IS - 004 1 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES
CONCRETO
SEGUIMIENTO A RESULTADOS DE CONCRETO SEGÚN NTC 396, NTC 454, NTC 550, NTC 673, NSR-10 NUMERAL C.5.6.2
Criterios de Aceptación
DIAS
Concreto
No. Elemento Estructural Ubicación Informe Cilindro Fecha Toma 7 CORRELACION A 14 DIAS 28 56
(Kg/cm2) RESISTENCIA RESISTENCIA RESISTENCIA RESISTENCIA
Fecha Falla ≥60% ≥80% Fecha Falla ≥100% ≥100%
Kg/cm2 Mpa Kg/cm2 Mpa Kg/cm2 Mpa Kg/cm2 Mpa
333 PANTALLA M-36 (6-7)(H) 66 333 280 07/06/2013 14/06/2013 308 30.2 96% 326.7 32.0 106% 05/07/2013 364 35.7 127%
334 PANTALLA M-10 (D-C)(1) 66 334 420 08/06/2013 15/06/2013 309.5 30.4 72% 357.2 35.0 83% 06/07/2013 452.5 44.4 106%
335 PILOTE 185 66 335 280 08/06/2013 15/06/2013 388.5 38.1 76% 378.5 37.1 93% 06/07/2013 358.5 35.2 126%
336 PILOTE 110 66 336 280 08/06/2013 15/06/2013 260.5 25.5 91% 324.5 31.8 114% 06/07/2013 452.5 44.4 159%
337 PANTALLA M-10 (D-C)(1) 66 337 420 08/06/2013 15/06/2013 271.5 26.6 63% 350.3 34.4 82% 06/07/2013 508 49.8 119%
338 PANTALLA M-10 (D-C)(1) 66 338 420 08/06/2013 15/06/2013 313.5 30.7 73% 368.0 36.1 86% 06/07/2013 477 46.8 111%
339 PANTALLA M-35A (6-7)(H) 66 339 280 08/06/2013 15/06/2013 237.5 23.3 83% 264.2 25.9 93% 06/07/2013 317.5 31.1 111%
340 PANTALLA M-35A (6-7)(H) 66 340 280 08/06/2013 15/06/2013 274.5 26.9 96% 337.0 33.0 118% 06/07/2013 462 45.3 162%
341 PANTALLA M-10 (D-C)(1) 66 341 420 08/06/2013 15/06/2013 288 28.2 67% 366.3 35.9 86% 06/07/2013 523 51.3 122%
342 PILOTE 9 69 342 280 11/06/2013 18/06/2013 227.5 22.3 80% 287.5 28.2 101% 09/07/2013 407.5 40.0 143%
343 PANTALLA M-26 (1-2)(H) 69 343 280 11/06/2013 18/06/2013 264.5 25.9 93% 291.5 28.6 102% 09/07/2013 345.5 33.9 121%
344 PANTALLA M-30 (3-4)(H) 69 344 280 11/06/2013 18/06/2013 250.5 24.6 88% 295.0 28.9 103% 09/07/2013 384 37.7 134%
345 PANTALLA M-26 (1-2)(H) 69 345 280 11/06/2013 18/06/2013 229 22.5 80% 288.5 28.3 101% 09/07/2013 407.5 40.0 143%
346 PILOTE 66 69 346 280 11/06/2013 18/06/2013 235.5 23.1 83% 270.3 26.5 95% 09/07/2013 340 33.3 119%
347 PANTALLA M-30 (3-4)(H) 69 347 280 11/06/2013 18/06/2013 231.5 22.7 81% 301.5 29.6 106% 09/07/2013 441.5 43.3 155%
348 PANTALLA M-26 (1-2)(H) 69 348 280 11/06/2013 18/06/2013 231.5 22.7 81% 292.7 28.7 103% 09/07/2013 415 40.7 145%
349 PANTALLA M-30 (3-4)(H) 69 349 280 11/06/2013 18/06/2013 256.5 25.2 90% 308.0 30.2 108% 09/07/2013 411 40.3 144%
350 PILOTE 188 70 350 420 12/06/2013 19/06/2013 350 34.3 82% 409.2 40.1 96% 10/07/2013 527.5 51.7 123%
351 PANTALLA M-19 (G-H)(1) 70 351 280 12/06/2013 19/06/2013 271 26.6 95% 303.3 29.7 106% 10/07/2013 368 36.1 129%
352 PANTALLA M-19 (G-H)(1) 70 352 280 12/06/2013 19/06/2013 258 25.3 90% 309.3 30.3 108% 10/07/2013 412 40.4 144%
353 PANTALLA M-19 (G-H)(1) 70 353 280 12/06/2013 19/06/2013 237 23.2 83% 299.5 29.4 105% 10/07/2013 424.5 41.6 149%
354 PILOTE 182 70 354 280 12/06/2013 19/06/2013 229 22.5 80% 298.0 29.2 104% 10/07/2013 436 42.8 153%
355 PILOTE 15 71 355 280 13/06/2013 20/06/2013 197.5 19.4 69% 238.3 23.4 83% 11/07/2013 320 31.4 112%
356 PANTALLA M-27 (4-H) 71 356 280 13/06/2013 20/06/2013 179 17.6 69% 225.5 22.1 83% 11/07/2013 318.5 31.2 112%
357 PANTALLA M-27 (4-H) 71 357 280 13/06/2013 20/06/2013 220 21.6 77% 265.0 26.0 93% 11/07/2013 355 34.8 124%
358 PANTALLA M-29 (3-H) 71 358 280 13/06/2013 20/06/2013 214 21.0 75% 261.7 25.7 92% 11/07/2013 357 35.0 125%
359 PANTALLA M-27 (4-H) 71 359 280 13/06/2013 20/06/2013 184 18.0 64% 223.8 22.0 78% 11/07/2013 303.5 29.8 106%
360 PILOTE 05 71 360 280 13/06/2013 20/06/2013 206.5 20.3 72% 241.0 23.6 84% 11/07/2013 310 30.4 109%
361 PANTALLA M-29 (3-H) 71 361 280 13/06/2013 20/06/2013 244.5 24.0 86% 268.3 26.3 94% 11/07/2013 316 31.0 111%
362 PANTALLA M-29 (3-H) 71 362 280 13/06/2013 20/06/2013 220 21.6 77% 246.2 24.1 86% 11/07/2013 298.5 29.3 105%
363 PILOTE 184 72 363 420 14/06/2013 21/06/2013 290 28.4 68% 358.8 35.2 84% 12/07/2013 496.5 48.7 116%
364 PANTALLA M-18 (G-H)(1) 72 364 280 14/06/2013 21/06/2013 254 24.9 89% 287.0 28.1 101% 12/07/2013 353 34.6 124%
365 PANTALLA M-18 (G-H)(1) 72 365 280 14/06/2013 21/06/2013 192.5 18.9 67% 226.5 22.2 79% 12/07/2013 294.5 28.9 103%
366 PANTALLA M-18 (G-H)(1) 72 366 280 14/06/2013 21/06/2013 229.5 22.5 80% 291.3 28.6 102% 12/07/2013 415 40.7 145%
367 PILOTE 115 72 367 280 14/06/2013 21/06/2013 239.5 23.5 84% 300.8 29.5 105% 12/07/2013 423.5 41.5 148%
368 PANTALLA M-28 (2-3)(H) 73 368 280 15/06/2013 22/06/2013 241.5 23.7 85%
369 PILOTE 6 73 369 280 15/06/2013 22/06/2013 246 24.1 86%
370 PANTALLA M-28 (2-3)(H) 73 370 280 15/06/2013 22/06/2013 222.5 21.8 78%
371 PANTALLA M-28 (2-3)(H) 73 371 280 15/06/2013 22/06/2013 202 19.8 71%
372 PILOTE 67 73 372 420 15/06/2013 22/06/2013 276.5 27.1 65%
373 PANTALLA M-191 (1-1´)(C-D) 74 373 210 17/06/2013 24/06/2013 143.5 14.1 67%
374 PANTALLA M-191 (1-1´)(C-D) 74 374 210 17/06/2013 24/06/2013 171.5 16.8 80%
375 PILOTE 59 75 375 280 18/06/2013 25/06/2013 258 25.3 90%
376 PANTALLA M-31 (4-H) 75 376 280 18/06/2013 25/06/2013 253.5 24.9 89%
377 PANTALLA M-31 (4-H) 75 377 280 18/06/2013 25/06/2013 277.5 27.2 97%
378 PANTALLA M-31 (4-H) 75 378 280 18/06/2013 25/06/2013 257 25.2 90%

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 2 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES Criterios de Aceptación
DIAS
Concreto
No. Elemento Estructural Ubicación Informe Cilindro Fecha Toma 7 CORRELACION A 14 DIAS 28 56
(Kg/cm2)
RESISTENCIA RESISTENCIA RESISTENCIA RESISTENCIA
Fecha Falla Fecha Falla
Kg/cm2 Mpa ≥60% Kg/cm2 Mpa ≥80% Kg/cm2 Mpa ≥100% Kg/cm2 Mpa ≥100%
379 PILOTE 22 76 379 420 19/06/2013 26/06/2013 332.5 32.6 78%
380 PANTALLA M-108 (1-1) 76 380 210 19/06/2013 26/06/2013 278.5 27.3 130%
381 PILOTE 22 76 381 420 19/06/2013 26/06/2013 324 31.8 76%
382 PANTALLA M-181 (2-3)( C) 76 382 210 19/06/2013 26/06/2013 204 20.0 95%
383 PILOTE 103 76 383 280 19/06/2013 26/06/2013 191 18.7 67%
384 PILOTE 105 77 384 280 20/06/2013 27/06/2013 217.5 21.3 76%
385 PANTALLA M-8 (B-C)(1) 77 385 420 20/06/2013 27/06/2013 167 16.4 39%
386 PANTALLA M-8 (B-C)(1) 77 386 420 20/06/2013 27/06/2013 227 22.3 53%
387 PANTALLA M-8 (B-C)(1) 77 387 420 20/06/2013 27/06/2013 286.5 28.1 67%
388 PANTALLA M-165 EJES (C)(4-5) 80 388 210 20/06/2013 27/06/2013 196 19.2 92%
389 PANTALLA M-8 EJE (B-C)(1) 80 389 420 20/06/2013 27/06/2013 260.5 25.5 61%
390 PILOTE 51 80 390 420 20/06/2013 27/06/2013 266.5 26.1 62%
391 PANTALLA M-109 EJES (E-D)(1) 80 391 210 21/06/2013 28/06/2013 183 17.9 85%
392 PILOTE 45 80 392 280 21/06/2013 28/06/2013 176 17.3 62%
393 PANTALLA M-180 EJES (D)(2-3) 80 393 210 21/06/2013 28/06/2013 206.5 20.3 96%
394 PILOTE 21 81 394 420 22/06/2013 29/06/2013 208 20.4 66%
395 PANTALLA M-9 EJE (D-C)(1´) 81 395 280 22/06/2013 29/06/2013 227 22.3 80%
396 PANTALLA M-9 EJE (D-C)(1´) 81 396 280 22/06/2013 29/06/2013 212.5 20.8 74%
397 PANTALLA M-166 EJES (D)(4-5) 81 397 210 22/06/2013 29/06/2013 180 17.7 84%
398 PILOTE 42 81 398 280 22/06/2013 29/06/2013 229 22.5 80%
399 PANTALLA M-9 EJE (D-C)(1´) 81 399 280 22/06/2013 29/06/2013 270 26.5 95%
400 PANTALLA M-110 EJES (E-D)(1) 82 400 210 24/06/2013 01/07/2013 202.5 19.9 95%
401 PILOTE 6 82 401 420 24/06/2013 01/07/2013 217 21.3 51%
402 PANTALLA M-113 EJES (E-D)(3) 82 402 210 24/06/2013 01/07/2013 224.5 22.0 105%
403 PILOTE 48 82 403 280 24/06/2013 01/07/2013 251.5 24.7 88%
404 PILOTE 191 83 404 280 25/06/2013 03/07/2013 164.5 16.1 58%
405 PILOTE 186 83 405 280 25/06/2013 03/07/2013 182.5 17.9 64%
406 PANTALLA M-192 EJES (E-1) 83 406 210 25/06/2013 03/07/2013 176.5 17.3 80%
407 PANTALLA M-155 EJES (D)(6-7) 83 407 210 25/06/2013 03/07/2013 152 14.9 71%
408 PANTALLA M-111 EJES (E-D)(1-2) 83 408 210 26/06/2013 03/07/2013 169.5 16.6 79%
409 PILOTE 28 83 409 420 26/06/2013 03/07/2013 275 27.0 64%
410 PANTALLA M-114 EJES (E-D) 4 83 410 210 26/06/2013 03/07/2013 228 22.4 106%
411 PILOTE 28 83 411 420 26/06/2013 03/07/2013 220 21.6 51%
412 PANTALLA M-111 EJES (E-D)(1-2) 83 412 210 26/06/2013 03/07/2013 152 14.9 71%
413 PILOTE 46 84 413 280 27/06/2013 04/07/2013 234.5 23.0 82%
414 PANTALLA M-16 EJE (E-F) (1´) 84 414 420 27/06/2013 04/07/2013 338 33.1 79%
415 PANTALLA M-16 EJE (E-F) (1´) 84 415 420 27/06/2013 04/07/2013 342.5 33.6 80%
M-119 y 120 EJES (E-
416 PANTALLA D)(7) 84 416 210 27/06/2013 04/07/2013 167 16.4 78%
417 PILOTE 44 84 417 420 27/06/2013 04/07/2013 342.5 33.6 80%
418 PANTALLA M-16 EJE (E-F) (1´) 84 418 420 27/06/2013 04/07/2013 288 28.2 67%
419 PANTALLA M-16 EJE (E-F) (1´) 84 419 420 27/06/2013 04/07/2013 340.5 33.4 80%
420 PILOTE 34 84 420 420 27/06/2013 04/07/2013 258 25.3 60%
421 PILOTE 34 84 421 420 27/06/2013 04/07/2013 292 28.6 68%
422 PANTALLA M-112 EJES (E-D)(1-2) 85 422 210 28/06/2013 05/07/2013 183.5 18.0 86%
423 PANTALLA M-115 EJES (E-D) 4 85 423 210 28/06/2013 05/07/2013 167.5 16.4 78%
424 PANTALLA M-17 EJES (G-H)(1-1´) 86 424 280 29/06/2013 06/07/2013 292 28.6 102%
425 PILOTE 187 86 425 280 29/06/2013 06/07/2013 237 23.2 83%
426 PANTALLA M-17 EJES (G-H)(1-1´) 86 426 280 29/06/2013 06/07/2013 251.5 24.7 88%

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 3 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES Criterios de Aceptación
DIAS
Concreto
No. Elemento Estructural Ubicación Informe Cilindro Fecha Toma 7 CORRELACION A 14 DIAS 28 56
(Kg/cm2)
RESISTENCIA RESISTENCIA RESISTENCIA RESISTENCIA
Fecha Falla Fecha Falla
Kg/cm2 Mpa ≥60% Kg/cm2 Mpa ≥80% Kg/cm2 Mpa ≥100% Kg/cm2 Mpa ≥100%
427 PANTALLA M-178 EJES (F)(2-3) 86 427 210 29/06/2013 06/07/2013 192.5 18.9 90%
428 PANTALLA M-178 EJES (F)(2-3) 86 428 210 29/06/2013 06/07/2013 247 24.2 115%
429 PILOTE 175 86 429 280 29/06/2013 06/07/2013 228.5 22.4 80%
430 PILOTE 47 87 430 420 02/07/2013 09/07/2013 264 25.9 62%
431 PANTALLA M-118 (D-E)(6-7) 87 431 210 02/07/2013 09/07/2013 212.5 20.8 99%
432 PANTALLA M-136 (D-E)(6-7) 87 342 210 02/07/2013 09/07/2013 224 22.0 105%
433 PILOTE 43 88 433 280 03/07/2013 10/07/2013 276.5 27.1 97%
434 PANTALLA M-179 (2-3)( E ) 88 434 210 03/07/2013 10/07/2013 228 22.4 106%
435 PILOTE 76 88 435 280 03/07/2013 10/07/2013 269 26.4 94%
436 PANTALLA M-117 (D-E)(6) 88 436 210 03/07/2013 10/07/2013 194.5 19.1 91%
437 PANTALLA M-193 (F)(1-1´) 88 437 210 03/07/2013 10/07/2013 178.5 17.5 83%
438 PILOTE 49 89 438 280 04/07/2013 11/07/2013 278.5 27.3 98%
439 PANTALLA M-116 (D-E)(5-6) 89 439 210 04/07/2013 11/07/2013 203 19.9 95%
440 PANTALLA M-134 (F-G)(1) 89 440 210 04/07/2013 11/07/2013 234 22.9 109%
441 PILOTE 38 89 441 280 04/07/2013 11/07/2013 360.5 35.4 71%
441 PILOTE 38 89 441 280 04/07/2013 11/07/2013 360.5 35.4 71%
442 PANTALLA M-130 (G-F)(2) 89 442 210 04/07/2013 11/07/2013 207 20.3 97%
443 PILOTE 73 90 443 280 05/07/2013 12/07/2013 286 28.0 100%
444 PANTALLA M-154 (6-7)(F) 90 444 210 05/07/2013 12/07/2013 195 19.1 91%
445 PANTALLA M-133 (F-G)(1-1´) 90 445 210 05/07/2013 12/07/2013 207.5 20.3 97%
OBSERVACIONES.
La Muestra 304 pilote 70 Resistencia Baja a los 28 días, se debe fallar cilindro a los 56 días (27 de julio)
La Muestra 305 (M-21) Resistencia Baja a los 28 días, se debe fallar cilindro a los 56 días (27 de julio)
La Muestra 306 (M-38) Resistencia Baja a los 28 días, se debe fallar cilindro a los 56 días (27 de julio)
La Muestra 307 (M-21) Resistencia Baja a los 28 días, se debe fallar cilindro a los 56 días (27 de julio)
La Muestra 308 (M-38) Resistencia Baja a los 28 días, se debe fallar cilindro a los 56 días (27 de julio)
La Muestra 310 pilote 4 Resistencia Baja a los 28 días, se debe fallar cilindro a los 56 días (27 de julio)
La Muestra 311 (M-38) Resistencia Baja a los 28 días, se debe fallar cilindro a los 56 días (27 de julio)
La muestra 385 (M-8) Resistencia Baja a los 7 días.
La muestra 386 (M-8) Resistencia Baja a los 7 días.
La Muestra 401 pilote 6 Resistencia Baja a los 7 días
La Muestra 404 pilote 191 Resistencia Baja a los 7 días
La Muestra 411 pilote 28 Resistencia Baja a los 7 días

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 4 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
CONTROLGRAFICO
DE CALIDAD MATERIALES
DE SEGUIMIENTO

Resistencias Normales - Pilotes Normal


1.8 70

185

110

9
1.6
66

188

182

15

1.4 15

05

184

115

6
1.2
67

59

22

22
Resistencia a la compresión

1 103

105

51

45

21
0.8
42

48

191

186
0.6
28

28

46

44
0.4 34

34

187

175

47
0.2
43

76

49

38

0 38
0 5 10 15 20 25 30
73
Edad (días)

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 5 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES Normal

1.8
Resultados Normales - Pantalla M-21 (I-H)(1)
M-38 (H-7)
M-21 (I-H)(1)
M-38 (H-7)
M-21 (I-H)(1)
M-38 (H-7)
M-10 (D-C)(1)
M-36 (6-7)(H)
M-10 (D-C)(1)
1.6 M-10 (D-C)(1)
M-35A (6-7)(H)
M-35A (6-7)(H)
M-10 (D-C)(1)
M-26 (1-2)(H)
M-30 (3-4)(H)
M-26 (1-2)(H)
M-30 (3-4)(H)
1.4 M-26 (1-2)(H)
M-30 (3-4)(H)
M-19 (G-H)(1)
M-19 (G-H)(1)
M-19 (G-H)(1)
M-27 (4-H)
M-27 (4-H)
M-29 (3-H)
1.2 M-27 (4-H)
M-29 (3-H)
M-29 (3-H)
M-18 (G-H)(1)
M-18 (G-H)(1)
M-18 (G-H)(1)
M-28 (2-3)(H)
Resistencia a la compresión

M-28 (2-3)(H)
1 M-28 (2-3)(H)
M-191 (1-1´)(C-D)
M-191 (1-1´)(C-D)
M-31 (4-H)
M-31 (4-H)
M-31 (4-H)
M-108 (1-1)
M-181 (2-3)( C)
M-8 (B-C)(1)
0.8 M-8 (B-C)(1)
M-8 (B-C)(1)
M-165 EJES (C)(4-5)
M-8 EJE (B-C)(1)
M-109 EJES (E-D)(1)
M-180 EJES (D)(2-3
M-9 EJE (D-C)(1´)
M-9 EJE (D-C)(1´)
0.6 M-166 EJES (D)(4-5)
M-9 EJE (D-C)(1´)
M-110 EJES (E-D)(1)
M-113 EJES (E-D)(3)
M-192 EJES (E-1)
M-155 EJES (D)(6-7)
M-111 EJES (E-D)(1-2)
M-114 EJES (E-D) 4
0.4 M-111 EJES (E-D)(1-2)
M-16 EJE (E-F) (1´)
M-16 EJE (E-F) (1´)
M-119 y 120 EJES (E-D)(7)
M-16 EJE (E-F) (1´)
M-16 EJE (E-F) (1´)
M-112 EJES (E-D)(1-2)
M-115 EJES (E-D) 4
0.2 M-17 EJES (G-H)(1-1´)
M-178 EJES (F)(2-3)
M-178 EJES (F)(2-3)
M-118 (D-E)(6-7)
M-136 (D-E)(6-7)
M-179 (2-3)( E )
M-117 (D-E)(6)
M-193 (F)(1-1´)
0 M-116 (D-E)(5-6)
M-134 (F-G)(1)
0 5 10 15 20 25 30 M-130 (G-F)(2)
Edad (días) M-154 (6-7)(F)
M-133 (F-G)(1-1´)

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 6 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
SUPERVISIÓN DE ACTIVIDADES
CONTROL DE CALIDAD- INSPECCIÓN
MATERIALESEN CAMPO
Recepción de Concreto Pilotes
CEC – T2 PILOTES
ELEMENTO DIMENSIONES CONCRETO VOLUMEN EXPANSIONES
FECHA OBSERVACIONES
# PILOTE TIPO Ǿ L.EFECT NIVEL CIMENTACION NIVEL SUPERIOR Kg/cm2 PSI TEORICO REAL EXPANSION (+) EXPANSION (-)
09/jul/13 #153 P5 0.90 50.00 -63.60 SOTANO 4 280 4000 31.81 36 13.17% 0.00%
09/jul/13 #75 P9 0.90 56.60 -63.60 SOTANO 2 420 6000 36.00 39 8.33% 0.00%
10/jul/13 #40 P7 1.00 63.60 -63.60 PISO 1 420 6000 50.74 68 34.02% 0.00%
10/jul/13 #112 P5 0.90 49.00 -62.60 SOTANO 4 280 4000 31.17 35 12.29% 0.00%
11/jul/13 #258 P4 0.80 44.00 -57.60 SOTANO 4 280 4000 22.12 24 8.50% 0.00%
11/jul/13 #190 P5 0.90 47.00 -60.60 SOTANO 4 280 4000 29.90 31 3.68% 0.00%
11/jul/13 #181 P5 0.90 48.00 -61.60 SOTANO 4 280 4000 30.53 32 4.81% 0.00%
12/jul/13 #255 P4 0.80 44.00 -57.60 SOTANO 4 280 4000 22.12 24 8.50% 0.00%
13/jul/13 #117 P9 0.90 55.60 -62.60 SOTANO 2 420 6000 35.37 38 7.44% 0.00%
13/jul/13 #183 P4 0.80 44.00 -57.60 SOTANO 4 280 4000 22.12 24 8.50% 0.00%
15/jul/13 #39 P1 0.80 59.80 -59.80 PISO 1 420 6000 30.06 42 39.72% 0.00%
15/jul/13 #74 P5 0.90 47.00 -60.60 SOTANO 4 280 4000 29.90 32 7.02% 0.00%
PILOTES FUNDIDOS EN EL PERIODO 12 PILOTES FUNDIDOS ACUMULADOS AL INFORME 018
PROMEDIOS EXPANSION ACUMULADA PILOTES FUNDIDOS ACUMULADOS PROMEDIOS EXPANSION ACUMULADA PILOTES FUNDIDOS ACUMULADOS
TIPO EXPANSION VALOR TIPO TOTAL TIPO EXPANSION VALOR TIPO TOTAL
POSITIVAS 9.06% P1 5 POSITIVAS 9.29% P1 6
NEGATIVAS -1.67% P2 3 NEGATIVAS -1.67% P2 3
PILOTES FUNDIDOS AL INFORME 018 9 P3 6 P3 6
P4 58 P4 61
P5 80 P5 85
P6 11 P6 11
P7 5 P7 6
P8 3 P8 3
P9 27 P9 29
TOTAL 198 TOTAL 210
Recepción de Concreto Muros Pantallas Internas
CEC – T2 PANTALLAS INTERNAS
ELEMENTO DIMENSIONES CONCRETO VOLUMEN EXPANSIONES
FECHA OBSERVACIONES
# PANTALLA TIPO A B LONGITUD NIVEL CIMENT. NIVEL SUPERIOR Kg/cm2 PSI TEORICO REAL EXPANSION (+) EXPANSION (-)
09/jul/13 M132 EJES (G-F)(7) MP3 5.20 0.40 17.20 -24.2 SOTANO 2 210 3000 35.78 41.55 16.14% 0.00%
09/jul/13 M123 EJES (G-F)(7) MP3 5.20 0.40 17.20 -24.2 SOTANO 2 210 3000 35.78 43 20.19% 0.00%
10/jul/13 M151 Y 152 EJES (6-7)(G) MP3 8.48 0.40 17.20 -24.2 SOTANO 2 210 3000 58.34 64 9.70% 0.00%
11/jul/13 M167 EJES (4-5)(E) MP2 6.40 0.40 16.2 -23.2 SOTANO 2 210 3000 40.15 44.0 9.59% 0.00%
11/jul/13 M194 y 195 EJES G-1 MP3 8.48 0.40 17.20 -24.2 SOTANO 2 210 3000 58.34 61 4.56% 0.00%
12/jul/13 M129 EJES (G-F)(2-3) MP3 5.20 0.40 17.20 -24.2 SOTANO 2 210 3000 32.91 40 21.54% 0.00%
12/jul/13 M146 EJES (6-7)(H) MP3 6.94 0.40 17.20 -24.2 SOTANO 2 210 3000 47.71 53 11.08% 0.00%
13/jul/13 M137 y 197 EJES H-1 MP3 7.80 0.40 17.20 -24.2 SOTANO 2 210 3000 55.41 63.5 14.60% 0.00%
13/jul/13 M150 EJES (H) (6-7) MP3 7.10 0.40 17.20 -24.2 SOTANO 2 210 3000 48.85 49 0.31% 0.00%
15/jul/13 M124 EJES (6) (G-F) MP3 6.60 0.40 17.2 -24.2 SOTANO 2 210 3000 45.41 47.5 4.61% 0.00%
15/jul/13 M138 EJES (H-G) (1-2) MP3 6.68 0.40 17.2 -24.2 SOTANO 2 210 3000 47.19 50.5 7.01% 0.00%
PANTALLAS FUNDIDAS EN EL PERIODO 11 PANTALLAS INTERNAS FUNDIDAS AL INFORME 018 PANTALLAS INTERNAS FUNDIDAS AL PRESENTE INFORME
PROMEDIOS EXPANSION ACUMULADA PANTALLAS FUNDIDAS ACUMULADAS PROMEDIOS EXPANSION ACUMULADA PANTALLAS FUNDIDAS ACUMULADAS
TIPO EXPANSION VALOR TIPO TOTAL TIPO EXPANSION VALOR TIPO TOTAL
PANTALLAS FUNDIDAS AL INFORME 018 13 POSITIVAS 8.23% MP-2 36 POSITIVAS 8.53% MP-2 37
NEGATIVAS 0.00% MP-3 38 NEGATIVAS 0.00% MP-3 48
TOTAL 74 TOTAL 85
TOTAL ELEMENTOS FUNDIDOS EN EL PERIODO 23
TOTAL ELEMENTOS FUNDIDOS INFORME 018 22
OBSERVACIONES.
No se Funden Pantallas Perimetrales Durante el Periodo

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 7 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
CONTROL
SUPERVISIÓN DE CALIDAD
DE ACTIVIDADES MATERIALES
- INSPECCIÓN EN CAMPO
Inspección Refuerzo placas
Ubicación
Fecha Elemento OBSERVACIONES
ARMADO DESDE ARMADO HASTA
09-07-12 VG-8 P1 P-1 EJE 1' EJE 3
09-07-12 VG-20 P1 P-1 EJE A'' B
10-07-12 VG-35 P1 P-1 BARRETE 2 C-21
10-07-12 VG-26 P1 P-1 BARRETE 71 1/3 DESPUES DE VG-36
11-07-12 VG-24 P1 P-1 BARRETE 71 1/3 DESPUES DE VG-26 Demora en el armado de refuerzo
11-07-12 VG-36 P1 P-1 C-21 1/3 DESPUES DE VG-26 Demora en el armado de refuerzo
12-07-12 VT-1 P-1 BARRETE 2 1/3 DESPUES DE VG-36
12-07-12 VT-2 P-1 MODULO 3 1/3 DESPUES DE VG-36
13-07-12 VT-11 P-1 BARRETE 4 1/3 DESPUES DE VG-36
15-07-12 VT-31 P-1 MODULO 72 1/3 DESPUES DE VG-26 Traslapos cortos
15-07-12 VT-32 P-1 MODULO 72 1/3 DESPUES DE VG-26 Traslapos cortos
Inspección Refuerzo
Amarre Empalme Cumple
Fecha Elemento Estructural Tipo Ubicación Espaciam. Flejes Malla Diámetro Observación
refuerzo canastas SI NO
PILOTE P-153 P5 (E-D)(1-1´) OK OK N.A OK OK OK X
PILOTE P-75 P9 (C )(1-1´) OK OK N.A OK OK OK X
09-07-13
PANTALLA M-123 MP3 (F-G)(6-7) OK OK N.A OK OK OK X
PANTALLA M-132 MP3 (F-G)(1-1´) OK OK N.A OK OK OK X
PILOTE P-40 P7 (A-A´)(6) OK OK N.A OK OK OK X
10-07-13 PILOTE P-112 P5 (B-C)(6-7) OK OK N.A OK OK OK X
PANTALLA M-151 MP3 (H-G)(6-7) OK OK N.A OK OK OK X
PILOTE P-258 P4 (H)(2-3) OK OK N.A OK OK OK X
PILOTE P-190 P5 (E-F)(5-6) OK OK N.A OK OK OK X
11-07-13 PILOTE P-181 P5 (E-F)(6-7) OK OK N.A OK OK OK X
PANTALLA M-167 MP2 ( E )(4-5) OK OK N.A OK OK OK X
PANTALLA M-195 MP3 (H-G)(1) OK OK N.A OK OK OK X
PILOTE P-255 P4 (H)(3-4) OK OK N.A OK OK OK X
12-07-13 PANTALLA M-129 MP3 (G-F)(2-3) OK OK N.A OK OK OK X
PANTALLA M-146 MP3 (H-G)(6-7) OK OK N.A OK OK OK X
PILOTE P-117 P9 (D-5) OK OK N.A OK OK OK X
PILOTE P-183 P4 (E-D)(7) OK OK N.A OK OK OK X
13-07-13
PANTALLA M-137 MP3 (H-G)(1) OK OK N.A OK OK OK X
PANTALLA M-150 MP3 (H-G)(6-7) OK OK N.A OK OK OK X
PILOTE P-39 P1 (A-6) OK OK N.A OK OK OK X
PILOTE P-74 P5 (C-D)(1-1´) OK OK N.A OK OK OK X
15-07-13
PANTALLA M-124 MP3 (G-F)(6) OK OK N.A OK OK OK X
PANTALLA M-138 MP3 (H-G)(2-3) OK OK N.A OK OK OK X

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 8 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE DE
CONTROL CALIDAD MATERIALES
ASENTAMIENTO
VÍAS CERCANAS
CL 127 A
PUNTO FECHA E-1 E-2 E-3 E-4 V-5 P-1 P-2 V-1 P-3 P-4 P-5 P-6
COTA INICIAL 18-mar-13 49.782 49.876 49.941 50.027 50.144 49.643 49.528 49.435 49.340 49.293 49.245 49.191
CONTROL 15-jul-13 49.791 49.890 49.954 50.036 50.146 49.657 49.533 49.441 49.340 49.293 49.245 49.191
DIFERENCIA 15-jul-13 0.009 0.014 0.013 0.009 0.002 0.014 0.005 0.006 0.000 0.000 0.000 0.000
CARRERA 53A COMPORTAMIENTO DESDE INFORME 016 HASTA EL 017
PUNTO FECHA V-7 E-H E-G E-F E-E E-D E-C E-B E-A E-A" V-11 Puntos que Presentan Movimiento.
COTA INICIAL 18-mar-13 50.239 50.309 50.394 50.486 50.533 50.579 50.616 50.649 50.672 50.637 50.645 Puntos que No Presentan Movimiento.
CONTROL 15-jul-13 50.245 50.315 50.404 50.498 50.542 50.579 50.619 50.652 50.676 50.649 50.643
DIFERENCIA 15-jul-13 0.006 0.006 0.010 0.012 0.009 0.000 0.003 0.003 0.004 0.012 -0.002
CONTROL DE CLL 127A Hasta este periodo existe un rebote máximo en el punto E-2 de 0.014m
ASENTAMIENTOS CARRERA 53 A Hasta este periodo existe un rebote máximo en el punto E-F de 0.012m y un asentamiento máximo en el punto V-11 de -0.002m
DIFICULTADES E IMPREVISTOS DURANTE LA SEMANA
OBSERVACIONES:
Los refuerzos que especifican los planos para las vigas de piso 1, no caben dentro de la fila que indica pues se genera bastante congestión entre aceros.
Los ganchos suplementarios quedan sin amarrar por no existir su par de refuerzo longitudinal en la cara opuesta a este.
Los traslapos se han movido a escala en planos pues no existe por parte del diseñador una tabla de traslapos mínimos.
Observamos que cortan las escuadras del acero de superior en pantallas, barretes y pilotes sin consultar con el personal adecuado para autorizar esta actividad.
En general existe bastante dificultad al armar el acero de los elementos por las deficiencias en el proyecto estructural.
ESTADO DEL TIEMPO DURANTE EL PERIODO
ESTADO DEL TIEMPO 09 JULIO 2013
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total CONVENCIONES
SECO 13 LL-L Lluvia Leve
LL.L LL-M Lluvia Moderada
LL.M LL-F Lluvia Fuerte
LL.F
ESTADO DEL TIEMPO 10 JULIO 2013 TOTAL ESTADO DE TIEMPO EN EL PERIODO
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total Tiempo Horas % Tiempo
SECO 10 Seco 75 96.15
LL.L Lluvia Leve 0 0.00
LL.M 3 Lluvia Moderada 3 3.85
LL.F Lluvia Fuerte 0 0.00
ESTADO DEL TIEMPO 11 JULIO 2013 Total Horas 78 100
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total ESTADO DE TIEMPO INFORME 018
SECO 13 Tiempo Horas % Tiempo
LL.L Seco 78 100.00
LL.M Lluvia Leve 0 3.08
LL.F Lluvia Moderada 0 0.00
ESTADO DEL TIEMPO 12 JULIO 2013 Lluvia Fuerte 0 0.00
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total Total Horas 78 100
SECO 13
LL.L
LL.M
LL.F
ESTADO DEL TIEMPO 13 JULIO 2013
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total
SECO 13
LL.L
LL.M
LL.F

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 9 de 9

INFORME SEMANAL No 019


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparo Ing. Juan Carlos Cruz Diaz Reviso Ing. Luis Gonzalo Villada B.
ESTADO DEL TIEMPO 15 JULIO 2013 CONTROL DE CALIDAD MATERIALES
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total
SECO 13
LL.L
LL.M
LL.F
RECOMENDACIONES
MUESTRA SEPARADORES Se recomienda utilizar las muestras presentadas (separador tipo clip) solo en las placas inferiores, pues este tipo de separador no es de mucha utilidad cuando se apoya en casetón .
CORTE DE ACEROS DE
Por ningún motivo se debe cortar el acero de refuerzo en pantallas, barretes, pilotes y demás elementos estructurales, sin consultar con la supervisión técnica.
REFUERZO
FLEJES DE BARRETES Y
Se deben reemplazar los flejes superiores de las pantallas y barretes que fueron afectados en el momento de la demolición antes de armar las viga perimetral.
PANTALLAS
ARMADO DE ELEMENTOS
Comunicar al contratista de la estructura, que toda dificultad en el amarre del acero tendrá que comunicarla al personal especialista que se encuentra en obra quien dará una solución acertada al respecto.
ESTRUCTURALES

(Firma)

(Nombre) Ing. Luis Gonzalo Villada CONSULTORÍA ESTRUCTURAL


Director Supervisión Técnica

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
AVANCE DE OBRA
Avance en Pilotaje

PLANO DE AVANCE

OBSERVACIONES.
Pilotes Ejecutados a informe 018 Pilotes Ejecutados durante el periodo Total Acumulado Pilotes Totales Pilotes Faltantes
198 12 210 257 47
Avance muros pantallas y contrafuertes

PLANO DE AVANCE

OBSERVACIONES.
Avance en Excavacion, Solado de Limpieza ,Armado de refuerzo y Fundida de placas. Nivel -0.50

PLANO DE AVANCE

OBSERVACIONES.
PLANO DE LOCALIZACION CONTROL DE ASENTAMIENTOS
GRAFICA CONTROL DE ASENTAMIENTOS
CONTROL ASENTAMIENTO CEC T-2
Normal
15
E-1

14
E-2

13 E-3

12 E-4

V-5
11
V-7
10
E-H

9 E-G

8 E-F
COMPORTAMIENTO (mm)

E-E
7
E-D
6
E-C
5
E-B

4 E-A

3 E-A"

V-11
2
P-1
1
P-2

0
V-1

-1 P-3

-2 P-4

FECHA LECTURAS TOPOGRAFICAS P-5


-3
P-6
GRAFICA CONTROL DE ASENTAMIENTOS
CONTROL ASENTAMIENTO CEC T-2 Normal
15
E-1

14 E-2

13 E-3

E-4
12
V-5
11
V-7
10
E-H

9 E-G

8 E-F
COMPORTAMIENTO (mm)

E-E
7

E-D
6
E-C
5
E-B

4
E-A

3 E-A"

V-11
2

P-1
1
P-2
0
V-1

-1
P-3

-2 P-4
FECHA LECTURAS TOPOGRAFICAS
-3 P-5

P-6
INFORME SEMANAL No 019
CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparó Ing. Juan Carlos Cruz Diaz Revisó Ing. Luis Gonzalo Villada B.
ANEXO 1. REGISTRO FOTOGRÁFICO

Foto 1 y 2.Fundida de Solado Limpieza y Afinado de Piso Base para Placa .

Foto 3 y 4. Corte del Solado y Excavación de Vigas Reforzadas para la Torre grúa.
INFORME SEMANAL No 019
CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparó Ing. Juan Carlos Cruz Diaz Revisó Ing. Luis Gonzalo Villada B.
ANEXO 1. REGISTRO FOTOGRÁFICO

Foto 5 y 6. Muestra para Bloquear el Acero de Vigas y Malla inferior .

Foto 7 y 8. Demolición Cabeza Para C-21 y MP-63.


INFORME SEMANAL No 019
CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 09 de Julio al 15 de Julio de 2013
Preparó Ing. Juan Carlos Cruz Diaz Revisó Ing. Luis Gonzalo Villada B.
ANEXO 1. REGISTRO FOTOGRÁFICO

Foto 9 y 10.Fundida Pilote 39 y Control Excavación M-124 .

Foto 11 y 12. Excavación pilote, Viga guía