CRONOGRAMA VALORIZADO

PROYECTO

IOARR
UNIDAD EJECUTORA

PRESUPUESTO DEL EXPEDIENTE TECNICO MES 01 MES 02 MES 03 MES 04


ITEM DESCRIPCION UND
METRADO PRECIO (S/) PARCIAL (S/) PARCIAL % PARCIAL % PARCIAL % PARCIAL %
MODULO 01 PRIMER PISO S/ 54,200.54 S/ 12,311.90 22.72% S/ 19,201.02 35.43% S/ 13,979.58 25.79% S/ 8,708.04 16.07%
01 OBRAS PRELIMINARES 2,046.50 S/ 1,146.50 56.02% S/ 300.00 14.66% S/ 300.00 14.66% S/ 300.00 14.66%
01.01 ALQUILER DE ALMACEN Y GUARDIANIA mes 4.00 300.00 1,200.00 S/ 300.00 25.00% S/ 300.00 25.00% S/ 300.00 25.00% S/ 300.00 25.00%
01.02 CARTEL DE OBRA und 1.00 846.50 846.50 S/ 846.50 100.00% 0.00% 0.00% 0.00%
02 SEGURIDAD Y SALUD 12,435.00 S/ 6,495.00 52.23% S/ 1,980.00 15.92% S/ 1,980.00 15.92% S/ 1,980.00 15.92%
02.01 SEGURIDAD Y SALUD EN EL TRABAJO 2,576.00 S/ 2,576.00 100.00% 0.00% 0.00% 0.00%
EQUIPOS DE PORTECCION INDIVIDUAL
02.01.01 GLB 1.00 2,386.00 2,386.00 S/ 2,386.00 100.00% 0.00% 0.00% 0.00%
SEÑALIZACION TEMPORAL DE SEGURIDAD
02.01.02 GLB 1.00 190.00 190.00 S/ 190.00 100.00% 0.00% 0.00% 0.00%
02.02 RECURSOS ANTE EMERGENCIA COVID 19 9,859.00 S/ 3,919.00 39.75% S/ 1,980.00 20.08% S/ 1,980.00 20.08% S/ 1,980.00 20.08%
02.02.01 ADECUACION DE AMBIENTES, CONTROL Y VESTUARIOS m2 3.00 300.00 900.00 S/ 225.00 25.00% S/ 225.00 25.00% S/ 225.00 25.00% S/ 225.00 25.00%
02.02.02 EQUIPO DE PROTECCION PERSONAL DE BIOSEGURIDAD und 18.00 40.00 720.00 S/ 720.00 100.00% 0.00% 0.00% 0.00%
02.02.03 EQUIPO Y MATERIALES DE BIOSEGURIDAD GLB 1.00 1,219.00 1,219.00 S/ 1,219.00 100.00% 0.00% 0.00% 0.00%
02.02.04 SERVICIO DE CONTROL EN SEGURIDAD Y SALUD mes 4.00 1,755.00 7,020.00 S/ 1,755.00 25.00% S/ 1,755.00 25.00% S/ 1,755.00 25.00% S/ 1,755.00 25.00%
03 TRABAJOS PRELIMINARES 3,467.19 S/ 3,467.19 100.00% 0.00% 0.00% 0.00%
03.01 LIMPIEZA DE TERRENO MANUAL m2 530.15 0.77 408.22 S/ 408.22 100.00% 0.00% 0.00% 0.00%
03.02 TRAZO NIVELES Y REPLANTEO PRELIMINAR m2 530.15 5.77 3,058.97 S/ 3,058.97 100.00% 0.00% 0.00% 0.00%
04 MOVIMIENTO DE TIERRAS 932.33 S/ 932.33 100.00% 0.00% 0.00% 0.00%
04.01 DESMONTAJE DE APARATOS SANITARIOS und 4.00 24.38 97.52 S/ 97.52 100.00% 0.00% 0.00% 0.00%
04.02 DEMOLICIÓN DE EST. DE CONCRETO ARMADO m3 14.78 22.76 336.39 S/ 336.39 100.00% 0.00% 0.00% 0.00%
04.03 ELIMINACION DE MATERIAL EXCEDENTE D (PROM)=30 M m3 18.78 26.54 498.42 S/ 498.42 100.00% 0.00% 0.00% 0.00%
05 ARQUITECTURA 22,645.58 S/ 270.88 1.20% S/ 6,037.85 26.66% S/ 11,699.58 51.66% S/ 4,637.27 20.48%
05.01 MUROS Y TABIQUES DE ALBAÑILERIA 270.88 S/ 270.88 100.00% S/ - 0.00% 0.00% 0.00%
05.01.01 MUROS DE LADRILLO K.K. DE ARCILLA 14x24x9 DE SOGA m2 2.93 92.45 270.88 S/ 270.88 100.00% S/ - 0.00% 0.00% 0.00%
05.02 REVOQUES ENLUCIDOS Y MOLDURAS 145.84 0.00% S/ 145.84 100.00% 0.00% 0.00%
05.02.01 TARRAJEO EN INTERIORES CEMENTO-ARENA (MORTERO 1:5) m2 5.85 24.93 145.84 0.00% S/ 145.84 100.00% 0.00% 0.00%
05.03 PISOS Y PAVIMENTOS 6,279.73 0.00% S/ 5,892.01 93.83% S/ 387.72 6.17% 0.00%
05.03.01 PISO DE CERAMICO 45x45 cm ANTIDESLIANTE m2 13.30 60.02 798.27 0.00% S/ 410.55 51.43% S/ 387.72 48.57% 0.00%
05.03.02 PISO PORCELANATO DE 60X60cm DE ALTO TRANSITO-AULAS-DEPOSITOS m2 56.32 64.26 3,619.12 0.00% S/ 3,619.12 100.00% 0.00% 0.00%
05.03.03 CONTRAPISO DE 5cm m2 69.62 26.75 1,862.34 0.00% S/ 1,862.34 100.00% 0.00% 0.00%
05.04 ZOCALOS Y CONTRAZOCALOS 2,722.35 0.00% 0.00% S/ 2,722.35 100.00% 0.00%
05.04.01 CONTRAZOCALO CERAMICO DE 40X40cm H=10cm, INTERIOR m 34.12 14.14 482.46 0.00% 0.00% S/ 482.46 100.00% 0.00%
05.04.02 ZOCALO DE CERAMICO 45X45cm H=1.80m EN MUROS m2 43.35 51.67 2,239.89 0.00% 0.00% S/ 2,239.89 100.00% 0.00%
05.05 PINTURA 13,226.78 0.00% 0.00% S/ 8,589.51 64.94% S/ 4,637.27 35.06%
05.05.01 PINTURA EN MUROS INTERIORES m2 587.92 14.61 8,589.51 0.00% 0.00% S/ 8,589.51 100.00% S/ - 0.00%
05.05.02 PINTURA EN MUROS EXTERIORES AL LATEX m2 259.67 14.61 3,793.78 0.00% 0.00% 0.00% S/ 3,793.78 100.00%
05.05.03 PINTURA EN PUERTAS DE MADERA CON BARNIZ m2 69.48 12.14 843.49 0.00% 0.00% 0.00% S/ 843.49 100.00%
06 INSTALACIONES SANITARIAS 1,790.77 0.00% 0.00% 0.00% S/ 1,790.77 100.00%
06.01 APARATOS SANITARIOS 1,349.38 0.00% 0.00% 0.00% S/ 1,349.38 100.00%
06.01.01 APARATOS Y ACCESORIOS SANITARIOS 1,349.38 0.00% 0.00% 0.00% S/ 1,349.38 100.00%
06.01.01.01 LAVATORIO DE LOSA BLANCA DE PRIMERA CALIDAD DE 545X460mm und 4.00 151.98 607.92 0.00% 0.00% 0.00% S/ 607.92 100.00%
06.01.01.02 ESPEJO und 1.00 78.16 78.16 0.00% 0.00% 0.00% S/ 78.16 100.00%
06.01.01.03 BARRA DE APOYO DISCAPACITADOS und 1.00 663.30 663.30 0.00% 0.00% 0.00% S/ 663.30 100.00%
06.02 SISTEMA DE DESAGUE Y VENTILACION 441.39 0.00% 0.00% 0.00% S/ 441.39 100.00%
06.02.01 DESINFECCION Y LIMPIEZA DE LA RED COLECTORA GLB 1.00 441.39 441.39 0.00% 0.00% 0.00% S/ 441.39 100.00%
07 INSTALACIONES ELECTRICAS 1,860.87 0.00% S/ 1,860.87 100.00% 0.00% 0.00%
07.01 SALIDA PARA INTERRUPTORES 161.10 0.00% S/ 161.10 100.00% 0.00% 0.00%
07.01.01 SALIDA PARA INTERRUPTORES DOBLES pto 5.00 32.22 161.10 0.00% S/ 161.10 100.00% 0.00% 0.00%
07.02 SALIDA PARA TOMACORRIENTES DOBLES 976.74 0.00% S/ 976.74 100.00% 0.00% 0.00%
07.02.01 SALIDA PARA TOMACORRIENTES DOBLES pto 6.00 162.79 976.74 0.00% S/ 976.74 100.00% 0.00% 0.00%
07.03 LUMINARIAS 193.03 0.00% S/ 193.03 100.00% 0.00% 0.00%
07.03.01 LUZ DE EMERGENCIA/AUTONOMIA 1.5 HORAS/2x55w/900LM pza 1.00 193.03 193.03 0.00% S/ 193.03 100.00% 0.00% 0.00%
07.04 PRUEBA ELECTRICA 530.00 0.00% S/ 530.00 100.00% 0.00% 0.00%
07.04.01 PRUEBAS DE AISLAMIENTO, RESISTIVIDAD E ILUMINANCIA GLB 1.00 530.00 530.00 0.00% S/ 530.00 100.00% 0.00% 0.00%
08 SISTEMAS ESPECIALES 9,022.30 0.00% S/ 9,022.30 100.00% 0.00% 0.00%
08.01 TABLERO GENERAL TG-01 pza 1.00 1,135.45 1,135.45 0.00% S/ 1,135.45 100.00% 0.00% 0.00%
08.02 TABLERO DE DISTRIBUCION und 1.00 816.25 816.25 0.00% S/ 816.25 100.00% 0.00% 0.00%
08.03 MEDIDOR DE ENERGIA TRIFASICO 15 100A TKL und 1.00 880.00 880.00 S/ 880.00 100.00%
08.04 SISTEMA PARARRAYO und 1.00 4,998.20 4,998.20 0.00% S/ 4,998.20 100.00% 0.00% 0.00%
08.05 SISTEMA DE PUESTA A TIERRA und 1.00 1,192.40 1,192.40 0.00% S/ 1,192.40 100.00% 0.00% 0.00%
MODULO 02 SEGUNDO PISO S/ 43,088.73 S/ 814.82 1.89% S/ 8,913.63 20.69% S/ 17,497.37 40.61% S/ 15,862.91 36.81%
09 ESTRUCTURAS 4,965.11 S/ 814.82 16.41% S/ 4,150.29 83.59% 0.00% 0.00%
09.01 LOSAS ALIGERADAS 4,965.11 S/ 814.82 16.41% S/ 4,150.29 83.59% 0.00% 0.00%
09.01.01 CONCRETO F'C= 210 KG/CM2 EN LOSAS ALIGERADAS m3 3.04 435.02 1,322.46 0.00% S/ 1,322.46 100.00% 0.00% 0.00%
09.01.02 ENCOFRADO Y DESENCOFRADO EN LOSAS ALIGERADAS m2 15.22 48.16 733.00 0.00% S/ 733.00 100.00% 0.00% 0.00%
PRESUPUESTO DEL EXPEDIENTE TECNICO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION UND
METRADO PRECIO (S/) PARCIAL (S/) PARCIAL % PARCIAL % PARCIAL % PARCIAL %
09.01.03 ACERO Fy=4200 KG/CM2 GRADO 60 EN LOSAS ALIGERADAS kg 445.99 5.22 2,328.07 S/ 814.82 35.00% S/ 1,513.25 65.00% 0.00% 0.00%
09.01.04 LADRILLO HUECO/ARCILLA 12X30X30 P/TECHO ALIGERADO und 162.00 3.59 581.58 0.00% S/ 581.58 100.00% 0.00% 0.00%
10 ARQUITECTURA 31,883.31 0.00% S/ 4,763.34 14.94% S/ 17,497.37 54.88% S/ 9,622.60 30.18%
10.01 PISOS Y PAVIMENTOS 13,162.59 0.00% S/ 4,763.34 36.19% S/ 8,399.25 63.81% 0.00%
10.01.01 PISO DE CERAMICO 45x45 cm ANTIDESLIANTE m2 14.59 60.02 875.69 0.00% 0.00% S/ 875.69 100.00% 0.00%
10.01.02 PISO PORCELANATO DE 60X60cm DE ALTO TRANSITO-AULAS-DEPOSITOS m2 117.08 64.26 7,523.56 0.00% 0.00% S/ 7,523.56 100.00% 0.00%
10.01.03 CONTRAPISO DE 5cm m2 131.67 26.75 3,522.17 0.00% S/ 3,522.17 100.00% 0.00% 0.00%
10.01.04 FALSO PISO DE 8" CONCRETO 1:8 m2 14.59 85.07 1,241.17 0.00% S/ 1,241.17 100.00%
10.02 ZOCALOS Y CONTRAZOCALOS 3,299.39 0.00% 0.00% S/ 3,299.39 100.00% 0.00%
10.02.01 ZOCALO DE CERAMICO 45X45cm H=1.80m EN MUROS m2 32.80 51.67 1,694.78 0.00% 0.00% S/ 1,694.78 100.00% 0.00%
10.02.02 CONTRAZOCALO CERAMICO DE 40X40cm H=10cm, INTERIOR m 113.48 14.14 1,604.61 0.00% 0.00% S/ 1,604.61 100.00% 0.00%
10.03 CARPINTERIA METALICA 2,344.64 0.00% 0.00% 0.00% S/ 2,344.64 100.00%
10.03.01 BARANDA METALICA DE F°G° (SEGUN DISEÑO) m 11.40 205.67 2,344.64 0.00% 0.00% 0.00% S/ 2,344.64 100.00%
10.04 PINTURA 13,076.69 0.00% 0.00% S/ 5,798.73 44.34% S/ 7,277.96 55.66%
10.04.01 PINTURA EN MUROS INTERIORES m2 664.53 14.61 9,708.78 0.00% 0.00% S/ 5,798.73 59.73% S/ 3,910.05 40.27%
10.04.02 PINTURA EN MUROS EXTERIORES AL LATEX m2 175.91 14.61 2,570.05 0.00% 0.00% 0.00% S/ 2,570.05 100.00%
10.04.03 PINTURA EN PUERTAS DE MADERA CON BARNIZ m2 38.28 17.54 671.43 0.00% 0.00% 0.00% S/ 671.43 100.00%
10.04.04 PINTURA EN CARPINTERIA METALICA m2 11.40 11.09 126.43 0.00% 0.00% 0.00% S/ 126.43 100.00%
11 INSTALACIONES SANITARIAS 4,029.97 0.00% 0.00% 0.00% S/ 4,029.97 100.00%
11.01 APARATOS SANITARIOS 2,254.27 0.00% 0.00% 0.00% S/ 2,254.27 100.00%
11.01.01 INODORO TANQUE BAJO LOSA und 5.00 312.77 1,563.85 0.00% 0.00% 0.00% S/ 1,563.85 100.00%
11.01.02 LAVATORIO DE LOSA BLANCA DE PRIMERA CALIDAD DE 545X460mm und 3.00 151.98 455.94 0.00% 0.00% 0.00% S/ 455.94 100.00%
11.01.03 ESPEJO und 3.00 78.16 234.48 0.00% 0.00% 0.00% S/ 234.48 100.00%
11.02 SISTEMA DE DESAGUE Y VENTILACION 1,775.70 0.00% S/ 1,775.70 100.00% 0.00% 0.00%
11.02.01 SALIDA DE VENTILACION DE 2" pto 8.00 59.03 472.24 0.00% S/ 472.24 100.00% 0.00% 0.00%
11.02.02 SALIDA DE DESAGUE EN PVC DE 4" pto 5.00 33.51 167.55 0.00% S/ 167.55 100.00% 0.00% 0.00%
11.02.03 SALIDA DE DESAGUE EN PVC DE 2" pto 5.00 31.41 157.05 0.00% S/ 157.05 100.00% 0.00% 0.00%
11.02.04 RED DE DISTRIBUCION TUBERIA PVC SAP 4" m 23.60 25.89 611.00 0.00% S/ 611.00 100.00% 0.00% 0.00%
11.02.05 SUMIDEROS DE BRONCE 2" CON REJILLA Y TAPA ROSCADA pza 6.00 51.78 310.68 0.00% S/ 310.68 100.00% 0.00% 0.00%
11.02.06 REGISTRO ROSCASO DE BRONCE DE 2" und 6.00 9.53 57.18 0.00% S/ 57.18 100.00% 0.00% 0.00%
12 INSTALACIONES ELECTRICAS 2,210.34 0.00% 0.00% 0.00% S/ 2,210.34 100.00%
12.01 TABLERO DE DISTRIBUCION und 1.00 1,101.25 1,101.25 0.00% 0.00% 0.00% S/ 1,101.25 100.00%
12.02 LUZ DE EMERGENCIA/AUTONOMIA 1.5 HORAS/2x55w/900LM pza 3.00 193.03 579.09 0.00% 0.00% 0.00% S/ 579.09 100.00%
12.03 PRUEBAS DE AISLAMIENTO, RESISTIVIDAD E ILUMINANCIA GLB 1.00 530.00 530.00 0.00% 0.00% 0.00% S/ 530.00 100.00%
MODULO 03 TERCER PISO S/ 251,256.99 S/ 5,403.97 2.15% S/ 66,091.82 26.30% S/ 96,717.57 38.49% S/ 83,043.63 33.05%
13 ESTRUCTURAS 62,767.83 S/ 2,528.97 4.03% S/ 59,500.96 94.80% S/ 737.90 1.18% 0.00%
13.01 LOSAS ALIGERADAS 4,965.11 0.00% S/ 4,965.11 100.00% 0.00% 0.00%
13.01.01 CONCRETO F'C= 210 KG/CM2 EN LOSAS ALIGERADAS m3 3.04 435.02 1,322.46 0.00% S/ 1,322.46 100.00% 0.00% 0.00%
13.01.02 ENCOFRADO Y DESENCOFRADO EN LOSAS ALIGERADAS m2 15.22 48.16 733.00 0.00% S/ 733.00 100.00% 0.00% 0.00%
13.01.03 ACERO Fy=4200 KG/CM2 GRADO 60 EN LOSAS ALIGERADAS kg 445.99 5.22 2,328.07 0.00% S/ 2,328.07 100.00% 0.00% 0.00%
13.01.04 LADRILLO HUECO/ARCILLA 12X30X30 P/TECHO ALIGERADO und 162.00 3.59 581.58 0.00% S/ 581.58 100.00% 0.00% 0.00%
13.02 ESTRUCTURAS METALICA Y COBERTURAS 57,802.72 S/ 2,528.97 4.38% S/ 54,535.85 94.35% S/ 737.90 1.28% 0.00%
13.02.01 ESTRUCTURAS METALICAS 28,900.00 S/ 2,528.97 8.75% S/ 26,371.03 91.25% 0.00% 0.00%
13.02.01.01 ESTRUCTURA METALICA PARA TECHO GLB 1.00 28,900.00 28,900.00 S/ 2,528.97 8.75% S/ 26,371.03 91.25% 0.00% 0.00%
13.02.02 COBERTURA 28,902.72 0.00% S/ 28,164.82 97.45% S/ 737.90 2.55% 0.00%
13.02.02.01 COBERTURA CON TEJA ANDINA m2 518.59 51.18 26,541.44 0.00% S/ 26,541.44 100.00% 0.00% 0.00%
13.02.02.02 CUMBRERA DE TEJA ANDINA m 57.55 41.03 2,361.28 0.00% S/ 1,623.38 68.75% S/ 737.90 31.25%
14 ARQUITECTURA 131,828.03 0.00% S/ 3,715.86 2.82% S/ 66,090.07 50.13% S/ 62,022.10 47.05%
14.01 PISOS Y PAVIMENTOS 34,344.82 0.00% S/ 3,715.86 10.82% S/ 29,752.62 86.63% S/ 876.34 2.55%
14.01.01 FALSO PISO DE 8" CONCRETO 1:8 m2 43.68 85.07 3,715.86 0.00% S/ 3,715.86 100.00% 0.00% 0.00%
14.01.02 CONTRAPISO DE 5cm m2 338.58 26.75 9,057.02 0.00% 0.00% S/ 9,057.02 100.00% 0.00%
14.01.03 PISO DE CERAMICO 45x45 cm ANTIDESLIANTE m2 43.68 60.02 2,621.67 0.00% 0.00% S/ 2,621.67 100.00% 0.00%
14.01.04 PISO PORCELANATO DE 60X60cm DE ALTO TRANSITO-AULAS-DEPOSITOS m2 294.90 64.26 18,950.27 0.00% 0.00% S/ 18,073.93 95.38% S/ 876.34 4.62%
14.02 CIELOS RASOS 23,854.78 0.00% 0.00% S/ - 0.00% S/ 23,854.78 100.00%
14.02.01 FALSO CIELO RASO CON BALDOSA DE FIBRA MINERAL DE 60X60 CM m2 368.46 54.56 20,103.18 0.00% S/ 20,103.18
14.02.02 CIELO RASO CON SISTEMA DRYWALL m2 83.00 45.20 3,751.60 0.00% 0.00% S/ - 0.00% S/ 3,751.60 100.00%
14.03 SISTEMA DRYWALL 36,991.05 0.00% 0.00% S/ 36,337.45 98.23% S/ 653.60 1.77%
14.03.01 TABIQUERIA DE DRYWALL DOS CARAS ESTRUCTURA METALICA CARA EXTERIOR CON SUPER m2 335.29 82.62 27,701.66 0.00% 0.00% S/ 27,701.66 100.00% 0.00%
14.03.02 TABIQUERIA DE DRYWALL DOS CARAS ESTRUCTURA METALICA CON PLACA RH SANITARIA e= m2 113.59 81.78 9,289.39 0.00% 0.00% S/ 8,635.79 92.96% S/ 653.60 7.04%
14.04 ZOCALOS Y CONTRAZOCALOS 8,267.71 0.00% 0.00% 0.00% S/ 8,267.71 100.00%
14.04.01 ZOCALO DE CERAMICO 45X45cm H=1.80m EN MUROS m2 109.90 51.67 5,678.53 0.00% 0.00% 0.00% S/ 5,678.53 100.00%
14.04.02 CONTRAZOCALO CERAMICO DE 40X40cm H=10cm, INTERIOR m 183.11 14.14 2,589.18 0.00% 0.00% 0.00% S/ 2,589.18 100.00%
14.05 PUERTAS 6,418.35 0.00% 0.00% 0.00% S/ 6,418.35 100.00%
14.05.01 PUERTA PREFABRICADA HDF CON MARCO 2.10X1.0 M und 15.00 327.05 4,905.75 0.00% 0.00% 0.00% S/ 4,905.75 100.00%
14.05.02 PUERTA PREFABRICADA HDF CON MARCO DE 2.10X0.90 M und 2.00 307.05 614.10 0.00% 0.00% 0.00% S/ 614.10 100.00%
14.05.03 PUERTAS PRINCIPALES, CON SISTEMA NOVA + INC. INSTA. und 2.00 449.25 898.50 0.00% 0.00% 0.00% S/ 898.50 100.00%
14.06 VENTANAS 7,581.23 0.00% 0.00% 0.00% S/ 7,581.23 100.00%
14.06.01 VENTANAS CON SISTEMA CORREDISO +INC. INST. m2 55.95 135.50 7,581.23 0.00% 0.00% 0.00% S/ 7,581.23 100.00%
14.07 PINTURA 14,370.09 0.00% 0.00% 0.00% S/ 14,370.09 100.00%
14.07.01 PINTURA EN MUROS INTERIORES m2 712.58 14.61 10,410.79 0.00% 0.00% 0.00% S/ 10,410.79 100.00%
PRESUPUESTO DEL EXPEDIENTE TECNICO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION UND
METRADO PRECIO (S/) PARCIAL (S/) PARCIAL % PARCIAL % PARCIAL % PARCIAL %
14.07.02 PINTURA EN MUROS EXTERIORES AL LATEX m2 185.28 14.61 2,706.94 0.00% 0.00% 0.00% S/ 2,706.94 100.00%
14.07.03 PINTURA EN PUERTAS DE MADERA CON BARNIZ m2 71.40 17.54 1,252.36 0.00% 0.00% 0.00% S/ 1,252.36 100.00%
15 INSTALACIONES SANITARIAS 14,414.06 0.00% 0.00% S/ 8,543.20 59.27% S/ 5,870.86 40.73%
15.01 APARATOS SANITARIOS 5,871.05 0.00% 0.00% 0.00% S/ 5,871.05 100.00%
15.01.01 APARATOS Y ACCESORIOS SANITARIOS 5,871.05 0.00% 0.00% 0.00% S/ 5,871.05 100.00%
15.01.01.01 INODORO TANQUE BAJO LOSA pza 4.00 312.77 1,251.08 0.00% 0.00% 0.00% S/ 1,251.08 100.00%
15.01.01.02 LAVATORIO DE LOSA BLANCA DE PRIMERA CALIDAD DE 545X460mm und 4.00 151.98 607.92 0.00% 0.00% 0.00% S/ 607.92 100.00%
15.01.01.03 URINARIO LINEAL ENCHAPADO DE MAYOLICA m 0.90 170.05 153.05 0.00% 0.00% 0.00% S/ 153.05 100.00%
15.01.01.04 URINARIO DE LOSACADET DE 310X460X680mm und 1.00 432.77 432.77 0.00% 0.00% 0.00% S/ 432.77 100.00%
15.01.01.05 LAVADERO DE ACERO INOXIDABLE TIPO I pza 1.00 673.77 673.77 0.00% 0.00% 0.00% S/ 673.77 100.00%
15.01.01.06 JABONERA, TOALLERA Y PAPELERA GLB 4.00 106.33 425.32 0.00% 0.00% 0.00% S/ 425.32 100.00%
15.01.01.07 ESPEJO und 4.00 79.16 316.64 0.00% 0.00% 0.00% S/ 316.64 100.00%
15.01.01.08 BARRA DE APOYO DISCAPACITADOS und 3.00 550.00 1,650.00 0.00% 0.00% 0.00% S/ 1,650.00 100.00%
15.01.01.09 COLOCACION DE PARATOS SANITARIOS und 10.00 36.05 360.50 0.00% 0.00% 0.00% S/ 360.50 100.00%
15.02 SISTEMA DE AGUA FRIA 2,084.79 0.00% 0.00% S/ 2,084.79 100.00% 0.00%
15.02.01 SALIDA DE AGUA FRIA TUB 1/2" pto 12.00 53.06 636.72 0.00% 0.00% S/ 636.72 100.00% 0.00%
15.02.02 RED DE DISTRIBUCION TUBERIA PVC SAP 1/2" m 22.78 20.89 475.87 0.00% 0.00% S/ 475.87 100.00% 0.00%
15.02.03 VALVULA DE COMPUERTA DE 1/2" CIM O SIMILAR und 5.00 42.73 213.65 0.00% 0.00% S/ 213.65 100.00% 0.00%
15.02.04 CAJA DE INSPECCION PARA VALVULAS DE AGUA FRIA und 5.00 45.51 227.55 0.00% 0.00% S/ 227.55 100.00% 0.00%
15.02.05 PRUEBA HIDRAULICA m 1.00 531.00 531.00 0.00% 0.00% S/ 531.00 100.00% 0.00%
15.03 SISTEMA DE DESAGUE Y VENTILACION 1,917.20 0.00% 0.00% S/ 1,917.20 100.00% 0.00%
15.03.01 SALIDA DE DESAGUE EN PVC DE 2" pto 8.00 31.41 251.28 0.00% 0.00% S/ 251.28 100.00% 0.00%
15.03.02 SALIDA DE DESAGUE EN PVC DE 4" pto 4.00 33.51 134.04 0.00% 0.00% S/ 134.04 100.00% 0.00%
15.03.03 SALIDA DE VENTILACION DE 2" pto 4.00 59.03 236.12 0.00% 0.00% S/ 236.12 100.00% 0.00%
15.03.04 RED DE DISTRIBUCION TUBERIA PVC SAP 4" m 35.84 25.89 927.90 0.00% 0.00% S/ 927.90 100.00% 0.00%
15.03.05 REGISTRO ROSCASO DE BRONCE DE 2" und 6.00 9.53 57.18 0.00% 0.00% S/ 57.18 100.00% 0.00%
15.03.06 SUMIDEROS DE BRONCE 2" CON REJILLA Y TAPA ROSCADA pza 6.00 51.78 310.68 0.00% 0.00% S/ 310.68 100.00% 0.00%
15.04 SISTEMA DE DRENAJE PLUVIAL 4,541.02 0.00% 0.00% S/ 4,541.02 100.00% 0.00%
15.04.01 ABRAZADERA DE FIJACION DE TUBERIA DE 3" und 12.00 26.51 318.12 0.00% 0.00% S/ 318.12 100.00% 0.00%
15.04.02 CANALETA DE EVACUACION PLUVIAL GALVANIZADA m 91.56 38.73 3,546.12 0.00% 0.00% S/ 3,546.12 100.00% 0.00%
15.04.03 TUBERIA DE BAJADA Y DISTRIBUCION DE PVC SAL 3" P/LLUVIAS m 38.00 17.81 676.78 0.00% 0.00% S/ 676.78 100.00% 0.00%
16 INSTALACIONES ELECTRICAS 18,471.40 0.00% 0.00% S/ 18,471.40 100.00% 0.00%
16.01 SALIDA PARA CENTRO DE LUZ 12,603.75 0.00% 0.00% S/ 12,603.75 100.00% 0.00%
16.01.01 SALIDA PARA CENTROS DE LUZ EN TECHO pto 33.00 122.69 4,048.77 0.00% 0.00% S/ 4,048.77 100.00% 0.00%
16.01.02 SALIDA PARA INTERRUPTORES DOBLES pto 23.00 32.22 741.06 0.00% 0.00% S/ 741.06 100.00% 0.00%
16.01.03 SALIDA PARA TOMACORRIENTES DOBLES pto 48.00 162.79 7,813.92 0.00% 0.00% S/ 7,813.92 100.00% 0.00%
16.02 CAJA DE PASO 53.28 0.00% 0.00% S/ 53.28 100.00% 0.00%
16.02.01 CAJA RECTAGULAR 100x55x50 mm pza 1.00 53.28 53.28 0.00% 0.00% S/ 53.28 100.00% 0.00%
16.03 LUMINARIAS 4,183.12 0.00% 0.00% S/ 4,183.12 100.00% 0.00%
16.03.01 LUZ DE EMERGENCIA/AUTONOMIA 1.5 HORAS/2x55w/900LM pza 1.00 199.03 199.03 0.00% 0.00% S/ 199.03 100.00% 0.00%
16.03.02 LUMINARIA RECTANGULAR TIPO H PARA ADOSAR 2 LÁMPARAS DE 35Wc/u pza 33.00 120.73 3,984.09 0.00% 0.00% S/ 3,984.09 100.00% 0.00%
16.04 PRUEBA ELECTRICA 1,631.25 0.00% 0.00% S/ 1,631.25 100.00% 0.00%
16.04.01 TABLERO DE DISTRIBUCION und 1.00 1,101.25 1,101.25 0.00% 0.00% S/ 1,101.25 100.00% 0.00%
16.04.02 PRUEBAS DE AISLAMIENTO, RESISTIVIDAD E ILUMINANCIA GLB 1.00 530.00 530.00 0.00% 0.00% S/ 530.00 100.00% 0.00%
17 MEDIDAS DE MITIGACION AMBIENTAL 2,775.67 0.00% 0.00% 0.00%S/ 2,775.67 100.00%
17.01 DESMONTAJE DE OBRAS PROVISIONALES GLB 1.00 731.30 731.30 0.00% 0.00% 0.00%S/ 731.30 100.00%
17.02 LIMPIEZA FINAL DE OBRA m2 530.15 3.09 1,638.16 0.00% 0.00% 0.00%S/ 1,638.16 100.00%
17.03 DISPOSICION FINAL DE MATERIAL EXCEDENTE m3 18.78 21.63 406.21 0.00% 0.00% 0.00%S/ 406.21 100.00%
18 VARIOS 21,000.00 S/ 2,875.00 13.69% S/ 2,875.00 13.69% S/ 2,875.00 13.69%S/ 12,375.00 58.93%
18.01 EQUIPAMIENTO Y MOBILIARIO GLB 1.00 9,500.00 9,500.00 0.00% S/ 9,500.00
18.03 FLETE TERRESTRE GLB 1.00 11,500.00 11,500.00 S/ 2,875.00 25.00% S/ 2,875.00 25.00% S/ 2,875.00 25.00% S/ 2,875.00 25.00%

COSTO TOTAL: 348,546.26 18,530.69 5.32% 94,206.47 27.03% 128,194.52 36.78% 107,614.58 30.88%
GASTOS GENERALES 12.73% 44,366.00 S/.2,358.75 S/.11,991.42 S/.16,317.71 S/.13,698.12
SUPERVISION 5.32% 20,903.00 S/.3,346.11 S/.5,011.80 S/.6,819.97 S/.5,725.11
EXPEDIENTE TECNICO 10,500.00 S/.10,500.00
LIQUIDACION 3,500.00 S/.3,500.00
PRESUPUESTO TOTAL 427,815.26 S/.38,235.55 8.94% S/.111,209.69 25.99% S/.151,332.20 35.37% S/.127,037.81 29.69%