IS - 004 1 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES
CONCRETO
SEGUIMIENTO A RESULTADOS DE CONCRETO SEGÚN NTC 396, NTC 454, NTC 550, NTC 673, NSR-10 NUMERAL C.5.6.2
Criterios de Aceptación
DIAS
Concreto
No. Elemento Estructural Ubicación Informe Cilindro Fecha Toma 7 CORRELACION A 14 DIAS 28 56
(Kg/cm2)
RESISTENCIA RESISTENCIA RESISTENCIA RESISTENCIA
Fecha Falla ≥60% ≥80% Fecha Falla ≥100% ≥100%
Kg/cm2 Mpa Kg/cm2 Mpa Kg/cm2 Mpa Kg/cm2 Mpa
275 PILOTE 79 57 275 420 24/05/2013 24/05/2013 284.5 27.9 66% 345.8 33.915 81% 21/06/2013 468.5 45.9 109%
276 PILOTE 13 57 276 280 25/05/2013 24/05/2013 257.5 25.25 90% 322.5 31.6 113% 22/06/2013 452.5 44.4 159%
277 PANTALLA M-14 (E-F)(1) 57 277 420 25/05/2013 24/05/2013 328.5 37.15 88% 387.3 41.3 98% 22/06/2013 505 49.5 118%
278 PANTALLA M-43 (E-F)(7) 57 278 280 25/05/2013 25/05/2013 296.5 29.05 104% 367.3 36.0 129% 22/06/2013 509 49.9 178%
279 PANTALLA M-14 (E-F)(1) 57 279 420 25/05/2013 25/05/2013 401.5 39.35 94% 417.7 40.9 98% 22/06/2013 450 44.1 105%
280 PILOTE 16 57 280 420 25/05/2013 25/05/2013 415.5 40.75 97% 463.0 45.4 108% 22/06/2013 558 54.7 130%
281 PANTALLA M-43 (E-F)(7) 57 281 280 25/05/2013 25/05/2013 199.5 19.55 70% 252.7 24.8 88% 22/06/2013 359 35.2 126%
282 PANTALLA M-14 (E-F)(1) 57 282 420 25/05/2013 25/05/2013 289 28.3 68% 339.7 33.3 79% 22/06/2013 441 43.2 103%
283 PILOTE 37 57 283 280 25/05/2013 25/05/2013 212 20.8 74% 272.8 26.8 96% 22/06/2013 394.5 38.7 138%
284 PILOTE 102 58 284 420 27/05/2013 25/05/2013 327 32.1 74% 387.7 38.0 89% 24/06/2013 509 49.9 119%
285 PILOTE 53 58 285 280 28/05/2013 27/05/2013 259.5 25.45 91% 323.2 31.7 113% 25/06/2013 450.5 44.2 158%
286 PANTALLA M-40 (H-8) 58 286 280 28/05/2013 27/05/2013 226 22.2 79% 293.7 28.8 103% 25/06/2013 429 42.1 150%
287 PANTALLA M-22 Y M-23 (H-1) 58 287 280 28/05/2013 28/05/2013 246 24.1 86% 303.3 29.7 106% 25/06/2013 418 41.0 146%
288 PANTALLA M-40 (H-8) 58 288 280 28/05/2013 28/05/2013 257.5 25.25 90% 322.0 31.6 113% 25/06/2013 451 44.2 158%
289 PANTALLA M-22 Y M-23 (H-1) 58 289 280 28/05/2013 28/05/2013 233.5 22.9 82% 274.3 26.9 96% 25/06/2013 356 34.9 125%
290 PANTALLA M-22 Y M-23 (H-1) 58 290 280 28/05/2013 28/05/2013 279.5 27.45 98% 357.8 35.1 125% 25/06/2013 514.5 50.5 180%
291 PILOTE 69 60 291 280 29/05/2013 28/05/2013 253 24.8 89% 315.3 30.9 110% 26/06/2013 440 43.1 154%
292 PILOTE 8 60 292 280 29/05/2013 29/05/2013 238.5 23.35 84% 307.2 30.1 108% 26/06/2013 444.5 43.6 156%
293 PANTALLA M-105 (E-D)(1´) 60 293 210 29/05/2013 29/05/2013 182.5 17.9 85% 240.3 23.6 112% 26/06/2013 356 34.9 166%
294 PILOTE 58 60 294 420 29/05/2013 29/05/2013 274.5 26.95 64% 333.8 32.8 78% 26/06/2013 452.5 44.4 106%
295 PILOTE 10 60 295 280 30/05/2013 29/05/2013 247.5 24.25 87% 262.3 25.7 92% 27/06/2013 292 28.6 102%
297 PANTALLA M-24 (H-1) 60 297 280 30/05/2013 29/05/2013 247 24.2 87% 310.0 30.4 109% 27/06/2013 436 42.8 153%
298 PANTALLA M-42 (F-7) 60 298 280 30/05/2013 30/05/2013 227.5 22.35 80% 266.2 26.1 93% 27/06/2013 343.5 33.7 120%
299 PILOTE 77 60 299 280 30/05/2013 30/05/2013 195.5 19.15 68% 241.3 23.7 85% 27/06/2013 333 32.7 117%
300 PANTALLA M-24 (H-1) 60 300 280 30/05/2013 30/05/2013 190 18.6 67% 225.3 22.1 79% 27/06/2013 296 29.0 104%
301 PANTALLA M-42 (F-7) 60 301 280 30/05/2013 30/05/2013 195.5 19.15 68% 230.7 22.6 81% 27/06/2013 301 29.5 105%
302 PILOTE 104 61 302 280 31/05/2013 30/05/2013 261 25.6 91%
303 PANTALLA M-107 (E-F)(1) 61 303 210 31/05/2013 30/05/2013 167.5 16.45 78%
304 PILOTE 70 62 304 280 01/06/2013 31/05/2013 176 17.3 62%
305 PANTALLA M-21 (I-H)(1) 62 305 280 01/06/2013 01/06/2013 229 22.5 80%
306 PANTALLA M-38 (H-7) 62 306 280 01/06/2013 01/06/2013 192.5 18.9 67%
307 PANTALLA M-21 (I-H)(1) 62 307 280 01/06/2013 01/06/2013 216.5 21.3 76%
308 PANTALLA M-38 (H-7) 62 308 280 01/06/2013 01/06/2013 189 18.5 66%
309 PANTALLA M-21 (I-H)(1) 62 309 280 01/06/2013 01/06/2013 179 17.6 63%
310 PILOTE 4 62 310 420 01/06/2013 01/06/2013 270 26.5 63%
311 PANTALLA M-38 (H-7) 62 311 280 01/06/2013 01/06/2013 181.5 17.8 64%
312 PANTALLA M-41(F-G)(7) 63 312 280 04/06/2013 01/06/2013 251 24.6 88%
313 PANTALLA M-15 (F-1) 63 313 280 04/06/2013 03/06/2013 270 26.5 95%
314 PANTALLA M-41(F-G)(7) 63 314 280 04/06/2013 04/06/2013 219 21.5 77%
315 PANTALLA M-15 (F-1) 63 315 280 04/06/2013 04/06/2013 256.5 25.2 90%
316 PILOTE 78 63 316 280 04/06/2013 04/06/2013 256.5 25.2 90%
317 PANTALLA M-15 (F-1) 63 317 280 04/06/2013 04/06/2013 267 26.2 94%
318 PANTALLA M-41(F-G)(7) 63 318 280 04/06/2013 04/06/2013 283.5 27.8 99%

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 2 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES Criterios de Aceptación
DIAS
Concreto
No. Elemento Estructural Ubicación Informe Cilindro Fecha Toma 7 CORRELACION A 14 DIAS 28 56
(Kg/cm2)
RESISTENCIA RESISTENCIA RESISTENCIA RESISTENCIA
Fecha Falla Fecha Falla
Kg/cm2 Mpa ≥60% Kg/cm2 Mpa ≥80% Kg/cm2 Mpa ≥100% Kg/cm2 Mpa ≥100%
319 PILOTE 7 64 319 280 05/06/2013 12/06/2013 238.5 23.4 84%
320 PANTALLA M-25 (H-1) 64 320 280 05/06/2013 12/06/2013 252.5 24.8 88%
321 PILOTE 100 64 321 280 05/06/2013 12/06/2013 267 26.2 94%
322 PANTALLA M-37 (H-7) 64 322 280 05/06/2013 12/06/2013 229.5 22.6 80%
323 PANTALLA M-25 (H-1) 64 323 280 05/06/2013 12/06/2013 228 22.4 80%
324 PANTALLA M-37 (H-7) 64 324 280 05/06/2013 12/06/2013 185 18.1 65%
325 PANTALLA M-25 (H-1) 64 325 280 05/06/2013 12/06/2013 243.5 23.9 85%
326 PILOTE 107 64 326 280 05/06/2013 12/06/2013 235 23.0 82%
327 PILOTE 14 65 327 280 06/06/2013 13/06/2013 231 22.7 81%
328 PANTALLA M-20 (G-H)(1) 65 328 280 06/06/2013 13/06/2013 237.5 23.3 83%
329 PILOTE 71 65 329 280 06/06/2013 13/06/2013 228.5 22.5 80%
330 PANTALLA M-20 (G-H)(1) 65 330 280 06/06/2013 13/06/2013 225.5 22.2 79%
331 PANTALLA M-36 (6-7)(H) 66 331 280 07/06/2013 14/06/2013 235 23.0 82%
332 PILOTE 55 66 332 420 07/06/2013 14/06/2013 308 30.2 72%
333 PANTALLA M-36 (6-7)(H) 66 333 280 07/06/2013 14/06/2013 273.5 26.8 96%
334 PANTALLA M-10 (D-C)(1) 66 334 420 08/06/2013 15/06/2013 309.5 30.4 72%
335 PILOTE 185 66 335 280 08/06/2013 15/06/2013 388.5 38.1 76%
336 PILOTE 110 66 336 280 08/06/2013 15/06/2013 260.5 25.5 91%
337 PANTALLA M-10 (D-C)(1) 66 337 420 08/06/2013 15/06/2013 271.5 26.6 63%
338 PANTALLA M-10 (D-C)(1) 66 338 420 08/06/2013 15/06/2013 313.5 30.7 73%
339 PANTALLA M-35A (6-7)(H) 66 339 280 08/06/2013 15/06/2013 237.5 23.3 83%
340 PANTALLA M-35A (6-7)(H) 66 340 280 08/06/2013 15/06/2013 274.5 26.9 96%
341 PANTALLA M-10 (D-C)(1) 66 341 420 08/06/2013 15/06/2013 288 28.2 67%
342 PILOTE 9 69 342 280 11/06/2013 18/06/2013 227.5 22.3 80%
343 PANTALLA M-26 (1-2)(H) 69 343 280 11/06/2013 18/06/2013 264.5 25.9 93%
344 PANTALLA M-30 (3-4)(H) 69 344 280 11/06/2013 18/06/2013 250.5 24.6 88%
345 PANTALLA M-26 (1-2)(H) 69 345 280 11/06/2013 18/06/2013 229 22.5 80%
346 PILOTE 66 69 346 280 11/06/2013 18/06/2013 235.5 23.1 83%
347 PANTALLA M-30 (3-4)(H) 69 347 280 11/06/2013 18/06/2013 231.5 22.7 81%
348 PANTALLA M-26 (1-2)(H) 69 348 280 11/06/2013 18/06/2013 231.5 22.7 81%
349 PANTALLA M-30 (3-4)(H) 69 349 280 11/06/2013 18/06/2013 256.5 25.2 90%
350 PILOTE 188 70 350 420 12/06/2013 19/06/2013 350 34.3 82%
351 PANTALLA M-19 (G-H)(1) 70 351 280 12/06/2013 19/06/2013 271 26.6 95%
352 PANTALLA M-19 (G-H)(1) 70 352 280 12/06/2013 19/06/2013 258 25.3 90%
353 PANTALLA M-19 (G-H)(1) 70 353 280 12/06/2013 19/06/2013 237 23.2 83%
354 PILOTE 182 70 354 280 12/06/2013 19/06/2013 229 22.5 80%
355 PILOTE 15 71 355 280 13/06/2013 20/06/2013 197.5 19.4 69%
356 PANTALLA M-27 (4-H) 71 356 280 13/06/2013 20/06/2013 179 17.6 69%
357 PANTALLA M-27 (4-H) 71 357 280 13/06/2013 20/06/2013 220 21.6 77%
358 PANTALLA M-29 (3-H) 71 358 280 13/06/2013 20/06/2013 214 21.0 75%
359 PANTALLA M-27 (4-H) 71 359 280 13/06/2013 20/06/2013 184 18.0 64%
360 PILOTE 05 71 360 280 13/06/2013 20/06/2013 206.5 20.3 72%
361 PANTALLA M-29 (3-H) 71 361 280 13/06/2013 20/06/2013 244.5 24.0 86%
362 PANTALLA M-29 (3-H) 71 362 280 13/06/2013 20/06/2013 220 21.6 77%
363 PILOTE 184 72 363 420 14/06/2013 21/06/2013 290 28.4 68%
364 PANTALLA M-18 (G-H)(1) 72 364 280 14/06/2013 21/06/2013 254 24.9 89%

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 3 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES Criterios de Aceptación
DIAS
Concreto
No. Elemento Estructural Ubicación Informe Cilindro Fecha Toma 7 CORRELACION A 14 DIAS 28 56
(Kg/cm2)
RESISTENCIA RESISTENCIA RESISTENCIA RESISTENCIA
Fecha Falla Fecha Falla
Kg/cm2 Mpa ≥60% Kg/cm2 Mpa ≥80% Kg/cm2 Mpa ≥100% Kg/cm2 Mpa ≥100%
365 PANTALLA M-18 (G-H)(1) 72 365 280 14/06/2013 21/06/2013 192.5 18.9 67%
366 PANTALLA M-18 (G-H)(1) 72 366 280 14/06/2013 21/06/2013 229.5 22.5 80%
367 PILOTE 115 72 367 280 14/06/2013 21/06/2013 239.5 23.5 84%
368 PANTALLA M-28 (2-3)(H) 73 368 280 15/06/2013 22/06/2013 241.5 23.7 85%
369 PILOTE 6 73 369 280 15/06/2013 22/06/2013 246 24.1 86%
370 PANTALLA M-28 (2-3)(H) 73 370 280 15/06/2013 22/06/2013 222.5 21.8 78%
371 PANTALLA M-28 (2-3)(H) 73 371 280 15/06/2013 22/06/2013 202 19.8 71%
372 PILOTE 67 73 372 420 15/06/2013 22/06/2013 276.5 27.1 65%
373 PANTALLA M-191 (1-1´)(C-D) 74 373 210 17/06/2013 24/06/2013 143.5 14.1 67%
374 PANTALLA M-191 (1-1´)(C-D) 74 374 210 17/06/2013 24/06/2013 171.5 16.8 80%
375 PILOTE 59 75 375 280 18/06/2013 25/06/2013 258 25.3 90%
376 PANTALLA M-31 (4-H) 75 376 280 18/06/2013 25/06/2013 253.5 24.9 89%
377 PANTALLA M-31 (4-H) 75 377 280 18/06/2013 25/06/2013 277.5 27.2 97%
378 PANTALLA M-31 (4-H) 75 378 280 18/06/2013 25/06/2013 257 25.2 90%
379 PILOTE 22 76 379 420 19/06/2013 26/06/2013 332.5 32.6 78%
380 PANTALLA M-108 (1-1) 76 380 210 19/06/2013 26/06/2013 278.5 27.3 130%
381 PILOTE 22 76 381 420 19/06/2013 26/06/2013 324 31.8 76%
382 PANTALLA M-181 (2-3)( C) 76 382 210 19/06/2013 26/06/2013 204 20.0 95%
383 PILOTE 103 76 383 280 19/06/2013 26/06/2013 191 18.7 67%
384 PILOTE 105 77 384 280 20/06/2013 27/06/2013 217.5 21.3 76%
385 PANTALLA M-8 (B-C)(1) 77 385 420 20/06/2013 27/06/2013 167 16.4 39%
386 PANTALLA M-8 (B-C)(1) 77 386 420 20/06/2013 27/06/2013 227 22.3 53%
387 PANTALLA M-8 (B-C)(1) 77 387 420 20/06/2013 27/06/2013 286.5 28.1 67%

OBSERVACIONES.
La muestra 385 (M-8) resistencia baja a los 7 dias.
La muestra 386 (M-8) resistencia baja a los 7 dias.

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 4 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD
GRAFICO MATERIALES
DE SEGUIMIENTO

1.8
Resistencias Normales - Pilotes Normal

79

13

16

37

1.6 102

53

69

1.4 58

10

77

104

1.2 70

78

7
Resistencia a la compresión

100
1
107

14

71

55
0.8
185

110

66
0.6
188

182

15

15
0.4
05

184

115

6
0.2 67

59

22

22

0 103
0 5 10 15 20 25 30
105
Edad (días)

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 5 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES Normal
Resultados Normales - Pantalla M-14 (E-F)(1)
M-43 (E-F)(7)
2 M-14 (E-F)(1)
M-43 (E-F)(7)
M-14 (E-F)(1)
M-40 (H-8)
M-22 Y M-23 (H-1)
M-40 (H-8)
M-22 Y M-23 (H-1)
1.8
M-22 Y M-23 (H-1)
M-105 (E-D)(1´)
M-24 (H-1)
M-42 (F-7)
M-24 (H-1)
M-42 (F-7)
1.6 M-107 (E-F)(1)
M-21 (I-H)(1)
M-38 (H-7)
M-21 (I-H)(1)
M-38 (H-7)
M-21 (I-H)(1)
M-38 (H-7)
1.4 M-41(F-G)(7)
M-15 (F-1)
M-41(F-G)(7)
M-15 (F-1)
M-15 (F-1)
M-41(F-G)(7)
M-25 (H-1)
1.2 M-37 (H-7)
Resistencia a la compresión

M-25 (H-1)
M-37 (H-7)
M-25 (H-1)
M-20 (G-H)(1)
M-20 (G-H)(1)
M-36 (6-7)(H)
1 M-10 (D-C)(1)
M-36 (6-7)(H)
M-10 (D-C)(1)
M-10 (D-C)(1)
M-35A (6-7)(H)
M-35A (6-7)(H)
M-10 (D-C)(1)
0.8 M-26 (1-2)(H)
M-30 (3-4)(H)
M-26 (1-2)(H)
M-30 (3-4)(H)
M-26 (1-2)(H)
M-30 (3-4)(H)
M-19 (G-H)(1)
0.6 M-19 (G-H)(1)
M-19 (G-H)(1)
M-27 (4-H)
M-27 (4-H)
M-29 (3-H)
M-27 (4-H)
M-29 (3-H)
0.4
M-29 (3-H)
M-18 (G-H)(1)
M-18 (G-H)(1)
M-18 (G-H)(1)
M-28 (2-3)(H)
M-28 (2-3)(H)
0.2 M-28 (2-3)(H)
M-191 (1-1´)(C-D)
M-191 (1-1´)(C-D)
M-31 (4-H)
M-31 (4-H)
M-31 (4-H)
M-108 (1-1)
0 M-181 (2-3)( C)
M-8 (B-C)(1)
0 5 10 15 20 25 30 M-8 (B-C)(1)
Edad (días) M-8 (B-C)(1)

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 6 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL
SUPERVISIÓN DE CALIDAD
DE ACTIVIDADES MATERIALESEN CAMPO
- INSPECCIÓN
Recepción de Concreto Pilotes
CEC – T2 PILOTES
ELEMENTO DIMENSIONES CONCRETO VOLUMEN EXPANSIONES
FECHA OBSERVACIONES
# PILOTE TIPO Ǿ L.EFECT NIVEL CIMENTACION NIVEL SUPERIOR Kg/cm2 PSI TEORICO REAL EXPANSION (+) EXPANSION (-)

25/jun/13 #186 P5 0.90 47.00 -60.60 SOTANO 4 280 4000 30.10 31 2.99%
25/jun/13 #191 P6 1.00 48.00 -61.60 SOTANO 4 280 4000 38.11 42 10.21%
26/jun/13 #28 P7 1.00 63.60 -63.60 PISO 1 420 6000 49.95 60 20.12%
27/jun/13 #46 P4 0.80 44.00 -57.60 SOTANO 4 280 4000 22.13 23 3.93%
27/jun/13 #44 P1 0.80 61.60 -61.60 PISO 1 420 6000 30.96 36 16.28%
28/jun/13 #34 P7 1.00 63.60 -63.60 PISO 1 420 6000 50.73 56 10.39%
29/jun/13 #187 P5 0.90 47.00 -60.60 SOTANO 4 280 4000 29.90 31 3.68%
29/jun/13 #175 P5 0.90 49.00 -62.60 SOTANO 4 280 4000 31.16 33 5.91%
PILOTES FUNDIDOS EN EL PERIODO 8 PILOTES FUNDIDOS ACUMULADOS AL INFORME 016
PROMEDIOS EXPANSION ACUMULADA PILOTES FUNDIDOS ACUMULADOS PROMEDIOS EXPANSION ACUMULADA PILOTES FUNDIDOS ACUMULADOS
TIPO EXPANSION VALOR TIPO TOTAL TIPO EXPANSION VALOR TIPO TOTAL
POSITIVAS 8.81% P1 3 POSITIVAS 8.85% P1 4
NEGATIVAS -1.67% P2 3 NEGATIVAS -1.67% P2 3
PILOTES FUNDIDOS AL INFORME 016 10 P3 5 P3 5
P4 56 P4 57
P5 72 P5 75
P6 10 P6 11
P7 2 P7 4
P8 3 P8 3
P9 27 P9 27
TOTAL 181 TOTAL 189
OBSERVACIONES.
El cuadro de pilotes acumulados ya esta adaptado a la nueva versión de planos
Recepción de Concreto Muros Pantallas Internas
CEC – T2 PANTALLAS INTERNAS
ELEMENTO DIMENSIONES CONCRETO VOLUMEN EXPANSIONES
FECHA NIVEL NIVEL OBSERVACIONES
# PANTALLA TIPO A B LONGITUD Kg/cm2 PSI TEORICO REAL EXPANSION (+) EXPANSION (-)
CIMENT. SUPERIOR
25/jun/13 M155 EJES (D)(6-7) MP3 6.73 0.4 17.2 -24.2 SOTANO 2 210 3000 46.34 51 10.06% 0.00%
25/jun/13 M192 EJES (E-1) MP3 6.40 0.4 17.2 -24.2 SOTANO 2 210 3000 44.70 48 7.38% 0.00%
26/jun/13 M111 EJES (E-D)(1-2) MP2 6.68 0.4 16.2 -23.2 SOTANO 2 210 3000 43.15 48 11.24% 0.00%
26/jun/13 M114 EJES (E-D) 4 MP2 6.60 0.4 16.2 -23.2 SOTANO 2 210 3000 42.77 46 7.56% 0.00%
27/jun/13 M119 y 120 EJES (E-D)(7) MP2 7.33 0.4 16.2 -23.2 SOTANO 2 210 3000 47.50 53 11.58% 0.00%
28/jun/13 M112 EJES (E-D)(1-2) MP2 5.2 0.4 16.2 -23.2 SOTANO 2 210 3000 33.51 40 19.37% 0.00%
28/jun/13 M115 EJES (E-D) 4 MP2 5.2 0.4 16.2 -23.2 SOTANO 2 210 3000 33.69 39 15.76% 0.00%
29/jun/13 M178 EJES (2-3) F MP2 6.40 0.4 16.2 -23.2 SOTANO 2 210 3000 42.76 45 5.24% 0.00%
PANTALLAS FUNDIDAS EN EL PERIODO 8 PANTALLAS INTERNAS FUNDIDAS ACUMULADAS AL INFORME 016 PANTALLAS INTERNAS FUNDIDAS AL PRESENTE INFORME
PROMEDIOS EXPANSION ACUMULADA PANTALLAS FUNDIDAS ACUMULADAS PROMEDIOS EXPANSION ACUMULADA PANTALLAS FUNDIDAS ACUMULADAS

TIPO EXPANSION VALOR TIPO TOTAL TIPO EXPANSION VALOR TIPO TOTAL
POSITIVAS 7.94% MP-2 27 POSITIVAS 8.31% MP-2 33
PANTALLAS FUNDIDAS AL INFORME 016 8 NEGATIVAS 0.00% MP-3 26 NEGATIVAS 0.00% MP-3 28
TOTAL 53 TOTAL 61

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 7 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL
Recepción DE CALIDAD
de Concreto MATERIALES
Muros Pantallas Perimetrales
CEC – T2 PANTALLAS PERIMETRALES
ELEMENTO DIMENSIONES PANTALLA DIMENSIONES CONTRAFUERTE CONCRETO VOLUMEN EXPANSIONES
FECHA VOLUMEN NIVEL NIVEL VOLUMEN EXPAN ( EXPAN OBSERVACIONES
# PANTALLA TIPO A B LONGITUD A B Kg/cm2 PSI TEORICO REAL
TEORICO CIMENT. SUPERIOR TEORICO +) (-)
27/jun/13 M16 EJE (E-F) (1´) BA-2 2.50 0.8 -35.20 70.40 2.30 0.80 -35.20 PISO1 64.77 420 6000 134.68 152 12.86% 0.00%
29/jun/13 M17 EJE (G-H) (1-1´) MP-1 3.75 0.5 -30.20 56.62 PISO1 280 4000 GC 60.14 64 6.42% 0.00%
PANTALLAS FUNDIDAS EN EL PERIODO 2 PANTALLAS PERIMETRALES FUNDIDAS ACUMULADAS AL INFORME 016 PANTALLAS PERIMETRALES FUNDIDAS AL PRESENTE INFORME

PROMEDIOS EXPANSION ACUMULADA PANTALLAS FUNDIDAS ACUMULADAS PROMEDIOS EXPANSION ACUMULADA PANTALLAS FUNDIDAS ACUMULADAS

PANTALLAS FUNDIDAS AL INFORME 016 3 TIPO EXPANSION VALOR TIPO TOTAL TIPO EXPANSION VALOR TIPO TOTAL
POSITIVAS 22.23% BA-1 25 POSITIVAS 21.95% BA-1 25
NEGATIVAS 0.00% BA-2 4 NEGATIVAS 0.00% BA-2 5
BA-3 2 BA-3 2
TOTAL ELEMENTOS FUNDIDOS EN EL PERIODO 18 MP-1 36 MP-1 37
TOTAL ELEMENTOS FUNDIDOS INFORME 016 21 TOTAL 67 TOTAL 69
Inspección Refuerzo
Espaciami Amarre Empalme Cumple
Fecha Elemento Estructural Tipo Ubicación Flejes Malla Diámetro Observación
ento refuerzo canastas SI NO
PILOTE P-186 P5 (E-F)(6-7) OK OK N.A OK OK OK X
PILOTE P-191 P6 (F)(5-6) OK OK N.A OK OK OK X
25-06-13
PANTALLA M-155 MP-3 (6-7)(D) OK OK N.A OK OK OK X
PANTALLA M-192 MP-3 (E-1) OK OK N.A OK OK OK X
PILOTE P-28 P7 (4)(A-A') OK OK N.A OK OK OK X
26-06-13 PANTALLA M-111 MP-2 (E-D)(1-2) OK OK N.A OK OK OK X
PANTALLA M-114 MP-2 (E-D)(4) OK OK N.A OK OK OK X
PILOTE P-46 P4 (A-B)(7) OK OK N.A OK OK OK X
PILOTE P-44 P1 (A)(7) OK OK N.A OK OK OK X
27-06-13
PANTALLA M-16 BA-2 (E-F)(1´) OK OK N.A OK OK OK X
PANTALLA M-119 MP-2 (E-D)(7) OK OK N.A OK OK OK X
PILOTE P-34 P7 (5)(A-A') OK OK N.A OK OK OK X
28-06-13 PANTALLA M-112 MP-2 (E-D)(1-2) OK OK N.A OK OK OK X
PANTALLA M-115 MP-2 (E-D)(4) OK OK N.A OK OK OK X
PILOTE P-187 P5 (G-F)(6-7) OK OK N.A OK OK OK X
PILOTE P-175 P5 (E-F)(5-6) OK OK N.A OK OK OK X
29-06-13
PANTALLA M-178 MP-2 (2-3)(F) OK OK N.A OK OK OK X
PANTALLA M-17 MP-1 (G-H)(1-1') OK OK N.A OK OK OK X

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 8 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE DE
CONTROL CALIDAD MATERIALES
ASENTAMIENTO
VÍAS CERCANAS
CL 127 A
PUNTO FECHA E-1 E-2 E-3 E-4 V-5 P-1 P-2 V-1 P-3 P-4 P-5 P-6
COTA INICIAL 18-mar-13 49.782 49.876 49.941 50.027 50.144 49.643 49.528 49.435 49.340 49.293 49.245 49.191
CONTROL 02-jul-13 49.790 49.888 49.952 50.035 50.146 49.647 49.533 49.440 49.340 49.293 49.245 49.191
DIFERENCIA 02-jul-13 0.008 0.012 0.011 0.008 0.002 0.004 0.005 0.005 0.000 0.000 0.000 0.000
CARRERA 53A COMPORTAMIENTO DESDE INFORME 016 HASTA EL 017
PUNTO FECHA V-7 E-H E-G E-F E-E E-D E-C E-B E-A E-A" V-11 Puntos que Presentan Movimiento.
COTA INICIAL 18-mar-13 50.239 50.309 50.394 50.486 50.533 50.579 50.616 50.649 50.672 50.637 50.645 Puntos que No Presentan Movimiento.
CONTROL 02-jul-13 50.245 50.315 50.404 50.497 50.542 50.579 50.619 50.650 50.674 50.647 50.645
DIFERENCIA 02-jul-13 0.006 0.006 0.010 0.011 0.009 0.000 0.003 0.001 0.002 0.010 0.000
CONTROL DE CLL 127A Durante el periodo se presenta un rebote máximo en el punto E-2 de 0.012m
ASENTAMIENTOS CARRERA 53 A Durante el periodo se presenta un rebote máximo en el punto E-F de 0.011m
DIFICULTADES E IMPREVISTOS DURANTE LA SEMANA
Fecha OBSERVACIONES

ESTADO DEL TIEMPO 25 JUNIO 2013


HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total CONVENCIONES
SECO 13 LL-L Lluvia Leve
LL.L LL-M Lluvia Moderada
LL.M LL-F Lluvia Fuerte
LL.F
ESTADO DEL TIEMPO 26 JUNIO 2013 TOTAL ESTADO DE TIEMPO EN EL PERIODO
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total Tiempo Horas % Tiempo
SECO 13 Seco 63 96.92
LL.L Lluvia Leve 2 3.08
LL.M Lluvia Moderada 0 0.00
LL.F Lluvia Fuerte 0 0.00
ESTADO DEL TIEMPO 27 JUNIO 2013 Total Horas 65 100
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total ESTADO DE TIEMPO INFORME 016
SECO 13 Tiempo Horas % Tiempo
LL.L Seco 74 97.37
LL.M Lluvia Leve 2 2.63
LL.F Lluvia Moderada 0 0.00
ESTADO DEL TIEMPO 28 JUNIO 2013 Lluvia Fuerte 0 0.00
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total Total Horas 76 100
SECO 13
LL.L
LL.M
LL.F
ESTADO DEL TIEMPO 29 JUNIO 2013
HORA 7 8 9 10 11 12 13 14 15 16 17 18 19 Total
SECO 11
LL.L 2
LL.M
LL.F

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
IS - 004 9 de 9

INFORME SEMANAL No 017


CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparo Jose Jair Forero Acosta Reviso Ing. Luis Gonzalo Villada B.
CONTROL DE CALIDAD MATERIALES
RECOMENDACIONES
MUESTRA SEPARADORES Se esta a la espera de las muestras de los separadores que se utilizaran por parte del contratista de estructura en las placas.
PRUEBA DE ACERO Se solicita resultados de los ensayos de la primera muestra de acero utilizados en la cimentacion.

(Firma)

(Nombre) Ing. Luis Gonzalo Villada CONSULTORÍA ESTRUCTURAL


Director Supervisión Técnica

PBX (57) (1) 253 9838 Bogotá D.C. Colombia. GRATIS 018000 119838 resto del país y el exterior. Cel. (57) (03)
315 5876767 E-mails:lgv@consultoriaestructural.com - comercial@consultoriaestructural.com
AVANCE DE OBRA
Avance en Pilotaje

PLANO DE AVANCE

OBSERVACIONES.
Pilotes Ejecutados a informe 016 Pilotes Ejecutados durante el periodo Total Acumulado Pilotes Totales Pilotes Faltantes
181 8 189 257 68
Avance muros pantallas y contrafuertes

PLANO DE AVANCE

OBSERVACIONES.
Avance en Excavacion y Solado de Limpieza Nivel -0.50

PLANO DE AVANCE

OBSERVACIONES.
PLANO DE LOCALIZACION CONTROL DE ASENTAMIENTOS
GRAFICA CONTROL DE ASENTAMIENTOS

Normal
15
E-1
E-2
14 E-3
E-4
13 V-5
V-7
12 E-H
E-G
11 E-F
E-E
E-D
10
E-C
E-B
9
E-A
E-A"
8 V-11
COMPORTAMIENTO (mm)

P-1
7 P-2
V-1
6 P-3
P-4
5 P-5
P-6

-1

-2

-3 FECHA LECTURAS TOPOGRAFICAS


INFORME SEMANAL No 017
CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparó Jose Jair Forero Acosta Revisó Ing. Luis Gonzalo Villada B.
ANEXO 1. REGISTRO FOTOGRÁFICO

Foto 1 y 2.Adecuacion del Acceso y Campamento nuevo costado Occidental.

Foto 3 y 4. Demolicion Excesos Pantallas Externas eje A'.


INFORME SEMANAL No 017
CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparó Jose Jair Forero Acosta Revisó Ing. Luis Gonzalo Villada B.
ANEXO 1. REGISTRO FOTOGRÁFICO

Foto 5 y 6.Excavacion y Demolicion Mecanica Zona Pantallas Interiores.

Foto 7 y 8.Fundida Vigas Guia y solado de limpieza (N-0.50).


INFORME SEMANAL No 017
CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparó Jose Jair Forero Acosta Revisó Ing. Luis Gonzalo Villada B.
ANEXO 1. REGISTRO FOTOGRÁFICO

Foto 9 y 10. Fundida MP2-119 y 178.

Foto 11 y 12.Ubicacion del Refuerzo y Fundida P-187


INFORME SEMANAL No 017
CENTRO EMPRESARIAL COLPATRIA - TORRE 2
CONSTRUCTORA CONSTRUCTORA COLPATRIA
SUPERVISIÓN TÉCNICA CONSULTORIA ESTRUCTURAL
PERIODO 25 de Junio al 1 de Julio de 2013
Preparó Jose Jair Forero Acosta Revisó Ing. Luis Gonzalo Villada B.
ANEXO 1. REGISTRO FOTOGRÁFICO

Foto 13 y 14.Ubicacion del Refuerzo y Fundida del BA-2 M16

Foto 15 y 16. Ubicacion del Refuerzo y Fundida P-34