1.3 SOBREACARREO DE MATERIAL. FACTOR EXPANSIÓN 20% M3/KM 3,373.63 $ 1,426.72 $ 6,305,325.27 1.49% 11/14/2020 11/24/2020 11.00
2.2 SOBREACARREO DE MATERIAL. FACTOR EXPANSIÓN 20% M3/KM 4,123.23 $ 1,426.72 $ 7,706,316.87 1.82% 11/17/2020 11/24/2020 8.00
2.6 PIEDRA PEGADA CONCRETO 3000 PSI E=0,15M M3 230.93 $ 88,945.80 $ 26,907,732.67 6.36% 12/26/2020 2/14/2021 38.00
2.7 CONCRETO VIGA CIMENTACIÓN 20.7 MPA (3000 PSI) NO INCLUYE HIERRO M3 21.52 $ 698,986.26 $ 19,701,598.75 4.66% 1/12/2021 2/14/2021 34.00
3.1 CONCRETO 13.8 MPA (2000 PSI) SOLADO, CONCRETO DE LIMPIEZA M3 2.11 $ 438,251.91 $ 1,209,075.66 0.29% 1/29/2021 2/1/2021 4.00
3.2 CONCRETO 20.7 MPA (3000 PSI) BOX, ALETAS, MUROS ARMADOS M3 16.99 $ 748,177.86 $ 16,647,219.31 3.93% 2/1/2021 2/16/2021 16.00
3.3 CONCRETO CICLÓPEO 21 MPA (3000 PSI) RELACIÓN 60C/40P M3 11.72 $ 497,080.92 $ 7,628,526.84 1.80% 1/31/2021 2/14/2021 15.00
N.P 3.6.1 EXCAVACION MANUAL EN CONGLOMERADO H= 0 - 2.00 M INCLUYE CARGUE M3 12.73 $ 61,603.00 $ 1,027,104.32 0.24% 1/27/2021 1/30/2021 4.00
N.P 3.6.2 DEMOLICION CIMIENTO ENTERRADO. INCLUYE TRASIEGO Y CARGUE MANUAL. M3 19.61 $ 329,081.00 $ 8,451,639.24 2.00% 1/27/2021 1/30/2021 4.00
Elaboro; Ing. JEFERSON STEVEN RODRIGUEZ Reviso;R/L. ING.ROLAN GIOVANNY MORALES Avaló;R/L. ING.ALEXANDRA TORRES GARZON
Residente Obra Representante legal Directora de Interventoria
12 OCTUBRE - 18 OCTUBRE 19 OCTUBRE - 25 OCTUBRE 26 OCTUBRE - 01 NOVIEMBRE 2 NOVIEMBRE - 8 NOVIEMBRE 9 NOVIEMBRE - 15 NOVIEMBRE
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10
SÁB. DOM LUN MAR MIÉ JUE VIE. SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN MAR.
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37
12 OCTUBRE - 18 OCTUBRE 19 OCTUBRE - 25 OCTUBRE 26 OCTUBRE - 01 NOVIEMBRE 2 NOVIEMBRE - 8 NOVIEMBRE 9 NOVIEMBRE - 15 NOVIEMBRE
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10
SÁB. DOM LUN MAR MIÉ JUE VIE. SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN MAR.
FECHA DE INCIO 7 DE OCTUBRE 2020 TIEMPO EJECUCION
1.3 SOBREACARREO DE MATERIAL. FACTOR EXPANSIÓN 20% M3/KM 3,373.63 $ 1,426.72 $ 6,305,325.27 11.00 $ 0.00 $ 0.00
2.2 SOBREACARREO DE MATERIAL. FACTOR EXPANSIÓN 20% M3/KM 4,123.23 $ 1,426.72 $ 7,706,316.87 8.00 $ 0.00 $ 0.00
2.6 PIEDRA PEGADA CONCRETO 3000 PSI E=0,15M M3 230.93 $ 88,945.80 $ 26,907,732.67 38.00 $ 0.00 $ 0.00
3 OBRAS DE DRENAJE
4 SEÑALIZACION VIAL
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
TOTAL TOTAL TOTAL
SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
TOTAL TOTAL TOTAL
SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
TOTAL TOTAL TOTAL
SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN MAR. MIÉ. JUE. VIE. SÁB. DOM LUN
$ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00
VR. CONTRATO
$ 1,750,365,834.47
-$ 1,750,365,834.47
EJECUTADO - PRORROGA
MES VR. ACUMULADO % COSTO ACUMULADO %
OCTUBRE $ - 0.00% $ - 0.00%
NOVIEMBRE $ 122,525,608.37 7.00% $ 122,525,608.37 7.00%
DICIEMBRE $ 242,717,508.19 13.87% $ 365,243,116.56 20.87%
ENERO $ 375,956,541.51 21.48% $ 741,199,658.07 42.35%
FEBRERO $ - 0.00% 0.00%
TOTAL $ 741,199,658.07 42.35%