Está en la página 1de 1

OBRA : MEJORAMIENTO DEL SERVICIO EDUCATIVO INICIAL DE LA I.E.

324 ESPERANZA CARRILLO DE PESCHIERA


ENTIDAD : V&V CONTRATISTAS GENERALES SRL
PROVEEDOR : ELESSANG E.I.R.L.
RUC : 20605001379
SERVICIO : MANO DE OBRA DE PINTURA PARA LEVANTAMIENTO DE OBSERVACIONES
FECHA : 19 DE DICIEMBRE DE 2020
PERIODO : DEL 11/12/2020 AL 19/12/2020

VALORIZACION Nº 01
: MANO DE OBRA DE PINTURA PARA LEVANTAMIENTO DE OBSERVACIONES
CONTRACTUAL ACUMULADO ANTERIOR COMPRA ACTUAL ACUMULADO ACTUAL SALDO POR VALORIZAR
ITEM DESCRIPCION UND PRECIO
CANTIDAD PARCIAL CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
1 MANO DE OBRA EN PINTURA INTERIORES LATEX Y EMPASTADO Y EN EXTERIORES AL OLEO MATE
1.01 BLOQUE D M2 6.00 252.17 1,512.99 176.52 1,059.09 70.00% 176.52 1,059.09 70.00% 75.65 453.90 30.00%
1.02 BLOQUE E M2 6.00 252.17 1,512.99 176.52 1,059.09 70.00% 176.52 1,059.09 70.00% 75.65 453.90 30.00%
1.03 BLOQUE F M2 6.00 252.17 1,512.99 176.52 1,059.09 70.00% 176.52 1,059.09 70.00% 75.65 453.90 30.00%
1.04 BLOQUE A PRIMER PISO M2 6.00 90.54 543.23 63.38 380.26 70.00% 63.38 380.26 70.00% 27.16 162.97 30.00%
1.05 BLOQUE A SEGUNDO PISO M2 6.00 190.07 1,140.41 133.05 798.29 70.00% 133.05 798.29 70.00% 57.02 342.12 30.00%
1.06 GUARDIANIA M2 6.00 30.75 184.48 21.52 129.13 70.00% 21.52 129.13 70.00% 9.22 55.34 30.00%
1.07 TOPICO M2 6.00 15.03 90.18 0.00 0.00% 0.00 0.00 0.00% 15.03 90.18 100.00%
1.08 COCINA M2 6.00 16.38 98.28 0.00 0.00% 0.00 0.00 0.00% 16.38 98.28 100.00%
1.09 DEPOSITO M2 6.00 24.49 146.94 17.14 102.86 70.00% 17.14 102.86 70.00% 7.35 44.08 30.00%
1.1 CASETA DE BOMBAS SUPERIOR M2 6.00 19.88 119.28 13.92 83.50 70.00% 13.92 83.50 70.00% 5.96 35.78 30.00%
1.11 CASETA DE BOMBAS INFERIOR M2 6.00 26.50 159.00 0.00 0.00% 0.00 0.00 0.00% 26.50 159.00 100.00%
1.12 CASETA DE TABLEROS M2 6.00 13.20 79.20 9.24 55.44 70.00% 9.24 55.44 70.00% 3.96 23.76 30.00%
1.13 CASETA DE ASCENSOR M2 6.00 7.02 42.12 0.00 0.00% 0.00 0.00 0.00% 7.02 42.12 100.00%
1.14 CASETA DE DE GAS M2 6.00 7.83 46.98 0.00 0.00% 0.00 0.00 0.00% 7.83 46.98 100.00%
2 MANO DE OBRA EN PINTURA CIELO RASO Y RESANES
2.01 BLOQUE D M2 3.00 126.00 378.00 100.80 302.40 80.00% 100.80 302.40 80.00% 25.20 75.60 20.00%
2.02 BLOQUE E M2 3.00 126.00 378.00 100.80 302.40 80.00% 100.80 302.40 80.00% 25.20 75.60 20.00%
2.03 BLOQUE F M2 3.00 126.00 378.00 100.80 302.40 80.00% 100.80 302.40 80.00% 25.20 75.60 20.00%
2.04 BLOQUE A PRIMER PISO M2 3.00 70.20 210.60 56.16 168.48 80.00% 56.16 168.48 80.00% 14.04 42.12 20.00%
2.05 BLOQUE A SEGUNDO PISO M2 3.00 70.20 210.60 56.16 168.48 80.00% 56.16 168.48 80.00% 14.04 42.12 20.00%
2.06 GUARDIANIA M2 3.00 16.88 50.64 13.50 40.51 80.00% 13.50 40.51 80.00% 3.38 10.13 20.00%
2.07 TOPICO M2 3.00 11.40 34.20 0.00 0.00% 0.00 0.00 0.00% 11.40 34.20 100.00%
2.08 COCINA M2 3.00 11.76 35.28 11.76 35.28 100.00% 11.76 35.28 100.00% 0.00 0.00 0.00%
2.09 DEPOSITO M2 3.00 4.20 12.60 4.20 12.60 100.00% 4.20 12.60 100.00% 0.00 0.00 0.00%
2.1 CASETA DE BOMBAS SUPERIOR M2 3.00 3.66 10.98 0.00 0.00% 0.00 0.00 0.00% 3.66 10.98 100.00%
2.11 CASETA DE BOMBAS INFERIOR M2 3.00 6.09 18.27 0.00 0.00% 0.00 0.00 0.00% 6.09 18.27 100.00%
2.12 CASETA DE TABLEROS M2 3.00 2.85 8.55 2.85 8.55 100.00% 2.85 8.55 100.00% 0.00 0.00 0.00%
2.13 CASETA DE ASCENSOR M2 3.00 0.82 2.46 0.00 0.00% 0.00 0.00 0.00% 0.82 2.46 100.00%
2.14 CASETA DE DE GAS M2 3.00 0.99 2.97 0.00 0.00% 0.00 0.00 0.00% 0.99 2.97 100.00%
2.15 CERCO PERIMETRICO M2 3.00 105.96 317.88 0.00 0.00% 0.00 0.00 0.00% 105.96 317.88 100.00%
COSTO DIRECTO 9,238.10 - 0.00% 6,067.86 65.68% 6,067.86 65.68% 3,170.24 34.32%
IGV 1,662.86 1,092.22 1,092.22 570.64
- -

COSTO TOTAL 10,900.96 - 7,160.08 7,160.08 3,740.89

RESUMEN
DESCRIPCION VALORIZADO DEDUCTIVO COSTO DIR IMPUESTOS TOTAL SALDO
VALORIZACION N 01 6,067.86 6,067.86 1,092.22 7,160.08 3,740.89
ACUMULADO TOTAL 6,067.86 6,067.86 7,160.08

Nota: EL PRECIO INCLUYE IGV