CRONOGRAMA VALORIZADO

MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE RIEGO POR ASERSION EN LA C.C. DE QUEUÑA CANCHA, DISTR. HUANARANI - PAUCARTAMBO -
PROYECTO:
CUSCO
EJECUTADO SALDO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION Und. METRADO PRECIO S/ PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ % S/. % S/. % S/. % S/. %

1 OBRAS PRELIMINARES 2,055.20


1.01 Cartel de Obra y Placa Glb 1.00 351.5 351.50 0.00 0.00% 1.00 351.50 100.00% 351.50
1.02 Campamento de obra m2 30.00 44.86 1,345.80 30.00 1,345.80 100.00% 0.00 0.00 0.00%
1.03 Placa recordatorio Und. 1 357.9 357.90 0.00 0.00% 1.00 357.90 100.00% 357.90
2 CAPTACION TIPO MANANTE (8 UND) 22,743.92
2.01 Trazo y Replanteo m2 50.00 0.69 34.50 31.25 21.56 62.50% 18.75 12.94 37.50% 12.94
2.02 Excavacion para cimientos hasta 1m. m3 25.00 14 350.00 15.63 218.76 62.50% 9.37 131.24 37.50% 131.24
2.03 Refine y nivelaciòn en terreno normal m2 50.00 1.05 52.50 31.25 32.81 62.50% 18.75 19.69 37.50% 19.69
2.04 Eliminacion de material excedente m3 27.50 8.4 231.00 17.19 144.38 62.50% 10.31 86.62 37.50% 86.62
2.05 Encofrado y desencofrado de muros m2 110.34 24.02 2,650.37 68.96 1,656.42 62.50% 41.38 993.95 37.50% 993.95
2.06 Acero estructural trabajado para obras de arte kg 250.16 4.13 1,033.16 156.35 645.73 62.50% 93.81 387.44 37.50% 387.44
2.07 Concreto Simple fc= 175 kg/cm2 m3 16.65 436.81 7,272.89 10.41 4,545.55 62.50% 6.24 2,727.34 37.50% 2,727.34
2.08 Tarrajeo con impermeabilizante m2 42.88 18.42 789.85 26.80 493.66 62.50% 16.08 296.19 37.50% 296.19
2.09 Tarrajeo en exteriores m2 48.40 15.97 772.95 30.25 483.09 62.50% 18.15 289.86 37.50% 289.86
2.1 Filtro de Grava o Cascajo m3 5.48 189.43 1,038.08 0.00 0.00 0.00% 5.48 1,038.08 100.00% 1,038.08
2.11 Concreto 1:8 Sello de Filtro m3 11.64 335.89 3,909.76 0.00 0.00 0.00% 11.64 3,909.76 100.00% 3,909.76
2.12 suministro de accesorios para captacion tipo manante DE 2" und 2.00 459.86 919.72 0.00 0.00% 2.00 919.72 100.00% 919.72
2.13 SUMINISTRO DE ACCESORIOS PARA CAPTACION TIPO MANANTE DE 1" und 2.00 353.86 707.72 0.00 0.00% 2.00 707.72 100.00% 707.72
2.14 SUMINISTRO DE ACCESORIOS PARA CAPTACION TIPO MANANTE DE 3/4" und 4.00 286.49 1,145.96 0.00 0.00% 4.00 1,145.96 100.00% 1,145.96
2.15 Provicion e instalacion tub. Pvc- sap crbada de 3" m 80.00 14.49 1,159.20 0.00 0.00% 80.00 1,159.20 100.00% 1,159.20
2.16 Proteccion de manantes (Alambre de puas) m 120.00 2.89 346.80 0.00 0.00% 120.00 346.80 100.00% 346.80
2.17 Pintado de Obra de Arte m2 56.61 5.82 329.47 0.00 0.00% 56.61 329.47 100.00% 329.47
3 BOCATOMA TIROLESA SUMERGIDA (01 und) 11,462.98
3.01 Trazo y Replanteo m2 38.50 0.69 26.57 38.50 26.57 100.00% 0.00 0.00 0.00% -
3.02 Excavacion para cimientos hasta 1m. Terreno natural m3 7.95 14 111.30 7.95 111.30 100.00% 0.00 0.00 0.00% -
3.03 Refine y nivelaciòn en terreno normal m2 19.50 1.05 20.48 0.00 0.00 0.00% 19.50 20.48 100.00% 20.48
3.04 Eliminacion de material excedente hasta 30 mt ( a mano usando carretilla) m3 8.75 8.4 73.50 8.75 73.50 100.00% 0.00 0.00 0.00% -
3.05 Encofrado y desencofrado de muros m2 43.83 24.02 1,052.80 0.00 0.00 0.00% 43.83 1,052.80 100.00% 1,052.80
3.06 Acero estructural trabajado para obras de arte ( bocatoma riachuelo) kg 160.11 7.77 1,244.05 0.00 0.00 0.00% 160.11 1,244.05 100.00% 1,244.05
3.07 Concreto Ciclopeo fc=140 kg/cm2+30%PM m3 5.53 316.06 1,747.81 0.00 0.00 0.00% 5.53 1,747.81 100.00% 1,747.81
3.08 Concreto Simple fc= 175 kg/cm2 m3 11.98 436.81 5,232.98 0.00 0.00% 11.98 5,232.98 100.00% 5,232.98
3.09 mortero 1:8 m3 1.13 271.49 306.78 0.00 0.00% 1.13 306.78 100.00% 306.78
3.1 Tarrajeo con impermeabilizante m2 44.70 18.42 823.37 0.00 0.00% 44.70 823.37 100.00% 823.37
3.11 suministro de accesorios para bocatoma de riachuelo glb 1.00 693.26 693.26 0.00 0.00% 1.00 693.26 100.00% 693.26
3.12 Pintado de Obra de Arte m2 22.35 5.82 130.08 0.00 0.00% 22.35 130.08 100.00% 130.08
4 DESARENADOR Y CAMARA DE CARGA (01 UND) 4,169.76
4.01 Trazo y Replanteo m2 9.68 0.69 6.68 0.00 0.00% 9.68 6.68 100.00% 6.68
4.02 Excavacion para cimientos hasta 1m. m3 8.08 14 113.12 0.00 0.00% 8.08 113.12 100.00% 113.12
4.03 Refine y nivelaciòn en terreno normal m2 9.68 1.05 10.16 0.00 0.00% 9.68 10.16 100.00% 10.16
4.04 Eliminacion de material excedente m3 8.89 8.4 74.68 0.00 0.00% 8.89 74.68 100.00% 74.68
4.05 Encofrado y desencofrado de muros m2 37.32 24.02 896.43 0.00 0.00% 37.32 896.43 100.00% 896.43
4.06 Acero estructural trabajado para obras de arte kg 194.65 4.13 803.90 0.00 0.00% 194.65 803.90 100.00% 803.90
4.07 Concreto Simple fc= 175 kg/cm2 m3 3.20 436.81 1,397.79 0.00 0.00% 3.20 1,397.79 100.00% 1,397.79
4.08 Tarrajeo con impermeabilizante m2 20.01 18.42 368.58 0.00 0.00% 20.01 368.58 100.00% 368.58
4.09 suministro de accesorios para desarenador y camara de carga glb 1.00 381.96 381.96 0.00 0.00% 1.00 381.96 100.00% 381.96
4.1 Pintura de Obra de Arte m2 20.01 5.82 116.46 0.00 0.00% 20.01 116.46 100.00% 116.46
5 LINEA DE CONDUCCION (2986m) 52,287.38
5.01 Trazo y Replanteo ml 2986.00 1.22 3,642.92 480.00 585.60 16.08% 2,506.00 3,057.32 83.92% 3,057.32
5.02 Excavacion caja de canal en tierra ( a mano) m3 716.64 14 10,032.96 115.20 1,612.80 16.08% 601.44 8,420.16 83.92% 8,420.16
5.03 Refine y nivelacion en terreno normal m2 1194.40 1.05 1,254.12 0.00 0.00% 1,194.40 1,254.12 100.00% 1,254.12
5.04 Cama de apoyo paratuberia pvc sap ml 2986.00 0.7 2,090.20 0.00 0.00% 2,986.00 2,090.20 100.00% 2,090.20
5.05 Relleno y compactado con material propio m3 716.64 8.4 6,019.78 0.00 0.00% 716.64 6,019.78 100.00% 6,019.78
5.06 Provisión tuberias PVC SAP C-7.5 D =3" ml 940.00 14.03 13,188.20 0.00 0.00% 940.00 13,188.20 100.00% 13,188.20
5.08 Provisión tuberias PVC SAP C-7.5 D =2" ml 1394.00 7.6 10,594.40 0.00 0.00% 1,394.00 10,594.40 100.00% 10,594.40
5.09 Provisión tuberias PVC SAP C-7.5 D =1" m 185.00 4.17 771.45 0.00 0.00% 185.00 771.45 100.00% 771.45
5.1 Provisión tuberias PVC SAP C-7.5 D =3/4" ml 467.00 2.81 1,312.27 0.00 0.00% 467.00 1,312.27 100.00% 1,312.27
5.11 Codo PVC SAP de 3" x 45° und 6.00 23.52 141.12 0.00 0.00% 6.00 141.12 100.00% 141.12
5.12 Codo PVC SAP de 3" x 22.5° und 6.00 22.42 134.52 0.00 0.00% 6.00 134.52 100.00% 134.52
5.14 Prueba hidraulica para tuberias pvc sap ml 2986.00 1.04 3,105.44 0.00 0.00% 2,986.00 3,105.44 100.00% 3,105.44
6 CRUCE AEREO 01 UND 580.62
CRONOGRAMA VALORIZADO
MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE RIEGO POR ASERSION EN LA C.C. DE QUEUÑA CANCHA, DISTR. HUANARANI - PAUCARTAMBO -
PROYECTO:
CUSCO
EJECUTADO SALDO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION Und. METRADO PRECIO S/ PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ % S/. % S/. % S/. % S/. %
6.01 Trazo y Replanteo ml 0.25 0.69 0.17 0.00 0.00% 0.25 0.17 100.00% 0.17
6.02 Excavacion para cimientos hasta 1m. m3 0.25 14 3.50 0.00 0.00% 0.25 3.50 100.00% 3.50
6.03 encofrado y desencofrado normal m2 2.00 24.02 48.04 0.00 0.00% 2.00 48.04 100.00% 48.04
6.04 Concreto Simple fc=175 kg/cm2 m3 0.50 436.81 218.41 0.00 0.00% 0.50 218.41 100.00% 218.41
6.05 Tarrajeo con impermeabilizante m2 2.00 18.42 36.84 0.00 0.00% 2.00 36.84 100.00% 36.84
6.06 suministro e instalacion tuberia f°g° 2"x 6m m 6.00 33.21 199.26 0.00 0.00% 6.00 199.26 100.00% 199.26
6.07 suministro de accesorios cruce aereo glb 1.00 62.76 62.76 0.00 0.00% 1.00 62.76 100.00% 62.76
6.08 pintado de obras de arte m2 2.00 5.82 11.64 0.00 0.00% 2.00 11.64 100.00% 11.64
7 CAMARA DE REUNION (2 UND) 3,272.93
7.01 Trazo y Replanteo ml 2.42 0.69 1.67 0.00 0.00% 2.42 1.67 100.00% 1.67
7.02 Excavacion para cimientos hasta 1m. m3 2.18 14 30.52 0.00 0.00% 2.18 30.52 100.00% 30.52
7.03 Refine y nivelacion en terreno normal m2 2.42 1.05 2.54 0.00 0.00% 2.42 2.54 100.00% 2.54
7.04 encofrado y desencofrado normal m2 22.66 24.02 544.29 0.00 0.00% 22.66 544.29 100.00% 544.29
7.05 Acero estructural trabajado para obras de arte kg 122.50 4.13 505.93 0.00 0.00% 122.50 505.93 100.00% 505.93
7.06 Concreto Simple fc=175 kg/cm2 m3 2.97 436.81 1,297.33 0.00 0.00% 2.97 1,297.33 100.00% 1,297.33
7.07 Tarrajeo con impermeabilizante m2 22.66 18.42 417.40 0.00 0.00% 22.66 417.40 100.00% 417.40
7.08 suministro de accesorios para camara de reunion de 2" glb 1.00 234.96 234.96 0.00 0.00% 1.00 234.96 100.00% 234.96
7.09 suministrode accesorios para camara de reunion de 1" glb 1.00 181.96 181.96 0.00 0.00% 1.00 181.96 100.00% 181.96
7.1 pintado de obras de arte m2 9.68 5.82 56.34 0.00 0.00% 9.68 56.34 100.00% 56.34
08 RESERVORIO DE CONCRETO V=303 m3 73,636.97
08.01 Trazo y Replanteo m2 400.00 0.69 276.00 400.00 276.00 100.00% 0.00 0.00 0.00% -
08.02 Excavacion para estructuras m3 476.38 14 6,669.32 476.38 6,669.32 100.00% 0.00 0.00 0.00% -
08.03 Refine y nivelacion en terreno normal m2 400.00 1.05 420.00 400.00 420.00 100.00% 0.00 0.00 0.00% -
08.04 Eliminacion de material excedente m3 619.30 8.4 5,202.12 619.30 5,202.12 100.00% 0.00 0.00 0.00% -
08.05 Empedrado de la base H=0.15 m m2 178.75 21.38 3,821.68 178.75 3,821.68 100.00% 0.00 0.00 0.00% -
08.06 encofrado y desencofrado normal m2 132.00 24.02 3,170.64 132.00 3,170.64 100.00% 0.00 0.00 0.00% -
08.07 Acero estructural trabajado para obras de arte ( reservorio) kg 1183.28 6.5 7,691.32 1,183.28 7,691.32 100.00% 0.00 0.00 0.00% -
08.08 Concreto Ciclopeo f'c=140 kg/cm2 + 70% PG m3 19.11 198.33 3,790.09 19.11 3,790.09 100.00% 0.00 0.00 0.00% -
08.09 Concreto simple f'c=210 kg/cm2 m3 60.39 465.23 28,095.24 60.39 28,095.24 100.00% 0.00 0.00 0.00% -
08.10 Tarrajeo con impermeabilizante m2 301.95 18.42 5,561.92 301.95 5,561.92 100.00% 0.00 0.00 0.00% -
08.11 Juntas asfalticas de dilatación m 179.00 13.63 2,439.77 0.00 0.00 0.00% 179.00 2,439.77 100.00% 2,439.77
08.12 juntas water stop 6" m 179.00 23.68 4,238.72 179.00 4,238.72 100.00% 0.00 0.00 0.00% -
08.13 Suministro de accesorios para reservorio glb 1 561.76 561.76 0.40 224.70 40.00% 0.60 337.06 60.00% 337.06
08.14 Suministro de accesorios cerco perimetrico 1.00 1259.05 1,259.05 0.00 0.00 0.00% 1.00 1,259.05 100.00% 1,259.05
08.15 Pintura de Obra de Arte m2 75.49 5.82 439.35 0.00 0.00 0.00% 75.49 439.35 100.00% 439.35
09 RESERVORIO DE CONCRETO V=123 m3 40,443.00
09.01 Trazo y Replanteo m2 217.50 0.69 150.08 217.50 150.08 100.00% 0.00 0.00 0.00% -
09.02 Excavacion para estructuras m3 207.94 14 2,911.16 207.94 2,911.16 100.00% 0.00 0.00 0.00% -
09.03 Refine y nivelacion m2 217.50 1.05 228.38 217.50 228.38 100.00% 0.00 0.00 0.00% -
09.04 eliminacion material hasta 30.00MT(a mano usando carretilla m3 270.32 8.4 2,270.69 270.32 2,270.69 100.00% 0.00 0.00 0.00% -
09.05 Empedrado de la base H=0.15 m m2 156.61 21.38 3,348.32 156.61 3,348.32 100.00% 0.00 0.00 0.00% -
09.06 Encofrado y desencofrado normal m2 143.36 24.02 3,443.51 143.36 3,443.51 100.00% 0.00 0.00 0.00% -
09.07 Acero estructural kg 515.48 6.5 3,350.62 515.48 3,350.62 100.00% 0.00 0.00 0.00% -
09.08 Concreto Ciclopeo f'c=140 kg/cm2 + 70% PG m3 9.31 198.33 1,846.45 9.31 1,846.45 100.00% 0.00 0.00 0.00% -
09.09 Concreto simple f'c=175 kg/cm2 m3 32.59 465.23 15,161.85 32.59 15,161.85 100.00% 0.00 0.00 0.00% -
09.10 Tarrajeo con impermeabilizante m2 162.95 18.42 3,001.54 162.95 3,001.54 100.00% 0.00 0.00 0.00% -
09.11 juntas asfalticas de dilatacion m 72.00 13.63 981.36 0.00 0.00 0.00% 72.00 981.36 100.00% 981.36
09.12 juntas water stop 6" m 75.00 23.68 1,776.00 75.00 1,776.00 100.00% 0.00 0.00 0.00% -
09.13 Suministro de accesorios para reservorio glb 1.00 655.26 655.26 0.40 262.10 40.00% 0.60 393.16 60.00% 393.16
09.14 Suministro de accesorios cerco perimetrico glb 1.00 1074.05 1,074.05 0.00 0.00% 1.00 1,074.05 100.00% 1,074.05
09.15 Pintura de Obra de Arte m2 41.88 5.82 243.74 0.00 0.00% 41.88 243.74 100.00% 243.74
10 reservorio de concreto (108m3) 30,240.04
10.01 Trazo y Replanteo m2 217.50 0.69 150.08 217.50 150.08 100.00% - 0.00 0.00% -
10.02 excavacion para estructuras m3 179.30 14 2,510.20 179.30 2,510.20 100.00% - 0.00 0.00% -
10.03 refine y nivelacion en terreno normal m2 217.50 1.05 228.38 217.50 228.38 100.00% - 0.00 0.00% -
10.04 eliminacion materialexcedente hasta 30.00MT(a mano usando carretilla) m3 233.09 8.4 1,957.96 233.09 1,957.96 100.00% - 0.00 0.00% -
10.05 empedrado de la base H=0.15 m m2 123.48 21.38 2,640.00 123.48 2,640.00 100.00% - 0.00 0.00% -
10.06 Encofrado y desencofrado normal m2 129.25 24.02 3,104.59 129.25 3,104.59 100.00% - 0.00 0.00% -
10.07 acero estructural trabajado para obras de barte(reservorio) kg 481.87 6.5 3,132.16 481.87 3,132.16 100.00% - 0.00 0.00% -
10.08 concreto siclopio pc=140 kg/cm2+70%pg m3 4.25 198.33 842.90 4.25 842.90 100.00% - 0.00 0.00% -
10.09 concreto simple f'c=210 kg/cm2 m3 18.60 465.23 8,653.28 18.60 8,653.28 100.00% - 0.00 0.00% -
10.1 tarrageo impermeabilizante m2 125.00 18.42 2,302.50 125.00 2,302.50 100.00% - 0.00 0.00% -
10.11 juntas asfalticas de dilatacion m 72.00 13.63 981.36 0.00 0.00 0.00% 72.00 981.36 100.00% 981.36
CRONOGRAMA VALORIZADO
MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE RIEGO POR ASERSION EN LA C.C. DE QUEUÑA CANCHA, DISTR. HUANARANI - PAUCARTAMBO -
PROYECTO:
CUSCO
EJECUTADO SALDO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION Und. METRADO PRECIO S/ PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ % S/. % S/. % S/. % S/. %
10.12 juntas water stop 6" m 75.00 23.68 1,776.00 75.00 1,776.00 100.00% - 0.00 0.00% -
10.13 suministro de accesorios para reservorio glb 1.00 655.26 655.26 0.40 262.10 40.00% 0.60 393.16 60.00% 393.16
10.14 suministro de accesorios para cerco perimetrico glb 1.00 1074.05 1,074.05 0.00 0.00 0.00% 1.00 1,074.05 100.00% 1,074.05
10.15 pintado de obra de arte m2 39.75 5.82 231.35 0.00 0.00 0.00% 39.75 231.35 100.00% 231.35
11 caja de valvula principal 3,120.96
11.01 Trazo y Replanteo m2 1.47 0.69 1.01 0.00 0.00% 1.47 1.01 100.00% 1.01
11.02 excavacion para cimientos hasta 1m terreno normal m3 0.74 14 10.36 0.00 0.00% 0.74 10.36 100.00% 10.36
11.03 eliminacion material excesente hasta 30.00mt (a mano usando crretilla) m3 2.87 8.4 24.11 0.00 0.00% 2.87 24.11 100.00% 24.11
11.04 encofrado y desencofrado normal m2 7.20 24.02 172.94 0.00 0.00% 7.20 172.94 100.00% 172.94
11.05 concreto simple fc=175 kg/cm2 m3 0.58 436.81 253.35 0.00 0.00% 0.58 253.35 100.00% 253.35
11.06 tarrageo con impermeabilizante m2 4.20 18.42 77.36 0.00 0.00% 4.20 77.36 100.00% 77.36
11.07 suministro de accesorios para caja de valvula principal 3 glb 1.00 1004.46 1,004.46 0.00 0.00% 1.00 1,004.46 100.00% 1,004.46
11.08 suministro de accesorios para caja de valvula principal 2 glb 2.00 776.46 1,552.92 0.00 0.00% 2.00 1,552.92 100.00% 1,552.92
11.09 pintado de obras de arte m2 4.20 5.82 24.44 0.00 0.00% 4.20 24.44 100.00% 24.44
12 red de distribucion (4213.14m) 71,237.09
12.01 obras preliminares 5,140.03
12.01.01 trazo y Replanteo m 4213.14 1.22 5,140.03 0.00 0.00% 4,213.14 5,140.03 100.00% 5,140.03
12.02 movimientos de tierras 32,677.05
12.02.01 excabacion de caja de canales en tierra (a mano) 3m 1011.15 14 14,156.10 0.00 0.00% 1,011.15 14,156.10 100.00% 14,156.10
12.02.02 refine y nivelacion terreno normal para tub. 1"a4" n2 1,685.26 4.20 7,078.09 0.00 0.00% 1,685.26 7,078.09 100.00% 7,078.09
12.02.03 cama de apoyo para tuberia pvc sap m 4,213.14 0.70 2,949.20 0.00 0.00% 4,213.14 2,949.20 100.00% 2,949.20
12.02.04 relleno y comp.mat.propio en zanjas m3 1,011.15 8.40 8,493.66 0.00 0.00% 1,011.15 8,493.66 100.00% 8,493.66
12.03 instalacion de tuberias 32,028.37
12.03.01 provision e instalacion tuberia pvc.sap c-7.5d=3" m 715.28 14.03 10,035.38 0.00 0.00% 715.28 10,035.38 100.00% 10,035.38
12.03.02 provision e instalcion tuberia pvc -sapc-7.5d=2" m 1024.29 7.6 7,784.60 0.00 0.00% 1,024.29 7,784.60 100.00% 7,784.60
12.03.03 provision e istalacion tuberias pvc-sapc-10d=11/2" m 548.69 6.29 3,451.26 0.00 0.00% 548.69 3,451.26 100.00% 3,451.26
12.03.04 provision e instalacion tuberia pvc-sapc10d=1" m 710.70 4.17 2,963.62 0.00 0.00% 710.70 2,963.62 100.00% 2,963.62
12.03.05 provision e instalacion tuberia pvc.sap c-10d=3/4" m 1,214.18 2.81 3,411.85 0.00 0.00% 1,214.18 3,411.85 100.00% 3,411.85
12.03.06 prueba hidraulica tuberias pvc sap m 4,213.14 1.04 4,381.67 0.00 0.00% 4,213.14 4,381.67 100.00% 4,381.67
12.04 instalacione de accesorios 1,391.64
12.04.01 tee pvc-sap 3"x1" und 3.00 32.52 97.56 0.00 0.00% 3.00 97.56 100.00% 97.56
12.04.02 tee pvc-sap 3"x2" und 3.00 28.02 84.06 0.00 0.00% 3.00 84.06 100.00% 84.06
12.04.03 tee pvc-sap 2"x1" und 14.00 21.67 303.38 0.00 0.00% 14.00 303.38 100.00% 303.38
12.04.04 reduccion pvc sap de 3"a 2" und 3.00 16.98 50.94 0.00 0.00% 3.00 50.94 100.00% 50.94
12.04.05 rduccion pvc sap de 2" a1" und 10.00 12.98 129.80 0.00 0.00% 10.00 129.80 100.00% 129.80
12.04.06 reduccion pvc sap de 2"a1.5" und 15.00 13.48 202.20 0.00 0.00% 15.00 202.20 100.00% 202.20
12.04.07 reduccion pvc de 1" a 3/4" und 20.00 12.98 259.60 0.00 0.00% 20.00 259.60 100.00% 259.60
12.04.08 codo pvc-sap3"x45" und 3.00 23.52 70.56 0.00 0.00% 3.00 70.56 100.00% 70.56
12.04.09 cdo pvc-sap2"x45" und 3.00 16.52 49.56 0.00 0.00% 3.00 49.56 100.00% 49.56
12.04.10 codo pvc-sap 1"x45 und 3.00 12.98 38.94 0.00 0.00% 3.00 38.94 100.00% 38.94
12.04.11 codo pvc-sap 3"x90 und 2.00 24.52 49.04 0.00 0.00% 2.00 49.04 100.00% 49.04
12.04.12 CODO PVC SAP 2" X 90° und 2.00 15.02 30.04 0.00 0.00% 2.00 30.04 100.00% 30.04
12.04.13 coDO PVC SAP 1" X 90° und 2.00 12.98 25.96 0.00 0.00% 2.00 25.96 100.00% 25.96
13 caja de valvulas de control (09UND) 4,776.82
13.01 TRAZO Y REPLANTEO m2 3.24 0.69 2.24 0.00 0.00% 3.24 2.24 99.80% 2.24
13.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 1.94 14.00 27.16 0.00 0.00% 1.94 27.16 100.00% 27.16
13.03 eliminacion de material excedente hasta 30.00 MT (A MANO USANDO CARREm3 3.53 8.40 21.25 0.00 0.00% 3.53 29.65 139.54% 29.65
13.04 encofrado desencofrado normal m2 20.16 24.02 484.24 0.00 0.00% 20.16 484.24 100.00% 484.24
13.05 concreto simple FC=175KG/CM2 m3 1.22 436.81 532.91 0.00 0.00% 1.22 532.91 100.00% 532.91
13.06 tarrajeo exteriores m2 7.20 15.97 114.98 0.00 0.00% 7.20 114.98 100.00% 114.98
13.07 suminestro de accesorios para caja de valvula de 3" GLB 4.00 553.46 2,213.84 0.00 0.00% 4.00 2,213.84 100.00% 2,213.84
13.08 SUminestro de accesorios para caja de valvula de 2" GLB 2.00 325.46 650.92 0.00 0.00% 2.00 650.92 100.00% 650.92
13.09 suminestro de accesorios para caja de valvula de 1.05" GLB 1.00 252.46 252.46 0.00 0.00% 1.00 252.46 100.00% 252.46
13.10 suminestro de accesorios para caja de valvula de 1" GLB 2.00 217.46 434.92 0.00 0.00% 2.00 434.92 100.00% 434.92
13.11 pintado de hobra de arte m2 7.20 5.82 41.90 0.00 0.00% 7.20 41.90 100.01% 41.90
14 CAMARA ROMPREPRESION (02 UND) 3,802.02
14.01 TRAZO Y REPLANTEO m2 3.30 0.69 2.28 0.00 0.00% 3.30 2.28 99.87% 2.28
14.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 2.64 14.00 36.96 0.00 0.00% 2.64 36.96 100.00% 36.96
14.03 refine y nivelacion en terreno normal m2 3.30 1.05 3.47 0.00 0.00% 3.30 3.47 99.86% 3.47
14.04 acero estructural trabajando para obra de arte KG 80.04 4.13 330.57 0.00 0.00% 80.04 330.57 100.00% 330.57
14.05 encofrado desencofrado MUROS m2 27.22 24.02 653.82 0.00 0.00% 27.22 653.82 100.00% 653.82
14.06 concreto simple FC=175KG/CM2 m3 3.87 436.81 1,690.45 0.00 0.00% 3.87 1,690.45 100.00% 1,690.45
14.07 tarajeo con impermeabilizante m2 27.22 18.42 501.39 0.00 0.00% 27.22 501.39 100.00% 501.39
CRONOGRAMA VALORIZADO
MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE RIEGO POR ASERSION EN LA C.C. DE QUEUÑA CANCHA, DISTR. HUANARANI - PAUCARTAMBO -
PROYECTO:
CUSCO
EJECUTADO SALDO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION Und. METRADO PRECIO S/ PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ % S/. % S/. % S/. % S/. %
14.08 suministro de accesorios para camara de ronpepresion de 3" GLB 1.00 307.96 307.96 0.00 0.00% 1.00 307.96 100.00% 307.96
14.09 suministro de accesorios para camara de ronpepresion de 2" GLB 1.00 234.96 234.96 0.00 0.00% 1.00 234.96 100.00% 234.96
14.10 pintado de hobra de arte m2 6.20 5.82 40.16 0.00 0.00% 6.20 36.08 89.85% 36.08
15 valvula reductora de presion(02UND) 678.69
15.01 TRAZO Y REPLANTEO m2 0.41 0.69 0.28 0.00 0.00% 0.41 0.28 100.00% 0.28
15.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 0.20 14.00 2.80 0.00 0.00% 0.20 2.80 100.00% 2.80
15.03 ENCOFRADO Y DESENCOFRADO DE MUROS m2 2.12 24.02 50.92 0.00 0.00% 2.12 50.92 100.00% 50.92
15.04 concreto simple FC=175KG/CM2 m3 0.15 436.81 65.52 0.00 0.00% 0.15 65.52 100.00% 65.52
15.05 TARRAJEO EN EXTERIORES m2 1.80 15.97 28.75 0.00 0.00% 1.80 28.75 100.00% 28.75
15.06 SUMINISTROS ACCESORIOS REDUCTORA DE PRESION2" GLB 1.00 326.97 326.97 0.00 0.00% 1.00 326.97 100.00% 326.97
15.07 SUMINISTRO ACCESORIOS REDUCTORA DEPRESION 3/4" GLB 1.00 192.97 192.97 0.00 0.00% 1.00 192.97 100.00% 192.97
15.08 PINTADO DE OBRAS DE ARTE m2 1.80 5.82 10.48 0.00 0.00% 1.80 10.48 100.00% 10.48
16 VALVULA DE PURGA (04 UND) 1,442.50
16.01 TRAZO Y REPLANTEO m2 1.44 0.69 0.99 0.00 0.00% 1.44 0.99 100.00% 0.99
16.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 0.72 14.00 10.08 0.00 0.00% 0.72 10.08 100.00% 10.08
16.03 ELIMINACION MATERIAL EXCEDENTE HASTA 30.00MT (A MANNO USANO CARR m3 0.94 8.40 7.90 0.00 0.00% 0.94 7.90 100.00% 7.90
16.04 ENCOFRADO Y DESENCOFRADO DE MUROS m2 8.96 24.02 215.22 0.00 0.00% 8.96 215.22 100.00% 215.22
16.05 concreto simple FC=175KG/CM2 m3 0.54 436.81 235.88 0.00 0.00% 0.54 235.88 100.00% 235.88
16.06 TARRAJEO EN EXTERIORES m2 4.80 15.97 76.66 0.00 0.00% 4.80 76.66 100.00% 76.66
16.07 SUMINISTROS ACCESORIOS VALVULA DE PURGA DE 1" und 4.00 216.96 867.84 0.00 0.00% 4.00 867.84 100.00% 867.84
16.08 PINTADO DE OBRAS DE ARTE m2 4.80 5.82 27.94 0.00 0.00% 4.80 27.94 100.00% 27.94
17 HIDRANTES (45 UND) 12,126.15
17.01 TRAZO Y REPLANTEO m2 9.11 0.69 6.29 0.00 0.00% 9.11 6.29 100.00% 6.29
17.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 4.56 14.00 63.84 0.00 0.00% 4.56 63.84 100.00% 63.84
17.03 ELIMINACION MATERIAL EXCEDENTE HASTA 30.00MT (A MANNO USANO CARR m3 5.92 8.40 49.73 0.00 0.00% 5.92 49.73 100.00% 49.73
17.04 ENCOFRADO Y DESENCOFRADO DE MUROS m2 63.00 24.02 1,513.26 0.00 0.00% 63.00 1,513.26 100.00% 1,513.26
17.05 concreto simple FC=175KG/CM2 m3 4.06 436.81 1,773.45 0.00 0.00% 4.06 1,773.45 100.00% 1,773.45
17.06 TARRAJEO EN EXTERIORES m2 63.00 15.97 1,006.11 0.00 0.00% 63.00 1,006.11 100.00% 1,006.11
17.07 SUMINISTRO DE ACCESORIOS PARA HIDRANTE PASANTE DE 1" GLB 10.00 201.87 2,018.70 0.00 0.00% 10.00 2,018.70 100.00% 2,018.70
17.08 SUMINISTRO DE ACCESORIOS PARA HIDRANTE FIN DE LINEA 3/4" GLB 35.00 157.47 5,511.45 0.00 0.00% 35.00 5,511.45 100.00% 5,511.45
17.09 PINTADO DE OBRAS DE ARTE m2 31.50 5.82 183.33 0.00 0.00% 31.50 183.33 100.00% 183.33
18 EQUIPO MOVIL (28) 7,392.00
18.01 suministracion de accesorios para equipo movil (naan 423) glb 28.00 264.00 7,392.00 0.00 0.00% 28.00 7,392.00 100.00% 7,392.00
19 transporte de materiales 16,749.99
19.01 flete terreste glb 1.00 10732.33 10,732.33 0.90 9,659.10 90.00% 0.10 1,073.23 10.00% 1,073.23
19.02 flete rural glb 1.00 6017.66 6,017.66 0.90 5,415.89 90.00% 0.10 601.77 10.00% 601.77
20 IMPACTO AMBIENTAL 5,480.20
20.01 PLAN DE MANEJO AMBIENTAL 532.20
20.01.01 botadero de desperdicio en obra m3 10.00 16.80 168.00 0.00 0.00% 10.00 168.00 100.00% 168.00
20.01.02 reforestacion (plantas nativas) und 1.00 364.20 364.20 0.00 0.00% 1.00 364.20 100.00% 364.20
20.02 plan de seguridad 980.00
20.02.01 equipo de proteccion individual glb 1.00 980.00 980.00 0.00 0.00% 1.00 980.00 100.00% 980.00
20.03 plan de contingencia 3,800.00
20.03.01 acciones `preventibas de riesgo glb 1.00 3,800.00 3,800.00 0.00 0.00% 1.00 3,800.00 100.00% 3,800.00
20.04 plan de cierre de obras 168.00
20.04.01 desmotaje de instalaciones provisionales glb 1.00 84.00 84.00 0.00 0.00% 1.00 84.00 100.00% 84.00
20.04.02 limpieza final de obras glb 1.00 84.00 84.00 0.00 0.00% 1.00 84.00 100.00% 84.00
21 PLAN DE CAPACITACION 7,000.00
21.01 adeuada organización de benificiarios glb 1.00 3500 3,500.00 0.00 0.00% 1.00 3,500.00 100.00% 3,500.00
21.02 plan de capacitacion e operación y mantenimiento de sistema riego GLB 1.00 3500 3,500.00 0.00 0.00% 1.00 3,500.00 100.00% 3,500.00
COSTO DIRECTO 374,699.31 161,545.13 43.11% 213,154.17 56.89% 45,302.17 12.09% 52,819.75 14.10% 86,070.76 22.97% 28,961.49 7.73%
GASTOS GENERALES 40,377.00
GASTOS DE SUPERVISION 16,037.00
GASTOS DE EVALUACION 3,320.00
GASTOS DE LIQUIDACION 6,650.00
GASTOS DE EXPEDIENTE TECNICO 16,100.00
COSTO TOTAL DE OBRA 457,183.31
% AVANCE MENSUAL 161,545.13 43.11% 45,302.17 12.09% 52,819.75 14.10% 86,070.76 22.97% 28,961.49 7.73%
% AVANCE ACUMULADO 161,545.13 43.11% 206,847.30 55.20% 259,667.05 69.30% 345,737.81 92.27% 374,699.31 100.00%
CRONOGRAMA REPROGRAMADO DE EJECUCION
MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE RIEGO POR ASERSION EN LA C.C. DE QUEUÑA CANCHA, DISTR. HUANARANI - PAUCARTAMBO -
PROYECTO:
CUSCO
EJECUTADO SALDO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION Und. METRADO PRECIO S/ PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ % S/. % S/. % S/. % S/. %

1 OBRAS PRELIMINARES 2,055.20


1.01
1.02
Cartel de Obra y Placa
Campamento de obra
Glb
m2
1.00
30.00
351.5
44.86
351.50
1,345.80 30.00
0.00
1,345.80
0.00%
100.00%
1.00
0.00
351.50
0.00
100.00%
0.00%
###
1.03
2
Placa recordatorio
CAPTACION TIPO MANANTE (8 UND)
Und. 1 357.9 357.90
22,743.92
0.00 0.00% 1.00 357.90 100.00% ###
2.01 Trazo y Replanteo m2 50.00 0.69 34.50 31.25 21.56 62.50% 18.75 12.94 37.50% ###
2.02 Excavacion para cimientos hasta 1m. m3 25.00 14 350.00 15.63 218.76 62.50% 9.37 131.24 37.50% ###
2.03 Refine y nivelaciòn en terreno normal m2 50.00 1.05 52.50 31.25 32.81 62.50% 18.75 19.69 37.50% ###
2.04 Eliminacion de material excedente m3 27.50 8.4 231.00 17.19 144.38 62.50% 10.31 86.62 37.50% ###
2.05 Encofrado y desencofrado de muros m2 110.34 24.02 2,650.37 68.96 1,656.42 62.50% 41.38 993.95 37.50% ###
2.06 Acero estructural trabajado para obras de arte kg 250.16 4.13 1,033.16 156.35 645.73 62.50% 93.81 387.44 37.50% ###
2.07 Concreto Simple fc= 175 kg/cm2 m3 16.65 436.81 7,272.89 10.41 4,545.55 62.50% 6.24 2,727.34 37.50% ###
2.08 Tarrajeo con impermeabilizante m2 42.88 18.42 789.85 26.80 493.66 62.50% 16.08 296.19 37.50% ###
2.09 Tarrajeo en exteriores m2 48.40 15.97 772.95 30.25 483.09 62.50% 18.15 289.86 37.50% ###
2.1 Filtro de Grava o Cascajo m3 5.48 189.43 1,038.08 0.00 0.00 0.00% 5.48 1,038.08 100.00% ###
2.11 Concreto 1:8 Sello de Filtro m3 11.64 335.89 3,909.76 0.00 0.00 0.00% 11.64 3,909.76 100.00% ###
2.12 suministro de accesorios para captacion tipo manante DE 2" und 2.00 459.86 919.72 0.00 0.00% 2.00 919.72 100.00% ###
2.13 SUMINISTRO DE ACCESORIOS PARA CAPTACION TIPO MANANTE DE 1" und 2.00 353.86 707.72 0.00 0.00% 2.00 707.72 100.00% ###
2.14 SUMINISTRO DE ACCESORIOS PARA CAPTACION TIPO MANANTE DE 3/4" und 4.00 286.49 1,145.96 0.00 0.00% 4.00 1,145.96 100.00% ###
2.15 Provicion e instalacion tub. Pvc- sap crbada de 3" m 80.00 14.49 1,159.20 0.00 0.00% 80.00 1,159.20 100.00% ###
2.16 Proteccion de manantes (Alambre de puas) m 120.00 2.89 346.80 0.00 0.00% 120.00 346.80 100.00% ###
2.17
3
Pintado de Obra de Arte
BOCATOMA TIROLESA SUMERGIDA (01 und)
m2 56.61 5.82 329.47
11,462.98
0.00 0.00% 56.61 329.47 100.00% ###
3.01 Trazo y Replanteo m2 38.50 0.69 26.57 38.50 26.57 100.00% 0.00 0.00 0.00%
3.02 Excavacion para cimientos hasta 1m. Terreno natural m3 7.95 14 111.30 7.95 111.30 100.00% 0.00 0.00 0.00%
3.03
3.04
Refine y nivelaciòn en terreno normal
Eliminacion de material excedente hasta 30 mt ( a mano usando carretilla)
m2
m3
19.50
8.75
1.05
8.4
20.48
73.50
0.00
8.75
0.00
73.50
0.00%
100.00%
19.50
0.00
20.48
0.00
100.00%
0.00%
###
3.05 Encofrado y desencofrado de muros m2 43.83 24.02 1,052.80 0.00 0.00 0.00% 43.83 1,052.80 100.00% ###
3.06 Acero estructural trabajado para obras de arte ( bocatoma riachuelo) kg 160.11 7.77 1,244.05 0.00 0.00 0.00% 160.11 1,244.05 100.00% ###
3.07 Concreto Ciclopeo fc=140 kg/cm2+30%PM m3 5.53 316.06 1,747.81 0.00 0.00 0.00% 5.53 1,747.81 100.00% ###
3.08 Concreto Simple fc= 175 kg/cm2 m3 11.98 436.81 5,232.98 0.00 0.00% 11.98 5,232.98 100.00% ###
3.09 mortero 1:8 m3 1.13 271.49 306.78 0.00 0.00% 1.13 306.78 100.00% ###
3.1 Tarrajeo con impermeabilizante m2 44.70 18.42 823.37 0.00 0.00% 44.70 823.37 100.00% ###
3.11 suministro de accesorios para bocatoma de riachuelo glb 1.00 693.26 693.26 0.00 0.00% 1.00 693.26 100.00% ###
3.12
4
Pintado de Obra de Arte
DESARENADOR Y CAMARA DE CARGA (01 UND)
m2 22.35 5.82 130.08
4,169.76
0.00 0.00% 22.35 130.08 100.00% ###
4.01 Trazo y Replanteo m2 9.68 0.69 6.68 0.00 0.00% 9.68 6.68 100.00% 6.68
4.02 Excavacion para cimientos hasta 1m. m3 8.08 14 113.12 0.00 0.00% 8.08 113.12 100.00% ###
4.03 Refine y nivelaciòn en terreno normal m2 9.68 1.05 10.16 0.00 0.00% 9.68 10.16 100.00% ###
4.04 Eliminacion de material excedente m3 8.89 8.4 74.68 0.00 0.00% 8.89 74.68 100.00% ###
4.05 Encofrado y desencofrado de muros m2 37.32 24.02 896.43 0.00 0.00% 37.32 896.43 100.00% ###
4.06 Acero estructural trabajado para obras de arte kg 194.65 4.13 803.90 0.00 0.00% 194.65 803.90 100.00% ###
4.07 Concreto Simple fc= 175 kg/cm2 m3 3.20 436.81 1,397.79 0.00 0.00% 3.20 1,397.79 100.00% ###
4.08 Tarrajeo con impermeabilizante m2 20.01 18.42 368.58 0.00 0.00% 20.01 368.58 100.00% ###
4.09 suministro de accesorios para desarenador y camara de carga glb 1.00 381.96 381.96 0.00 0.00% 1.00 381.96 100.00% ###
4.1
5
Pintura de Obra de Arte
LINEA DE CONDUCCION (2986m)
m2 20.01 5.82 116.46
52,287.38
0.00 0.00% 20.01 116.46 100.00% ###
5.01 Trazo y Replanteo ml 2986.00 1.22 3,642.92 480.00 585.60 16.08% 2,506.00 3,057.32 83.92% ###
5.02 Excavacion caja de canal en tierra ( a mano) m3 716.64 14 10,032.96 115.20 1,612.80 16.08% 601.44 8,420.16 83.92% ###
5.03 Refine y nivelacion en terreno normal m2 1194.40 1.05 1,254.12 0.00 0.00% 1,194.40 1,254.12 100.00% ###
5.04 Cama de apoyo paratuberia pvc sap ml 2986.00 0.7 2,090.20 0.00 0.00% 2,986.00 2,090.20 100.00% ###
5.05 Relleno y compactado con material propio m3 716.64 8.4 6,019.78 0.00 0.00% 716.64 6,019.78 100.00% ###
5.06 Provisión tuberias PVC SAP C-7.5 D =3" ml 940.00 14.03 13,188.20 0.00 0.00% 940.00 13,188.20 100.00% ###
5.08 Provisión tuberias PVC SAP C-7.5 D =2" ml 1394.00 7.6 10,594.40 0.00 0.00% 1,394.00 10,594.40 100.00% ###
5.09 Provisión tuberias PVC SAP C-7.5 D =1" m 185.00 4.17 771.45 0.00 0.00% 185.00 771.45 100.00% ###
5.1 Provisión tuberias PVC SAP C-7.5 D =3/4" ml 467.00 2.81 1,312.27 0.00 0.00% 467.00 1,312.27 100.00% ###
5.11 Codo PVC SAP de 3" x 45° und 6.00 23.52 141.12 0.00 0.00% 6.00 141.12 100.00% ###
5.12 Codo PVC SAP de 3" x 22.5° und 6.00 22.42 134.52 0.00 0.00% 6.00 134.52 100.00% ###
5.14
6
Prueba hidraulica para tuberias pvc sap
CRUCE AEREO 01 UND
ml 2986.00 1.04 3,105.44
580.62
0.00 0.00% 2,986.00 3,105.44 100.00% ###
CRONOGRAMA REPROGRAMADO DE EJECUCION
MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE RIEGO POR ASERSION EN LA C.C. DE QUEUÑA CANCHA, DISTR. HUANARANI - PAUCARTAMBO -
PROYECTO:
CUSCO
EJECUTADO SALDO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION Und. METRADO PRECIO S/ PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ % S/. % S/. % S/. % S/. %
6.01 Trazo y Replanteo ml 0.25 0.69 0.17 0.00 0.00% 0.25 0.17 100.00% 0.17
6.02 Excavacion para cimientos hasta 1m. m3 0.25 14 3.50 0.00 0.00% 0.25 3.50 100.00% 3.50
6.03 encofrado y desencofrado normal m2 2.00 24.02 48.04 0.00 0.00% 2.00 48.04 100.00% ###
6.04 Concreto Simple fc=175 kg/cm2 m3 0.50 436.81 218.41 0.00 0.00% 0.50 218.41 100.00% ###
6.05 Tarrajeo con impermeabilizante m2 2.00 18.42 36.84 0.00 0.00% 2.00 36.84 100.00% ###
6.06 suministro e instalacion tuberia f°g° 2"x 6m m 6.00 33.21 199.26 0.00 0.00% 6.00 199.26 100.00% ###
6.07 suministro de accesorios cruce aereo glb 1.00 62.76 62.76 0.00 0.00% 1.00 62.76 100.00% ###
6.08
7
pintado de obras de arte
CAMARA DE REUNION (2 UND)
m2 2.00 5.82 11.64
3,272.93
0.00 0.00% 2.00 11.64 100.00% ###
7.01 Trazo y Replanteo ml 2.42 0.69 1.67 0.00 0.00% 2.42 1.67 100.00% 1.67
7.02 Excavacion para cimientos hasta 1m. m3 2.18 14 30.52 0.00 0.00% 2.18 30.52 100.00% ###
7.03 Refine y nivelacion en terreno normal m2 2.42 1.05 2.54 0.00 0.00% 2.42 2.54 100.00% 2.54
7.04 encofrado y desencofrado normal m2 22.66 24.02 544.29 0.00 0.00% 22.66 544.29 100.00% ###
7.05 Acero estructural trabajado para obras de arte kg 122.50 4.13 505.93 0.00 0.00% 122.50 505.93 100.00% ###
7.06 Concreto Simple fc=175 kg/cm2 m3 2.97 436.81 1,297.33 0.00 0.00% 2.97 1,297.33 100.00% ###
7.07 Tarrajeo con impermeabilizante m2 22.66 18.42 417.40 0.00 0.00% 22.66 417.40 100.00% ###
7.08 suministro de accesorios para camara de reunion de 2" glb 1.00 234.96 234.96 0.00 0.00% 1.00 234.96 100.00% ###
7.09 suministrode accesorios para camara de reunion de 1" glb 1.00 181.96 181.96 0.00 0.00% 1.00 181.96 100.00% ###
7.1
08
pintado de obras de arte
RESERVORIO DE CONCRETO V=303 m3
m2 9.68 5.82 56.34
73,636.97
0.00 0.00% 9.68 56.34 100.00% ###
08.01 Trazo y Replanteo m2 400.00 0.69 276.00 400.00 276.00 100.00% 0.00 0.00 0.00%
08.02 Excavacion para estructuras m3 476.38 14 6,669.32 476.38 6,669.32 100.00% 0.00 0.00 0.00%
08.03 Refine y nivelacion en terreno normal m2 400.00 1.05 420.00 400.00 420.00 100.00% 0.00 0.00 0.00%
08.04 Eliminacion de material excedente m3 619.30 8.4 5,202.12 619.30 5,202.12 100.00% 0.00 0.00 0.00%
08.05 Empedrado de la base H=0.15 m m2 178.75 21.38 3,821.68 178.75 3,821.68 100.00% 0.00 0.00 0.00%
08.06 encofrado y desencofrado normal m2 132.00 24.02 3,170.64 132.00 3,170.64 100.00% 0.00 0.00 0.00%
08.07 Acero estructural trabajado para obras de arte ( reservorio) kg 1183.28 6.5 7,691.32 1,183.28 7,691.32 100.00% 0.00 0.00 0.00%
08.08 Concreto Ciclopeo f'c=140 kg/cm2 + 70% PG m3 19.11 198.33 3,790.09 19.11 3,790.09 100.00% 0.00 0.00 0.00%
08.09 Concreto simple f'c=210 kg/cm2 m3 60.39 465.23 28,095.24 60.39 28,095.24 100.00% 0.00 0.00 0.00%
08.10 Tarrajeo con impermeabilizante m2 301.95 18.42 5,561.92 301.95 5,561.92 100.00% 0.00 0.00 0.00%
08.11
08.12
Juntas asfalticas de dilatación
juntas water stop 6"
m
m
179.00
179.00
13.63
23.68
2,439.77
4,238.72
0.00
179.00
0.00
4,238.72
0.00%
100.00%
179.00
0.00
2,439.77
0.00
100.00%
0.00%
###
08.13 Suministro de accesorios para reservorio glb 1 561.76 561.76 0.40 224.70 40.00% 0.60 337.06 60.00% ###
08.14 Suministro de accesorios cerco perimetrico 1.00 1259.05 1,259.05 0.00 0.00 0.00% 1.00 1,259.05 100.00% ###
08.15
09
Pintura de Obra de Arte
RESERVORIO DE CONCRETO V=123 m3
m2 75.49 5.82 439.35
40,443.00
0.00 0.00 0.00% 75.49 439.35 100.00% ###
09.01 Trazo y Replanteo m2 217.50 0.69 150.08 217.50 150.08 100.00% 0.00 0.00 0.00%
09.02 Excavacion para estructuras m3 207.94 14 2,911.16 207.94 2,911.16 100.00% 0.00 0.00 0.00%
09.03 Refine y nivelacion m2 217.50 1.05 228.38 217.50 228.38 100.00% 0.00 0.00 0.00%
09.04 eliminacion material hasta 30.00MT(a mano usando carretilla m3 270.32 8.4 2,270.69 270.32 2,270.69 100.00% 0.00 0.00 0.00%
09.05 Empedrado de la base H=0.15 m m2 156.61 21.38 3,348.32 156.61 3,348.32 100.00% 0.00 0.00 0.00%
09.06 Encofrado y desencofrado normal m2 143.36 24.02 3,443.51 143.36 3,443.51 100.00% 0.00 0.00 0.00%
09.07 Acero estructural kg 515.48 6.5 3,350.62 515.48 3,350.62 100.00% 0.00 0.00 0.00%
09.08 Concreto Ciclopeo f'c=140 kg/cm2 + 70% PG m3 9.31 198.33 1,846.45 9.31 1,846.45 100.00% 0.00 0.00 0.00%
09.09 Concreto simple f'c=175 kg/cm2 m3 32.59 465.23 15,161.85 32.59 15,161.85 100.00% 0.00 0.00 0.00%
09.10 Tarrajeo con impermeabilizante m2 162.95 18.42 3,001.54 162.95 3,001.54 100.00% 0.00 0.00 0.00%
09.11
09.12
juntas asfalticas de dilatacion
juntas water stop 6"
m
m
72.00
75.00
13.63
23.68
981.36
1,776.00
0.00
75.00
0.00
1,776.00
0.00%
100.00%
72.00
0.00
981.36
0.00
100.00%
0.00%
###
09.13 Suministro de accesorios para reservorio glb 1.00 655.26 655.26 0.40 262.10 40.00% 0.60 393.16 60.00% ###
09.14 Suministro de accesorios cerco perimetrico glb 1.00 1074.05 1,074.05 0.00 0.00% 1.00 1,074.05 100.00% ###
09.15
10
Pintura de Obra de Arte
reservorio de concreto (108m3)
m2 41.88 5.82 243.74
30,240.04
0.00 0.00% 41.88 243.74 100.00% ###
10.01 Trazo y Replanteo m2 217.50 0.69 150.08 217.50 150.08 100.00% - 0.00 0.00%
10.02 excavacion para estructuras m3 179.30 14 2,510.20 179.30 2,510.20 100.00% - 0.00 0.00%
10.03 refine y nivelacion en terreno normal m2 217.50 1.05 228.38 217.50 228.38 100.00% - 0.00 0.00%
10.04 eliminacion materialexcedente hasta 30.00MT(a mano usando carretilla) m3 233.09 8.4 1,957.96 233.09 1,957.96 100.00% - 0.00 0.00%
10.05 empedrado de la base H=0.15 m m2 123.48 21.38 2,640.00 123.48 2,640.00 100.00% - 0.00 0.00%
10.06 Encofrado y desencofrado normal m2 129.25 24.02 3,104.59 129.25 3,104.59 100.00% - 0.00 0.00%
10.07 acero estructural trabajado para obras de barte(reservorio) kg 481.87 6.5 3,132.16 481.87 3,132.16 100.00% - 0.00 0.00%
10.08 concreto siclopio pc=140 kg/cm2+70%pg m3 4.25 198.33 842.90 4.25 842.90 100.00% - 0.00 0.00%
10.09 concreto simple f'c=210 kg/cm2 m3 18.60 465.23 8,653.28 18.60 8,653.28 100.00% - 0.00 0.00%
10.1 tarrageo impermeabilizante m2 125.00 18.42 2,302.50 125.00 2,302.50 100.00% - 0.00 0.00%
10.11 juntas asfalticas de dilatacion m 72.00 13.63 981.36 0.00 0.00 0.00% 72.00 981.36 100.00% ###
CRONOGRAMA REPROGRAMADO DE EJECUCION
MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE RIEGO POR ASERSION EN LA C.C. DE QUEUÑA CANCHA, DISTR. HUANARANI - PAUCARTAMBO -
PROYECTO:
CUSCO
EJECUTADO SALDO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION Und. METRADO PRECIO S/ PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ % S/. % S/. % S/. % S/. %
10.12 juntas water stop 6" m 75.00 23.68 1,776.00 75.00 1,776.00 100.00% - 0.00 0.00%
10.13 suministro de accesorios para reservorio glb 1.00 655.26 655.26 0.40 262.10 40.00% 0.60 393.16 60.00% ###
10.14 suministro de accesorios para cerco perimetrico glb 1.00 1074.05 1,074.05 0.00 0.00 0.00% 1.00 1,074.05 100.00% ###
10.15
11
pintado de obra de arte
caja de valvula principal
m2 39.75 5.82 231.35
3,120.96
0.00 0.00 0.00% 39.75 231.35 100.00% ###
11.01 Trazo y Replanteo m2 1.47 0.69 1.01 0.00 0.00% 1.47 1.01 100.00% 1.01
11.02 excavacion para cimientos hasta 1m terreno normal m3 0.74 14 10.36 0.00 0.00% 0.74 10.36 100.00% ###
11.03 eliminacion material excesente hasta 30.00mt (a mano usando crretilla) m3 2.87 8.4 24.11 0.00 0.00% 2.87 24.11 100.00% ###
11.04 encofrado y desencofrado normal m2 7.20 24.02 172.94 0.00 0.00% 7.20 172.94 100.00% ###
11.05 concreto simple fc=175 kg/cm2 m3 0.58 436.81 253.35 0.00 0.00% 0.58 253.35 100.00% ###
11.06 tarrageo con impermeabilizante m2 4.20 18.42 77.36 0.00 0.00% 4.20 77.36 100.00% ###
11.07 suministro de accesorios para caja de valvula principal 3 glb 1.00 1004.46 1,004.46 0.00 0.00% 1.00 1,004.46 100.00% ###
11.08 suministro de accesorios para caja de valvula principal 2 glb 2.00 776.46 1,552.92 0.00 0.00% 2.00 1,552.92 100.00% ###
11.09
12
pintado de obras de arte
red de distribucion (4213.14m)
m2 4.20 5.82 24.44
71,237.09
0.00 0.00% 4.20 24.44 100.00% ###
12.01 obras preliminares 5,140.03
12.01.01
12.02
trazo y Replanteo
movimientos de tierras
m 4213.14 1.22 5,140.03
32,677.05
0.00 0.00% 4,213.14 5,140.03 100.00% ###
12.02.01 excabacion de caja de canales en tierra (a mano) 3m 1011.15 14 14,156.10 0.00 0.00% 1,011.15 14,156.10 100.00% ###
12.02.02 refine y nivelacion terreno normal para tub. 1"a4" n2 1,685.26 4.20 7,078.09 0.00 0.00% 1,685.26 7,078.09 100.00% ###
12.02.03 cama de apoyo para tuberia pvc sap m 4,213.14 0.70 2,949.20 0.00 0.00% 4,213.14 2,949.20 100.00% ###
12.02.04
12.03
relleno y comp.mat.propio en zanjas
instalacion de tuberias
m3 1,011.15 8.40 8,493.66
32,028.37
0.00 0.00% 1,011.15 8,493.66 100.00% ###
12.03.01 provision e instalacion tuberia pvc.sap c-7.5d=3" m 715.28 14.03 10,035.38 0.00 0.00% 715.28 10,035.38 100.00% ###
12.03.02 provision e instalcion tuberia pvc -sapc-7.5d=2" m 1024.29 7.6 7,784.60 0.00 0.00% 1,024.29 7,784.60 100.00% ###
12.03.03 provision e istalacion tuberias pvc-sapc-10d=11/2" m 548.69 6.29 3,451.26 0.00 0.00% 548.69 3,451.26 100.00% ###
12.03.04 provision e instalacion tuberia pvc-sapc10d=1" m 710.70 4.17 2,963.62 0.00 0.00% 710.70 2,963.62 100.00% ###
12.03.05 provision e instalacion tuberia pvc.sap c-10d=3/4" m 1,214.18 2.81 3,411.85 0.00 0.00% 1,214.18 3,411.85 100.00% ###
12.03.06
12.04
prueba hidraulica tuberias pvc sap
instalacione de accesorios
m 4,213.14 1.04 4,381.67
1,391.64
0.00 0.00% 4,213.14 4,381.67 100.00% ###
12.04.01 tee pvc-sap 3"x1" und 3.00 32.52 97.56 0.00 0.00% 3.00 97.56 100.00% ###
12.04.02 tee pvc-sap 3"x2" und 3.00 28.02 84.06 0.00 0.00% 3.00 84.06 100.00% ###
12.04.03 tee pvc-sap 2"x1" und 14.00 21.67 303.38 0.00 0.00% 14.00 303.38 100.00% ###
12.04.04 reduccion pvc sap de 3"a 2" und 3.00 16.98 50.94 0.00 0.00% 3.00 50.94 100.00% ###
12.04.05 rduccion pvc sap de 2" a1" und 10.00 12.98 129.80 0.00 0.00% 10.00 129.80 100.00% ###
12.04.06 reduccion pvc sap de 2"a1.5" und 15.00 13.48 202.20 0.00 0.00% 15.00 202.20 100.00% ###
12.04.07 reduccion pvc de 1" a 3/4" und 20.00 12.98 259.60 0.00 0.00% 20.00 259.60 100.00% ###
12.04.08 codo pvc-sap3"x45" und 3.00 23.52 70.56 0.00 0.00% 3.00 70.56 100.00% ###
12.04.09 cdo pvc-sap2"x45" und 3.00 16.52 49.56 0.00 0.00% 3.00 49.56 100.00% ###
12.04.10 codo pvc-sap 1"x45 und 3.00 12.98 38.94 0.00 0.00% 3.00 38.94 100.00% ###
12.04.11 codo pvc-sap 3"x90 und 2.00 24.52 49.04 0.00 0.00% 2.00 49.04 100.00% ###
12.04.12 CODO PVC SAP 2" X 90° und 2.00 15.02 30.04 0.00 0.00% 2.00 30.04 100.00% ###
12.04.13
13
coDO PVC SAP 1" X 90°
caja de valvulas de control (09UND)
und 2.00 12.98 25.96
4,776.82
0.00 0.00% 2.00 25.96 100.00% ###
13.01 TRAZO Y REPLANTEO m2 3.24 0.69 2.24 0.00 0.00% 3.24 2.24 99.80% 2.24
13.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 1.94 14.00 27.16 0.00 0.00% 1.94 27.16 100.00% ###
13.03 eliminacion de material excedente hasta 30.00 MT (A MANO USANDO CARREm3 3.53 8.40 21.25 0.00 0.00% 3.53 29.65 139.54% ###
13.04 encofrado desencofrado normal m2 20.16 24.02 484.24 0.00 0.00% 20.16 484.24 100.00% ###
13.05 concreto simple FC=175KG/CM2 m3 1.22 436.81 532.91 0.00 0.00% 1.22 532.91 100.00% ###
13.06 tarrajeo exteriores m2 7.20 15.97 114.98 0.00 0.00% 7.20 114.98 100.00% ###
13.07 suminestro de accesorios para caja de valvula de 3" GLB 4.00 553.46 2,213.84 0.00 0.00% 4.00 2,213.84 100.00% ###
13.08 SUminestro de accesorios para caja de valvula de 2" GLB 2.00 325.46 650.92 0.00 0.00% 2.00 650.92 100.00% ###
13.09 suminestro de accesorios para caja de valvula de 1.05" GLB 1.00 252.46 252.46 0.00 0.00% 1.00 252.46 100.00% ###
13.10 suminestro de accesorios para caja de valvula de 1" GLB 2.00 217.46 434.92 0.00 0.00% 2.00 434.92 100.00% ###
13.11
14
pintado de hobra de arte
CAMARA ROMPREPRESION (02 UND)
m2 7.20 5.82 41.90
3,802.02
0.00 0.00% 7.20 41.90 100.01% ###
14.01 TRAZO Y REPLANTEO m2 3.30 0.69 2.28 0.00 0.00% 3.30 2.28 99.87% 2.28
14.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 2.64 14.00 36.96 0.00 0.00% 2.64 36.96 100.00% ###
14.03 refine y nivelacion en terreno normal m2 3.30 1.05 3.47 0.00 0.00% 3.30 3.47 99.86% 3.47
14.04 acero estructural trabajando para obra de arte KG 80.04 4.13 330.57 0.00 0.00% 80.04 330.57 100.00% ###
14.05 encofrado desencofrado MUROS m2 27.22 24.02 653.82 0.00 0.00% 27.22 653.82 100.00% ###
14.06 concreto simple FC=175KG/CM2 m3 3.87 436.81 1,690.45 0.00 0.00% 3.87 1,690.45 100.00% ###
14.07 tarajeo con impermeabilizante m2 27.22 18.42 501.39 0.00 0.00% 27.22 501.39 100.00% ###
CRONOGRAMA REPROGRAMADO DE EJECUCION
MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE RIEGO POR ASERSION EN LA C.C. DE QUEUÑA CANCHA, DISTR. HUANARANI - PAUCARTAMBO -
PROYECTO:
CUSCO
EJECUTADO SALDO MES 01 MES 02 MES 03 MES 04
ITEM DESCRIPCION Und. METRADO PRECIO S/ PARCIAL S/ METRADO PARCIAL S/ % METRADO PARCIAL S/ % S/. % S/. % S/. % S/. %
14.08 suministro de accesorios para camara de ronpepresion de 3" GLB 1.00 307.96 307.96 0.00 0.00% 1.00 307.96 100.00% ###
14.09 suministro de accesorios para camara de ronpepresion de 2" GLB 1.00 234.96 234.96 0.00 0.00% 1.00 234.96 100.00% ###
14.10
15
pintado de hobra de arte
valvula reductora de presion(02UND)
m2 6.20 5.82 40.16
678.69
0.00 0.00% 6.20 36.08 89.85% ###
15.01 TRAZO Y REPLANTEO m2 0.41 0.69 0.28 0.00 0.00% 0.41 0.28 100.00% 0.28
15.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 0.20 14.00 2.80 0.00 0.00% 0.20 2.80 100.00% 2.80
15.03 ENCOFRADO Y DESENCOFRADO DE MUROS m2 2.12 24.02 50.92 0.00 0.00% 2.12 50.92 100.00% ###
15.04 concreto simple FC=175KG/CM2 m3 0.15 436.81 65.52 0.00 0.00% 0.15 65.52 100.00% ###
15.05 TARRAJEO EN EXTERIORES m2 1.80 15.97 28.75 0.00 0.00% 1.80 28.75 100.00% ###
15.06 SUMINISTROS ACCESORIOS REDUCTORA DE PRESION2" GLB 1.00 326.97 326.97 0.00 0.00% 1.00 326.97 100.00% ###
15.07 SUMINISTRO ACCESORIOS REDUCTORA DEPRESION 3/4" GLB 1.00 192.97 192.97 0.00 0.00% 1.00 192.97 100.00% ###
15.08
16
PINTADO DE OBRAS DE ARTE
VALVULA DE PURGA (04 UND)
m2 1.80 5.82 10.48
1,442.50
0.00 0.00% 1.80 10.48 100.00% ###
16.01 TRAZO Y REPLANTEO m2 1.44 0.69 0.99 0.00 0.00% 1.44 0.99 100.00% 0.99
16.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 0.72 14.00 10.08 0.00 0.00% 0.72 10.08 100.00% ###
16.03 ELIMINACION MATERIAL EXCEDENTE HASTA 30.00MT (A MANNO USANO CARR m3 0.94 8.40 7.90 0.00 0.00% 0.94 7.90 100.00% 7.90
16.04 ENCOFRADO Y DESENCOFRADO DE MUROS m2 8.96 24.02 215.22 0.00 0.00% 8.96 215.22 100.00% ###
16.05 concreto simple FC=175KG/CM2 m3 0.54 436.81 235.88 0.00 0.00% 0.54 235.88 100.00% ###
16.06 TARRAJEO EN EXTERIORES m2 4.80 15.97 76.66 0.00 0.00% 4.80 76.66 100.00% ###
16.07 SUMINISTROS ACCESORIOS VALVULA DE PURGA DE 1" und 4.00 216.96 867.84 0.00 0.00% 4.00 867.84 100.00% ###
16.08
17
PINTADO DE OBRAS DE ARTE
HIDRANTES (45 UND)
m2 4.80 5.82 27.94
12,126.15
0.00 0.00% 4.80 27.94 100.00% ###
17.01 TRAZO Y REPLANTEO m2 9.11 0.69 6.29 0.00 0.00% 9.11 6.29 100.00% 6.29
17.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 MT TERRENO NORMAL m3 4.56 14.00 63.84 0.00 0.00% 4.56 63.84 100.00% ###
17.03 ELIMINACION MATERIAL EXCEDENTE HASTA 30.00MT (A MANNO USANO CARR m3 5.92 8.40 49.73 0.00 0.00% 5.92 49.73 100.00% ###
17.04 ENCOFRADO Y DESENCOFRADO DE MUROS m2 63.00 24.02 1,513.26 0.00 0.00% 63.00 1,513.26 100.00% ###
17.05 concreto simple FC=175KG/CM2 m3 4.06 436.81 1,773.45 0.00 0.00% 4.06 1,773.45 100.00% ###
17.06 TARRAJEO EN EXTERIORES m2 63.00 15.97 1,006.11 0.00 0.00% 63.00 1,006.11 100.00% ###
17.07 SUMINISTRO DE ACCESORIOS PARA HIDRANTE PASANTE DE 1" GLB 10.00 201.87 2,018.70 0.00 0.00% 10.00 2,018.70 100.00% ###
17.08 SUMINISTRO DE ACCESORIOS PARA HIDRANTE FIN DE LINEA 3/4" GLB 35.00 157.47 5,511.45 0.00 0.00% 35.00 5,511.45 100.00% ###
17.09
18
PINTADO DE OBRAS DE ARTE
EQUIPO MOVIL (28)
m2 31.50 5.82 183.33
7,392.00
0.00 0.00% 31.50 183.33 100.00% ###
18.01
19
suministracion de accesorios para equipo movil (naan 423)
transporte de materiales
glb 28.00 264.00 7,392.00
16,749.99
0.00 0.00% 28.00 7,392.00 100.00% ###
19.01 flete terreste glb 1.00 10732.33 10,732.33 0.90 9,659.10 90.00% 0.10 1,073.23 10.00% ###
19.02
20
flete rural
IMPACTO AMBIENTAL
glb 1.00 6017.66 6,017.66
5,480.20
0.90 5,415.89 90.00% 0.10 601.77 10.00% ###
20.01 PLAN DE MANEJO AMBIENTAL 532.20
20.01.01 botadero de desperdicio en obra m3 10.00 16.80 168.00 0.00 0.00% 10.00 168.00 100.00% ###
20.01.02
20.02
reforestacion (plantas nativas)
plan de seguridad
und 1.00 364.20 364.20
980.00
0.00 0.00% 1.00 364.20 100.00% ###
20.02.01
20.03
equipo de proteccion individual
plan de contingencia
glb 1.00 980.00 980.00
3,800.00
0.00 0.00% 1.00 980.00 100.00% ###
20.03.01
20.04
acciones `preventibas de riesgo
plan de cierre de obras
glb 1.00 3,800.00 3,800.00
168.00
0.00 0.00% 1.00 3,800.00 100.00% ###
20.04.01 desmotaje de instalaciones provisionales glb 1.00 84.00 84.00 0.00 0.00% 1.00 84.00 100.00% ###
20.04.02
21
limpieza final de obras
PLAN DE CAPACITACION
glb 1.00 84.00 84.00
7,000.00
0.00 0.00% 1.00 84.00 100.00% ###
21.01 adeuada organización de benificiarios glb 1.00 3500 3,500.00 0.00 0.00% 1.00 3,500.00 100.00% ###
21.02 plan de capacitacion e operación y mantenimiento de sistema riego GLB 1.00 3500 3,500.00 0.00 0.00% 1.00 3,500.00 100.00% ###
descripcion fecha
programacion de obra 150.00 dias
inicio de obra 10/17/2016
fecha de culminacion 10/17/2017
tiempo de ejecucion anterior 180.00 dias
atraso de en ejecucion anterior 30.00 dias
ampliacion de plazo por desabastecimiento de 90
materiales y precipitacion pluvial dias
ampliacion de plazo por mayores metrados 15 dias
ampliacion de plazo por paralizaciones 228 dia
culminacion de obra 10/15/2018
363.00

6/30/2018
256.00
150.00

180.00

2.00
226.00 360