2,548.97
48+880 49+120 240.00 5.30 1,272.00 78.88 0.00 0.40 540.35 1.20 648.42
49+700 50+460 760.00 5.30 4,028.00 83.72 124.88 0.40 1,694.64 1.20 2,033.57
50+780 51+040 260.00 5.30 1,378.00 71.91 62.44 1.00 1,512.34 1.20 1,814.81
54+500 54+700 200.00 5.30 1,060.00 32.65 62.44 0.40 462.04 1.20 554.44
ADICIONAL DE OBRA N° 01
MEJORAMIENTO DE SUELOS CON OVER

OBRA: "CONSTRUCCIÓN DE LA CARRETERA LA JALCA - NUEVA ESPERANZA, DISTRITO DE LA JALCA, CHACHAPOYAS,


AMAZONAS"
55+500 56+000 500.00 5.30 2,650.00 74.58 62.44 0.40 1,114.81 1.20 1,337.77
56+500 57+000 500.00 5.30 2,650.00 80.40 62.44 0.40 1,117.13 1.20 1,340.56
57+000 57+845 845.00 5.30 4,478.50 48.68 124.88 0.40 1,860.82 1.20 2,232.99
8,475.00 1,588.70 1,123.88 25,480.71 M3

02.01.04 EXTENDIDO Y COMPACTADO DE OVER

PROGRESIVA AREA
LONGITUD ANCHO AREA AREA SA AREA TOTAL
PLAZOLET
(m) (m) (m2) (m2) (m2)
DEL AL A (m2)

1+740 5+340 3,600.00 5.30 19,080.00 817.72 437.06 20,334.78


44+500 44+540 40.00 5.30 212.00 15.81 62.44 290.25
44+700 45+190 490.00 5.30 2,597.00 123.05 62.44 2,782.49
45+840 46+140 300.00 5.30 1,590.00 19.77 0.00 1,609.77
46+900 47+110 210.00 5.30 1,113.00 80.43 0.00 1,193.43
47+230 47+380 150.00 5.30 795.00 13.39 0.00 808.39
47+600 47+980 380.00 5.30 2,014.00 47.71 62.44 2,124.14
48+880 49+120 240.00 5.30 1,272.00 78.88 0.00 1,350.88
49+700 50+460 760.00 5.30 4,028.00 83.72 124.88 4,236.60
50+780 51+040 260.00 5.30 1,378.00 71.91 62.44 1,512.34
54+500 54+700 200.00 5.30 1,060.00 32.65 62.44 1,155.09
55+500 56+000 500.00 5.30 2,650.00 74.58 62.44 2,787.02
56+500 57+000 500.00 5.30 2,650.00 80.40 62.44 2,792.84
57+000 57+845 845.00 5.30 4,478.50 48.68 124.88 4,652.06
8,475.00 1,588.70 1,123.88 47,630.07 M2
METRADO DE SOBRE ANCHOS
N° CURVA PI RADIO LONG.CURVA S/A ÁREA (M2)

PI-26 1+737.241 225.00 37.219 0.3 7.3

PI-27 1+791.011 30.00 20.524 0.9 12.0

PI-28 1+827.552 55.00 16.748 0.6 6.5

PI-29 1+856.078 20.00 16.973 1.2 13.2

PI-30 1+886.307 45.00 23.219 0.9 13.6

PI-31 1+925.215 46.95 18.816 0.6 7.3

PI-32 1+946.660 240.00 24.310 0.3 4.7

PI-33 2+169.576 28.24 33.055 0.9 19.3

PI-34 2+202.892 49.80 36.261 0.6 14.1

PI-35 2+281.328 280.00 104.231 0.3 20.3

PI-36 2+428.783 170.00 69.409 0.3 13.5

PI-37 2+680.249 270.00 57.639 0.3 11.2

PI-38 2+741.804 120.00 25.177 0.3 4.9

PI-39 2+785.841 35.00 24.750 0.9 14.5

PI-40 2+868.624 30.00 49.640 0.9 29.0

PI-41 2+945.049 50.00 27.241 0.6 10.6

PI-42 3+001.513 14.43 19.988 1.5 19.5

PI-43 3+019.971 11.87 17.129 1.8 20.0

PI-44 3+071.843 25.00 39.619 1.2 30.9

PI-45 3+132.197 95.00 30.228 0.6 11.8

PI-46 3+200.039 50.00 36.450 0.6 14.2

PI-47 3+305.988 75.00 53.329 0.6 20.8

PI-48 3+414.605 20.00 29.618 1.2 23.1

PI-49 3+481.646 30.00 37.807 0.9 22.1

PI-50 3+578.174 18.00 20.848 1.2 16.3

PI-51 3+612.321 53.71 21.471 0.6 8.4

PI-52 3+637.077 26.10 25.956 0.9 15.2

PI-53 3+710.399 20.00 33.591 1.2 26.2

PI-54 3+754.824 90.04 28.652 0.6 11.2

PI-55 3+783.970 60.00 29.288 0.6 11.4

PI-56 3+813.851 40.99 29.698 0.9 17.4

PI-57 3+847.261 30.00 22.945 0.9 13.4

PI-58 3+880.134 70.00 21.466 0.6 8.4

PI-59 3+921.449 60.00 33.825 0.6 13.2

PI-60 4+027.627 125.00 42.796 0.3 8.3

PI-61 4+100.570 50.00 26.678 0.6 10.4

PI-62 4+133.448 100.00 21.847 0.6 8.5

PI-63 4+181.784 200.00 48.195 0.3 9.4

PI-64 4+265.322 40.00 28.075 0.9 16.4

PI-65 4+362.427 50.00 26.943 0.6 10.5

PI-66 4+477.959 100.00 28.301 0.6 11.0


METRADO DE SOBRE ANCHOS
N° CURVA PI RADIO LONG.CURVA S/A ÁREA (M2)

PI-67 4+526.596 120.00 36.529 0.3 7.1

PI-68 4+580.612 150.00 38.086 0.3 7.4

PI-69 4+670.704 50.00 57.902 0.6 22.6

PI-70 4+717.500 40.00 24.477 0.9 14.3

PI-71 4+834.304 25.00 24.592 1.2 19.2

PI-72 4+896.641 135.00 25.604 0.3 5.0

PI-73 4+954.270 29.79 39.775 0.9 23.3

PI-74 4+990.543 19.18 30.915 1.2 24.1

PI-75 5+074.151 100.00 39.129 0.6 15.3

PI-76 5+131.050 75.00 44.484 0.6 17.3

PI-77 5+176.845 25.00 24.810 1.2 19.4

PI-78 5+216.140 30.00 37.871 0.9 22.2

PI-79 5+256.217 30.00 31.335 0.9 18.3

PI-80 5+313.951 279.24 30.138 0.3 5.9

PI-81 5+350.346 60.00 41.007 0.6 16.0

SUB TOTAL DEL 1+740 AL 5+340 817.7


PI-916 44+512.990 25.51 27.029 0.90 15.81

SUB TOTAL DEL 44+500 AL 44+540 15.8


PI-918 44+730.124 100.00 35.425 0.60 13.82

PI-919 44+872.949 25.00 26.711 1.20 20.83

PI-920 44+908.258 16.33 14.889 1.50 14.52

PI-921 44+933.826 16.76 28.144 1.50 27.44

PI-922 44+996.603 25.00 32.885 1.20 25.65

PI-923 45+192.290 43.69 35.541 0.90 20.79

SUB TOTAL DEL 44+700 AL 45+190 123.0


PI-935 45+854.388 191.11 58.983 0.30 11.50

PI-936 45+907.954 191.18 42.410 0.30 8.27

PI-937 45+957.423 871.74 56.682 0.00 0.00

SUB TOTAL DEL 45+840 AL 46+140 19.8


PI-947 46+959.935 45.00 28.565 0.90 16.71

PI-948 47+006.316 19.02 20.101 1.2 15.68

PI-949 47+030.264 17.87 24.901 1.2 19.42

PI-950 47+050.659 18.64 19.040 1.2 14.85

PI-951 47+071.894 25.97 23.527 0.9 13.76

SUB TOTAL DEL 46+900 AL 47+110 80.4


PI-954 47+264.946 120.00 68.670 0.3 13.39

SUB TOTAL DEL 47+230 AL 47+380 13.4


PI-958 47+661.529 70.00 58.952 0.6 22.99

PI-959 47+747.925 465.00 47.725 0.3 9.31

PI-960 47+941.277 60.00 39.511 0.6 15.41

SUB TOTAL DEL 47+600 AL 47+980 47.7


METRADO DE SOBRE ANCHOS
N° CURVA PI RADIO LONG.CURVA S/A ÁREA (M2)
PI-973 48+912.144 75.00 63.650 0.6 24.82

PI-974 49+003.544 36.46 41.317 0.9 24.17

PI-975 49+054.035 114.81 63.103 0.3 12.31

PI-976 49+118.385 40.00 30.049 0.9 17.58

SUB TOTAL DEL 48+880 AL 49+120 78.9


PI-984 49+824.421 45.00 36.424 0.9 21.31

PI-985 49+887.539 41.20 40.649 0.9 23.78

PI-986 49+935.599 316.03 58.953 0.3 11.50

PI-987 50+008.023 325.00 73.506 0.30 14.33

PI-988 50+266.934 450.00 65.679 0.30 12.81

SUB TOTAL DEL 49+700 AL 50+460 83.7


PI-994 50+854.242 70.00 95.576 0.60 37.27

PI-995 50+937.987 45.00 59.199 0.90 34.63

SUB TOTAL DEL KM 50+780 AL KM 51+040 71.9


PI-1022 54+515.603 360.00 74.751 0.30 14.58

PI-1023 54+624.076 150.00 42.871 0.30 8.36

PI-1024 54+712.868 265.71 49.828 0.30 9.72

SUB TOTAL DEL 54+500 AL 54+700 32.7


PI-1031 55+509.561 85.00 33.251 0.60 12.97

PI-1032 55+749.298 85.00 24.828 0.60 9.68

PI-1033 55+802.517 60.00 30.398 0.60 11.86

PI-1034 55+835.602 40.00 22.274 0.90 13.03

PI-1035 55+883.087 60.00 19.713 0.60 7.69

PI-1036 55+933.418 35.00 20.198 0.90 11.82

PI-1037 55+988.572 50.91 19.334 0.60 7.54

SUB TOTAL DEL 55+500 AL 56+000 74.6


PI-1044 56+656.065 35.00 26.856 0.90 15.71

PI-1045 56+698.162 70.00 22.266 0.60 8.68

PI-1046 56+747.732 60.00 25.974 0.60 10.13

PI-1047 56+789.911 35.00 22.379 0.90 13.09

PI-1048 56+844.538 99.03 66.426 0.60 25.91

PI-1049 56+894.184 132.33 35.264 0.30 6.88

SUB TOTAL DEL 56+500 AL 57+000 80.4


PI-1050 57+041.724 200.00 150.582 0.30 29.36

PI-1051 57+446.070 160.00 99.078 0.30 19.32

SUB TOTAL DEL 57+000 AL 57+845 48.7


METRADO DE PLAZOLETAS
UBICACIÓN
N° LONGITUD (m) ANCHO (m) AREA (m2)
INICIO FINAL
4 2+090 2+120 30.00 2.25 62.44
5 2+620 2+650 30.00 2.25 62.44
6 3+150 3+180 30.00 2.25 62.44
7 3+680 3+710 30.00 2.25 62.44
8 4+210 4+240 30.00 2.25 62.44
9 4+740 4+770 30.00 2.25 62.44
10 5+270 5+300 30.00 2.25 62.44
SUB TOTAL DEL 1+740 AL 5+340 437.06

84 44+490 44+520 30.00 2.25 62.44


SUB TOTAL DEL 44+500 AL 44+540 62.44

85 45+020 45+050 30.00 2.25 62.44


SUB TOTAL DEL 44+700 AL 45+190 62.44

90 47+670 47+700 30.00 2.25 62.44


SUB TOTAL DEL 47+600 AL 47+980 62.44

94 49+790 49+820 30.00 2.25 62.44


95 50+320 50+350 30.00 2.25 62.44
SUB TOTAL DEL 49+700 AL 50+460 124.88

96 0+500 0+530 30.00 2.25 62.44


50+780 - 51+040 62.4

103 0+500 0+530 30.00 2.25 62.44


SUB TOTAL DEL 54+500 AL 54+700 62.44

105 55+620 55+650 30.00 2.25 62.44


SUB TOTAL DEL 55+500 AL 56+000 62.44

107 56+680 56+710 30.00 2.25 62.44


SUB TOTAL DEL 56+500 AL 57+000 62.44

108 57+210 57+240 30.00 2.25 62.44


109 57+740 57+770 30.00 2.25 62.44
SUB TOTAL DEL 57+000 AL 57+845 124.88
CALCULO DE DISTANCIA MEDIA PARA MEJORAMIENTO

PROYECTO: CONSTRUCCION DE LA CARRETERA LA JALCA - NUEVA ESPERANZA, DISTRITO DE LA


JALCA, CHACHAPOYAS, AMAZONAS

VOLUMEN VOLUMEN CENTRO DE DISTANCIA MOMENTO DE


UBICACIÓN
CANTERA ACCESO RELLENO ESPESOR RELLENO TOTAL GRAVEDAD MEDIA TRANSPORTE
Km Km Chinchinya KM M2 M. M3 M3 KM KM M3-KM

01+740 05+340 00+200.00 3.34 20,334.78 0.40 8,133.91 8,133.91 3.54 6.68 54,334.53

20,334.78 8,133.91 8,133.91 54,334.53

DISTANCIA MEDIA TOTAL = 6.68 Km

TOTAL M3-KM = 54,334.53


TOTLA M3-KM TRANSPORTADO = 9,760.69
TRANSPORTE MATERIAL PARA MEJORAMIENTO CON OVER DM=6.68 KM

4.- TRANSPORTE
Distancia Media 6.68 km capacidad de volquete 15.00 m3

Velocidades promedio 10.00 km/h 15.00 km/h

Tiempo de carga 3.30 min Num. De Volquetes 5.00

tiempo de descarga 3.00 min Tiempo util 432.00 min/dia

Tiempo de recorrido cargado 40.08 min Numero de viajes 5.91

tiempo de recorrido descargado 26.72 min Volumen transportado 443.00 m3/dia

ciclo 73.10 min Rendimiento m3/km 2,466.03 m3/dia


Eficiencia 90.00 %
TRANSPORTE MATERIAL PARA MEJORAMIENTO CON OVER DM=6.68 KM
COSTO POR TRANSPORTE
Rendimiento: 443.00 m3/día horas/ día 8.00

Mano de obra unidad cantidad P.U. parcial total


1.00 Oficial hh 0.0181 15.90 0.29 0.29

Equipo
5.00 Camión volquete 15 m3 hm 0.0903 180.00 16.25 16.25
costo unitario 16.54
CALCULO DE DISTANCIA MEDIA PARA MEJORAMIENTO

PROYECTO: CONSTRUCCION DE LA CARRETERA LA JALCA - NUEVA ESPERANZA, DISTRITO DE LA


JALCA, CHACHAPOYAS, AMAZONAS

VOLUMEN VOLUMEN CENTRO DE DISTANCIA MOMENTO DE


UBICACIÓN
CANTERA ACCESO RELLENO ESPESOR RELLENO TOTAL GRAVEDAD MEDIA TRANSPORTE
Km Km KM M2 M. M3 M3 KM KM M3-KM

44+500 44+540 290.25 0.40 116.10 116.10 44.52 3.98 462.08


44+700 45+190 2,782.49 0.40 1,112.99 1,112.99 44.95 3.56 3,956.70
45+840 46+140 1,609.77 0.40 643.91 643.91 45.99 2.51 1,616.21
46+900 47+110 1,193.43 0.40 477.37 477.37 47.01 1.50 713.67
47+230 47+380 808.39 0.40 323.36 323.36 47.31 1.20 386.41
47+600 47+980 47+500.00 1.00 2,124.14 1.00 2,124.14 2,124.14 47.79 1.29 2,740.15
48+880 49+120 1,350.88 0.40 540.35 540.35 49.00 2.50 1,350.88
49+700 50+460 4,236.60 0.40 1,694.64 1,694.64 50.08 3.58 6,066.81
50+780 51+040 1,512.34 1.00 1,512.34 1,512.34 50.91 4.41 6,669.44

15,908.29 8,545.21 8,545.21 23,962.33

VOLUMEN VOLUMEN CENTRO DE DISTANCIA MOMENTO DE


UBICACIÓN
CANTERA ACCESO RELLENO ESPESOR RELLENO TOTAL GRAVEDAD MEDIA TRANSPORTE
Km Km Nueva Luz KM M2 M. M3 M3 KM KM M3-KM

54+500 54+700 1,155.09 0.40 462.04 462.04 54.60 3.85 1,776.53


55+500 56+000 2,787.02 0.40 1,114.81 1,114.81 55.75 2.70 3,004.41
56+500 57+000 2,792.84 0.40 1,117.13 1,117.13 56.75 1.70 1,893.54
57+000 57+845 57+845.00 0.60 4,652.06 0.40 1,860.82 1,860.82 57.42 1.02 1,902.69

11,387.00 4,554.80 4,554.80 8,577.17

DISTANCIA MEDIA TOTAL = 2.48 Km

TOTAL M3-KM = 32,539.50


TOTLA M3-KM TRANSPORTADO = 15,720.01
TRANSPORTE MATERIAL PARA MEJORAMIENTO CON OVER DM=2.48 KM

4.- TRANSPORTE
Distancia Media 2.48 km capacidad de volquete 15.00 m3

Velocidades promedio 10.00 km/h 15.00 km/h

Tiempo de carga 3.30 min Num. De Volquetes 5.00

tiempo de descarga 3.00 min Tiempo util 432.00 min/dia

Tiempo de recorrido cargado 14.90 min Numero de viajes 13.87

tiempo de recorrido descargado 9.94 min Volumen transportado 1040.00 m3/dia

ciclo 31.14 min Rendimiento m3/km 2,152.74 m3/dia


Eficiencia 90.00 %
TRANSPORTE MATERIAL PARA MEJORAMIENTO CON OVER DM=2.48 KM
COSTO POR TRANSPORTE
Rendimiento: 1040.00 m3/día horas/ día 8.00

Mano de obra unidad cantidad P.U. parcial total


1.00 Oficial hh 0.0077 15.90 0.12 0.12

Equipo
5.00 Camión volquete 15 m3 hm 0.0385 180.00 6.93 6.93
costo unitario 7.05